Arlington County, Virginia
WATER AND SEWER INFRASTRUCTURE
Program Description
These programs construct and maintain the infrastructure, facilities, and equipment which provides safe, reliable, and compliant drinking
water, sanitary sewer collection, and wastewater treatment for the County's residents, businesses, and visitors. In addition to the County
owned and operated systems and facilities, there are programs for the Washington Aqueduct Division (WAD) which is the potable water
treatment plant owned and operated by the Army Corps of Engineers that provides Arlington's drinking water, and for the Blue Plains
Advanced Wastewater Treatment Plant which treats approximately six percent of Arlington County's wastewater. The County's Wat er
Pollution Control Plant (WPCP) provides wastewater treatment for 94 percent of the County, and also treats wastewater from portions of
Fairfax County, the City of Falls Church, and the City of Alexandria, collectively known as the Inter -Jurisdictional (IJ) partners. These IJ
partners' flows comprise approximately 17 percent of the wastewater volume trea ted at the WPCP; therefore, they pay a portion of the
capital costs for maintenance and upgrades at the Water Pollution Control Plant and for the large transmission sewer mains which convey
their wastewater. The WPCP Capital Improvement Program directly supports Arlington's vision for a world class, environmentally friendly,
sustainable community as well as the Water Pollution Control Bureau's (WPCB) mission of safely and cost -effectively protecting public
health and the environment.
Program Summary
The Capital Improvement Programs (CIP) for the water distribution and sanitary sewer collection systems are guided by System Plans
adopted by the Board in 2014 for the Water Distribution system and in 2024 for the Sanitary Sewer system. Programs for both systems are
bifurcated into Expansion and Capital Sustainment (formerly called Non-Expansion) programs. The Expansion programs provide
additional system capacity to accommodate anticipated growth through the year 2040 and are included in the Water Distribution and Sanitary
Sewer Improvements Programs, while the Capital Sustainment programs are focused on asset maintenance, rehabilitation, and replacement
and are included in the WS Maintenance Capital Program.
The System Plans for both systems identify large infrastructure projects to expand capacity, improve redundancy, and replace or rehabilitate
existing infrastructure, as well as identify key programs based upon core asset management principles. Many of the large infrastructure
projects in the System Plans have already been completed, others are well -underway, and others are programmed in this CIP. Likewise,
most of the asset -based infrastructure programs are recurring programs which rehabilitate or replace a consistent portion of our
infrastructure on a regular cycle to ensure that we are maintaining a system which is efficient, reliable, and avoids abrupt funding needs.
Meaningful changes from the previous CIP include increased priority placed on both finished and source (raw) water resiliency projects and
programs. At the Washington Aqueduct, the County's wholesale water supplier which is managed by the U.S. Army Corps of Engineers,
the three wholesale customers (DC Water, Fairfax Water, and Arlington County) approved increased funding to address previously deferred
and planned capital investments. Conceptual planning has also started for future projects related to regulatory changes. Additionally, the
County is conducting a study which is exploring options to increase our own finished water redundancy through connections with regional
partners. Regionally, Arlington is partnering with the water resources team at the Metro Washington Council of Governments (COG) and
our regional water utility partners in a scoping and study effort for Potomac River source water resilience. The effort is ba cked by recently
passed Water Resources Development Act which authorized a secondary source study for the National Capital Region.
The WPCP Capital Sustainment Program (formerly called WPCP Non -Expansion) focuses on projects that rehabilitate, replace, and/or
upgrade existing WPCP infrastructure, including process control/ automation, to ensure that the facility can safely protect the public health
and the environment by reliably maintaining continuity of service and simultaneously meeting the permit requirements. Also included in
the Capital Sustainment program are annual repairs and replacement of current equipment and infrastructure at the plant and 15 pumping
and metering stations. WPCP Capital Sustainment also funds Arlington's pro-rata share of improvements at DC Water's Blue Plains
Advanced Wastewater Treatment Plant and the associated conveyance infrastructure.
The WPCP Capital Sustainment Program provides for significant investment in the Solids Handling processes at the Plant. The 2001 WPCP
Master Plan identified the need to address Solids Handling, but prioritized the liquid processes and capacity issues, and thu s the Solids
Planning was deferred. A subsequent Solids Master Plan was adopted by the County Board in conjunction with the FY 2019 - FY 2028
CIP. The Solids Master Plan identified core criteria spanning operational, economic, environmental, regulatory, and social co nsiderations.
It evaluated the state of current technology to identify processes w hich best meets the needs of the community. This suite of projects to
replace and upgrade the solids handling processes and equipment, collectively known as Arlington Re -Gen, has been broken into three
phases, described below:
F - 1
• Re-Gen, Phase I - Immediate project needs to replace solids handling critical equipment that are failing and costly and labor -
intensive to maintain. These projects are anticipated to be completed by the end of Fiscal Year 2024.
• Re -Gen, Phase II - Projects that need to be completed in advance of Phase III. This may involve additional equipment
replacement or demolition of underutilized facilities in preparation for the Phase III construction.
• Phase III - Implementation of technology to provide long -term sustainability of the WPCP's solids handling processes, using
processes that are less likely to be subjected to increasing regulatory demands, while reducing the impacts on the surroundin g
community and increasing energy efficiency.
With the completion of the 2001 WPCP Master Plan (MP01) program in 2014, which increased treatment system capacity from 30 mi llion
gallons per day (MGD) to 40 MGD and looking at the steady treatment volumes despite growing population, no treatment system capacity
expansion projects are included in this CIP.
F - 2
Arlington County, Virginia
WATER AND SEWER INFRASTRUCTURE
CIP
2025 − 2034
10 Y
EAR CATEGORY SUMMARY (in $1,000s)
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year
Total
WS Maintenance Capital 30,605 30,615 31,640 35,840 35,440 35,200 33,415 94,455 29,355 31,455 388,020
Water Distribution 3,400 3,010 6,685 12,430 22,650 23,495 34,770 715 585 61,240 168,980
Sanitary Sewer System
Improvements
900 260 265 275 275 285 285 295 295 300 3,435
WPCP Capital Sustainment 36,810 71,930 71,540 62,275 29,730 5,465 11,820 9,570 11,575 8,735 319,450
Total Recommendation 71,715 105,815 110,130 110,820 88,095 64,445 80,290 105,035 41,810 101,730 879,885
Implementation Adjustment (14,340) (21,160) (22,030) (22,160) (17,620) (12,890) (16,060) (21,010) (8,360) (20,350) (175,980)
Adjusted CIP 57,375 84,655 88,100 88,660 70,475 51,555 64,230 84,025 33,450 81,380 703,905
P
ROGRAM FUNDING SOURCES (in $1,000s)
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year
Total
New Funding
Federal Funding 0 0 0 0 0 0 0 0 0 0 0
State Funding 0 0 0 0 0 0 0 0 0 0 0
Developer Contributions 7,900 9,385 9,665 10,270 10,265 10,875 10,875 11,420 11,415 12,025 104,095
New Bond Issue 3,400 10,820 17,665 33,795 50,545 32,890 48,535 74,355 15,550 73,785 361,340
PAYG 7,993 13,202 19,470 18,050 22,355 19,790 19,930 16,365 12,830 14,065 164,050
Short Term Finance 0 0 0 0 0 0 0 0 0 0 0
Stormwater Utility Fee Revenue 0 0 0 0 0 0 0 0 0 0 0
Other Funding 9,040 13,050 13,495 10,940 4,930 890 2,050 1,795 2,225 1,645 60,060
Subtotal New Funding 28,333 46,457 60,295 73,055 88,095 64,445 81,390 103,935 42,020 101,520 689,545
Previously Approved Funding
Authorized but Unissued
Bonds 23,640 52,205 52,225 34,290 0 0 0 0 0 0 162,360
Issued but Unspent Bonds 0 0 0 0 0 0 0 0 0 0 0
Other Previously Approved
Funds 20,242 7,738 0 0 0 0 0 0 0 0 27,980
Subtotal Previously Approved
Funding 43,882 59,943 52,225 34,290 0 0 0 0 0 0 190,340
Total Funding Sources 72,215 106,400 112,520 107,345 88,095 64,445 81,390 103,935 42,020 101,520 879,885
Implementation Adjustment (14,340) (21,160) (22,030) (22,160) (17,620) (12,890) (16,060) (21,010) (8,360) (20,350) (175,980)
Adjusted CIP 57,875 85,240 90,490 85,185 70,475 51,555 65,330 82,925 33,660 81,170 703,905
F - 3