WPCP Capital Sustainment Program(PDF, 1018KB)

Arlington County · Arlington County · Budget documents

Open the original document More from Arlington County

Text

Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.

Arlington County, Virginia CIP 2025 − 2034 WATER AND SEWER INFRASTRUCTURE: WPCP CAPITAL SUSTAINMENT PROGRAM 10 YEAR CATEGORY SUMMARY (in $1,000s) FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year Total 1. Activated Sludge Effluent Pump Station 1 (ASE1) 800 1,550 2,675 4,970 1,655 0 0 0 0 0 11,650 2. Asset Management System Replacement 1,000 1,035 265 0 0 0 0 0 0 0 2,300 3. Blue Plains Capital Improvements 1,210 1,705 1,825 2,775 3,010 2,605 2,130 1,455 885 1,555 19,155 4. Grit System Upgrades 300 595 1,175 635 0 0 0 0 0 0 2,705 5. Improvements to Eads St Property 0 10 0 10 0 10 0 10 0 10 50 6. Odor Control 0 0 0 550 550 0 0 0 0 0 1,100 7. Re-Gen Phase II 10,600 4,865 0 0 0 0 0 0 0 0 15,465 8. Re-Gen Phase III 17,200 58,030 62,925 50,575 21,755 0 0 0 0 0 210,485 9. Secondary Clarifiers 0 0 0 0 0 0 1,140 5,170 7,755 4,145 18,210 10. USACE Coastal Storm Resiliency 200 0 0 0 0 0 5,700 0 0 0 5,900 11. WPCP Maintenance Capital 2,000 2,070 2,140 2,210 2,210 2,280 2,280 2,350 2,350 2,420 22,310 12. WPCP Technology Enhancements 3,500 2,070 535 550 550 570 570 585 585 605 10,120 Total Recommendation 36,810 71,930 71,540 62,275 29,730 5,465 11,820 9,570 11,575 8,735 319,450 CATEGORY FUNDING SOURCES (in $1,000s) FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year Total New Funding Federal Funding 0 0 0 0 0 0 0 0 0 0 0 State Funding 0 0 0 0 0 0 0 0 0 0 0 Developer Contributions 485 665 690 715 715 735 735 865 1,950 2,010 9,565 New Bond Issue 0 1,285 2,590 12,335 19,430 0 5,675 4,290 6,435 3,440 55,480 PAYG 990 3,423 4,180 4,810 5,040 4,240 3,760 3,030 1,370 2,060 32,903 Short Term Finance 0 0 0 0 0 0 0 0 0 0 0 Stormwater Utility Fee Revenue 0 0 0 0 0 0 0 0 0 0 0 Other Funding 6,030 11,935 11,855 10,125 4,545 490 1,650 1,385 1,820 1,225 51,060 Subtotal New Funding 7,505 17,308 19,315 27,985 29,730 5,465 11,820 9,570 11,575 8,735 149,008 Previously Approved Funding Authorized but Unissued Bonds 20,740 52,205 52,225 34,290 0 0 0 0 0 0 159,460 Issued but Unspent Bonds 0 0 0 0 0 0 0 0 0 0 0 Other Previously Approved Funds 8,565 2,417 0 0 0 0 0 0 0 0 10,982 Subtotal Previously Approved Funding 29,305 54,622 52,225 34,290 0 0 0 0 0 0 170,442 Total Funding Sources 36,810 71,930 71,540 62,275 29,730 5,465 11,820 9,570 11,575 8,735 319,450 F - 30 WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan WPCP Capital Sustainment FY 2025-2034 1. ACTIVATED SLUDGE EFFLUENT PUMP STATION 1 (ASE1) Project Highlights: • The Activated Sludge Effluent #1 (ASE1) pump station project will replace all the pumping equipment, valves and piping within the station, as well as the associated electrical equipment. Additionally, other components will also be evaluated such as equipme nt and personnel access, pump station storage tanks condition, and controls equipment. Relocating the station to an adjacent area will be considered so the existing pumps can remain in service during construction, rather than using a long -term bypass pump system while the existing station is being overhauled. More efficient pumps will be specified for the upgrades, resulting in energy savings. • ASE1 continuously pumps partially treated wastewater to the filtration and disinfection treatment processes. • This facility was constructed in the 1970s and partially rehabbed in the 1990s and is due for a complete upgrade given the current condition of the infrastructure and its criticality. Associated Plan(s): WPCP Master Plan Neighborhood(s): Arlington Ridge Aurora Highlands Funding Notes: Other Funding includes Inter-Jurisdictional (IJ) revenue. Each IJ Partner's portion of the cost is based on its reserved capacity. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total New Bond Issue 1,285 1,685 4,125 1,375 8,470 PAYG 280 535 815 Other Funding 135 265 455 845 280 1,980 Previous Funding Other Previously Approved Funds 385 385 Total Funding 800 1,550 2,675 4,970 1,655 0 0 0 0 0 11,650 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • Condition Assessment Summer 2024 - Spring 2025 • Design Summer 2025 - Summer 2026 • Construction Spring 2027 - Spring 2029 Changes from Prior CIP: The project is new to the FY 2025 - 2034 CIP. . F - 31 WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan WPCP Capital Sustainment FY 2025-2034 2. ASSET MANAGEMENT SYSTEM REPLACEMENT Project Highlights: • This project implements a new asset management system which will allow better monitoring of equipment performance and maintenance of systems in a timely fashion, while at the same time determining when to replace aging equipment in a proactive manner. • The new system will include changes to asset classification, organization, and will streamline planning of maintenance activities and asset analysis. Funding Notes: Other funding includes Inter-Jurisdictional (IJ) revenue. Each IJ Partner's portion of the cost is based on its reserved capacity. Other Previously Approved Funds includes PAYG balances. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total PAYG 30 220 250 Other Funding 170 175 45 390 Previous Funding Other Previously Approved Funds 830 830 1,660 Total Funding 1,000 1,035 265 0 0 0 0 0 0 0 2,300 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Operations Costs (+/-) 200 210 221 232 243 255 268 1,629 Total Impact 0 0 0 200 210 221 232 243 255 268 1,629 Critical Milestones: • Procurement & Software Selection Fall 2022 - Fall 2024 • Implementation Spring 2025 - Spring 2027 Changes from Prior CIP: Timing of expenditures has pushed one year from the previous CIP. F - 32 WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan WPCP Capital Sustainment FY 2025-2034 3. BLUE PLAINS CAPITAL IMPROVEMENTS Project Highlights: • DC Water's Blue Plains Advanced Wastewater Treatment Plant processes a portion of Arlington County's sewage after transmission through Fairfax County mains. • Arlington's share of funds is based on the County's reserved capacity and supports Blue Plains capital improvements and improvements to the associated sewage conveyance system. Funding Notes: Other Previously Approved Funds include existing PAYG balances. Blue Plains Advanced Water Treatment Plant is owned by DC Water. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total PAYG 710 1,705 1,825 2,775 3,010 2,605 2,130 1,455 885 1,555 18,655 Previous Funding Other Previously Approved Funds 500 500 Total Funding 1,210 1,705 1,825 2,775 3,010 2,605 2,130 1,455 885 1,555 19,155 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Changes from Prior CIP: The current CIP reflects Arlington County's share (based on reserved capacity) of the current complement of projects anticipated to be undertaken by DC Water at the Blue Plains treatment facility. F - 33 WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan WPCP Capital Sustainment FY 2025-2034 4. GRIT SYSTEM UPGRADES Project Highlights: • This project will evaluate and rehabilitate/ improve the grit collection and disposal system in the Preliminary Treatment Building to improve removal of the abrasive material and protect downstream equipment. • Preliminary engineering, initiated in FY 2024, will study the condition of the grit collection tanks, piping, classifiers, and other related equipment. Detailed design and construction will follow. Associated Plan(s): Community Energy Plan Neighborhood(s): Arlington Ridge Aurora Highlands Funding Notes: Other funding includes Inter-Jurisdictional (IJ) revenue. Each IJ partner's portion of the cost is based on its reserved capacity. Other previously approved funds include existing PAYG balance. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total New Bond Issue 905 525 1,430 PAYG 18 70 88 Other Funding 50 100 200 110 460 Previous Funding Other Previously Approved Funds 250 477 727 Total Funding 300 595 1,175 635 0 0 0 0 0 0 2,705 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • Grit System - Condition Assessment Winter 2024 (3Q FY2024) - Fall 2024 • Grit System Upgrades - Design Fall 2024 - Fall 2025 • Grit System Upgrades - Construction Spring 2026 - Summer 2028 Changes from Prior CIP: The project name (previously Primary Clarifiers Upgrades) and scope has changed to better reflect the planned improvements. The scope will focus on rehabilitating the grit removal process to improve removal of the abrasive material and protect downstream e quipment. F - 34 WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan WPCP Capital Sustainment FY 2025-2034 5. IMPROVEMENTS TO EADS ST PROPERTY Project Highlights: • The Eads Street property serves as the WPCP's off -site warehouse and is used for storage of larger and less frequently used items. Additionally, Arlington Transit (ART) has some offices within the facility, as well as partial use of the warehouse. • Maintenance capital and capital improvements (HVAC upgrades, roof replacements, etc.) are addressed under this project. Associated Plan(s): WPCP Master Plan Neighborhood(s): Arlington Ridge Aurora Highlands Funding Notes: Both Transit Bureau and IJ Partner contributions are included in 'Other Funding'. The Inter-Jurisdictional (IJ) Partners share in a portion of the capital costs at the facility. The Transit Bureau also contributes a prorate share of applicable ca pital costs at the Eads Street facility, consistent with its share of the space used there and the terms of the MOU. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total PAYG 5 5 5 5 5 25 Other Funding 5 5 5 5 5 25 Previous Funding Total Funding 0 10 0 10 0 10 0 10 0 10 50 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Changes from Prior CIP: No change from the previous CIP. F - 35 WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan WPCP Capital Sustainment FY 2025-2034 6. ODOR CONTROL Project Highlights: • Due to the location of the WPCP, it is necessary to tightly control and limit odors by collecting and treating odorous air. • The Preliminary Treatment Building ventilation and odor control improvements were constructed in FY 2022 - FY 2024 in conjunction with Re -Gen Phase I. Additional odor control needs will be assessed in future years. Associated Plan(s): WPCP Master Plan Neighborhood(s): Arlington Ridge Aurora Highlands Funding Notes: Other funding includes Inter-Jurisdictional (IJ) Partners revenue. Each partner's portion of the cost is based on its reserved capacity. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total PAYG 455 455 910 Other Funding 95 95 190 Previous Funding Total Funding 0 0 0 550 550 0 0 0 0 0 1,100 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • Study with recommendations for system Winter 2028 (3Q FY 2028) Winter 2029 (3Q FY 2029) Changes from Prior CIP: No change from the previous CIP. F - 36 WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan WPCP Capital Sustainment FY 2025-2034 7. RE-GEN PHASE II Project Highlights: • Re-Gen focuses on upgrades to the WPCP's solids treatment facilities to provide long -term resource recovery and prioritize safe and sustainable operations that provide quality end products for use in our community. The program was broken into three phases for implementation over a number of years. Phase I was completed in 2024. • Re-Gen Phase II includes projects that need to be completed in advance of Phase III. This may involve additional equipment replacement or demolition of unused facilities in preparation for the Phase III construction. • Funds will be used to demolish existing unused facilities and relocate in -service process piping in advance of Phase III upgrades. Associated Plan(s): Community Energy Plan WPCP Master Plan Neighborhood(s): Arlington Ridge Aurora Highlands Funding Notes: Other funding includes Inter-Jurisdictional (IJ) revenue. Each IJ Partner's portion of the cost is based on its reserved capacity. Other Previously Approved Funds include existing PAYG balances. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Other Funding 1,800 825 2,625 Previous Funding Authorized but Unissued Bonds 7,145 4,040 11,185 Other Previously Approved Funds 1,655 1,655 Total Funding 10,600 4,865 0 0 0 0 0 0 0 0 15,465 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • Design & Construction Spring 2023 - Fall 2025 Changes from Prior CIP: Timing of expenditures has pushed out one year from the previous CIP. Project Links: • https://www.arlingtonva.us/Government/Projects/Proje ct-Types/Uncategorised/Water-Pollution-Control- Plant-Solids-Master-Plan • https://arlingtonregen.com/ F - 37 WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan WPCP Capital Sustainment FY 2025-2034 8. RE-GEN PHASE III Project Highlights: • Re-Gen focuses on upgrades to the WPCP's solids treatment facilities to provide long -term resource recovery and prioritize safe and sustainable operations that provide quality end products for use in our community. The program was broken into three phases for implementation over a number of years. Phase I was completed in 2024. • Re-Gen Phase III includes implementation of Thermal Hydrolysis Pretreatment followed by Anaerobic Digestion (THP/AD), as well as replacing or upgrading the remaining solids handling equipment, as recommended in the Solids Master Plan. This will result in a higher quality biosolids product suitable for gardens, forests, farms, and lawns. • Methane from the digestion process will be used to produce renewable natural gas (RNG). Gas handling facilities will be constructed to optimize the utilization of the RNG. • The scope also includes rehabbing the existing gravity thickeners to renew their service life. Associated Plan(s): Community Energy Plan WPCP Master Plan Neighborhood(s): Arlington Ridge Aurora Highlands Project Links: • https://www.arlingtonva.us/Government/Projects/Project- Types/Uncategorised/Water-Pollution-Control-Plant-Solids- Master-Plan • https://arlingtonregen.com/ Funding Notes: Other funding includes Inter-Jurisdictional (IJ) revenue. Each IJ Partner's portion of the cost is based on its reserved capacity. Other Previously Approved Funds include existing PAYG balances. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total New Bond Issue 7,685 18,055 25,740 Other Funding 2,925 9,865 10,700 8,600 3,700 35,790 Previous Funding Authorized but Unissued Bonds 13,595 48,165 52,225 34,290 148,275 Other Previously Approved Funds 680 680 Total Funding 17,200 58,030 62,925 50,575 21,755 0 0 0 0 0 210,485 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Anticipated FTEs (+/-) 2 2 2 2 8 Personnel ($) 230 460 750 1,030 1,082 1,136 1,192 1,252 1,315 8,447 Total Impact 0 232 462 752 1,030 1,082 1,136 1,192 1,252 1,315 8,447 Critical Milestones: • Design & Construction Winter 2024 (3Q FY2024) – Spring 2029 Changes from Prior CIP: Funding has increased based on current design efforts and reflects cost growth in commodities affecting Re-Gen. Program has been delayed approximately one year. F - 38 WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan WPCP Capital Sustainment FY 2025-2034 9. SECONDARY CLARIFIERS Project Highlights: • Rehabilitation and/or replacement of three secondary clarifiers, originally built in the 1960s, will restore the tanks to full working condition. • The timeline for this project has been pushed out due to existing adequate capacity within the six available secondary clarifiers with respect to current plant flows. Associated Plan(s): WPCP Master Plan Neighborhood(s): Arlington Ridge Aurora Highlands Funding Notes: Other funding includes Inter-Jurisdictional (IJ) revenue. Each IJ Partner's portion of the cost is based on its reserved capacity. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total New Bond Issue 945 4,290 6,435 3,440 15,110 Other Funding 195 880 1,320 705 3,100 Previous Funding Total Funding 0 0 0 0 0 0 1,140 5,170 7,755 4,145 18,210 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Changes from Prior CIP: Timing of expenditures: nine years later than the previous CIP. F - 39 WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan WPCP Capital Sustainment FY 2025-2034 10. USACE COASTAL STORM RESILIENCY Project Highlights: • The U.S. Army Corps of Engineers (USACE) is conducting a study to reduce long- term coastal flood risk to vulnerable populations, properties, infrastructure, and environmental and cultural resources in Northern Virginia within the Middle Potomac River watershed. • The project will study a potential floodwall that would be constructed along the northern bank of Four Mile Run between the Four Mile Run bike trail and the WPCP. Funding Notes: Other funding includes Inter-Jurisdictional (IJ) revenue. Each IJ Partner's portion of the cost is based on its reserved capacity. Other previously approved funds include existing PAYG balances. Future assets in this program may be owned by the County or the USACE. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total New Bond Issue 4,730 4,730 Other Funding 15 970 985 Previous Funding Other Previously Approved Funds 185 185 Total Funding 200 0 0 0 0 0 5,700 0 0 0 5,900 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Changes from Prior CIP: The project is new to the FY 2025 – FY 2034 CIP. F - 40 WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan WPCP Capital Sustainment FY 2025-2034 11. WPCP MAINTENANCE CAPITAL Project Highlights: • Funding covers a wide variety of one -to-one capital replacements and capital maintenance associated with the Water Pollution Control Plant's assets, including items such as HVAC overhauls, major equipment rehabilitation or replacements, and capital repairs to process structures such as tanks or pipes. Associated Plan(s): Community Energy Plan Neighborhood(s): Arlington Ridge Aurora Highlands Funding Notes: A portion of the annual funding will be from infrastructure availability fees (developer contributions). Other funding includes Inter -Jurisdictional (IJ) revenue. Each IJ Partner's portion of the cost is based on its reserved capacity. Other previously approved funds include existing PAYG balances. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Developer Contributions 485 665 690 715 715 735 735 865 1,950 2,010 9,565 PAYG 540 1,085 1,120 1,120 1,155 1,155 1,085 7,260 Other Funding 340 350 365 375 375 390 390 400 400 410 3,795 Previous Funding Other Previously Approved Funds 1,175 515 1,690 Total Funding 2,000 2,070 2,140 2,210 2,210 2,280 2,280 2,350 2,350 2,420 22,310 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Changes from Prior CIP: No significant change from the previous CIP. F - 41 WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan WPCP Capital Sustainment FY 2025-2034 12. WPCP TECHNOLOGY ENHANCEMENTS Project Highlights: • This program includes a comprehensive suite of projects to address needed upgrades to the WPCP's Process Control System (PCS) and associated technology infrastructure. • Technology upgrades are necessary to prevent failures, improve reliability, and protect the Water Pollution Control Plant from potential cyber-security threats. Neighborhood(s): VARIOUS Funding Notes: Other funding includes Inter-Jurisdictional (IJ) revenue. Each IJ Partner's portion of the cost is based on its reserved capacity. Other previously approved funds include existing PAYG balances. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total PAYG 1,125 445 455 455 475 475 485 485 500 4,900 Other Funding 595 350 90 95 95 95 95 100 100 105 1,720 Previous Funding Other Previously Approved Funds 2,905 595 3,500 Total Funding 3,500 2,070 535 550 550 570 570 585 585 605 10,120 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Changes from Prior CIP: FY 2025 and FY 2026 expenditures reflect an increase due to current priorities. F - 42

Source: Arlington County website. First collected Oct 27, 2026.