Arlington County, Virginia CIP
2025 − 2034
TRANSPORTATION: MAINTENANCE CAPITAL PROGRAM
10 YEAR CATEGORY SUMMARY (in $1,000s)
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year
Total
1. Bridge Maintenance 1,040 986 1,026 1,068 1,101 1,134 1,167 1,205 1,238 1,276 11,241
2. Curb & Gutter Missing Links 129 130 135 140 145 150 155 160 165 170 1,479
3. Paving 13,489 12,980 13,488 13,661 14,192 14,374 14,933 15,124 15,712 15,911 143,864
4. Sidewalk, Curb, Gutter
Proactive Zone Maintenance
1,029 1,071 1,106 1,141 1,171 1,207 1,243 1,284 1,320 1,357 11,929
5. Signals & ITS Maintenance 1,355 1,440 1,506 1,586 1,666 1,752 1,842 1,927 2,017 2,108 17,199
6. Trail Light Maintenance
Program
20 21 21 22 23 23 24 25 26 26 231
Total Recommendation 17,062 16,628 17,282 17,618 18,298 18,640 19,364 19,725 20,478 20,848 185,943
CATEGORY FUNDING SOURCES (in $1,000s)
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year
Total
New Funding
Federal Funding 0 0 0 0 0 0 0 0 0 0 0
State Funding 0 0 0 0 0 0 0 0 0 0 0
Developer Contributions 0 0 0 0 0 0 0 0 0 0 0
New Bond Issue 11,985 13,045 13,825 14,060 14,635 14,870 15,485 15,735 16,375 16,630 146,645
PAYG 2,830 3,336 3,436 3,536 3,645 3,770 3,879 3,990 4,103 4,218 36,743
Short Term Finance 0 0 0 0 0 0 0 0 0 0 0
Stormwater Utility Fee Revenue 0 0 0 0 0 0 0 0 0 0 0
Other Funding 0 0 0 0 0 0 0 0 0 0 0
TCF - Commercial & Industrial
Tax (C&I) 0 0 0 0 0 0 0 0 0 0 0
TCF - NVTA Local 0 0 0 0 0 0 0 0 0 0 0
Regional Funding 0 0 0 0 0 0 0 0 0 0 0
TCF Bonds 0 0 0 0 0 0 0 0 0 0 0
Tax Increment Financing (TIF) 0 0 0 0 0 0 0 0 0 0 0
TIF Bonds 0 0 0 0 0 0 0 0 0 0 0
TCF for Operating Costs 0 0 0 0 0 0 0 0 0 0 0
Subtotal New Funding 14,815 16,381 17,261 17,596 18,280 18,640 19,364 19,725 20,478 20,848 183,388
Previously Approved Funding
Authorized but Unissued
Bonds 1,882 226 0 0 0 0 0 0 0 0 2,108
Issued but Unspent Bonds 151 0 0 0 0 0 0 0 0 0 151
TCF - Commercial & Industrial
Tax (C&I) 0 0 0 0 0 0 0 0 0 0 0
TCF - NVTA Local 0 0 0 0 0 0 0 0 0 0 0
Regional Funding 0 0 0 0 0 0 0 0 0 0 0
Tax Increment Financing (TIF) 0 0 0 0 0 0 0 0 0 0 0
Other Previously Approved
Funds 214 21 21 22 18 0 0 0 0 0 296
Subtotal Previously Approved
Funding 2,247 247 21 22 18 0 0 0 0 0 2,555
Total Funding Sources 17,062 16,628 17,282 17,618 18,298 18,640 19,364 19,725 20,478 20,848 185,943
E - 77
TRANSPORTATION Capital Improvement Plan
Maintenance Capital FY 2025-2034
1. BRIDGE MAINTENANCE
Project Highlights:
• Ongoing cyclical inspection, maintenance, and rehabilitation
of 36 vehicular and pedestrian bridges in Arlington County
to ensure safety of the structures for pedestrians and vehicular
traffic.
• This program maintains the overall rating of the c ounty’s
bridges between "Satisfactory" and "Good" and is necessary
to ensure safety for the traveling public.
Associated Plan(s):
Master Transportation Plan
Neighborhood(s):
VARIOUS
Funding Notes: Other Previously Approved Funding are PAYG.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
New Bond Issue 530 790 825 850 875 900 930 955 985 7,640
PAYG 221 230 236 243 251 259 267 275 283 291 2,556
Previous Funding
Authorized but Unissued
Bonds 474 226 700
Issued but Unspent Bonds 151 151
Other Previously
Approved Funds 194 194
Total Funding 1,040 986 1,026 1,068 1,101 1,134 1,167 1,205 1,238 1,276 11,241
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
C
ritical Milestones:
• Barcroft Neighborhood/Glencarlyn Park
pedestrian bridge construction completion
Fall 2024
• South Glebe Road at Water Pollution
Control Plant construction completion
Fall 2024
C
hanges from Prior CIP:
No change from the previous CIP.
E - 78
TRANSPORTATION Capital Improvement Plan
Maintenance Capital FY 2025-2034
2. CURB & GUTTER MISSING LINKS
Project Highlights:
• Program constructs curb & gutter along street sections where
they are missing to resolve drainage issues.
• Projects are prioritized based on flooding risk, presence of
nearby curb and gutter, and particular site constraints.
• If new sidewalk is feasible to add, program works with the
Arlington Neighborhoods program.
Associated Plan(s):
Master Transportation Plan
Storm Water Master Plan
Neighborhood(s):
VARIOUS
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
New Bond Issue 110 130 135 140 145 150 155 160 165 170 1,460
Previous Funding
Authorized but Unissued
Bonds 19 19
Total Funding 129 130 135 140 145 150 155 160 165 170 1,479
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
No significant change from the previous CIP.
E - 79
TRANSPORTATION Capital Improvement Plan
Maintenance Capital FY 2025-2034
3. PAVING
Project Highlights:
• The County maintains and manages 1,058 lane miles of
paved streets.
• The goal is to achieve a Pavement Condition Index (PCI)
between 75 and 80 (considered "good" by the Army Corps of
Engineers). The 2023 PCI was 83.3 indicating a state of good
repair near “Excellent.”
• The County uses a mix of strategies under the Paving
program to achieve this goal in a cost -effective manner: hot-
mix resurfacing, slurry seal, micro-surfacing, and rebuilding.
Associated Plan(s):
Master Transportation Plan
Neighborhood(s):
VARIOUS
Funding Notes: Program is entirely funded by a mix of PAYG and bonds.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
New Bond Issue 10,800 11,235 11,690 11,810 12,285 12,410 12,910 13,040 13,565 13,700 123,445
PAYG 1,300 1,745 1,798 1,851 1,907 1,964 2,023 2,084 2,147 2,211 19,030
Previous Funding
Authorized but Unissued
Bonds 1,389 1,389
Total Funding 13,489 12,980 13,488 13,661 14,192 14,374 14,933 15,124 15,712 15,911 143,864
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
The only change versus the previous CIP is a
reduction in bond funding and a small reduction
in PAYG funding in light of the high 2023 PCI.
Impact on road conditions will be monitored
over time to ensure roads are maintained in an
adequate manner.
Project Links:
• https://www.arlingtonva.us/Government/Programs/Transportation/Streets/Street-
Maintenance
E - 80
TRANSPORTATION Capital Improvement Plan
Maintenance Capital FY 2025-2034
4. SIDEWALK, CURB, GUTTER PROACTIVE ZONE MAINTENANCE
Project Highlights:
• Program funds proactive inspection and maintenance of
County-maintained, curb, gutter, and sidewalks. It remediates
and improves sidewalk condition to encourage use of
sidewalks and increase safety.
• The County is divided into 20 concrete zones and the
program’s goal is to undertake proactive maintenance of two
zones a year, for a ten-year maintenance interval.
• Program will pursue low carbon concrete pilot installations.
Associated Plan(s):
Master Transportation Plan
Vision Zero Action Plan
Neighborhood(s):
VARIOUS
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
New Bond Issue 720 750 775 800 820 845 870 900 925 950 8,355
PAYG 309 321 331 341 351 362 373 384 395 407 3,574
Previous Funding
Total Funding 1,029 1,071 1,106 1,141 1,171 1,207 1,243 1,284 1,320 1,357 11,929
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
No significant change from the previous CIP.
E - 81
TRANSPORTATION Capital Improvement Plan
Maintenance Capital FY 2025-2034
5. SIGNALS & ITS MAINTENANCE
Project Highlights:
• This program covers the inspection, maintenance, and repair
of the county’s 302 signalized intersections as well as ITS
devices such as push buttons, CCTV, video detection, battery
back-up, flashing beacons, and speed indicators.
• Program pays for structural inspections of signal poles,
undertaken on a six-year cycle.
Associated Plan(s):
Master Transportation Plan
Vision Zero Action Plan
Neighborhood(s):
VARIOUS
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
New Bond Issue 355 400 435 485 535 590 650 705 765 825 5,745
PAYG 1,000 1,040 1,071 1,101 1,131 1,162 1,192 1,222 1,252 1,283 11,454
Previous Funding
Total Funding 1,355 1,440 1,506 1,586 1,666 1,752 1,842 1,927 2,017 2,108 17,199
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
In the previous CIP cycle, this program consisted of ITS device
replacements only, and was named as such. In this CIP, proactive
structural inspections,
and preventative maintenance of signals
(and related repairs) are included. All capital maintenance
activities related to signals and ITS devices are now centralized in
this CIP program.
E - 82
TRANSPORTATION Capital Improvement Plan
Maintenance Capital FY 2025-2034
6. TRAIL LIGHT MAINTENANCE PROGRAM
Project Highlights:
• The program covers minor operations and maintenance
repairs for trail lighting.
Associated Plan(s):
Master Transportation Plan
Neighborhood(s):
VARIOUS
Funding Notes: Other Previously Approved Funds are PAYG.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
PAYG 5 23 24 25 26 26 129
Previous Funding
Other Previously
Approved Funds 20 21 21 22 18 102
Total Funding 20 21 21 22 23 23 24 25 26 26 231
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
Project cost has been updated to reflect lower volume of service
requests more accurately.
E - 83