Maintenance Capital Program(PDF, 1MB)
Arlington County · Arlington County · Budget documents
Open the original document More from Arlington County
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Arlington County, Virginia CIP
2025 − 2034
WATER AND SEWER INFRASTRUCTURE: WS MAINTENANCE
CAPITAL PROGRAM
10 YEAR CATEGORY SUMMARY (in $1,000s)
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year
Total
1. Sewer-Infiltration and Inflow 3,000 3,105 3,210 3,315 3,315 3,420 3,420 3,525 585 605 27,500
2. Sewer-Large Diameter Main
Rehabilitation
2,780 2,185 4,140 2,550 3,090 2,340 100 4,220 1,040 2,050 24,495
3. Water-Large Diameter Main
& Valve Rehabilitation
1,000 1,035 1,070 1,105 1,105 1,140 1,140 1,175 1,175 1,210 11,155
4. Water-Large Meter Vault
Rehabilitation & Replacement
200 205 215 220 220 230 230 235 235 240 2,230
5. Manhole Rehabilitation 1,000 1,035 1,070 1,105 1,105 1,140 1,140 1,175 1,175 1,210 11,155
6. Water-Pump Station
Rehabilitation
0 105 0 110 0 115 0 115 0 120 565
7. Sewer-Force Mains 2,100 155 160 165 165 170 170 175 175 180 3,615
8. Sewer-Main Replacement
Program
2,000 2,590 3,210 3,315 3,315 3,420 3,420 3,525 3,525 3,630 31,950
9. Water-Small Diameter Valve
Rehabilitation & Replacement
300 310 320 330 330 340 340 350 350 365 3,335
10. Technology Enhancements 725 1,365 60 2,630 2,735 2,935 3,050 65 65 65 13,695
11. Trades Center Equipment
& Improvements
0 1,035 0 0 0 0 0 0 0 0 1,035
12. Washington Aqueduct
Capital
7,800 8,075 8,345 8,620 8,620 8,890 8,890 67,915 9,165 9,440 145,760
13. Water-Main Cleaning and
Lining Program
1,600 1,655 1,710 1,770 1,770 1,825 1,825 1,880 1,880 1,935 17,850
14. Water-Main Replacement
Program
7,000 6,725 6,955 7,180 7,735 7,980 8,550 8,810 8,810 9,075 78,820
15. Water/Sewer
Frames/Covers
1,000 1,035 1,070 1,105 1,105 1,140 1,140 1,175 1,175 1,210 11,155
16. Water-Tank Rehabilitation 100 0 105 2,320 830 115 0 115 0 120 3,705
Total Recommendation 30,605 30,615 31,640 35,840 35,440 35,200 33,415 94,455 29,355 31,455 388,020
F - 4
CATEGORY FUNDING SOURCES (in $1,000s)
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year
Total
New Funding
Federal Funding 0 0 0 0 0 0 0 0 0 0 0
State Funding 0 0 0 0 0 0 0 0 0 0 0
Developer Contributions 6,665 7,940 8,175 8,730 8,725 9,285 9,285 9,675 8,585 9,110 86,175
New Bond Issue 3,400 9,030 9,190 10,410 9,015 10,090 8,660 70,065 9,115 9,845 148,820
PAYG 6,008 9,305 14,220 13,215 17,315 15,425 16,170 13,205 11,460 11,870 128,193
Short Term Finance 0 0 0 0 0 0 0 0 0 0 0
Stormwater Utility Fee Revenue 0 0 0 0 0 0 0 0 0 0 0
Other Funding 3,010 1,115 1,640 815 385 400 400 410 405 420 9,000
Subtotal New Funding 19,083 27,390 33,225 33,170 35,440 35,200 34,515 93,355 29,565 31,245 372,188
Previously Approved Funding
Authorized but Unissued
Bonds 2,900 0 0 0 0 0 0 0 0 0 2,900
Issued but Unspent Bonds 0 0 0 0 0 0 0 0 0 0 0
Other Previously Approved
Funds 9,122 3,810 0 0 0 0 0 0 0 0 12,932
Subtotal Previously Approved
Funding 12,022 3,810 0 0 0 0 0 0 0 0 15,832
Total Funding Sources 31,105 31,200 33,225 33,170 35,440 35,200 34,515 93,355 29,565 31,245 388,020
F - 5
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WS Maintenance Capital FY 2025-2034
1. SEWER-INFILTRATION AND INFLOW
Project Highlights:
• This program rehabilitates the small diameter (less than 15 -
inch) sanitary sewer system to eliminate infiltration and
inflow, the intrusion of rain, ground, or surface water into the
County's sanitary sewer system.
• The County's goal is to line two percent of the system
annually. As of March 2024, over 58 percent of the system
has been lined.
Associated Plan(s):
Sanitary Sewer Collection System Plan
Neighborhood(s):
VARIOUS
Funding Notes: A portion of the annual funding will be from infrastructure availability fees (developer contributions). Other funding
includes interest income.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Developer Contributions 2,100 2,275 2,355 2,485 2,485 2,620 2,620 2,700 295 300 20,235
PAYG 650 570 590 555 555 515 515 530 5 4,485
Other Funding 250 260 265 275 275 285 285 295 290 300 2,780
Previous Funding
Total Funding 3,000 3,105 3,210 3,315 3,315 3,420 3,420 3,525 585 605 27,500
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
The last two years of the CIP reflect anticipated reductions in the
small diameter relining program as program goals are achieved.
F - 6
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WS Maintenance Capital FY 2025-2034
2. SEWER-LARGE DIAMETER MAIN REHABILITATION
Project Highlights:
• This program rehabilitates 15-inch and larger sanitary sewer
mains and appurtenances to eliminate infiltration and inflow,
the intrusion of rain, ground, or surface water into the
County's sanitary sewer system.
• The County periodically performs condition inspections and
assessments on the large diameter sanitary sewer mains to
identify deficiencies and make recommendations on repairs.
Associated Plan(s):
Sanitary Sewer Collection System Plan
Neighborhood(s):
VARIOUS
Funding Notes: County funding is set aside annually for these larger cost projects to accumulate sufficient funding while avoiding
rate spikes. Other funding includes $2,030,000 of Inter -Jurisdictional (IJ) revenue for projects on the Four Mile Run Interceptor, with
each IJ's portion based on its reserved capacity. Other funding also includes HUD Community Project Funding grants and $1,500 ,000
of federal funding. Other Previously Approved Funds include existing PAYG balances.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Developer Contributions 500 1,000 1,000 1,100 1,100 1,200 1,200 1,200 1,250 1,500 11,050
New Bond Issue 1,000 1,015 1,000 1,140 1,920 340 6,415
PAYG 65 865 990 1,920
Other Funding 1,070 750 1,275 435 3,530
Previous Funding
Other Previously
Approved Funds 1,210 370 1,580
Total Funding 2,780 2,185 4,140 2,550 3,090 2,340 1,200 3,120 1,250 1,840 24,495
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 64 129 193 266 266 389 389 1,696
Changes from Prior CIP:
Projects originally scheduled for FY 2023 and FY 2024 have
shifted to FY 2025 and FY 2026 (Four Mile Run Relief Route 50
to Columbia Pike; Rosslyn - Potomac Interceptor). This CIP also
includes funding for additional large diameter sewer projects as
focus shifts from small diameter to large diameter rehabilitations.
F - 7
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WS Maintenance Capital FY 2025-2034
3. WATER-LARGE DIAMETER MAIN & VALVE REHABILITATION
Project Highlights:
• This program includes the rehabilitation of old (more than 50
years) large diameter (20 - 36-inch) water mains and the
rehabilitation or replacement of 16 -inch or larger valves and
pressure regulating valves.
Associated Plan(s):
Water System Master Plan
Neighborhood(s):
VARIOUS
Funding Notes: A portion of the annual funding is from infrastructure availability fees (developer contributions). Other Previously
Approved Funds include existing PAYG balances.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Developer Contributions 115 160 165 170 170 175 175 195 195 200 1,720
PAYG 680 875 905 935 935 965 965 980 980 1,010 9,230
Previous Funding
Other Previously
Approved Funds 205 205
Total Funding 1,000 1,035 1,070 1,105 1,105 1,140 1,140 1,175 1,175 1,210 11,155
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
Program costs have increased from the pr evious CIP based on
the priority to rehabilitate and/or replace large water valves based
on results from the large valve inspection program. These valves
are critical to the operation of the drinking water system and
enable control over transmission mains.
F - 8
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WS Maintenance Capital FY 2025-2034
4. WATER-LARGE METER VAULT REHABILITATION &
REPLACEMENT
Project Highlights:
• This program ensures that large commercial meters, which
account for approximately 75 percent of the system revenue,
remain in a good state of repair.
• Large meter vault inspections and condition assessments are
being conducted in conjunction with the large meter
replacements to identify vaults requiring rehabilitation or
replacement.
Associated Plan(s):
Water System Master Plan
Neighborhood(s):
VARIOUS
Funding Notes: Other previously approved funds include existing PAYG balances.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
PAYG 50 205 215 220 220 230 230 235 235 240 2,080
Previous Funding
Other Previously
Approved Funds 150 150
Total Funding 200 205 215 220 220 230 230 235 235 240 2,230
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
Program costs changed slightly from the previous CIP.
F - 9
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WS Maintenance Capital FY 2025-2034
5. MANHOLE REHABILITATION
Project Highlights:
• This program provides for the rehabilitation of sanitary sewer
manholes through epoxy lining and structural rebuilds when
necessary.
• Manhole rehabilitation occurs in conjunction with the
Infiltration and Inflow (I&I) Program (sewer main relining)
and the Large Diameter Sewer Rehabilitation Program.
Associated Plan(s):
Sanitary Sewer Collection System Plan
Neighborhood(s):
VARIOUS
Funding Notes: Other Previously Approved Funds include existing PAYG balances.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
PAYG 608 1,035 1,070 1,105 1,105 1,140 1,140 1,175 1,175 1,210 10,763
Previous Funding
Other Previously
Approved Funds 392 392
Total Funding 1,000 1,035 1,070 1,105 1,105 1,140 1,140 1,175 1,175 1,210 11,155
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
Investment in this program nearly doubled since the previous CIP
based on the recently adopted Sanitary Sewer Collection System
Plan.
F - 10
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WS Maintenance Capital FY 2025-2034
6. WATER-PUMP STATION REHABILITATION
Project Highlights:
• This program includes maintenance capital and rehabilitation
of various water pump stations throughout the County to keep
the equipment and facilities properly functioning.
Associated Plan(s):
Water System Master Plan
Neighborhood(s):
VARIOUS
Funding Notes: Other Previously Approved Funds include existing PAYG balances.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
PAYG 30 110 115 115 120 490
Previous Funding
Other Previously
Approved Funds
75 75
Total Funding 0 105 0 110 0 115 0 115 0 120 565
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
No significant change from the previous CIP.
F - 11
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WS Maintenance Capital FY 2025-2034
7. SEWER-FORCE MAINS
Project Highlights:
• This program rehabilitates and replaces the County's force
main systems, which are necessary to convey sewage for
much of the northern third of the County, which are at a lower
elevation than the rest of the County.
• Force mains are located at Donaldson Run, Gulf Run, Windy
Run, and other sewage lift stations.
Associated Plan(s):
Sanitary Sewer Collection System Plan
Neighborhood(s):
VARIOUS
Funding Notes: Other Previously Approved Funds include existing PAYG balances.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
PAYG 510 155 160 165 165 170 170 175 175 180 2,025
Other Funding 1,590 1,590
Previous Funding
Total Funding 2,100 155 160 165 165 170 170 175 175 180 3,615
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Gulf Run Force Main construction Fall 2024 - Summer 2025
Changes from Prior CIP:
This CIP includes funding for rehabilitation of the Gulf Run Force Main in
FY 2025.
F - 12
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WS Maintenance Capital FY 2025-2034
8. SEWER-MAIN REPLACEMENT PROGRAM
Project Highlights:
• This program replaces smaller diameter sewer mains when
lining sewer mains is not viable or recommended.
• Traditional replacement may be necessary to address
severely deteriorated or failed sanitary sewer mains.
Associated Plan(s):
Sanitary Sewer Collection System Plan
Neighborhood(s):
VARIOUS
Funding Notes: A portion of the annual funding will be from infrastructure availability fees (developer contributions). Other
Previously Approved Funds include existing PAYG balances.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Developer Contributions 750 830 855 885 885 910 910 940 2,205 2,150 11,320
PAYG 1,110 1,760 2,355 2,430 2,430 2,510 2,510 2,585 1,320 1,480 20,490
Previous Funding
Other Previously
Approved Funds 140 140
Total Funding 2,000 2,590 3,210 3,315 3,315 3,420 3,420 3,525 3,525 3,630 31,950
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
Program costs have increased from the previous CIP based on
priority and to align with actual spending levels.
F - 13
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WS Maintenance Capital FY 2025-2034
9. WATER-SMALL DIAMETER VALVE REHABILITATION &
REPLACEMENT
Project Highlights:
• This program rehabilitates and/or replaces small diameter
water valves throughout the County, as identified through the
Valve Inspection and Exercise Program.
• This program ensures the County's water distribution system
valves are operable to minimize the extent and duration of
water service outages during planned or emergency work.
Associated Plan(s):
Water System Master Plan
Neighborhood(s):
VARIOUS
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
PAYG 300 310 320 330 330 340 340 350 350 365 3,335
Previous Funding
Total Funding 300 310 320 330 330 340 340 350 350 365 3,335
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
A slight increase in annual funding from the previous CIP.
F - 14
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WS Maintenance Capital FY 2025-2034
10. TECHNOLOGY ENHANCEMENTS
Project Highlights:
• Periodic upgrades and replacements for technology
infrastructure and systems are necessary to maintain secure,
efficient, and effective operation of the water distribution and
sanitary sewer collection systems.
• FY 2024 – FY 2025 includes funding for planned
implementation of the next generation of meter reading
technology, including piloting Advanced Metering
Infrastructure (AMI). It also includes funding for a
systemwide leak detection pilot (FY 2025 - FY 2027).
Associated Plan(s):
Community Energy Plan
Water System Master Plan
Neighborhood(s):
VARIOUS
Funding Notes: Other previously approved funds include existing PAYG balances.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
PAYG 45 1,060 1,630 2,735 2,935 3,050 65 65 65 11,650
Previous Funding
Other Previously
Approved Funds 725 1,320 2,045
Total Funding 725 1,365 1,060 1,630 2,735 2,935 3,050 65 65 65 13,695
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Operations Costs (+/-) 21 56 108 197 301 404 455 455 455 2,452
Total Impact 0 21 56 108 197 301 404 455 455 455 2,452
Critical Milestones:
• Piloting AMI Spring 2024 - Summer 2025
• Transition commercial accounts to AMI Fall 2025 - Fall 2026
• Transition residential accounts to AMI Fall 2028 - Spring 2031
Changes from Prior CIP:
Costs for transition to Advanced Metering Infrastructure (AMI) increased in this
CIP due to further refinement of technology planned to be implemented and the
inclusion of meter replacements for those beyond their accuracy warranty period.
Meter replacement costs are approximately 50 percent of the total AMI costs.
F - 15
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WS Maintenance Capital FY 2025-2034
11. TRADES CENTER EQUIPMENT & IMPROVEMENTS
Project Highlights:
• Funding will be used for various equipment and facility
improvements at the Trades Center in support of Utilities
operations.
• Funding is related to relocating staff at the Trades Center
from trailers that are beyond their useful life to permanent
facilities.
Associated Plan(s):
Community Energy Plan
Water System Master Plan
Neighborhood(s):
Shirlington
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
New Bond Issue 535 535
PAYG 500 500
Previous Funding
Total Funding 500 535 0 0 0 0 0 0 0 0 1,035
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
Expenditures are one year later than the previous CIP.
F - 16
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WS Maintenance Capital FY 2025-2034
12. WASHINGTON AQUEDUCT CAPITAL
Project Highlights:
• This program provides the County's share of funding for
capital improvements at the Washington Aqueduct, the
County's wholesale water supplier, which is managed by the
U.S. Army Corps of Engineers.
• The Washington Aqueduct is currently the County's sole
source of drinking water.
• The Aqueduct’s capital budget is approved by its three
customers (DC Water, Fairfax Water, and Arlington County)
during the annual budget process. Arlington's contributions
are based upon a prorate share of usage of the system.
Associated Plan(s):
Water System Master Plan
Neighborhood(s):
VARIOUS
Funding Notes: Other previously approved funds include existing PAYG balances. The Aqueduct is owned and maintained by the
U.S. Army Corps of Engineers.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
New Bond Issue 3,400 6,005 4,600 5,305 4,200 4,330 4,045 62,920 3,885 4,300 102,990
PAYG 2,070 3,745 3,315 4,420 4,560 4,845 4,995 5,280 5,140 38,370
Previous Funding
Authorized but Unissued
Bonds 2,900 2,900
Other Previously
Approved Funds 1,500 1,500
Total Funding 7,800 8,075 8,345 8,620 8,620 8,890 8,890 67,915 9,165 9,440 145,760
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
The wholesale customers (DC Water, Fairfax Water, and
Arlington County) approved increased funding to address
previously deferred as well as currently planned capital
investments in the Washington Aqueduct. Notional future
amounts in FY 2032 are for regulatory changes and will be further
refined in future CIPs.
F - 17
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WS Maintenance Capital FY 2025-2034
13. WATER-MAIN CLEANING AND LINING PROGRAM
Project Highlights:
• This program rehabilitates small diameter (8-inch and below)
pre-1960s cast iron water mains to restore flow capacity and
improve water quality. In conjunction with the water main
replacement program, this project will improve the overall
condition of the County's water main assets.
• The Water Distribution System Master Plan's goal is to
rehabilitate the 250 miles of small diameter mains by 2040.
Associated Plan(s):
Water System Master Plan
Neighborhood(s):
VARIOUS
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
PAYG 1,600 1,655 1,710 1,770 1,770 1,825 1,825 1,880 1,880 1,935 17,850
Previous Funding
Total Funding 1,600 1,655 1,710 1,770 1,770 1,825 1,825 1,880 1,880 1,935 17,850
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
Slight annual increases from the previous CIP.
F - 18
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WS Maintenance Capital FY 2025-2034
14. WATER-MAIN REPLACEMENT PROGRAM
Project Highlights:
• This program replaces small diameter (8-inch and below) old
cast iron water mains that are more susceptible to breaks with
new ductile iron mains. In conjunction with the water main
cleaning and lining program, this project will improve the
overall condition of the County's water main assets.
• The Water Distribution System Master Plan's goal is to
rehabilitate the 250 miles of small diameter mains by 2040.
• As necessary, pipes are upsized to provide appropriate water
flow and pressure.
Associated Plan(s):
Water System Master Plan
Neighborhood(s):
VARIOUS
Funding Notes: A portion of the annual funding will be from infrastructure availability fees (developer contributions). Other funding
includes interest income. Other previously approved funds include existing PAYG balances.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Developer Contributions 2,200 2,640 2,730 2,985 2,980 3,245 3,250 3,470 3,465 3,750 30,715
New Bond Issue 2,490 3,590 4,090 3,815 4,620 4,615 5,225 5,230 5,205 38,880
PAYG 535 830 570 1,935
Other Funding 100 105 100 105 110 115 115 115 115 120 1,100
Previous Funding
Other Previously
Approved Funds 4,700 1,490 6,190
Total Funding 7,000 6,725 6,955 7,180 7,735 7,980 8,550 8,810 8,810 9,075 78,820
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
Funding reflects a slight increase from the previous CIP.
F - 19
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WS Maintenance Capital FY 2025-2034
15. WATER/SEWER FRAMES/COVERS
Project Highlights:
• This project involves raising or lowering a casting or precast
water valve or manhole frame top from its existing elevation
to line up with the adjacent grade, pavement, curb, etc.
• Water valve and manhole frames and covers are adjusted in
conjunction with the annual street paving program.
Associated Plan(s):
Water System Master Plan
Neighborhood(s):
VARIOUS
Funding Notes: A portion of the annual funding will be from infrastructure availability fees (developer contributions).
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Developer Contributions 1,000 1,035 1,070 1,105 1,105 1,135 1,130 1,170 1,175 1,210 11,135
PAYG 5 10 5 20
Previous Funding
Total Funding 1,000 1,035 1,070 1,105 1,105 1,140 1,140 1,175 1,175 1,210 11,155
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
Funding increases to align funding with actual spending levels and
pace of the paving program.
F - 20
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WS Maintenance Capital FY 2025-2034
16. WATER-TANK REHABILITATION
Project Highlights:
• Water tanks are inspected every five years. Painting and other
maintenance work are programmed accordingly based on
results.
• The current funding schedule includes rehabilitation of Lee
underground tank.
Associated Plan(s):
Water System Master Plan
Neighborhood(s):
VARIOUS
Funding Notes: Other Previously Approved Funds includes existing PAYG balances.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
PAYG 530 690 650 830 115 115 120 3,050
Previous Funding
Other Previously
Approved Funds 100 555 655
Total Funding 100 1,085 690 650 830 115 0 115 0 120 3,705
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
No change from the previous CIP.
F - 21
Source: Arlington County website. First collected Oct 27, 2026.