Arlington County, Virginia CIP
2025 − 2034
WATER AND SEWER INFRASTRUCTURE: WPCP CAPITAL
SUSTAINMENT PROGRAM
10 YEAR CATEGORY SUMMARY (in $1,000s)
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year
Total
1. Activated Sludge Effluent
Pump Station 1 (ASE1)
800 1,550 2,675 4,970 1,655 0 0 0 0 0 11,650
2. Asset Management System
Replacement
1,000 1,035 265 0 0 0 0 0 0 0 2,300
3. Blue Plains Capital
Improvements
1,210 1,705 1,825 2,775 3,010 2,605 2,130 1,455 885 1,555 19,155
4. Grit System Upgrades 300 595 1,175 635 0 0 0 0 0 0 2,705
5. Improvements to Eads St
Property
0 10 0 10 0 10 0 10 0 10 50
6. Odor Control 0 0 0 550 550 0 0 0 0 0 1,100
7. Re-Gen Phase II 10,600 4,865 0 0 0 0 0 0 0 0 15,465
8. Re-Gen Phase III 17,200 58,030 62,925 50,575 21,755 0 0 0 0 0 210,485
9. Secondary Clarifiers 0 0 0 0 0 0 1,140 5,170 7,755 4,145 18,210
10. USACE Coastal Storm
Resiliency
200 0 0 0 0 0 5,700 0 0 0 5,900
11. WPCP Maintenance Capital 2,000 2,070 2,140 2,210 2,210 2,280 2,280 2,350 2,350 2,420 22,310
12. WPCP Technology
Enhancements
3,500 2,070 535 550 550 570 570 585 585 605 10,120
Total Recommendation 36,810 71,930 71,540 62,275 29,730 5,465 11,820 9,570 11,575 8,735 319,450
CATEGORY FUNDING SOURCES (in $1,000s)
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year
Total
New Funding
Federal Funding 0 0 0 0 0 0 0 0 0 0 0
State Funding 0 0 0 0 0 0 0 0 0 0 0
Developer Contributions 485 665 690 715 715 735 735 865 1,950 2,010 9,565
New Bond Issue 0 1,285 2,590 12,335 19,430 0 5,675 4,290 6,435 3,440 55,480
PAYG 990 3,423 4,180 4,810 5,040 4,240 3,760 3,030 1,370 2,060 32,903
Short Term Finance 0 0 0 0 0 0 0 0 0 0 0
Stormwater Utility Fee Revenue 0 0 0 0 0 0 0 0 0 0 0
Other Funding 6,030 11,935 11,855 10,125 4,545 490 1,650 1,385 1,820 1,225 51,060
Subtotal New Funding 7,505 17,308 19,315 27,985 29,730 5,465 11,820 9,570 11,575 8,735 149,008
Previously Approved Funding
Authorized but Unissued
Bonds 20,740 52,205 52,225 34,290 0 0 0 0 0 0 159,460
Issued but Unspent Bonds 0 0 0 0 0 0 0 0 0 0 0
Other Previously Approved
Funds 8,565 2,417 0 0 0 0 0 0 0 0 10,982
Subtotal Previously Approved
Funding 29,305 54,622 52,225 34,290 0 0 0 0 0 0 170,442
Total Funding Sources 36,810 71,930 71,540 62,275 29,730 5,465 11,820 9,570 11,575 8,735 319,450
F - 30
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WPCP Capital Sustainment FY 2025-2034
1. ACTIVATED SLUDGE EFFLUENT PUMP STATION 1 (ASE1)
Project Highlights:
• The Activated Sludge Effluent #1 (ASE1) pump station
project will replace all the pumping equipment, valves and
piping within the station, as well as the associated electrical
equipment. Additionally, other components will also be
evaluated such as equipme nt and personnel access, pump
station storage tanks condition, and controls equipment.
Relocating the station to an adjacent area will be considered
so the existing pumps can remain in service during
construction, rather than using a long -term bypass pump
system while the existing station is being overhauled. More
efficient pumps will be specified for the upgrades, resulting
in energy savings.
• ASE1 continuously pumps partially treated wastewater to the
filtration and disinfection treatment processes.
• This facility was constructed in the 1970s and partially
rehabbed in the 1990s and is due for a complete upgrade
given the current condition of the infrastructure and its
criticality.
Associated Plan(s):
WPCP Master Plan
Neighborhood(s):
Arlington Ridge
Aurora Highlands
Funding Notes: Other Funding includes Inter-Jurisdictional (IJ) revenue. Each IJ Partner's portion of the cost is based on its reserved
capacity.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
New Bond Issue 1,285 1,685 4,125 1,375 8,470
PAYG 280 535 815
Other Funding 135 265 455 845 280 1,980
Previous Funding
Other Previously
Approved Funds 385 385
Total Funding 800 1,550 2,675 4,970 1,655 0 0 0 0 0 11,650
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Condition Assessment Summer 2024 - Spring 2025
• Design Summer 2025 - Summer
2026
• Construction Spring 2027 - Spring 2029
Changes from Prior CIP:
The project is new to the FY 2025 - 2034 CIP.
.
F - 31
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WPCP Capital Sustainment FY 2025-2034
2. ASSET MANAGEMENT SYSTEM REPLACEMENT
Project Highlights:
• This project implements a new asset management system
which will allow better monitoring of equipment
performance and maintenance of systems in a timely fashion,
while at the same time determining when to replace aging
equipment in a proactive manner.
• The new system will include changes to asset classification,
organization, and will streamline planning of maintenance
activities and asset analysis.
Funding Notes: Other funding includes Inter-Jurisdictional (IJ) revenue. Each IJ Partner's portion of the cost is based on its reserved
capacity. Other Previously Approved Funds includes PAYG balances.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
PAYG 30 220 250
Other Funding 170 175 45 390
Previous Funding
Other Previously
Approved Funds 830 830 1,660
Total Funding 1,000 1,035 265 0 0 0 0 0 0 0 2,300
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Operations Costs (+/-) 200 210 221 232 243 255 268 1,629
Total Impact 0 0 0 200 210 221 232 243 255 268 1,629
Critical Milestones:
• Procurement & Software Selection Fall 2022 - Fall 2024
• Implementation Spring 2025 - Spring 2027
Changes from Prior CIP:
Timing of expenditures has pushed one year from the previous CIP.
F - 32
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WPCP Capital Sustainment FY 2025-2034
3. BLUE PLAINS CAPITAL IMPROVEMENTS
Project Highlights:
• DC Water's Blue Plains Advanced Wastewater Treatment
Plant processes a portion of Arlington County's sewage after
transmission through Fairfax County mains.
• Arlington's share of funds is based on the County's reserved
capacity and supports Blue Plains capital improvements and
improvements to the associated sewage conveyance system.
Funding Notes: Other Previously Approved Funds include existing PAYG balances. Blue Plains Advanced Water Treatment Plant is
owned by DC Water.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
PAYG 710 1,705 1,825 2,775 3,010 2,605 2,130 1,455 885 1,555 18,655
Previous Funding
Other Previously
Approved Funds 500 500
Total Funding 1,210 1,705 1,825 2,775 3,010 2,605 2,130 1,455 885 1,555 19,155
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
The current CIP reflects Arlington County's share (based on
reserved capacity) of the current complement of projects
anticipated to be undertaken by DC Water at the Blue Plains
treatment facility.
F - 33
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WPCP Capital Sustainment FY 2025-2034
4. GRIT SYSTEM UPGRADES
Project Highlights:
• This project will evaluate and rehabilitate/ improve the grit
collection and disposal system in the Preliminary Treatment
Building to improve removal of the abrasive material and
protect downstream equipment.
• Preliminary engineering, initiated in FY 2024, will study the
condition of the grit collection tanks, piping, classifiers, and
other related equipment. Detailed design and construction
will follow.
Associated Plan(s):
Community Energy Plan
Neighborhood(s):
Arlington Ridge
Aurora Highlands
Funding Notes: Other funding includes Inter-Jurisdictional (IJ) revenue. Each IJ partner's portion of the cost is based on its reserved
capacity. Other previously approved funds include existing PAYG balance.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
New Bond Issue 905 525 1,430
PAYG 18 70 88
Other Funding 50 100 200 110 460
Previous Funding
Other Previously
Approved Funds 250 477 727
Total Funding 300 595 1,175 635 0 0 0 0 0 0 2,705
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Grit System - Condition Assessment Winter 2024 (3Q FY2024) - Fall 2024
• Grit System Upgrades - Design Fall 2024 - Fall 2025
• Grit System Upgrades - Construction Spring 2026 - Summer 2028
Changes from Prior CIP:
The project name (previously Primary Clarifiers Upgrades) and scope has changed to better
reflect the planned improvements. The scope will focus on rehabilitating the grit removal
process to improve removal of the abrasive material and protect downstream e quipment.
F - 34
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WPCP Capital Sustainment FY 2025-2034
5. IMPROVEMENTS TO EADS ST PROPERTY
Project Highlights:
• The Eads Street property serves as the WPCP's off -site
warehouse and is used for storage of larger and less
frequently used items. Additionally, Arlington Transit (ART)
has some offices within the facility, as well as partial use of
the warehouse.
• Maintenance capital and capital improvements (HVAC
upgrades, roof replacements, etc.) are addressed under this
project.
Associated Plan(s):
WPCP Master Plan
Neighborhood(s):
Arlington Ridge
Aurora Highlands
Funding Notes: Both Transit Bureau and IJ Partner contributions are included in 'Other Funding'. The Inter-Jurisdictional (IJ) Partners
share in a portion of the capital costs at the facility. The Transit Bureau also contributes a prorate share of applicable ca pital costs at
the Eads Street facility, consistent with its share of the space used there and the terms of the MOU.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
PAYG 5 5 5 5 5 25
Other Funding 5 5 5 5 5 25
Previous Funding
Total Funding 0 10 0 10 0 10 0 10 0 10 50
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
No change from the previous CIP.
F - 35
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WPCP Capital Sustainment FY 2025-2034
6. ODOR CONTROL
Project Highlights:
• Due to the location of the WPCP, it is necessary to tightly
control and limit odors by collecting and treating odorous air.
• The Preliminary Treatment Building ventilation and odor
control improvements were constructed in
FY 2022 - FY 2024 in conjunction with Re -Gen Phase I.
Additional odor control needs will be assessed in future
years.
Associated Plan(s):
WPCP Master Plan
Neighborhood(s):
Arlington Ridge
Aurora Highlands
Funding Notes: Other funding includes Inter-Jurisdictional (IJ) Partners revenue. Each partner's portion of the cost is based on its
reserved capacity.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
PAYG 455 455 910
Other Funding 95 95 190
Previous Funding
Total Funding 0 0 0 550 550 0 0 0 0 0 1,100
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Study with recommendations for system Winter 2028 (3Q FY 2028)
Winter 2029 (3Q FY 2029)
Changes from Prior CIP:
No change from the previous CIP.
F - 36
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WPCP Capital Sustainment FY 2025-2034
7. RE-GEN PHASE II
Project Highlights:
• Re-Gen focuses on upgrades to the WPCP's solids treatment
facilities to provide long -term resource recovery and
prioritize safe and sustainable operations that provide quality
end products for use in our community. The program was
broken into three phases for implementation over a number
of years. Phase I was completed in 2024.
• Re-Gen Phase II includes projects that need to be completed
in advance of Phase III. This may involve additional
equipment replacement or demolition of unused facilities in
preparation for the Phase III construction.
• Funds will be used to demolish existing unused facilities and
relocate in -service process piping in advance of Phase III
upgrades.
Associated Plan(s):
Community Energy Plan
WPCP Master Plan
Neighborhood(s):
Arlington Ridge
Aurora Highlands
Funding Notes: Other funding includes Inter-Jurisdictional (IJ) revenue. Each IJ Partner's portion of the cost is based on its reserved
capacity. Other Previously Approved Funds include existing PAYG balances.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Other Funding 1,800 825 2,625
Previous Funding
Authorized but Unissued
Bonds 7,145 4,040 11,185
Other Previously
Approved Funds 1,655 1,655
Total Funding 10,600 4,865 0 0 0 0 0 0 0 0 15,465
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Design & Construction Spring 2023 - Fall 2025
Changes from Prior CIP:
Timing of expenditures has pushed out one year from the previous CIP.
Project Links:
• https://www.arlingtonva.us/Government/Projects/Proje
ct-Types/Uncategorised/Water-Pollution-Control-
Plant-Solids-Master-Plan
• https://arlingtonregen.com/
F - 37
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WPCP Capital Sustainment FY 2025-2034
8. RE-GEN PHASE III
Project Highlights:
• Re-Gen focuses on upgrades to the WPCP's solids treatment
facilities to provide long -term resource recovery and
prioritize safe and sustainable operations that provide quality
end products for use in our community. The program was
broken into three phases for implementation over a number
of years. Phase I was completed in 2024.
• Re-Gen Phase III includes implementation of Thermal
Hydrolysis Pretreatment followed by Anaerobic Digestion
(THP/AD), as well as replacing or upgrading the remaining
solids handling equipment, as recommended in the Solids
Master Plan. This will result in a higher quality biosolids
product suitable for gardens, forests, farms, and lawns.
• Methane from the digestion process will be used to produce
renewable natural gas (RNG). Gas handling facilities will be
constructed to optimize the utilization of the RNG.
• The scope also includes rehabbing the existing gravity
thickeners to renew their service life.
Associated Plan(s):
Community Energy Plan
WPCP Master Plan
Neighborhood(s):
Arlington Ridge
Aurora Highlands
Project Links:
• https://www.arlingtonva.us/Government/Projects/Project-
Types/Uncategorised/Water-Pollution-Control-Plant-Solids-
Master-Plan
• https://arlingtonregen.com/
Funding Notes: Other funding includes Inter-Jurisdictional (IJ) revenue. Each IJ Partner's portion of the cost is based on its reserved
capacity. Other Previously Approved Funds include existing PAYG balances.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
New Bond Issue 7,685 18,055 25,740
Other Funding 2,925 9,865 10,700 8,600 3,700 35,790
Previous Funding
Authorized but Unissued
Bonds 13,595 48,165 52,225 34,290 148,275
Other Previously
Approved Funds 680 680
Total Funding 17,200 58,030 62,925 50,575 21,755 0 0 0 0 0 210,485
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Anticipated FTEs (+/-) 2 2 2 2 8
Personnel ($) 230 460 750 1,030 1,082 1,136 1,192 1,252 1,315 8,447
Total Impact 0 232 462 752 1,030 1,082 1,136 1,192 1,252 1,315 8,447
Critical Milestones:
• Design & Construction Winter 2024 (3Q FY2024) – Spring 2029
Changes from Prior CIP:
Funding has increased based on current design efforts
and reflects cost growth in commodities affecting
Re-Gen. Program has been delayed approximately
one year.
F - 38
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WPCP Capital Sustainment FY 2025-2034
9. SECONDARY CLARIFIERS
Project Highlights:
• Rehabilitation and/or replacement of three secondary
clarifiers, originally built in the 1960s, will restore the tanks
to full working condition.
• The timeline for this project has been pushed out due to
existing adequate capacity within the six available secondary
clarifiers with respect to current plant flows.
Associated Plan(s):
WPCP Master Plan
Neighborhood(s):
Arlington Ridge
Aurora Highlands
Funding Notes: Other funding includes Inter-Jurisdictional (IJ) revenue. Each IJ Partner's portion of the cost is based on its reserved
capacity.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
New Bond Issue 945 4,290 6,435 3,440 15,110
Other Funding 195 880 1,320 705 3,100
Previous Funding
Total Funding 0 0 0 0 0 0 1,140 5,170 7,755 4,145 18,210
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
Timing of expenditures: nine years later than the previous CIP.
F - 39
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WPCP Capital Sustainment FY 2025-2034
10. USACE COASTAL STORM RESILIENCY
Project Highlights:
• The U.S. Army Corps of Engineers (USACE) is conducting
a study to reduce long- term coastal flood risk to vulnerable
populations, properties, infrastructure, and environmental
and cultural resources in Northern Virginia within the Middle
Potomac River watershed.
• The project will study a potential floodwall that would be
constructed along the northern bank of Four Mile Run
between the Four Mile Run bike trail and the WPCP.
Funding Notes: Other funding includes Inter-Jurisdictional (IJ) revenue. Each IJ Partner's portion of the cost is based on its reserved
capacity. Other previously approved funds include existing PAYG balances. Future assets in this program may be owned by the County
or the USACE.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
New Bond Issue 4,730 4,730
Other Funding 15 970 985
Previous Funding
Other Previously
Approved Funds 185 185
Total Funding 200 0 0 0 0 0 5,700 0 0 0 5,900
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
The project is new to the FY 2025 – FY 2034 CIP.
F - 40
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WPCP Capital Sustainment FY 2025-2034
11. WPCP MAINTENANCE CAPITAL
Project Highlights:
• Funding covers a wide variety of one -to-one capital
replacements and capital maintenance associated with the
Water Pollution Control Plant's assets, including items such
as HVAC overhauls, major equipment rehabilitation or
replacements, and capital repairs to process structures such
as tanks or pipes.
Associated Plan(s):
Community Energy Plan
Neighborhood(s):
Arlington Ridge
Aurora Highlands
Funding Notes: A portion of the annual funding will be from infrastructure availability fees (developer contributions). Other funding
includes Inter -Jurisdictional (IJ) revenue. Each IJ Partner's portion of the cost is based on its reserved capacity. Other previously
approved funds include existing PAYG balances.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Developer Contributions 485 665 690 715 715 735 735 865 1,950 2,010 9,565
PAYG 540 1,085 1,120 1,120 1,155 1,155 1,085 7,260
Other Funding 340 350 365 375 375 390 390 400 400 410 3,795
Previous Funding
Other Previously
Approved Funds 1,175 515 1,690
Total Funding 2,000 2,070 2,140 2,210 2,210 2,280 2,280 2,350 2,350 2,420 22,310
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
No significant change from the previous CIP.
F - 41
WATER AND SEWER INFRASTRUCTURE Capital Improvement Plan
WPCP Capital Sustainment FY 2025-2034
12. WPCP TECHNOLOGY ENHANCEMENTS
Project Highlights:
• This program includes a comprehensive suite of projects to
address needed upgrades to the WPCP's Process Control
System (PCS) and associated technology infrastructure.
• Technology upgrades are necessary to prevent failures,
improve reliability, and protect the Water Pollution Control
Plant from potential cyber-security threats.
Neighborhood(s):
VARIOUS
Funding Notes: Other funding includes Inter-Jurisdictional (IJ) revenue. Each IJ Partner's portion of the cost is based on its reserved
capacity. Other previously approved funds include existing PAYG balances.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
PAYG 1,125 445 455 455 475 475 485 485 500 4,900
Other Funding 595 350 90 95 95 95 95 100 100 105 1,720
Previous Funding
Other Previously
Approved Funds 2,905 595 3,500
Total Funding 3,500 2,070 535 550 550 570 570 585 585 605 10,120
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
FY 2025 and FY 2026 expenditures reflect an increase due to
current priorities.
F - 42