Adopted FY 2022 – FY 2024 CIP(PDF, 19MB)
Arlington County · Arlington County · Budget documents
Open the original document More from Arlington County
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
COUNTY BOARD
MATT DE FERRANTI
CHAIR
KATIE CRISTOL
VICE CHAIR
CHRISTIAN DORSEY
LIBBY GARVEY
TAKIS KARANTONIS
COUNTY MANAGER’S OFFICE
MARK SCHWARTZ
COUNTY MANAGER
Table of Contents
INTROD
UCTION ............................................................................................................... 1
GUIDE T
O READING THE CIP ............................................................................................ 7
BUDGET
CALENDAR ........................................................................................................ 8
A. OVERVI
EW
Financi
al & Debt Management Policies ............................................................... A-1
Bonds Authorized but Unissued .......................................................................... A-8
Bond Referenda History ..................................................................................... A-9
Board Report – Adopted FY 2022 – 2024 CIP .................................................... A-18
Board Report – 2021 Bond Referenda .............................................................. A- 24
Projects Underway ............................................................................................ A- 38
B. CAPI
TAL FUNDING
CIP Pro
gram Cost Summary................................................................................. B-1
CIP Program Funding Source Summary ............................................................... B-2
Debt Capacity Analysis ........................................................................................ B-3
Debt Ratio Analysis Chart .................................................................................... B-5
Tax-Supported Debt Service to General Fund Expenditures Graph ...................... B-6
County General Obligation Bond Debt other Financings to Market Value Chart ... B-7
County General Obligation Bond Debt other Financings to Market
Value Graph ......................................................................................................... B-8
Tax Supported General Obligation Bond Debt to Income .................................... B-9
C. GENERAL
GOVERNMENT
1. REGION
AL PARTNERSHIPS
Regional Partnerships ................................................................................. C-1
2. LOCAL PA
RKS AND RECREATION PROGRAMS
Program Summary ..................................................................................... C-7
Maintenance Capital .................................................................................. C-9
Alcova Heights Park Phase 2 ........................................................... C10
Bluemont Park Tennis Complex Replacement .............................. C-12
Greenbrier Park Track Replacement.............................................. C-17
Par
k Master Plans ..................................................................................... C- 20
Arlington Boathouse ...................................................................... C21
Crystal City Parks and Public Space ............................................... C- 23
Parks Land Acquisition and Open Space ................................................... C- 25
Synthetic Turf ........................................................................................... C-2 7
TJ Upper Field Conversion ............................................................. C-31
Trail Modernization ..................................................................................C-33
3. COMMUNITY CONSERVATION PROGRAMS
Program Summary.................................................................................... C- 37
Neighborhood Conservation..................................................................... C- 39
4. P
UBLIC / GOVERNMENT FACILITIES
Program Summary.................................................................................... C- 41
Design and Construction Summary ........................................................... C- 44
Courthouse Complex Renovations & Infrastructure ...................... C-44
Courts/Police Building Improvements ........................................... C-4 5
Quincy Site Design ........................................................................ C-5 2
Facilities Maintenance Summary ..............................................................C-5 3
D. INFORMATION TECHNOLOGY/EQUIPMENT PROGRAMS
Program Summary ........................................................................................... D-1
Enterprise Information Technology .................................................................. D-5
Audio/Visual Equipment for Conference Rooms ......................................... D-6
Human Resources and Financial System Replacement.............................. D- 10
Network Equipment, Worker Mobility, Power Systems ............................ D- 11
PC Replacement ....................................................................................... D- 12
Information Technology/Other Equipment ................................................. D-17
Fire................................................................................................................. D- 22
Police ............................................................................................................. D- 26
Public Safety Communications and Emergency Mgmt. .................................. D- 29
Sheriff ........................................................................................................... D- 32
E. METRO AND TRANSPORTATION
1. M
ETRO
Program Summary.......................................................................................E-1
Metro ..........................................................................................................E-2
2. T
RANSPORTATION INITIATIVES
Program Summary.......................................................................................E-3
Transit Program ...........................................................................................E-9
ART Facilities .................................................................................. E- 11
Ballston-MU Metrorail Station West Entrance ............................... E-15
Crystal City Metro Station East Entrance ........................................ E-20
Pentagon City Metro Station Second Entrance ............................... E-21
PrTN: Columbia Pike Transit Stations ............................................. E- 22
Complete Streets ....................................................................................... E- 31
Army Navy Drive Complete Street .................................................. E- 32
Bridge Renovation/Replacement ................................................... E- 35
Columbia Pike Streets .................................................................... E- 37
Street Safety Improvements Program ............................................ E- 49
Maintenance Capital ................................................................................. E- 53
Bridge maintenance ...................................................................... E- 54
Paving ............................................................................................ E- 57
F. UTILITIES AND STORMWATER MANAGEMENT
1. UTILITIES
Program Summary....................................................................................... F-1
Sanitary Sewer System Improvements......................................................... F-5
Water Distribution ...................................................................................... F-7
WPCP Non-Expansion ............................................................................... F- 12
Solids Master Plan Phase I – Biosolids ............................................ F- 20
Solids Master Plan Phases II ........................................................... F- 21
Solids Master Plan Phases III .......................................................... F- 22
Maintenance Capital ................................................................................. F- 23
Washington Aqueduct Capital ........................................................ F- 27
2. STORMWATER MANAGEMENT
Program Summary..................................................................................... F- 33
Maintenance Capital ................................................................................. F- 38
Storm Drainage Improvements.................................................................. F- 44
Cardinal Elementary School Stormwater Detention ....................... F-46
Spout Run Watershed Capacity Improvements .............................. F-50
Streams and Water Quality ....................................................................... F- 52
Ballston Pond Watershed Retrofit .................................................. F- 53
G. Arlington Public Schools FY 2022-2024 Capital Improvement Plan
require that a project has an estimated useful life of at least ten years or more. However, they differ in scale and scope
of projects they typically fu nd. Bond funds are usually reserved for the big -ticket items such as new construction or
major renovations or alterations, while PAYG funds smaller scale renovations or maintenance type projects. In general,
capital projects in the CIP:
• Have a total project cost in excess of $100,000.
• Range from construction of new buildings to renovations, additions, or conversions, or demolition of
existing facilities.
• Have a minimum useful life of 10 years, significantly extend the useful life of an asset, or signi ficantly
alter the nature and character of an asset (i.e. not to include annual asset maintenance costs, annual
warranty cost or other ongoing costs).
The CIP has also traditionally been the vehicle by which planning for technology capital investments occurs. In general,
technology capital projects in the CIP:
• Have an estimated cost in excess of $25,000 and /or require six months or 1,000 hours for
implementation or completion.
• Include applications systems, network design and implementation, telecommunications infrastructure,
enterprise hardware and software s ystems, web design and implementation services, document
imaging, data base design and development, consulting services (business process studies,
requirements analysis or other studies), and technology associated with new construction and/or
renovation and relocation projects.
• Have a minimum useful life of three years, significantly extend the useful life of an asset (i.e. not to
include annual software and hardware maintenance and upgrade costs, warranty costs or other
ongoing costs), provide a significant enhancement to functionality, or represent a change of platform
or underlying structure.
C. CIP Development Process
Capital projects originate from a variety of sources. County Board appointed commissions, advisory groups, and task
forces typically advise the Board or develop long-term plans that recommend certain types of improvements. In some
cases, individual residents request improvements to their streets, playgrounds or other County facilities. Neighborhood
associations and business groups may also suggest projects and work with County staff on projects. Some projects are
initiated by staff based on adopted County master plans, such as the Transportation Master Plan or the Storm Water
Master Plan.
Projects typically come forward through the sponsoring department that is responsible for their implementation but
may also come from staff that exercises operational control over County asset. Investments were prioritized based on
the ability to deliver value to the County and their alignment with the priorities of key stakeholders such as the County
Board, County Government and the public.
As discussed in more detail under “Financial & Debt Management Policies” below, the consolidated recommendations
were considered against various debt capacity scenarios to develop the final adopted CIP. Throughout the process, the
team consulted with program managers and other subject matter experts within the departments.
2
Return to Table of Contents
D. Financial & Debt Management Policies
The Board-adopted financial and debt management policies provide the parameters for the amounts and timing of
bond-financed projects to be included in the CIP, ensuring that the CIP is financially sustainable and that it supports the
County’s triple-A bond ratings.
E. Sources of Capital Funds
Funding for capital improvements comes from a number of sources. These funds are generated through local taxes,
fees, charges, outside funding or other similar sources. The availability of these funds is sensitive to economic cycles.
Pay-As-You-Go (PAYG) comes from annual appropriations and is part of the adopted operating budget. PAYG funding
provides the greatest flexibility since it is not constrained by tax-exempt bond requirements and historically has funded
maintenance capital projects and regional partnership programs. Projects that are typically smaller in scale as well as
minor renovations are likely candidates for PAYG funding – as long as the project has an expected useful life of at least
10 years or more. PAYG also:
• Has no debt service cost that must be paid on the expenditure;
• Is available at the start of the fiscal year;
• Must compete with operating programs for funding;
• Does not have to be approved through referendum; and
• Can be carried over at the end of each fiscal year.
Bond financing refers to debt financing of projects. Arlington County most often sells general obligation bonds. Bond
financing is generated through the borrowing of funds (principal) at a cost (interest) through the sale of municipal bonds.
There are several types of bond financing:
• General obligation bonds - Arlington typically issues general obligation bonds, which must first be
approved by the County’s voters and are secured by the full faith and credit of the County. Arlington’s
practice is to schedule bond referenda for even -numbered calendar years, which correspond to the
bond sale in odd-number fiscal years.
• Revenue and other types of bonds – Arlington has issued low interest rate revenue bonds through the
Virginia Water Revolving Loan Fund (VRLF) run by the Virginia Resources Authority for improvements
to the Water Pollution Control Plant. Revenue bonds are typically secured solely by user fees or
projected revenues and include no pledge from the General Fund. Revenue and other types of bonds
(including those backed by the County’s subject to appropriation pledge) typically carry a higher interest
rate than GO bonds and generally have debt service coverage and other financial restrictions.
• Lease revenue or annual appropriation bonds – These types of bonds are secured by a “subject to
appropriation” pledge by the County Board and do not require voter approval. (See “Lease -purchase
finance” below) They generally require the use of a third party to execute the lease transaction, such
as the Industrial Development Authority (IDA), Virginia Resources Authority, or Virginia Municipal
League / Virginia Association of Counties.
One of the criteria used to determine which projects will be funded with bond proceeds is the useful life of the
improvement. Projects funded with bond proceeds generally have a useful life that is similar in length to the repayment
schedule of the bonds. Historically, Arlington has issued 20 -year general obligation serial bonds and paid the bonds
using a two -year step -up schedule of principal repayment, and the average bond principal is outstanding for
approximately 11 years. The Board’s financial policies allow for longer term bonds as long as the term of the bonds
3
Return to Table of Contents
does not exceed the useful life of the project, and also allows for alternative amortization structures such as level debt
service to better match certain revenue streams.
Inter-jurisdictional payments are another source of funding in the capital program . Arlington has agreed to provide
services to other jurisdictions through contractual agreements. For example, wastewater treatment services for some
areas of Alexandria, Falls Church, and Fairfax County are provided by Arlington’s Water Pollution Control Plant. These
jurisdictions also share in the cost of capital improvements of this facility, thus reducing the cost to Arlington users.
Short-Term Finance represents another source of capital financing to acquire equipment and technology, and to
perform certain capital maintenance projects that result in a more limited extension to useful life. Because of the short-
term maturities of these financing vehicles, interest rates are typically lower than rates on long-term bonds. The County
typically procures the goods and services using temporary funding sources, and then draws funds from the financing
institution to reimburse the temporary sources.
Infrastructure Availability (formerly hook-up) fees are another source of capital funding. These fees are assessed to
developers and builders to join the water and sewer systems, based on the cost of capacity (volume) of the systems
being “used up” by the customer. These funds are programmed during the annual budget process and can be used only
for utilities projects.
The Transportation Capital Fund – Commercial & Industrial Tax is a source of funding authorized by the General
Assembly in 2007 enabling the County to levy an additional real estate tax on industrial and commercial properties for
transportation initiatives. In April 2008, the County Board adopted a tax of $0.125 per $100 of assessed value for
transportation projects. Proceeds of the tax are held in a separate fund.
The Transportation Capital Fund – NVTA 30% Local Funds is comprised of a 0.7% increase in the local sales tax approved
in 2013 by the General Assembly as part of HB 2313. The Northern Virginia Transportation Authority (NVTA) receives
the proceeds of this tax and retains 70% for funding of projects that are regional in nature. The remaining thirty percent
of this tax is deposited in the Transportation Capital Fund along with the Commercial & Industrial tax. In 2018, The
General Assembly repealed two additional taxes and fees that were part of the original 2013 legislation and diverted
those funds to the Washington Metropolitan Area Transit Authority (WMATA) Capital Fund beginning in FY 2019.
The Northern Virginia Transportation Authority (NVTA) – All revenues from the tax adopted by the General Assembly
in 2013 as part of HB 2313 are distributed from the State to NVTA. Of these revenues, seventy percent (“Regional
Funds”) are retained by NVTA to fund regional transportation projects. By law, each locality’s long-term benefit must
be approximately equal to the proportion of the total fees and taxes generated in the locality divided by the total of all
fees and taxes received by NVTA. The remaining thirty percent (“Local Share”) will be returned on a pro rata basis to
the member localities based on the amount of revenue generated by the taxes and fees within the locality, to be used
for locally selected transportation projects and deposited into the Transportation Capital Fund. The NVTA Board will
approve projects for regional funding as part of its Six-Year Program (SYP).
The Crystal City – Potomac Yard – Pentagon City Tax Increment Financing Area was established in 2010 to support the
infrastructure investment needed as part of the Crystal City Sector Plan as well as the neighboring areas of Potomac
Yard and Pentagon City. Tax increment financing (TIF) is a mechanism used to support development and redevelopment
by capturing the projected increase in property tax revenues in the area and investing those related infrastructure
improvements. Unlike a special district, it is not an additional or new tax; rather, it redirects and segregates the
increased property tax revenues that would normally flow to the General Fund. The amount of tax increment revenue
is determined by setting a baseline assessed value of all property in the area on January 1, 2011 and in each subsequent
year, tracking the increm ental increase in assessed values relative to the base year, and segregating the incremental
revenues in a separate fund. Beginning in FY 19, the County Board approved allocating 25% percent of the incremental
revenues to the Crystal City – Potomac Yard – Pentagon City area.
4
Return to Table of Contents
The Stormwater Management Fund relies on a source of funding originally adopted by the County Board in April 2008
to fund operating and capital costs to upgrade and expand the County’s stormwater drainage and sewer infrastructure.
Since then the Board has increased the sanitary district tax rate in FY 2011 to $0.013 per $100 of assessed value and
then again in FY 2022 to $0.017 per $100 of assessed value. Recognizing the significance of the stormwater investment
that is needed, the voters approved the November 2020 bond referendum for stormwater and watershed
infrastructure. This will be a substantial, long -term investment in the County’s stormwater management system, with
multiple generations of taxpayers benefiting. Proceeds of this tax are held in a separate fund.
D
eveloper contributions are also an important source of funding. These are contributions paid by developers to finance
specific projects. Examples of these projects are utility undergrounding and street lighting.
F
inally, there are grants and reimbursements or other revenue from the state and federal governments. These are
funds provided by the Commonwealth of Virginia or the federal government for reimbursement of costs for certain
capital improvements. Whenever possible, state or federal reimbursement is sought to offset County tax support and
is included in the planning process. (See the Transportation & Pedestrian Initiatives section of the CIP for some current
examples.)
F
. Definition of Terms Used in Capital Planning
A
rbitrage: Arbitrage is the gain a tax -exempt issuer may be able to obtain by borrowing at a tax -exempt rate and
investing at a taxable rate. The Tax Reform Act of 1986 and subsequent amendments relating to the issuance of tax -
exempt debt and arbitrage regulations had a dramatic effect on all issuers of tax-exempt debt.
A
rbitrage Rebate: Refers to the requirement to rebate to the Federal government investment earnings derived with
the proceeds of tax-exempt debt that are in excess of the ear nings that would have been earned had the proceeds of
the debt been invested at the same interest rate as that paid to the holders of the tax-exempt debt.
A
rchitecture and Engineering (A&E): Professional services performed to facilitate planning, development, designs, cost
estimates and construction of buildings, parks, streets, utilities, and other capital infrastructure.
B
ond Funding: Funding derived from the public sale of bonds for which interest is paid to buyers for the use of the
money.
• CIP programs and projects included for bond funding are approved by the County Board for inclusion on a
bond referendum.
• Voters approve each bond referendum. In Arlington, a bond referendum is placed on the ballot for voter
approval every other November, concurrent with Congressional/Presidential elections.
• Funds cannot be spent until after the referendum is approved by the voters, the Board approv es the
authorization and the County has
developed cash flow plans.
• Spending rules are established based on referendum language and IRS regulations.
B
ond Issuance Costs: Costs associated with the sale of bonds. Expenditures include fees to bond rating a gencies,
administrative expenses, legal fees, etc.
C
apital Planning Process: The process of identifying, planning, evaluating and scoping projects, establishing
performance standards, conducting public discussion, estimating costs and financial planning for capital projects. These
processes should be completed for current year funding requests and underway for projects included in subsequent
years.
D
ebt Service: The amount of principal and interest the County pays on its debt financing.
5
Return to Table of Contents
Full Time Equivalent (FTE): The measure of authorized personnel. It is calculated by equating 2,080 hours of work per year
(2,912 for uniformed firefighters until the Kelly Day schedule is fully implemented, and 2,600 thereafter) with the full-time
equivalent of one position (referred to in the budget as an FTE).
O
ut Years: All years after the current funding year. For example, in the FY 2022 – FY 2024 CIP, all years after FY 2022
are considered out years.
O
verhead: The capital project should bear the cost of staff time spent directly on the implementation of the projects
funded. In certain cases, the project can also bear the cost of program planning or preliminary business processes used
in advance of funding or bringing the project to completion of scope.
R
ules: This applies to limitations on the use of funds as a result of special revenue requirements. Interjurisdictional
agreements for sewer construction reimbursement can only be applied to non -expansion costs of specific projects.
Grants can only be spent under the terms and conditions provided with the grant. Bonds can only be used consistent
with the language of the referendum and for items consistent with bond counsel determination, etc. Rules are not
intended to imply administrative procedures, but rather legal requirements.
T
otal Project Cost: The CIP reflects the full cost of each project. The total cost includes such items as design,
construction, right-of-way, construction management, utility relocations, hardware and software purchases, equipment
needed to make the improvement useful, and appropriate overhead and operating costs.
6
Return to Table of Contents
GUIDE TO READING THE FY 2022 – FY 2024
CAPITAL IMPROVEMENT PLAN
The adopted FY 2022 – FY 2024 Capital Improvement Plan (CIP) provides comprehensive information on the near and
longer-term facility and infrastructure capital improvements planned in the County over the next three years.
T
he book is organized by the following sections: an introductory section, overview, capital funding, and the program
areas under which the projects reside. Each one of these sections represents a key component of the overall picture of
the adopted FY 2022 – 2024 CIP:
The introductory section includes various information on the CIP process, policies , and governance that help
provide context and framework under which the CIP is formulated.
The Overview summarizes the Board’s decisions in the Chairman’s CIP Message and provides status of projects
u
nderway and summaries of authorized unissued bonds.
The Capital Funding section includes various financial summaries of the CIP by program and funding source. It
also includes analysis of the County’s debt capacity as impacted by the adopted CIP.
T
he remaining four sections are dedicated to describing specific programs and projects included under the General
Government section, IT and Equipment section, Metro and Transportation section, and the Utilities and Stormwater
section. These sections detail the projects by major program areas.
The first part of each of the programs provides a summary overview of costs and funding sources. Also included
is the impact that bond/debt financing will have on annual debt service payments to the operating budge t,
where applicable.
The following pages provide a description of each project, funding schedules, and operating impacts, if any. In
addition, where applicable, the pages have a link to additional project information such as capital project pages,
board reports, sector plans, etc.
In the funding schedule section on each project page, the fund sources that are consistently used across
all programs, are listed. However, for specific sources that may not apply across all programs, they
were combined in the 08 Other source. Examples of those sources include Inter -Jurisdictional (IJ)
contributions, Arlington Public School contributions, Transit contributions, interest earnings, etc. The
same applies for 19 Other and sources the re include previously appropriated balances from: Pay-As-
You-Go (PAYG), outside contributions, bond premium, etc.
L
ike previous CIPs, the adopted FY 2022 – 2024 CIP is largely funded by bond debt, PAYG, and short-term financing. In
addition, the Transportation Capital Fund, the Crystal City, Potomac Yard and Pentagon City tax increment financing
area, the Utilities Fund and the Stormwater Management Fund are integrated in the comprehensive funding strategy
for the CIP.
P
lease note that cost estimates are subject to market pressures and may not reflect the actual costs incurred at project
implementation.
7
Return to Table of Contents
CIP CALENDAR
F
EBRUARY 2021
County Manager presents Proposed FY 2022 PAYG Budget to the County Board
FY 2022 – FY 2024 Capital Improvement Program (CIP) staff kick-off
A
PRIL 2021
Community submits early feedback on CIP Priorities online
M
ARCH - APRIL 2021
County Board holds budget work sessions on PAYG and the operating budget with County departments and the
Fiscal Affairs Advisory Commission
A
PRIL 2021
County Board adopts FY 2022 Budget, PAYG Capital and Appropriations Resolutions for the County government
and the public schools
M
AY 2021
Superintendent submits FY 2022 – FY 2024 Proposed CIP to the School Board – May 6
County Manager submits FY 2022 – 2024 Proposed CIP to the County Board – May 18
County Board worksessions on CIP begin – May 25
Various boards and commissions review the FY 2022 – FY 2024 Proposed CIP
JUNE 2021
School Board adopts the School’s FY 2022 – FY 2024 CIP – June 24
County Board worksessions on CIP continue – May 25, June 22, June 24,
Joint worksession of the County Board and School Board – June 9
CIP Public Hearing – June 29
JULY 2021
County Board wrap-up worksession – July 13
County Board adopts the FY 2022 – FY 2024 CIP – July 20
County Board approves the general obligation bond referenda resolutions and the language to be inserted on the
ballot for the fall General Election
8
Return to Table of Contents
annual covered payroll are sufficient to accumulate assets to pay benefits when due), the County may reduce its
contribution provided that the amount reduced from the annual actuarial requirement will only be used for one-time,
non-recurring expenses in order to provide the ability to increase contributions as may be required by future ma rket
conditions.
Capital Improvement Plan
1. The County Manager will biennially submit a ten-year Capital Improvement Plan (CIP) to the County Board. The
CIP will address all known facility and infrastructure needs of the County, including the needs of the Arlington
County Public Schools.
2. The CIP shall include a detailed description of each capital project, identifying every source of funding, including
pay-as-you-go (PAYG), bond financing, and master lease financing. The source of funding will l argely be
determined based on the useful life of the project. Bond-funded projects will typically have a useful life at least
as long as the period over which the bonds will be repaid (generally twenty years). Master lease -financed
projects will generally have useful lives of three to ten years and typically include furniture, equipment, rolling
stock and technology purchases. PAYG funds provide greater flexibility and will be appropriated annually from
general fund revenues.
3. Each project budget shall identify the financial impact on the operating budget, if any.
4. In general, capital projects estimated to cost $100,000 or more should be included in the CIP, including
technology and equipment purchases.
5. The County will balance the use of debt financing sources against the ability to utilize PAYG funding for capital
projects. While major capital facility projects will generally be funded through bonds, the County will attempt
to maintain an appropriate balance of PAYG versus debt, particularly in light of the County’s debt capacity and
analysis of maintenance capital needs. As part of each biennial CIP process, the County will conduct a
comprehensive assessment of its maintenance capital needs.
6. The CIP will include an analysis of the impact the CIP has on the County’s debt capacity, debt ratios and long -
term financial plan.
7. Voter referenda to authorize general obligation bonds should only be presented to voters when the analysis of
the County’s debt capacity demonstrates the ability of the County to fund the debt service for the bonds based
on the County’s “Financial and Debt Service Policies.” Absent a compelling reason to do otherwise, the County
should have the capacity to initiate construction projects within the two- year peri od before the next bond
referendum. There should also be a demonstrated capability for the County to complete any project approved
by referendum within the eight-year time period mandated under state law for sale of authorized bonds. The
term “County” in this specific policy includes the Arlington County Government and any entity that receives
bond funding from the County (such as the Arlington County Public Schools and the Washington Metropolitan
Area Transit Authority).
8. In the off -years of the bienn ial CIP process, the County will conduct a needs assessment that will reflect, as
appropriate, existing master plans and assessments (e.g., the Master Transportation Plan and others) . Given
the significant size and diversity of the County’s infrastructure responsibilities, this assessment process will be
implemented over the next four to six years.
A - 2
Return to Table of Contents
Debt Management
The County will prudently use debt instruments, including general obligation bonds, revenue bonds, industrial
development authority (IDA) revenue bonds, and master lease financing in order to provide re -investment in public
infrastructure and to meet other public purposes, including inter -generational tax equity in capital investment. The
County will adhere to the following debt affordability criteria (excluding overlapping and self-supporting debt).
1. The ratio of net tax-supported debt service to general expenditures should not exceed ten percent, within the
ten-year projection.
2. The ratio of net tax-supported debt to full market value should not exceed three percent, within the ten -year
projection.
3. The ratio of net tax -supported debt to income should not exceed six percent, within the
ten-year projection.
4. Growth in debt service should be sustainable and consistent with the projected growth of revenues. Debt
service growth over the ten-year projection should not exceed the average ten-year historical revenue growth.
5. The term and amortization structure of County debt will be based on an analysis of the useful life of the asset(s)
being financed and the variability of the supporting revenue stream. The County will attempt to maximize the
rapidity of principal repayment where possible. In no case will debt maturity exceed the useful life of the
project.
6. The County will refund debt when it is in the best financial interest of the County to do so. When a refunding
is undertaken to generate interest rate cost savings, the minimum aggregate present value savings will be three
percent of the refunded bond principal amount.
Variable Rate Debt
1. Variable rate debt exposure should not exceed twenty percent of total outstanding debt.
2. Debt service on variable rate bonds will be budgeted at a conservative rate.
3. Before issuing variable rate bonds, the County will determine how potential spikes in the debt service will be
funded.
4. Before issuing any variable rate bonds, the County will determine the impact of the bonds on the County’s total
debt capacity under various interest rate scenarios; evaluate the risk inherent in the County’s capital structure,
giving consideration to both the County’s assets and its liabilities; and develop a method for budgeting for debt
service.
Moral Obligation Debt or Support
On an infrequent basis, the County provides its “moral obligation” support for partners, including regional public safety
agencies and affordable housing partners, among others. A moral obligation exists when the County Board has made a
commitment to support the debt of another entity to prevent a potential default. The County’s moral obligation will
only be authorized after an evaluation of the risk to the County’s balance sheet and stress testing of the financial
assumptions underlying the proposed project.
A - 3
Return to Table of Contents
Derivatives
Interest rate swaps and options (Swaps or Derivatives) are appropriate management tools that can help the County
meet important financial objectives. Properly used, these instruments can help the County increase its financial
flexibility, provide opportunities for interest rate savings or enhanced investment yields, and help the County reduce its
interest rate risk through better matching of assets and liabilities. The County must determine if the use of any Swap is
appropriate and warranted given the potential benefit, risks, and objectives of the County.
1. The County may consider the use of a derivative product if it achieves one or more of the following objectives:
Provides a specific benefit not otherwise available;
Produces greater than expected interest rate savings or incremental yield over other market alternatives;
Results in an improved capital structure or better asset/liability matching.
2. The County will not use derivative products that are speculative or create extraordinary leverage or risk; lack
adequate liquidity; provide insufficient price transparency; or are used as investments.
3. The County will only do business with highly rated counterparties or counterparties whose obligations are
supported by highly rated parties.
4. Before utilizing a Swap, the County, its financial advisor and legal counsel shall review the proposed Swap and
outline any associated considerations. Such review shall be provided to the Board and include analysis of
potential savings and stress testing of the proposed transaction; fixed versus variable rate and swap exposure
before and after the proposed transaction; maximum net termination exposure; and legal constraints.
5. Financial transactions using Swaps or other derivative products used in lieu of a fixed rate debt issue should
generate greater projected savings than the typical structure used by the County for fixed rate debt.
6. The County will limit the total notional amount of derivatives to an amount not to exceed twenty percent of
total outstanding debt.
7. All derivatives transactions will require County Board approval.
Special Revenue / Enterprise Funds
It is the general policy of the County to avoid designation of discretionary funds in order to maintain maximum financial
flexibility. The County may, however, create dedicated funding sources when there are compelling reasons based on
state law or policy objectives, as described below. The Utilities Fund was created as a self- sustaining, fee -based
enterprise fund under state code to support and maintain development of the County’s water and sewer infrastructure.
The Transportation Capital Fund was adopted pursuant to state legislation for new transportation funding. The
Stormwater Management Fund was adopted in lieu of a self -supporting, user fee -based enterprise fund. The CPHD
Development Fund was created as a self-sustaining, fee-based enterprise fund. Tax Increment Funds were established
to support redevelopment and preservation objectives associated with the County’s adoption of master plans, (e.g., the
Crystal City Sector Plan adopted in 2010 and the Columbia Pike Neighborhoods Plan adopted in 2013).
Utilities Fund
1. The County will annually develop a six -year forecast of projected water consumption, revenue, operating
expenditures, reserve requirements and capital needs for the Utilities Fund. The six -year forecast will show
projected water-sewer rate increases over the planning period.
A - 4
Return to Table of Contents
2. The County will implement water-sewer rate increases in a gradual manner, avoiding spike increases whenever
possible.
3. The County will meet or exceed all requirements of any financing agreements or trust indentures.
4. The Utilities Fund will maintain a reserve equivalent to three months’ operations and maintenance expenses.
The reserve may be used to address emergencies and unexpected declines in revenue. If utilized, the reserve
will be replenished over a three- year period to the minimum reserve level. This reserve is in addition to any
financing agreement-required debt service reserve funds.
5. The Utilities Fund will maintain debt service coverage of at least 1.25 times on all debt service obligations.
6. The Utilities Fund will be self-supporting.
Transportation Capital Fund
1. New revenue shall not be used to supplant existing transportation funding commitments, and capital
investments shall be compliant with state law restrictions on non -supplanting and maintenance of effort
requirements.
2. Operating program enhancements (outside base program) that clearly document transportation benefits may
be eligible for support from the Transportation Capital Fund.
3. No more than three to fi ve percent of annual funding should be used for project administration, indirect &
overhead costs to support capital projects.
4. A reserve equivalent of ten to twenty percent of annual budgeted revenue will be established.
5. A five to ten-year financial plan and model will be developed that integrates project cashflow forecasts, revenue
projections, and financial / debt management policies and will factor in other non -County funding sources,
including federal, state, regional, and private funding.
6. The County will prudently balance the use of new transportation funding sources between pay -as-you-go
funding and leveraging through new bond issuance. Use of leveraging will be dependent on project size, cash
flow, and timing projections.
7. I f the County chooses to issue debt supported by dedicated transportation funding sources, such debt will be
structured to be self-supporting and will not count against the County’s general tax supported obligation debt
ratios or capacity. Debt service cov erage on such debt will range from 1.10 to 1.50 times, depending on the
type of debt issued. The term on such bonds will not exceed the average useful life of the assets financed, and
amortization will be structured to match the supporting revenue stream.
8. The Transportation Capital Fund will be self-supporting.
Tax Increment Funds
1. The intended use of TIF monies will be specified at the time of TIF creation; changes or additional uses will be
determined as part of the annual budget process.
2. The assessed value of TIF areas will not exceed 25 percent of the County’s total assessed valuation. As of
January 1, 2016, existing TIF assessed valuation totaled 20 percent of County-wide assessed valuation.
A - 5
Return to Table of Contents
3. The percent of TIF revenue available for the intended uses within a TIF area will be established at the creation
of the TIF and will be less than or equal to 40 percent. This percent will be evaluated annually as part of the
budget process.
4. The County will prudently balance the use of PAYG funding and leveraging through TIF bond issuances. Use of
leveraging will be dependent on project type, size, cashflow and timing projections. Leveraging will only be
used for capital projects that meet useful life and other requirements for bond issuance.
5. If the County leverages TIF revenue on its own behalf, it will target a minimum debt service coverage ratio of
2.0 times and establish an appropriate level of debt service reserves and / or other contingencies.
6. The County will establish additional policies pertaining to the leverage of TIF revenue by a private development
entity prior to any such issuance.
7. A reserve equivalent to ten percent of annual budgeted revenue will be established.
Stormwater Fund
1. The County will annually develop a six-year projection of stormwater operating and capital expenses.
2. The County will prudently balance the use of new stormwater funding sources between pay-as-you-go
funding and leveraging through new bond issuance. Use of leveraging will be dependent on project size,
cashflow, and timing projections. If debt is issued for stormwater projects, it will generally follow the debt
issuance guidelines contained in this policy.
3. The Stormwater Fund will maintain a reserve equivalent to three months’ operating and maintenance
expenses. The reserve may be used to address emergencies and unexpected declines in revenue. If utilized,
the reserve will be replenished over a three-year period to the minimum reserve level. This reserve is in
addition to any financing agreement-required debt service reserve funds.
4. If the County chooses to issue debt supported by the Stormwater Fund, such debt will be structured to be
self-supporting and will not count against the County’s general obligation debt ratios or capacity as long as
annual net debt service coverage remains above a minimum of 1.25 times. The term on such bonds will not
exceed the average useful life of the assets financed, and amortization will be structured to match the
supporting revenue stream.
5. Prior to each new issuance of stormwater debt, the County will prepare a projection of net debt service
coverage demonstrating that the forecasted future net debt service coverage will be no less than 1.35 times,
over the life of the bonds.
6. Stormwater financial policies will be reviewed on a periodic basis.
7. The Stormwater Fund will be self-supporting.
CPHD Development Fund
1. A contingent reserve will be established equivalent to thirty percent of the Fund’s total operating budget based
on the fiscal year. This amount is equivalent to three to four months of annual operating expenditures. The
reserve may be used to address emergencies and unexpected declines in revenue only after authorization from
the County Board.
2. The CPHD Development Fund will be self-supporting.
A - 6
Return to Table of Contents
Ballston Garage and Ballston Garage 8
th Level Funds
1. The County will annually develop a multi -year forecast of garage revenue, operating expenses, and capital
maintenance costs to be updated with each County CIP cycle.
2. An economic stability reserve equivalent to three months of annual parking revenues will be established to
address potential revenue variability, ramping up to this level over a four-year period beginning in FY 2019. Any
draws upon this reserve will be replenished within the subsequent three (3) fiscal years.
3. A maintenance reserve will be established based on an assessment of expected capital renewal needs over a
10-year period.
4. A reserve will be established for the ensuing year of debt service o n the Series 2016B Ballston Quarter CDA
bonds allocable to garage improvements.
5. The County will meet or exceed all requirements of any financing agreements or trust indentures.
6. The County will target self -sufficiency in consideration of limits imposed on parking user fee raising ability in
the garage by the 1984 documents governing original and ongoing development of the garage.
A - 7
Return to Table of Contents
Arlington County, Virginia
BONDS AUTHORIZED BUT UNISSUED
Community Conservation 11,000,000
Facilities Infrastructure/Land Acquisition
Courthouse Complex Facility Improvements 2,000,000
North Side Salt Facility 800,000
Total Facilities Infrastructure/Land Acquisition 2,800,000
Metro & Transportation
Paving 3,000,000
Total Metro & Transportation 3,000,000
Total Authorized but Unissued - County 16,800,000
Stormwater 37,640,000
Schools 26,830,000
*Amounts based on authorized unissued bonds remaining after 2021 GO bond sale
A - 8
Return to Table of Contents
April 17, 1951
Schools $4,875,000 6,208 2,569 3,693 70.7
Total $4,875,00 0
November 6, 1951
Courts Building $ 505,000 4,086 7,475 3,389 64.7
Parking Lots 740,000 4,992 7,139 2,147 58.9
Parks and Playgrounds 882,000 6,334 5,595 739 53.1
Streets and Highways 1,318,000 7,465 4,651 2,814 61.6
Storm Drainage $1,382,000 7,330 4,790 2,540 60.5
Total $4,827,00 0
May 27, 1952
Schools $8,280,000 4,854 3,190 1,664 60.3
Total $8,280,00 0
November 3, 1953
Streets and Highways $1,720,000 7,035 4,588 2,447 60.5
Water 1,327,000 7,779 3,862 3,917 66.8
Storm Drainage 1,000,000 6,719 4,668 2,051 59.0
Total $4,047,00 0
November 2, 1954
Water $1,700,000 16,207 4,922 11,285 76.7
Incinerator 980,000 11,910 8,386 3,524 58.7
Fire Stations 470,000 13,138 7,271 5,867 64.4
Storm Drainage 200,000 13,196 7,524 5,672 63.7
County Building Sites 600,000 6,776 13,251 6,475 66.2
Swimming Pools 600,000 9,064 11,964 2,900 56.9
Total $4,550,00 0
November 8, 1955
Sanitary Sewers $1,000,000 7,203 7,014 189 50.7
Streets and Highways 1,330,000 5,930 8,067 2,137 57.6
Storm Drainage 1,200,000 5,783 8,144 2,361 58.5
Total $3,530,00 0
February 2, 1956
Schools $9,430,000 5,720 6,658 938 53.8
Total $9,430,00 0
June 5, 1956
Court House $2,200,000 5,933 795 5,138 88.2
Schools 4,492,000 6,167 4,928 1,239 55.6
Total $6,692,00 0
A - 9
Bond Referenda History
Return to Table of Contents
May 13, 1958
Libraries $ 560,000 7,137 4,982 2,155 58.9
Streets and Highways 1,790,000 7,320 4,869 2,451 60.1
Sidewalks 330,000 6,907 5,145 1,762 57.3
County Building Sites 50,000 6,358 5,299 1,059 54.5
Parks and Playgrounds 293,000 6,701 5,313 1,388 55.8
Sanitary Sewer 770,000 7,762 4,318 3,444 64.3
Storm Drainage 673,000 7,399 4,649 2,750 61.4
Schools 3,500,000 7,391 4,807 2,584 60.6
To tal $7,966,000
May 17, 1960
Storm Drainage $1,040,000 6,105 7,112 1,007 53.8
Regional Parks 130,000 5,593 7,642 2,049 57.7
Parks and Recreation Facilities 800,000 5,679 7,379 1,700 56.5
Libraries 250,000 6,275 6,918 643 52.4
Health Clinics 100,000 5,795 7,373 1,578 56.0
Sidewalks 450,000 5,757 7,420 1,663 56.3
Schools 1,750,000 5,650 7,258 1,608 56.2
Streets and Highways 2,660,000 5,853 7,297 1,444 55.5
Fire Stations 400,000 6,493 6,654 161 50.6
To tal $7,580,000
November 8, 1960
Water $2,172,000 20,535 11,733 8,802 63.6
Sanitary Sewers 675,000 21,434 11,972 9,462 64.2
To tal $2,847,000
November 7, 1961
County Land Acquisition $ 500,000 8,493 8,589 96 50.3
Storm Water Drainage 900,000 10,007 7,419 2,588 57.4
Streets and Highways 2,500,000 9,874 7,614 2,260 56.5
Sidewalk 475,000 9,149 8,215 934 52.7
Recreation Facilities 225,000 9,029 8,189 840 52.4
Library 495,000 9,209 8,002 1,207 53.5
Firefighting Facilities 475,000 11,519 5,919 5,600 66.1
Schools 950,000 9,246 7,902 1 ,344 53.9
To tal $6,520,000
November 5, 1963
Storm Water Drainage $1,000,000 12,523 7,494 5,029 62.6
Sewer 5,560,000 12,692 6,957 5,735 64.6
County Land Acquisition 1,000,000 10,409 8,914 1,495 53.9
Library 440,000 9,800 9,425 375 51.0
Schools 1,950,000 10,453 8,648 1,805 54.7
To tal $9,950,000
A - 10
Return to Table of Contents
Bond Referenda History
November 2, 1965
Storm Water Drainage $ 1,250,000 14,223 8,067 6,156 63.8
Streets and Highways 4,350,000 13,340 8,209 5,131 61.9
County Land Acquisition 1,000,000 12,814 9,321 3,493 57.9
Sidewalk 550,000 12,953 8,352 4,601 60.8
Schools 4,795,000 11,449 9,582 1,867 54.4
Schools, New Junior H.S. 4,250,000 8,413 13,153 4,740 61.0
To tal $16,195,000
November 8, 1966
No. Virginia
Higher Education $3,000,000 21,100 10,401 10,699 67.0
Tot al $3,000,000
November 7, 1967
Streets and Sidewalk $7,100,000 15,047 8,031 7,016 65.2
Storm Water Drainage 1,100,000 14,813 7,173 7,640 67.4
Sewer 1,000,000 15,108 6,936 8,172 68.5
To tal $9,200,000
June 11, 1968
Schools and Recreation $16,800,000 7,895 9,476 1,581 54.6
To tal $16,800,000
November 5, 1968
Transit Facilities $54,000,000 42,721 11,659 31,062 78.6
Schools (W-L Library) 225,000 34,331 19,715 14,616 63.5
Schools (Elementary) 6,900,000 35,993 17,696 18,297 67.0
Schools (New Junior H.S.) 4,150,000 34,485 19,163 15,322 64.3
Recreation Facilities 2,500,000 32,832 19,979 12,853 62.2
To tal $67,775,000
November 4, 1969
Paving $ 500,000 19,392 9,380 10,012 67.4
Police Headqtrs.-Jail 2,500,000 20,618 9,562 11,056 68.3
Public Library 550,000 17,866 11,071 6,795 61.7
Swimming Pool 900,000 14,862 13,975 887 51.5
Storm Drainage 1,000,000 21,192 7,947 13,245 72.7
Water System 5,500,000 20,526 8,344 12,182 71.1
Neighborhood Conservation 800,000 16,793 11,611 5,182 59.1
Park Authority 2,160,000 1,654 11,247 9,593 87.2
To tal $13,910,000
A - 11
Return to Table of Contents
Bond Referenda History
November 2, 1971
Sanitary Sewers $ 6,700,000 11,961 4,176 7,785 74.1
Waste Water Treatment 6,000,000 12,670 3,490 9,180 78.4
Recreation Facilities 3,000,000 9,873 5,999 3,874 62.2
Storm Water Drainage 2,500,000 12,215 4,114 8,101 74.8
Streets and Highways 1,000,000 16,675 10,211 6,464 62.0
Human Resources Center 850,000 15,347 11,520 3,827 57.1
Neighborhood Conservation 800,000 15,365 11,554 3,811 57.1
Technical Education Center 4,600,000 16,182 11,000 5,182 59.5
Schools 2,600,000 15,097 11,929 3,168 55.9
Library 470,000 14,742 11,98 2,758 55.2
To tal $28,520,000
November 7, 1972
Ad. Waste Water Treatment $15,000,000 38,705 11,829 26,876 76.6
Schools 6,275,000 31,390 18,917 12,473 62.4
To tal $21,275,000
*Referendum amended language of 1971 and 1972 referenda to expand how the $21.0 million could be used at the
wastewater treatment plant.
November 6, 1973
Local and Regional Parks $ 5,000,000 11,186 5,736 5,450 66.1
Sanitary Sewerage 4,500,000 13,613 5,744 7,869 70.3
Streets and Highways 3,000,000 10,903 7,276 3,627 60.0
Public Schools 2,350,000 14,647 15,843 1,196 52.0
Storm Water Drainage 1,500,000 20,034 10,286 9,748 66.1
Human Resources Center 1,000,000 17,462 12,660 4,802 58.0
County Property Yard 700,000 13,860 16,081 2,221 53.7
Nursing Home Sites 500,000 20,281 10,607 9,674 65.7
Fire Stations 300,000 20,867 9,925 10,942 67.8
To tal $18,850,000
November 4, 1975
Wastewater Treatment* $21,000,000 11,020 8,600 2,420 56.2
Transit Facilities 25,000,000 7,543 11,880 4,337 61.2
County Maintenance
and Service Facilities 1,500,000 5,003 13,968 8,965 73.6
Sidewalks, Curbs and Gutters,
Streets and Highways 3,000,000 7,923 20,553 12,630 72.2
Joint Community Theatre
and Schools Auditorium 1,300,000 5,169 23,612 18,443 82.0
Buildings and Building Sites 1,000,000 5,097 22,881 17,784 81.8
Park and Recreation
Acquisition and Development 6,000,000 9,036 20,140 11,104 69.0
Community Conservation 2,500,000 8,075 20,128 12,053 71.4
To tal $61,300,000
A - 12
Return to Table of Contents
Bond Referenda History
November 8, 1977
Water Storage $ 6,200,000 21,464 11,959 9,505 64.2
Storm Drainage 1,000,000 20,433 13,300 7,133 60.6
Streets and Highways 3,000,000 19,942 13,973 5,969 58.8
Neighborhood Conservation 2,500,000 19,193 14,777 4,416 56.5
Local and Regional Parks 2,500,000 18,849 14,868 3,981 55.9
To tal $15,200,000
*Referendum amended language of 1977 water bond to change from storage to distribution improvements as
permitted use.
November 6, 1979
Sanitary Sewerage $ 1,985,000 16,761 9,222 7,539 64.5
Streets and Highways 4,665,000 15,617 10,530 5,087 59.7
Local Parks 4,000,000 9,465 16,577 7,112 63.6
Regional Parks 1,705,000 9,780 16,200 6,420 62.4
To tal $12,355,000
November 4, 1980
Water Distribution* $6,000,000 41,328 8,756 32,572 82.5
To tal $6,000,000
November 3, 1981
Streets and Highways $ 3,000,000 23,751 12,583 11,168 65.4
Storm Drainage 1,800,000 22,652 13,420 9,232 62.8
Jail Expansion 2,100,000 25,485 11,251 14,234 69.4
Local and Regional Parks 3,000,000 22,886 13,465 9,421 63.0
Community Conservation 1,000,000 21,743 13,520 8,223 61.7
To tal $10,900,000
November 8, 1983
Metrorail $13,000,000 21,221 6,615 14,606 76.2
Streets and Highways 3,100,000 20,756 6,922 13,834 75.0
Community Conservation 1,950,000 19,624 7,840 11,784 71.5
Water Distribution 3,100,000 20,048 7,159 12,889 73.7
To tal $21,150,000 Average 74.1%
November 6, 1984
Local and
Regional Parks $ 4,035,000 38,785 21,771 17,014 64.1
Streets and Highways 6,140,000 39,644 20,630 19,014 65.8
Community Conservation 6,800,000 37,935 21,906 16,029 63.4
Metrorail 13,000,000 40,111 20,924 19,187 65.7
To tal $29,975,000 Average 64.8%
A - 13
Return to Table of Contents
Bond Referenda History
November 4, 1986
Local and Regional Parks $ 4,895,000 25,899 8,539 17,360 75.2
Streets and Highways 4,315,000 27,382 6,452 20,930 80.9
Community Conservation 10,835,000 25,626 8,741 16,885 74.6
Central Library Expansion 4,025,000 26,974 7,909 19,065 77.3
To tal $24,070,000 Average 77.0%
November 8, 1988
Local and Regional Parks $ 3,900,000 50,367 14,344 36,023 77.8
Streets and Highways 2,400,000 49,077 12,688 36,389 79.5
Community Conservation 2,900,000 49,295 14,928 34,367 76.8
Public Schools 12,800,000 49,905 12,251 37,654 80.3
Jail 35,000,000 40,731 22,662 18,069 64.3
Wastewater Treatment 12,000,000 52,216 8,970 43,246 85.3
To tal $69,000,000 Average 77.3%
November 6, 1990
Courts/Police Facility $53,850,000 25,061 17,381 7,680 59.0
Public Schools 23,000,000 31,367 11,833 19,534 72.6
Streets, Highways,
and Community
Conservation 10,930,000 28,357 11,980 16,377 70.3
Local and Regional
Parks and Recreation 4,220,000 27,857 12,544 15,313 69.0
Fire Station #3 2,500,000 28,642 11,319 17,323 71.7
To tal $94,500,000 Average 68.5%
November 3, 1992
Metrorail $ 17,800,000 58,898 16,057 42,841 78.6
Public Schools 24,425,000 56,903 17,647 39,256 76.3
Higher Education 3,125,000 51,355 23,199 28,156 68.9
Local and Regional
Parks and Recreation 11,870,000 51,504 23,176 28,328 69.0
Streets, Highways and
Community Conservation 13,415,000 55,185 19,551 35,634 73.8
Wastewater Treatment Plant 36,000,000 61,741 13,243 48,498 82.3
To tal $106,635,000 Average 74.8%
November 8, 1994
Metrorail $ 7,000,000 45,783 16,166 29,617 73.9
Public School 36,100,000 46,444 15,349 31,095 75.2
Fire Station #3 2,760,000 44,184 16,857 27,327 72.4
Local and Regional
Parks and Recreation 13,865,000 43,210 18,278 24,932 70.3
Streets, Highways and
Community Conservation 17,690,000 47,062 14,288 32,774 76.7
A - 14
Return to Table of Contents
Bond Referenda History
Water Distribution and
Wa stewater Treatment 12,200,000 50,049 10,885 39,164 82.1
To tal $89,615,000 Average 75.1%
November 5, 1996
Metrorail $ 9,560,000 52,289 15,733 36,556 76.9
Public School 29,120,000 53,783 14,510 39,273 78.6
Local and Regional
Parks and Recreation 12,920,000 45,336 23,539 21,797 65.8
Streets, Highways and
C ommunity Conservation 21,305,000 53,260 14,372 38,888 78.7
Tot al $72,905,000 Average 75.0%
November 3, 1998
Public Schools $50,705,000 35,552 9,721 25,831 78.5
Westover and Shirlington 8,000,000 34,298 10,760 23,538 76.1
Branch Libraries
Local and Regional Parks 17,055,000 34,438 10,651 23,787 76.4
And Recreation
Street, Highways, and
C ommunity Conservation 24,055,000 35,448 9,500 25,948 78.9
To tal $99,815,000 Average 77.5%
November 7, 2000
Public Schools $ 42,612,500 61,252 14,564 46,688 80.8
Local and Regional Parks 25,875,000 58,973 16,104 42,869 78.6
And Recreation
Street, Highways and 34,291,000 63,797 12,583 51,214 83.5
Community Conservation
Government Fac.& Higher Ed. 7,210,000 53,571 22,023 31,548 70.9
Utilities 12,070,000 65,109 11,202 53,907 85.3
To tal $122,058,500 Average 79.8%
November 5, 2002
Public Schools $ 78,996,000 43,877 12,258 31,619 78.2
Community Projects:
Community Conservation,
Parks, Public Safety,
Pedestrian Systems, Streets,
Highways, Transit, Metro,
Storm Drainage 67,428,500 44,592 11,320 33,272 79.8
Utilities 12,342,000 46,078 9,796 36,282 82.5
To tal $158,766,500 Average 80.2%
A - 15
Return to Table of Contents
Bond Referenda History
November 2, 2004
Public Schools $ 78,128,000 71,594 17,615 53,979 80.3
Local Parks and Recreation 78,395,000 67,588 21,450 46,138 75.9
Transportation & Community
Infrastructure 35,944,000 71,697 17,171 54,526 80.7
Metro 18,536,000 73,248 16,151 57,097 81.9
To tal $208,003,000 Average 79.7%
November 7, 2006
Public Schools $ 33,712,000 54,130 16,609 37,521 76.5
Local Parks and Recreation 35,550,000 52,257 18,238 34,019 74.1
Community infrastructure 27,300,000 49,905 20,233 29,672 71.2
Metro and Transportation 31,500,000 58,058 11,709 46,349 82.0
Utilities 79,000,000 59,797 10,878 48,919 84.6
To tal $207,062,000 Average 77.7%
November 4, 2008
Public Schools $ 99,425,000 76,325 25,360 50,965 75.1
Community infrastructure 10,800,000 68,967 31,321 37,646 68.8
Metro 10,000,000 79,178 22,713 56 ,465 77.7
Utilities 50,000,000 80,873 20,052 60,821 80.1
To tal $170,225,000 Average 77.3%
November 2, 2010
Public Schools $ 102,888,000 46,869 14,350 32,519 76.6
Local Parks and Recreation 5,975,000 41,745 19,427 22,318 68.2
Community Infrastructure 18,065,000 37,943 22,807 15,136 62.5
Metro 34,100,000 44,896 16,334 28,562 73.3
To tal $161,028,000 Average 70.2%
November 6, 2012
Public Schools $ 42,620,000 90,232 21,383 69,849 80.9
Local Parks and Recreation 50,553,000 70,920 40,039 30,881 63.9
Community Infrastructure 28,306,000 80,155 29,607 50,548 73.0
Metro and Transportation 31,946,000 89,000 22,101 66,899 80.1
To tal $153,425,000 Average 74.5%
November 4, 2014
Public Schools $ 105,780,000 49,439 16,899 32,540 74.5
Local Parks and Recreation 13,070,000 46,703 19,501 27,202 70.5
Community Infrastructure 39,900,000 44,858 21,073 23,785 68.0
Metro and Transportation 60,240,000 46,807 19,344 27,463 70.8
To tal $218,990,000 Average 71.0%
A - 16
Return to Table of Contents
Bond Referenda History
November 8, 2016
Public Schools $138,830,000 92,158 23,773 68,385 79.5
Local Parks and Recreation 19,310,000 87,331 28,344 58,987 75.5
Community Infrastructure 98,850,000 85,837 29,339 56,498 74.5
Metro and Transportation 58,785,000 90,703 25,244 65,459 79.5
To tal $315,775,000 Average 76.9%
November 6, 2018
Public Schools $103,000,000 85,576 18,912 66,664 81.9
Local Parks and Recreation 29,330,000 80,175 24,221 55,954 76.8
Community Infrastructure 37,015,000 76,772 27,089 49,683 73.9
Metro and Transportation 74,570,000 83,995 19,754 64,241 81.0
To tal $243,915,000 Average 78.4%
November 3, 2020
Public Schools $52,650,000 98,756 25,757 72,999 79.3
Local Parks and Recreation 3,630,000 101,602 23,267 78,355 81.4
Community Infrastructure 7,485,000 91,759 31,903 59,856 74.2
Metro and Transportation 29,940,000 98,730 25,740 72,990 79.3
Stormwater 50,840,000 97,847 25,948 71,899 79.0
To tal $144,545,000 Average 78.6%
A - 17
Return to Table of Contents
Bond Referenda History
County Manager:
County Attorney:
Staff: Karin Talley, Department of Management and Finance
ARLINGTON COUNTY, VIRGINIA
County Board Agenda Item
Meeting of July 17, 2021
DATE: July 16, 2021
SUBJECT: Fiscal Year (FY) 2022 – FY 2024 Capital Improvement Plan (CIP) Adoption (The
Public Hearing for this item has concluded).
C. M. RECOMMENDATIONS:
1. Adopt the Fiscal Year 2022 – FY 2024 Capital Improvement Plan.
2. Adopt the attached FY 2022 County Bond Funds Appropriations Resolution (Attachment
A).
3. Authorize the addition of seven (7) full-time permanent FTEs to support the
implementation of projects for the transportation capital program which will funded by
the Transportation Capital Fund.
ISSUES: This is a request for County Board consideration/adoption of the proposed FY 2022 –
FY 2024 Capital Improvement Plan and appropriate County bond funds.
SUMMARY: The proposed CIP provides a three-year plan for investment in County and
School infrastructure and assets, totaling $1.25 billion. Funding sources for the CIP include
federal and state grants, bonds, pay-as-you-go (PAYG) funding, short-term financing, developer
contribution, and dedicated funding sources such as water/sewer revenues, stormwater revenue,
and dedicated transportation taxes.
BACKGROUND: Given the continued uncertainty of future economic conditions due to the
financial impact of the COVID-19 pandemic, the County Manager proposed a three-year CIP in
May 2021. This “bridging” capital plan allowed us to move beyond our “must-do” investments
and afforded us the opportunity to invest in asset state-of-good repair and a limited set of
community priorities as laid out in various Board-adopted plans, and importantly continue
planning for future investments. While certainly an improvement over last spring’s outlook, this
three-year CIP is still constrained. With the reduced revenue resulting from the pandemic and
the continued commitment to reasonable and restrained spending, this CIP is focused on limiting
64. A.
A - 18
Return to Table of Contents
- 2 -
the projected growth in annual County General Fund debt service for the next few years. By
limiting the County debt service growth to $3.7 million in FY 2023 and $5.3 million in FY 2024,
it allows the County to bridge through the next year of budget deliberations and the economic
recovery, and then return to the normal 10-year CIP process in late spring 2022.
The CIP provides for more investment than we anticipated would be feasible at this same time
last year. It meets existing commitments to regional priorities like Metro, restarts efforts toward a
“state of good repair” for County infrastructure and makes down payments on commitments
made through land use, planning, and program review efforts. Many of these planning efforts
and the anticipation of better fiscal times ahead provide the start of the roadmap for the FY 2023
10-year CIP.
DISCUSSION: The table below summarizes the allocation of funds for the FY 2022 – FY 2024
Capital Improvement Plan by program area. The total County and School CIPs total $1.38
billion. Program summaries can be found on the following pages.
FY 2022 – FY 2024 Capital Improvement Plan
(in $000’s)
*The Arlington Public School (APS) Board proposed CIP is not included in the table above because the
School Board had not taken action at the time the County proposed its CIP.
Capital Program Area FY 22-24 FY 22-24
Proposed Adopted $ Change
Parks and Recreation $34,315 $34,815 $500
Transportation 710,128 710,328 200
Metro 93,200 93,200
Public/Government Facilities 37,345 37,345
Information Technology & Public Safety 68,881 68,881
Regional Partnerships & Contingencies 4,312 4,312
Community Conservation & Economic
Development 23,500 23,500
Subtotal County Capital 971,681 972,181 700
Water and Sewer Infrastructure 185,155 185,155
Stormwater Management 95,850 95,850
Total County CIP $1,252,686 1,253,186 $700
Schools Capital Program 123,200
Total County & Schools CIP $1,376,386
A - 19
Return to Table of Contents
- 3 -
Parks and Recreation Program includes $34.8 million in funding for park trail and bridge
modernization, parks capital maintenance, and synthetic turf replacements. Projects included in
the adopted CIP are in alignment with the adopted Public Spaces Master Plan and its goals to
move the Park program forward. The CIP continues the enhanced park trail and bridge program,
including the replacement of one bridge at Lubber Run and the Glencarlyn Park bridge. Park
capital maintenance includes the full renovation of the aging Bluemont Park tennis courts, picnic
shelter and related amenities and given its location in a resource protection area, it will require
substantial redesign. Funding is also included for the replacement of three existing synthetic turf
fields as they reach the 8- to 10-year age to ensure safety for field users. Conversion of the upper
grass field at Thomas Jefferson Park to synthetic is also planned. The CIP does include planning
funds for the Arlington Boathouse given the progress and momentum with our federal partners
on this generational project. Finally, an additional $500k are included in the adopted CIP for the
planning of Gateway Park in fiscal year 2022.
Transportation Program totals $710.3 million in investments including a number of significant
investments for bridge renovation and maintenance, the Columbia Pike Multi-Modal program,
Crystal City, Pentagon City and Potomac Yards Streets program, Metro station entrances, ART
facilities and Columbia Pike transit facilities. This total reflects a budget adjustment to include
risk of project execution to more accurately forecast annual expenditures. The unadjusted
program totals $710.3 million in projects. The goals of the Transportation Master Plan are
considered in the projects that are funded in this adopted CIP. The program includes $35.7
million for paving, maintaining the targeted paving condition index (PCI) of 75 – 80. To help
achieve accelerated implementation of projects in the transportation program, an additional 7.0
FTEs are requested that will be fully funded by the Transportation Capital Fund (no impact to the
General Fund). A change from the proposed to the adopted CIP is the addition of $200k for an
engineering feasibility study for the Arlington Boulevard Multi-Use Trail.
Metro Program includes $93.2 million for our required Metro contribution which is in line with
the expenditures projected in the previous CIP.
Public and Government Facilities Program investment of $37.3 million. Highlights include
capital maintenance of building systems (roof replacements; heating, ventilation, air conditioning
(HVAC) upgrades; electric system upgrades) and renovation of the 27-year-old Courts/Police
building to include upgrades to courtrooms and judge’s chambers, as well as technology
backbone infrastructure improvements. To consolidate some Fire business processes,
infrastructure and interior improvements are being made to the 2020 N. 14th Street building
located directly across from the Courts/Police building.
Information Technology investments of $43.4 million are primarily focused on maintenance and
replacement of PCs, servers, network equipment, and radio systems. Funding for new technology
systems to help manage the Child Welfare and Day-Care Child-Care Licensing systems for the
Department of Human Services is also included. Most significantly, the proposed CIP includes
$14 million to replace the County’s aging human resources and financial system (PRISM).
A - 20
Return to Table of Contents
- 4 -
Public Safety investments focus $25.5 million on end-of life equipment replacement such as fire
defibrillators, mobile data computers and, public safety radios. In addition, funding is provided for
improvements to the Justice Center Security System.
Water and Sewer Infrastructure includes $185.2 million with an emphasis on maintenance
capital, water distribution and sanitary sewer improvements. The CIP includes $185.2 million
for utilities, which includes the implementation of the Solids Master Plan, the Washington
Aqueduct Capital ($15.7million) and Gravity Transmission mains ($5.7 million), along with our
state of good repair programs for close to 1,000 miles of water and sanitary sewer lines across
the County. The Water Distribution Master Plan and Sanitary Master Plan were both pivotal in
helping prioritize the projects included in the adopted CIP. Several significant projects
underway include the Fairfax Water Interconnection, Spout Run Sanitary Sewer Relining, and
the South Troy Street Water & Sewer Improvements.
Stormwater Fund includes $95.9 million for capacity improvements, water quality projects and
maintenance capital. Projects and project criteria from the Stormwater Master Plan are
incorporated into the adopted stormwater CIP. Highlights include $26.8 million for the Spout
Run Watershed, $16.7 million for the Cardinal Elementary School Stormwater Detention, and
$5.4 million for the Ballston Pond Watershed Retrofit. These investments reflect the significant
effort that will be required to update the County’s stormwater infrastructure. Other projects
underway include the Donaldson Run Tributary B Stream Restoration, and Ballston Pond.
Arlington Public Schools Arlington Public Schools adopted its FY 2022 – FY 2024 CIP on June
24, 2021. The program totals $123.2 million, including $23.01 million of general obligation
bonds. The Schools CIP includes funding for kitchen improvements and major HVAC
replacements, entrance and vestibule renovations, improvements to The Heights Building and
synthetic turf field replacements.
County Bond Funds Appropriations Since a portion of the FY 2022 appropriation is for bond
funded projects to be approved on the November 2, 2021 Referenda, appropriation of those
projects is requested now but is contingent upon and will not occur until the respective
referendum for each project is approved by voters, has been filed with the Circuit Court, and the
required 30-day contest period has expired. All project expenditures being appropriated as FY
2022 bond funds are as planned in the FY 2022 – FY 2024 CIP and are consistent with the debt
projections included in the CIP.
PUBLIC ENGAGEMENT: Due to the impact of COVID-19, community input on the CIP was
sought primarily through online channels of communication. Input for the FY 2022 – FY 2024
CIP was solicited in April. This resulted in over 700 total online responses. In addition, an online
feedback form was posted in June and constituents were encouraged to share information to the
County Board on the County Manager’s proposed CIP.
In addition to the on-line engagement survey, program specific information was discussed at
Board work sessions on May 25, June 22 June 24 and July 13; a joint County-Schools work
session on June 9; a CIP public hearing held on June 29; a Planning Commission meeting on
July 6 as well as meetings with other commissions (Sports Commission, Parks and Recreation
A - 21
Return to Table of Contents
- 5 -
Commission, Natural Resources and Forestry Commission, Transportation Commission, Fiscal
Affairs Advisory Commission, and Civic Federation).
When the County Manager released his proposal, the news release, Board presentation and
Manager’s Message were translated into Spanish, Mongolian, Amharic and Arabic.
FISCAL IMPACT: The annual debt service includes both the Schools Adopted CIP and the
County’s proposed CIP. The CIP complies with the County Board’s debt and financial policies,
resulting in projected debt levels that are consistent with the County’s triple-AAA bond ratings.
A - 22
Return to Table of Contents
- 6 -
ATTACHMENT A
FISCAL YEAR 2022 COUNTY APPROPRIATION RESOLUTION
Be it resolved by the County Board of Arlington County, Virginia, that the following
appropriations of $57,505,000 are hereby made for Fiscal Year 2022 for projects to be approved
on the November 2, 2021 bond referenda. Appropriations are effective only after a) approval by
the voters of the bond referenda, b) the results have been certified and filed with the Circuit Court,
and c) the required thirty-day period for contesting each bond referendum has expired:
COUNTY BOND FUNDS: 2021 Referenda 1,2
Appropriation
Street and Highway Bond Fund (314) 8,000,000
Government Facility Bond Fund (317) 9,535,000
Public Recreation Bond Fund (324) 1,800,000
Metro Bond Fund (333) 20,700,000
TOTAL COUNTY BOND FUNDS APPROPRIATIONS: $40,035,000
For the operation and maintenance of Public Schools and Community Activities
Facilities to be expended on order of the School Board
Schools Bond Fund (887) $17,470,000
TOTAL APPROPRIATIONS FOR COUNTY $57,505,000
1 2021 bond referenda appropriations are effective only after a) approval by the voters of the bond
referenda, b) the results have been certified and filed with the Circuit Court, and c) the required
thirty-day period for contesting each bond referendum has expired
2 Only the 2021 referenda approved bonds planned to be issued in FY 2022 are included in the
appropriation for FY 2022
A - 23
Return to Table of Contents
County Board Agenda Item
Meeting of July 17, 2021
DATE: July 14, 2021
SUBJECT: Resolutions and Questions to be included in the 2021 Bond Referenda
C. M. RECOMMENDATIONS:
1. Adopt the resolutions in Attachment A, as summarized below, and the explanation of
the referendum questions to appear in publications, at voter registration sites, and
polling places as detailed in Attachment B, in order to initiate and facilitate the
November 2, 2021, bond referenda.
a. Metro and Transportation $ 38,700,000
b. Local Parks and Recreation 6,800,000
c. Community Infrastructure 17,035,000
d. Arlington Public Schools 23,010,000
TOTAL $85,545,000
2. Request that the Electoral Board list the referenda on the ballot in the order detailed in
this report as shown in the Ballot Layout section on page 3.
3. Direct the County Manager to take all the steps necessary to ensure that the
information provided to voters by the County is printed in English, Spanish, Amharic,
and Mongolian.
ISSUE: This is a request for approval for the placement of capital projects, consistent with the
County and Schools’ Adopted Capital Improvement Programs (CIP), on the November 2021 ballot
for consideration by the voters for general obligation bond funding.
SUMMARY: The County Board will approve the Fiscal Year (FY) 2022 – FY 2024 CIP and 2021
Bond Referenda at the July 17, 2021, recessed County Board Meeting to be held on July 20,
2021.The County’s Adopted CIP includes various projects to be considered for a November 2, 2021
County government bond referenda of $62.535 million, and a Schools’ bond referendum request of
$23.01 million, adopted by the School Board on June 24, 2021.
A - 26
Return to Table of Contents
BACKGROUND: The County government’s proposed bond totals are derived from a compilation
of individual projects contained in the Adopted CIP. These projects are classified into separate
categories. If the bond referenda questions are approved by the voters, the County is legally
prohibited from reallocating funding from one referenda category to another. Within the referenda
categories, however, the County Board may make changes to specific projects to the extent
permitted under the language; this flexibility is necessary because of potential rapid changes in
construction pricing or other uncontrollable factors. The County Board also has the option of
issuing a lesser amount of bonds than that approved by the voters or revising the specific projects,
within the proposed authorizing language, to be funded with bond proceeds. Attachment B is a draft
of the bond questions and explanations that would appear on the ballot and in informational
publications.
DISCUSSION: The County and Schools’ Adopted CIPs, which set the parameters for the
County and Schools bond referenda requests, reflects a balance of strategic investments and
maintaining our existing infrastructure. The adopted referenda requests, which are summarized
below, are consistent with the County’s financial and debt management policies.
REFERENDUM
QUESTION PRIMARY PROJECTS / PROGRAMS AMOUNT
Metro and
Transportation
Metro Capital Improvements, Paving, Bridge
Maintenance, Renovation and Replacement
$38,700,000
Local Parks &
Recreation
Arlington Boathouse, Bluemont Park Tennis Court
Complex Replacement, Trail and Bridge Modernization
6,800,000
Community
Infrastructure
Neighborhood Conservation, Facilities Maintenance
Capital, Courthouse Complex Facilities Improvements,
Courts/ Police Building Improvements, Quincy Property
Redevelopment
17,035,000
Arlington Public
Schools
Building refresh and kitchen renovations at Campbell,
Drew, and Randolph, Long Branch, and Hoffman-
Boston Elementary Schools, Swanson and Kenmore
Middle Schools, and the Langston High School
Continuation Program; Phase 2 of The Heights Building
23,010,000
TOTAL $85,545,000
More detail on each of the programs and projects can be found in the CIP documents on the
County’s and Schools’ websites. The summary of County projects included in the 2021 bond
referenda can be found in the Appendix of the County’s Adopted FY 2022 - FY 2024 CIP, with
additional details in the remainder of the County’s CIP document. The Adopted CIP document will
be published on the County’s website no later than September 2021.
A - 27
Return to Table of Contents
Attachment B includes the proposed bond questions and explanations as they would appear in
informational publications distributed by the County at polling places, other County facilities, and
on the County’s website. Limitations on the explanations are imposed by state law, including that
the explanations must be neutral and not present arguments in favor or against the bond questions.
Consistent with state law, the actual ballot will reflect only the proposed bond question.
BALLOT LAYOUT
It is recommended that the following four bond referenda questions be on one or more rows or
windows on the ballot in the following order:
a. Metro and Transportation
b. Local Parks & Recreation
c. Community Infrastructure
d. Arlington Public Schools
PUBLIC ENGAGEMENT: Due to the ongoing impact of COVID-19, community input on the
CIP was sought primarily through online channels of communication. During the CIP development
process in February through April, staff conducted an online CIP engagement survey. A significant
portion of the CIP engagement and outreach strategy leveraged social media (Facebook, Instagram,
Twitter), press releases, County emails, and other communication methods to promote and
encourage participation.
In addition to the on-line engagement survey, program specific information was discussed at on-
line CIP work sessions on May 25, June 22, and June 24; an on-line joint County-Schools work
session on June 9; an in-person and on-line CIP public hearing held on June 29, and a final Board
wrap-up work session on July 13.
When the County Manager released his proposal, the news release, Board presentation and
Manager’s Message were translated into Spanish, Mongolian, Amharic and Arabic.
FISCAL IMPACT: The estimated impact on the County’s General Fund and Stormwater fund
from the proposed bond financing plans included in the adopted CIP and the proposed referenda
are shown below for Fiscal Years 2022 and 2023. The table below includes all outstanding
general obligation and subject to appropriation bonds, planned bond issuance from previously
approved referenda, and the planned bonds and associated debt service to be approved as part of
the 2021 Bond Referenda. All bonds planned in the CIP comply with the County’s financial and
debt management policies.
A - 28
Return to Table of Contents
PROJECTED COUNTY, SCHOOLS, AND STORMWATER DEBT SERVICE
FY 2022 and FY 2023 Estimates
(In Millions of $)
PROJECTED
FY 2022
PROJECTED
FY 2023
County 73.6 77.3
Schools 58.5 60.0
TOTAL $127.0 $137.7
Stormwater $0.9 $0.9
DESCRIPTION OF ATTACHMENTS
Attachment A - 2021 Bond Resolutions
Attachment B - 2021 Bond Questions and Explanations (as they will appear in publications)
A - 29
Return to Table of Contents
ATTACHMENT A
METRO AND TRANSPORTATION PROJECTS
WHEREAS, the County Board of Arlington County, Virginia, has determined that it is
advisable to support construction, acquisition, and rehabilitation of facilities by the Washington
Metropolitan Area Transit Authority (WMATA/Metro) and other transportation projects as
described below at an estimated cost of $38,700,000; and
WHEREAS, it appears that such improvements cannot be financed from current revenues;
BE IT RESOLVED BY THE COUNTY BOARD OF ARLINGTON COUNTY, VIRGINIA:
1. It is hereby determined that it is advisable for Arlington County to contract a debt
and issue its general obligation capital improvement bonds in the maximum principal amount of
$38,700,000 pursuant to the Public Finance Act of 1991, as amended, to finance, together with other
available funds, the cost of construction, acquisition, and rehabilitation of WMATA/Metro facilities
by the Washington Metropolitan Area Transit Authority, and to pay the costs of other transit,
transportation, paving, road and pedestrian enhancement projects across the County (the “Projects”).
2. The Circuit Court of Arlington County is hereby requested to order an election to be
held on November 2, 2021, provided that such date is at least 81 days after the date on which the
Court enters its order upon the question of contracting such debt and issuing bonds for such
purposes. The question on the ballot shall be in substantially the form shown in Attachment B.
3. The Clerk of this Board is hereby authorized and directed to cause a certified copy of
this resolution to be presented to the Circuit Court of Arlington County.
4. The County Board adopts this declaration of official intent under the Treasury
Regulations Section 1.150-2. The County Board reasonably expects to reimburse advances made or
to be made by the County to pay the costs of the Projects from the proceeds of its bonds.
5. This resolution shall take effect immediately.
A - 30
Return to Table of Contents
LOCAL PARKS & RECREATION
WHEREAS, the County Board of Arlington County, Virginia, has determined that it is
advisable to undertake local parks & recreation projects as described below at an estimated cost of
$6,800,000; and
WHEREAS, it appears that such improvements cannot be financed from current revenues;
BE IT RESOLVED BY THE COUNTY BOARD OF ARLINGTON COUNTY, VIRGINIA:
1. It is hereby determined that it is advisable for Arlington County to contract a debt
and issue its general obligation capital improvement bonds in the maximum principal amount of
$6,800,000 pursuant to the Public Finance Act of 1991, as amended, to finance, together with other
available funds, the cost of public improvements for Arlington County local parks & recreation (the
“Projects”).
2. The Circuit Court of Arlington County is hereby requested to order an election to be held
on November 2, 2021, provided that such date is at least 81 days after the date on which the Court
enters its order upon the question of contracting such debt and issuing bonds for such purposes. The
question on the ballot shall be in substantially the form shown in Attachment B.
3. The Clerk of this Board is hereby authorized and directed to cause a certified copy
of this resolution to be presented to the Circuit Court of Arlington County.
4. The County Board adopts this declaration of official intent under the Treasury
Regulations Section 1.150-2. The County Board reasonably expects to reimburse advances made or
to be made by the County to pay the costs of the Projects from the proceeds of its bonds.
5. This resolution shall take effect immediately.
A - 31
Return to Table of Contents
COMMUNITY INFRASTRUCTURE
WHEREAS , the County Board of Arlington County, Virginia, has determined that it is
advisable to undertake public facility improvements and other County infrastructure improvements,
as described below, at an estimated cost of $17,035,000; and
WHEREAS, it appears that such improvements cannot be financed from current revenues;
BE IT RESOLVED BY THE COUNTY BOARD OF ARLINGTON COUNTY, VIRGINIA:
1. It is hereby determined that it is advisable for Arlington County to contract a debt
and issue its general obligation capital improvement bonds in the maximum principal amount of
$17,035,000 pursuant to the Public Finance Act of 1991, as amended, to finance, together with other
available funds, the cost of public improvements for Arlington County facilities needs including
infrastructure and facilities maintenance capital (the “Projects”).
2. The Circuit Court of Arlington County is hereby requested to order an election to be
held on November 2, 2021, provided that such date is at least 81 days after the date on which the
Court enters its order upon the question of contracting such debt and issuing bonds for such
purposes. The question on the ballot shall be in substantially the form shown in Attachment B.
3. The Clerk of this Board is hereby authorized and directed to cause a certified copy of
this resolution to be presented to the Circuit Court of Arlington County.
4. The County Board adopts this declaration of official intent under the Treasury
Regulations Section 1.150-2. The County Board reasonably expects to reimburse advances made or
to be made by the County to pay the costs of the Projects from the proceeds of its bonds.
This resolution shall take effect immediately.
A - 32
Return to Table of Contents
ARLINGTON PUBLIC SCHOOLS PROJECTS
WHEREAS, the County Board of Arlington County, Virginia, has determined that it is
advisable to undertake certain capital projects for Arlington Public Schools, as described below; and
WHEREAS, it appears that $23,010,000 of such improvements cannot be financed from
current revenues; and
WHEREAS, the Arlington County School Board has requested by resolution adopted June
24, 2021, that the County Board request the Circuit Court of Arlington County to order an election
on the question of the proposed issuance of bonds to finance such projects;
BE IT RESOLVED BY THE COUNTY BOARD OF ARLINGTON COUNTY, VIRGINIA:
1. It is hereby determined that it is advisable for Arlington County to contract a debt
and issue its general obligation bonds in the maximum principal amount of $23,010,000 pursuant to
the Public Finance Act of 1991, as amended, to finance, together with other available funds, the
design and construction costs for new schools, school facility additions and renovations, and various
capital projects for Arlington Public Schools (the “Projects”).
2. The Circuit Court of Arlington County is hereby requested to order an election to be
held on November 2, 2021, provided that such date is at least 81 days after the date on which the
Court enters its order, upon the question of contracting such debt and issuing bonds for such
purposes. The question on the ballot shall be in substantially the form shown in Attachment B.
3. The Clerk of this Board is hereby authorized and directed to cause a certified copy of
this resolution to be presented to the Circuit Court of Arlington County.
4. The County Board adopts this declaration of official intent under the Treasury
Regulations Section 1.150-2. The County Board reasonably expects to reimburse advances made or
to be made by the County to pay the costs of the Projects from the proceeds of its bonds.
5 This resolution shall take effect immediately.
A - 33
Return to Table of Contents
ATTACHMENT B
2021 Bond Referenda
1. Metro and Transportation
QUESTION: Shall Arlington County contract a debt and issue its general obligation
bonds in the maximum principal amount of $38,700,000 to finance, together with other
available funds, the cost of various capital projects for the Washington Metropolitan
Area Transit Authority and other transit, pedestrian, road or transportation projects?
EXPLANATION:
This proposal will fund a variety of transportation, road, pedestrian enhancement and transit projects
across the County. The projects to be financed under this proposal are expected to be $20.7 million
to fund a portion of Arlington County’s share of WMATA / Metro’s capital improvement program,
$17.5 million to fund a portion of the costs for paving local streets and roadways, and $0.5 million
to fund bridge maintenance, and replacement. The County Board may reallocate bond funds among
other transportation projects within the County’s Capital Improvement Plan, as amended from time
to time, to the extent necessary or desirable.
A - 34
Return to Table of Contents
2021 Bond Referenda
2. Local Parks and Recreation
QUESTION: Shall Arlington County contract a debt and issue its general obligation
bonds in the maximum principal amount of $6,800,000 to finance, together with other
available funds, the cost of various capital projects for local parks & recreation?
EXPLANATION:
This proposal will fund a variety of parks and recreation projects. The projects to be financed under
this proposal are expected to be $5.0 million for the Bluemont Park Tennis Court Complex, $1.0
million for the trail and bridge modernization program, $0.8 million for the Arlington Boathouse.
The County Board may reallocate bond funds among other parks and recreation projects within the
County’s Capital Improvement Plan, as amended from time to time, to the extent necessary or
desirable.
A - 35
Return to Table of Contents
2021 Bond Referenda
3. Community Infrastructure
QUESTION: Shall Arlington County contract a debt and issue its general obligation
bonds in the maximum principal amount of $17,035,000 to finance, together with other
available funds, the cost of various capital projects, including but not limited to
Neighborhood Conservation, improvements to County facilities in the Court House
area, and other County infrastructure?
EXPLANATION:
This proposal will fund a variety of County infrastructure projects. The projects to be financed
under this proposal are expected to be $8.0 million for Courthouse Complex Renovations and
Infrastructure, $4.6 million for facilities maintenance capital projects, $2.0 million for
Neighborhood Conservation, $1.8 million for Courts / Police Building Improvements, and $0.7
million for the Quincy Property redevelopment. The County Board may reallocate bond funds
among other County and community infrastructure projects within the County’s Capital
Improvement Plan, as amended from time to time, to the extent necessary or desirable.
A - 36
Return to Table of Contents
2021 Bond Referenda
4. Arlington Public Schools
QUESTION: Shall Arlington County contract a debt and issue its general obligation
bonds in the maximum principal amount of $23,010,000 to finance, together with other
available funds, the cost of various capital projects for Arlington Public Schools?
EXPLANATION:
This proposal will make funds available for the Arlington Public Schools' capital improvement
program. The proposed bonds are expected to fund the following projects:
• Building refresh and kitchen renovations at Campbell, Drew, and Randolph, Long
Branch, and Hoffman-Boston Elementary Schools, Swanson and Kenmore Middle
Schools, and the Langston High School Continuation Program ($11,620,000)
• Phase 2 of The Heights Building ($11,390,000)
The School Board may reallocate bond funds among other school projects within the School
Board’s Capital Improvement Plan, as amended from time to time, to the extent necessary or
desirable.
A - 37
Return to Table of Contents
Project Name Description Funding
Source
Project Cost Current Status Anticipated Completion
6th St N & N. Edison
St
Intersection Improvement Bonds $658,637 Design Spring 2023
11th St N &
N. Danville St
Open Space Improvement Bonds $492,338 Design Spring 2023
12th St S &
S. Scott St
Intersection Improvement Bonds $500,000 Design Spring 2023
S. Abingdon St –
31st St S to 31st Rd S
Street Improvement Bonds $394,694 Design Spring 2023
Nauck Town Square Construction of Town Square Bonds $6,550,000 Construction Fall 2021
INFORMATION TECHNOLOGY
Computer Aided
Dispatch (CAD)
Assessment
• Phase I – defining scope and timeline
of CAD
Design currently underway
PAYG $7,480,000 Planning Fall 2022
Fire Command Vehicle
Technology Refresh
• Upgrading the Fire Department’s
command vehicle for use by both
Police and Fire Departments.
PAYG $270,000 Implementation Fall 2021
ConnectArlington
Fiber Network
• Prepare utilities poles to receive new
fiber at various school locations
(aerial make-ready)
• Handhole corrections
• Extend fiber to APS Ed Center/Quincy
complex
Bonds $1,179,00 Planning &
Construction
Spring 2022
Core Network
Maintenance -
Network Edge Refresh
(CTP)
• In-Building Network Equipment
• Courts Police Building (CTP)
Short-Term
Financing
$550,000 Construction Fall 2021
Core Network
Maintenance -
Network Edge Refresh
(Countywide)
• In-Building Network Equipment
• Countywide Upgrades
Short-Term
Financing
$1,344,972 Planning Spring 2022
Electronic Payment
Portal
• Common Payment Engine for County
Inbound Payments
Short-Term
Financing
$2,000,000 RFP Winter 2022
County Website
Replacement
• New Public-Facing County Website PAYG $214,000 Design/
Implementation
Fall 2021
A - 39
Return to Table of Contents
PARKS & RECREATION
Alcova Heights Park
Renovation, Phase 1
• Phase 1 of the park redevelopment
• Includes replacement of one picnic
shelter, sand volleyball court, site
amenities, paths, right-of-way
improvements, new stairs, signage and
supplemental landscaping.
Bonds
$2,395,000 Plan Review
Bidding Fall
2021
Construction
Fall 2022
Bluemont Junction
Trail Milling and
Repaving
• Trail Modernization Program
• Repave the main trail from the
intersection of Wilson Boulevard and
George Mason Drive to the bridge over
Four Mile Run at the Washington and Old
Dominion
Bonds $550,000 Construction
Fall 2021
Crystal City Parks and
Public Spaces; 15
th
Street Park
• DPR will lead the public engagement/park
planning process anticipated to begin
summer 2021 with an anticipated County
Board adoption of the Park Master Plan
late 2021. A one-year final design process
is anticipated during 2022. Park
construction is anticipated to begin Spring
2023 soon after the roadway project is
completed. Some pre-design efforts have
taken place.
TIF $450,000 Scoping Design Completion
Winter 2022;
Construction Completion
Fall 2024
Crystal City Parks and
Public Spaces;
Temporary park at S.
Clark and Bell Street
• Scoping to upgrade a portion of the
right-of-way at S. Clark and Bell Street for
temporary use as a public space.
TIF $500,000 Design Design Completion
Fall 2021;
Construction Completion
Summer 2022
Fort Scott Park
Accessibility
Renovations
• Accessibility renovations to the parking
lot, park walkways and the restroom
building
Bonds $770,000 Construction Fall 2021
Glencarlyn Pedestrian
Bridge Replacement
• Design and construction to replace the
bridge near the dog park. Intend to reuse
existing concrete bridge abutments for
new bridge structure.
PAYG/
Bonds
$150,000/
$660,000
Construction
Document
Preparation and
Permit Review
Design Completion
Fall 2021;
Construction Completion
Summer 2022
Gunston Bubble
Replacement
• Design and construction of a structure to
replace the air-supported structure ("the
Bubble") over the indoor athletic field.
PAYG / Bonds $1,297,000 Construction Construction Completion
Spring 2022
A - 40
Return to Table of Contents
Gunston Park
Playground and Picnic
Shelter
• Project scope includes replacement of the
playground and picnic shelter.
Topographic survey complete. Some
pre-design efforts have taken place.
Bonds $1,205,000 Scoping Design Completion
Summer 2022;
Construction Completion
Winter 2023
Jennie Dean Park,
Phase 1
• Renovation of all park assets
• Including diamond fields, picnic shelter,
restrooms, playground, basketball court,
site furnishings, walkways, signage and
landscaping.
PAYG / Bonds $18,374,000 Construction Construction Completion
Spring 2022
Lacey Woods Park
Improvements
• Project involves accessibility upgrades to
the restroom building and replacement of
the basketball court.
PAYG/ Bonds $2,203,000 Scoping Design Completion
Fall 2022;
Construction Completion
Winter 2023
Long Bridge Park
Aquatics/Fitness
Center
• Construction of an aquatics and fitness
facility and seven-acre park to complete
the build-out of Long Bridge Park.
PAYG / Bonds $67,000,000 Close-Out Final Completion Fall2021
Lubber Run
Pedestrian Bridge #2
Replacement
• This project will provide a second bridge
in the park for the two bridges lost in the
storm of July 2019. Initial efforts will be to
determine the optimum location for this
bridge. Proposal from bridge consultant
under review. Staff is developing an
online survey and compiling a short
educational video of the stream corridor
that will highlight the project scope of
work and other key environmental
factors.
PAYG/
Bonds
$225,000/
$900,000
Design Design Completion
Spring 2022;
Construction Completion
Winter 2022
Madison Manor Park
Restroom
Renovations
• Demolition and renovation of the
restroom building
Bonds $394,000 Construction Final Completion Fall 2021
Marcey Road Park
Tennis/Basketball
Court
• Replacement of tennis and basketball
courts and associated improvements.
Bonds $1,785,000 Construction Construction Completion
Spring 2022
Monroe Park
Playground
• Design for the replacement of the
playground, site circulation, site
furnishings and stormwater management
improvements.
Bonds $236,000 Design Design Completion
Summer 2022
A - 41
Return to Table of Contents
Rosslyn Highlands
Park (RHP+)
• Construction of a new Rosslyn Highlands
Park at the Wilson School site and
construction of a children's playground.
PAYG / Bonds $4,283,000 Construction Construction Completion
Fall 2021
Thomas Jefferson
Park Planning &
Design
• Replacement of the tennis and basketball
courts at Thomas Jefferson Community
Center.
Bonds $915,000 On Hold
pending partial
master planning
of the entire
park area
Planning Completion
Spring 2023
Thomas Jefferson
Upper Field Synthetic
Turf Conversion
• Synthetic Turf Program. Project involves
conversion of the grass field to synthetic
turf plus additional site amenities, such as
bleachers, walkways and waste
receptacles. Some community
engagement efforts and project expenses
(including permitting) incurred prior to
project deferral due to COVID.
PAYG/ DPR
“Field Fund”
User Fees
$2,050,000 Construction Construction Completion
Spring 2022
Towers Park
Playground
Replacement
• Replacement of the children's playground
• Final asset to be replaced in the park
renovation
Bonds $1,065,000 Construction Construction Completion
Summer 2022
Tuckahoe Playground
Safety Surfacing
Replacement
• Design and construction for the
replacement of the synthetic playground
surfacing. Beginning preliminary scoping
work for project.
PAYG $485,000 Scoping Construction Completion
Spring 2022
Upper Bluemont Park
Improvements
• Conceptual Design only for the
replacement of the tennis courts, court
lighting, picnic shelter, restrooms, parking
lot, walkways, stormwater management,
signage and landscaping.
Bonds $575,000 Design Design Completion Summer
2022
"Teardrop Parcel" at
South Eads Street and
Army-Navy Drive in
Crystal City
• Park master planning process is underway
for this space and subsequent
construction of the park will be managed
by the County.
Developer
Funds
$3,063,737 Planning Construction Completion
Fall 2023
A - 42
Return to Table of Contents
PUBLIC / GOVERNMENT FACILITIES
Fire Station #10
Replacement
• Replaces the aged and undersized existing
Fire Station 10
• New fire station is being constructed by
Penzance
• Costs shown reflect cost of County Staff
time support of project; County staff is
responsible for project oversight.
PAYG
Developer
Contribution
$600,000 Construction Fall 2021
Courts Police Bldg.
Automatic Transfer
Switches and
Generator Controls
• Design & Construction: Electrical upgrade
design to replace all six Automatic
Transfer Switches (ATS's) and generator
controls.
PAYG / Bond $1,241,000 Design Summer 2022
1425 N. Quincy • Interior upgrades to accommodate Police
and Fire vehicles and equipment.
Includes: lighting, electrical, ventilation
for vehicles, new overhead doors, and
ADA restrooms.
• Site improvements to include concrete
ramp for vehicles and parking lot
improvements.
Bonds
$2,995,000
Design Summer 2022
Solid Waste/Traffic
Engineering &
Operations Building –
finish and systems
replacements
• Roof replacement; HVAC replacement;
install building automation system (BAS);
Exterior work- loading dock concrete
repairs.
• The project includes relocation of staff;
replacing acoustical ceiling tile system;
interior painting; replacing flooring;
kitchen counters and cabinet refresh;
complete refresh of 2 bathrooms and
showers; replacement of interior lighting
Bond $3,535,000 Design Winter 2022
A - 43
Return to Table of Contents
Fire Station #8
Rebuild
• Project is to replace the aged and
undersized existing Fire Station 8 at 4845
Lee Highway
• Approximately 20,000 square feet and
include four apparatus bays and gender-
neutral accommodations for staff
• Temporary Station that will utilize one of
the residential structures acquired for
dorms, offices and related support spaces
and a tent structure for two, apparatus
bays.
• Conversion from gas to diesel of the Fuel
Station located at Fire Station No. 2 to
provide temporary service during the
construction of the new Fire Station No. 8
project.
PAYG / Bonds $25,040,000 Construction Summer 2023
Bozman (CHP)
Renovation
• Concepts under review given COVID-19.
• Looking to enhance technology equipped
conference rooms, increase elevator
capacity and security.
Tenant
Improvement
and
Commission
Rebate
$25,500,000 Various phases
between design
and
construction
Fall 2023
Fire Station
Renovations (Kelly
Day)
• Renovations of County Fire Stations to
accommodate a fourth shift (Kelly Day).
• Renovations include additional storage,
living space, locker room facilities and
upgrading decontamination areas.
Bonds $3,545,000 Design Winter 2023
A - 44
Return to Table of Contents
STORMWATER MANAGEMENT
Spout Run Watershed
Capacity Infrastructure,
Phase 1
First of three planned phases project
with blended engineering (distributed
detention, pipe improvements, tertiary
assets installed, and overland relief)
Bonds $30,160,000 Design Spring 2025
Cardinal Elementary
School Stormwater
Detention (project
formerly named Reed
School Detention)
• Collaborative project with APS for
compound use of public lands (Schools,
Parks) to expand stormwater capacity
system (detention) and mitigate flood
intensities.
• Detention is anticipated to be located
below grass field and baseball diamond
located at the elementary school.
Bonds/ Other
Previously
Approved
Funds
$20,000,000 Design and
Construction
Fall/ Winter 2022
Donaldson Run
Tributary B Stream
Restoration
• Comprehensive restoration of 1,800
linear feet of degraded stream channel
to mitigate erosion, improve habitat,
and protect threatened drinking water,
sanitary sewer, and trail infrastructure
Other
Previously
Approved
Funds
$2,745,000 Construction Spring 2022
Ballston Pond
Watershed Retrofit
• Provides wetland restoration and
enhanced water quality treatment for
over 400 acres that drain to Lubber Run
• Improves aesthetics, interpretation, and
wildlife habitat
Grants /
Bonds
$6,040,000 Procurement Spring 2023
Sparrow Pond
Watershed Retrofit
• Retrofit the pond to create a
constructed wetland and restore the
pond’s volume, improve stormwater
treatment, provide habitat, and be
designed to make subsequent
maintenance easier and less costly.
Other
Previously
Approved
Funds/ Bonds
$3,135,000 Design Winter 2024
Donaldson Run Outfall
/ Channel
• Rehabilitates failing critical assets and
improves channel capacity
• Construction of the revised first phase of
this outfall, 110 linear feet of 18-inch
storm sewer and related appurtenances,
will divert surface flow away from
existing retaining walls and acquire
improved easements for existing storm
drainage infrastructure
Sanitary
District Tax
$1,433,000 Procurement Spring 2022
A - 45
Return to Table of Contents
Four Mile Run
Restoration/Flood
Control/Dredging
Project
• Capacity dredging and maintenance per
agreement with US Army Corps of
Engineers
• Collaborative project with City of
Alexandria
Sanitary
District Tax/
Other
Previously
Approved
Funds
$3,080,000 Procurement Spring 2022
Dumbarton Culverts
Replacement
• Replacement of two undersized culverts
that are in poor condition
Other
Previously
Approved
Funds/ Bonds
$6,760,000 Design Spring 2023
Risk Assessment and
Management Plan
(RAMP)
• A watershed-scale Vulnerability and Risk
Assessment
Sanitary
District Tax/
Other
Previously
Approved
Funds
$900,000 In Progress Winter 2022
TRANSPORTATION (Note: External funding may be under agreement, approved, or anticipated)
Army Navy Drive
Complete Street
• Re-build Army Navy Drive in Pentagon
City
• Includes protected bike lanes, safer
pedestrian crossings, accommodates
future high-capacity transit, and green
landscaping treatments to reduce
stormwater run-off.
NVTA
Regional
funds, Federal
funds, TCF
C&I, TIF,
Developer
Contributions
$16,100,000 Design Fall 2024
ART O&M Facility • Operations and maintenance facility for
growing fleet of ART buses
Will include parking for buses as well as
space for administration and O&M staff
State capital
grants, NVTA
Regional
funds, TCF
(C&I, NVTA
local)
$64,380,000 Design Winter 2025
Ballston Multimodal
Improvements
• Expand and update transit bays, bus
shelters, pedestrian circulation, and
bicycle parking at the surface level
around the Ballston-MU Metro station
State capital
grants, TCF
C&I, Federal
funds, GO
bonds
$7,835,100 Construction Spring 2022
A - 46
Return to Table of Contents
Ballston-MU Metro
Station West Entrance
• Construct a new west entrance to be
located at the intersection of N. Fairfax
Drive and N. Vermont Street to improve
Metrorail access.
State capital
grants,
Regional
funds (NVTA,
NVTC), TCF
(C&I, NVTA
local),
Developer
Contributions
$130,021,000 Design Summer 2026
Bike Arlington –
Cemetery Wall Trail
Project
• Construct a new 10'-wide, multi-use trail
to connect Memorial Avenue to new
Columbia Pike interchange being
implemented by Eastern Federal Lands
Highway as part of the Cemetery
expansion
Regional
funds, Federal
funds, TCF
(C&I, NVTA
local)
$25,153,000 Planning Fall 2027 (rough estimate)
Boundary Channel
Drive Interchange with
I-395
• Improve traffic operations and safety
and greatly expand pedestrian and
bicycle facilities to meet current
demands and for future planned growth
in Crystal City with multimodal
connections and conversion of ramp
terminals to roundabouts
State capital
grants, NVTA
Regional
grants, GO
bonds, TCF
C&I, TIF
$20,590,442 Bid Winter 2023
Bridge Renovation:
Arlington Ridge / Mt.
Vernon Bridge
Replace Arlington Ridge Road bridge
over Four Mile Run to address structural
deficiencies that have necessitated
partial closure of sidewalks.
50%
Contribution
from the City
of Alexandria,
State capital
grants,
Federal funds,
GO Bonds,
PAYG
$27,026,074 Planning Summer 2024
Bridge Renovation:
West Glebe Bridge
• Replace West Glebe Road bridge over
Four Mile Run to address structural
deficiencies that have necessitated
imposition of traffic restrictions and
closure of sidewalks
50%
Contribution
from the City
of Alexandria,
PAYG, GO
Bonds
$12,000,000 Design Summer 2022
A - 47
Return to Table of Contents
Columbia Pike
Multimodal Street
Improvements
• Multimodal street improvements to
include reconstructed streets, shifted
curb lines, streetlights, street trees, and
wider sidewalks achieved through
undergrounding overhead utilities.
State Capital
grants, NVTA
Regional
Funds, TCF
C&I, GO bonds
$157,612,000 9 projects:
1 complete
2 in
construction, 6 in
design
Spring 2025
Columbia Pike Transit
Stations
• Design and construct transit stations
along Columbia Pike to provide safer
access to transit, improved bus shelters,
increased seating and real-time bus
arrival information
•
TCF C&I,
Federal funds,
State capital
grants, and
GO bonds
$16,915,000 Site work for 8
locations in
construction,
others in various
stages of design
Summer 2025
Crystal City Metro
Station East Entrance
Construct a new entrance at the east
end of the Crystal City metro station to
provide easier access from Crystal Drive,
the Virginia Railway Express (VRE)
Station, and a Crystal City Potomac Yard
Transitway station (PPEA Project)
Federal funds,
State capital
grants, NVTA
Regional
funds, TCF
(C&I, NVTA
local), TIF
$94,891,000 Design Planning Fall 2023
Crystal City Street
Improvements -
Various locations
• Clark Bell extension at 15th Street
• Improvements along 23rd Street
• Rebuild 18th Street South between
South Fern Street and South Eads Street
to continue the existing South Hayes
Street protected bike lanes
• 12th Street multimodal improvements
to support the Transitway Extension
NVTA
Regional
funds, TCF
C&I, TIF
$28,157,000 4 projects:
1 in Construction,
3 in design
Winter 2023
Crystal City to
Washington National
Airport (CC2DCA)
Intermodal Connector
• Construct a multimodal connection
between Crystal Drive and Ronald
Reagan Washington National Airport
(DCA). The project will begin the federal
regulatory environmental analysis study
in 2021.
Federal Funds,
NVTA
Regional
funds, TCF
C&I, TIF
$38,088,000 Planning Summer 2029
Pentagon City Metro
Station Second
Elevator
Provide a street-to-mezzanine elevator
on the west side of South Hayes Street
to improve access to the Metro station,
improve ADA access, and provide
elevator redundancy.
Federal funds,
State capital
grants, GO
bonds, PAYG,
and TCF C&I
$10,499,000 Construction Summer 2023
A - 48
Return to Table of Contents
Premium Transit
Network (PrTN):
Transitway Extension
to Pentagon City
• Extend Crystal City-Potomac Yard
Transitway as a bus facility to Pentagon
City
Extension will serve local travel demand
within the corridor, including Amazon’s
HQ2, as well as enhance connections to
Metrorail and improve connections to
Columbia Pike.
State capital
grants, NVTA
Regional
funds, TCF
C&I, TIF
$27,667,000 Design Summer 2023
Rosslyn-Ballston Street
Improvements:
Washington Blvd and
13th Street North
• Reconstruct Washington Boulevard and
13th Street to remove the existing
reversible center lane and reorient the
i
ntersection to become a conventional
"T" intersection
• Redevelop the adjacent property into
County Parks and Recreation maintained
open space. Integrate with recent
im
provements at Clarendon Circle.
•
TCF C&I,
developer
contributions
$5,381,000 Construction Fall 2022
Rosslyn-Ballston Street
Improvements: Wilson
Blvd, 10
th St N to N.
Kenmore
• Street improvements on Wilson Blvd.
from N Kenmore Street to 10th Street
North, and on 10th Street N. from
Fairfax/N. Jackson Street to N. Ivy Street.
• New curb gutter and wider sidewalks,
stormwater upgrades, new crosswalks,
signal upgrades, streetlights, signage,
street trees and paving.
• Utility undergrounding along Wilson
Blvd.
TCF C&I,
developer
contributions
$11,114,000 Design Fall 2023
WATER & SEWER
Solids Master Plan
(Phase 2)
• Phase 2 projects focus on program
management and preparing the WPCP
site for future solids handling
improvements including relocation of
existing building functions, demolition of
underutilized facilities, and general site
work in advance of the Solids Master
Plan (Phase 3).
Utilities PAYG/
GO Bonds
$5,210,000 Planning Summer 2024
A - 49
Return to Table of Contents
Improvements to Eads
Street Property
• The Eads St. property serves as the
WPCP’s off-site warehouse. This project
replaces the failing retaining wall at the
back of the property.
Utilities PAYG 3,280,000 Procurement Summer 2022
Asset Management
Software Replacement
• Replacement of the WPCP’s Asset
Management Software used to track
equipment repairs, work orders,
warehouse inventory, and purchases.
Utilities PAYG $3,160,000 Planning Summer 2024
Gulf Run Sewer Force
Main
• Rehabilitation of approximately 2,191
linear feet of the 10-inch cast-iron force
main located uphill from the Gulf Run
Pump Station.
Utilities PAYG $1,700,000 Construction Fall 2021/ Winter 2022
Dover Run Sewer Force
Main
• Replace approximately 1,600 linear feet
of 6-inch cast-iron sewer force main
with corrosive-resistant 6-inch plastic
pipe.
• This is the entire segment of sewer force
main served by the Dover Run Pumping
Station.
Utilities
PAYG
$490,000 Construction Fall 2021
South Troy Street
Water and Sewer
Improvements
• This project will provide approximately
1,033 linear feet of 8-inch sanitary
sewer, 1,072 linear feet of 8-inch
watermain, and 86 linear feet of 12-inch
watermain.
• This project reduces the risk of sanitary
sewer backups in low lying areas of
South Troy Street and South Uhle Street
at South Glebe Road.
Utilities PAYG $1,100,000 Construction Fall 2021
Key Boulevard • Construction of a new water main along
Key Boulevard from North Jackson
Street to North Danville Street and on
North Herndon Street to replace an
existing and aging water main which was
built in 1920.
• The water main will improve fire flow
capacity and support demand in the
neighborhood.
Utilities PAYG $1,590,000 Construction Fall 2022
A - 50
Return to Table of Contents
Gravity Transmission
Mains - B1 (Phase 2)
• Completes a water main that will
provide redundant transmission capacity
through the Gravity One pressure zone.
• Project will provide an additional large
diameter supply for the Old Dominion,
Langston, Leeway, and Williamsburg
areas.
• Provides redundancy and additional
transmission capacity to pressure zones
serving much of the R-B corridor.
Utilities PAYG
/ GO bonds
$3,900,000 Construction Spring 2022
Fairfax Water
Interconnection
• Interconnection with adjacent water
system to provide an emergency water
supply.
Utilities PAYG $2,135,000 Procurement Spring 2022
Spout Run Sanitary
Sewer Relining
• Covers a 3,000-foot section of a 1930s
sewer main that runs under the North
Highlands neighborhood and is over 100
feet deep in some areas.
• The sewer line was inspected and will be
rehabilitated through trenchless
technology, including either
conventional or ultra-violet cured in-
place (CIPP) lining methods.
Utilities PAYG $7,068,000 Design Summer 2024
A - 51
Return to Table of Contents
Program Category FY 22 FY 23 FY 24 Total
Local Parks & Recreation 10,466 9,487 14,862 34,815
Transportation Initiatives 1
165,899 257,714 286,715 710,328
Metro 30,200 31,100 31,900 93,200
Community Conserv/Economic Develop. 7,500 8,500 7,500 23,500
Public / Government Facilities 23,845 10,500 3,000 37,345
Information Technology & Public Safety 17,931 26,862 24,088 68,881
Regional Partnerships 2,184 1,059 1,069 4,312
Total County Capital 258,025 345,222 369,134 972,381
Water & Sewer Infrastructure 50,545 59,435 75,175 185,155
Stormwater Management 2
37,510 24,935 33,405 95,850
Schools Capital 5 92,250 16,080 14,870 123,200
Total Program Cost 438,330 445,672 492,584 1,376,586
Arlington County, Virginia
Adopted CIP Program Summary
The Adopted FY 2022 - 2024 CIP includes typical capital projects such as maintenance capital, parks,
transportation, metro, community conservation, government facilities, information technology, regionals,
stormwater, water and sewer infrastructure, and Arlington Public Schools. Similar to the last CIP, this 3-
year CIP includes funding that has been previously approved in prior CIPs to show the full expenditure
by fiscal year of each capital project.
Capital Program Cost Summary (000s)
(1) Transportation Capital Fund is supported by a commercial real estate tax of $0.125 per $100 of assessed value and 30% of
revenues from regional taxes collected at the Northern Virginia Transportation Authority (NVTA). The Transportation Capital
Fund is supplemented by County PAYG as well as state and federal revenues.
(2) Stormwater Management Fund is funded from the Sanitary District Tax, Watershed Management Fund, State Grants and project
cost sharing with US Army Corps of Engineers. The sanitary district tax was increased for CY 2021 from $0.013 to $0.017 per $100
of assessed value by the County Board on April 20, 2021.
(3) Local and Regional funding for transportation projects from the Northern Virginia Transportation Authority (NVTA) were
approved by the General Assembly in 2013.
(4) Other previously approved funds: Any funds other than GO Bonds that were approved as part of prior CIPs that are to be
spent during the FY22-FY24 CIP.
(5) Excludes costs in the the Arlington Public Schools Adopted FY 2022 - FY 2024 CIP beyond FY 2024.
B - 1
Return to Table of Contents
Capital Funding Sources FY 22 FY 23 FY 24 Total
Pay-As-You-Go (PAYG) 5,925 11,142 11,341 28,408
Short Term Financing 13,452 18,870 18,130 50,452
General Fund GO Bond Issue 40,035 48,350 47,795 136,180
Utilities PAYG 14,430 14,995 13,630 43,055
Utility GO Bond Issue - 19,875 43,720 63,595
Sanitary District Tax 2
4,260 3,125 2,570 9,955
Stormwater GO Bond Issue - 11,140 19,510 30,650
Federal Funding 1,544 14,715 27,992 44,251
State Funding 20,039 23,908 67,791 111,738
Developer Contributions and Partnerships 7,400 7,200 7,770 22,370
Transportation Capital Fund (TCF) - C&I 1
11,896 20,492 57,263 89,651
TCF - HB2313 Local 3
8,175 7,135 13,957 29,267
HB2313 Regional 3
- 515 25,737 26,252
Tax Increment Financing 836 3,572 8,659 13,067
Other Funding 5,894 13,060 14,404 33,358
Schools GO Bond Issue 4
17,470 16,080 14,870 48,420
Subtotal New Funding 151,356 234,174 395,139 780,669
Previously Approved Funding
Authorized but Unissued Bonds 55,960 16,670 16,325 88,955
Issued but Unspent Bonds 58,502 4,112 212 62,826
Other Previously Approved Funds 4
172,512 190,716 80,908 444,136
Subtotal Previously Approved Funding 286,974 211,498 97,445 595,917
Total Funding 438,330 445,672 492,584 1,376,586
Capital Program Funding Source Summary (000s)
Arlington County, Virginia
Adopted CIP Program Summary
B - 2
Return to Table of Contents
It should be noted that these debt ratios include only general obligation and other tax-supported debt,
including bonds issued through the Industrial Development Authority (IDA) or other conduit issuers for
County projects where debt service is paid for from the General Fund. For example, these ratios include the
subject-to-appropriation Series 2017 IDA revenue bonds issued in October 2017 for the acquisition of the
Buck property, and for acquisition, design, and construction of the Head Start facility at 2920 South Glebe
Road. The ratios do not include bonds where the County has provided a moral obligation pledge as credit
support to a project (e.g., the Kettler Iceplex facility or the Gates of Ballston project). In charts C and D of
this section, the customary general obligation debt to the tax base ratio chart has been amended to also show
the effect of moral obligation or “subject-to-appropriation” backed capital financing. The ratios do not include
debt that is supported by user fees from enterprise funds, including debt included for the Utilities Fund.
It is also important to note that the FY 2022 – FY 2024 CIP does not include any funding beyond
FY 2024, including any future general obligation bond issuance. The County intends to return to a 10-year
CIP in FY 2023 at which time a full 10-year program for general obligation bond issuance will be presented
based on the estimated needs of the County and capacity within the County’s debt policies at that time.
Projected Debt Ratios
Ratio of Debt Service to General Expenditures No Greater Than 10% -- Over the ten -year
planning period, this ratio will range from 9.4% to 6.1%, peaking in FY 2024.
Outstanding Debt as Percentage of Market Valuation of Tax Base No Greater than 3% -- The
amount of debt that the County carries is moderate when compared to its tax base. This ratio is projected to
range from 1.4% to 0.5% over the ten-year planning period.
Ratio of Debt per Capita to Per Capita Income No Greater than 6% -- The County estimates
that the Debt to Income ratio will range from 5.0% to 1.7%, assuming 2.2% growth in per capita income.
Growth in Debt Service over the Ten -Year Planning Period No Greater than Ten- Year
Historical Growth in Revenues – Average annual growth in debt service is estimated at 2.2% from
FY 2021 – FY 2024 ( -1.0% over ten-years) compared to historical average ten-year revenue growth of 3.5%.
B - 4
Return to Table of Contents
Chart A
FY 2022 FY 2023 FY 2024 FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031
Adopted
GENERAL OBLIGATION BONDS ISSUED - COUNTY (1) 49,835,000 55,350,000 47,795,000 - - - - - - -
GENERAL OBLIGATION BONDS ISSUED - SCHOOLS (1) 41,870,000 36,080,000 44,870,000 14,010,000 9,500,000 10,000,000 - - - -
GENERAL OBLIGATION BONDS RETIRED 78,065,000 83,005,200 90,412,900 97,343,394 96,606,294 100,180,456 92,860,456 87,695,456 87,570,456 85,575,456
NET TAX-SUPPORTED GENERAL OBLIGATION
BONDS AT END OF FISCAL YEAR (2) 1,148,610,029 1,157,034,829 1,159,286,929 1,075,953,535 988,847,240 898,666,785 805,806,329 718,110,873 630,540,418 544,964,962
SUBJECT-TO-APPROPRIATION BOND ISSUANCE - - - - - - - - - -
SUBJECT-TO-APPROPRIATION BONDS RETIRED 5,945,000 6,060,000 6,110,000 6,185,000 5,105,000 5,190,000 5,280,000 5,370,000 5,435,000 5,495,000
NET TAX-SUPPORTED BONDS AT END OF FISCAL YEAR (3) 1,243,180,029 1,245,544,829 1,241,686,929 1,152,168,535 1,059,957,240 964,586,785 866,446,329 773,380,873 680,375,418 589,304,962
SCHOOLS DEBT SERVICE 58,495,553 60,026,573 63,057,233 66,989,104 64,348,968 66,030,027 59,860,344 55,007,541 53,218,645 50,244,336
COUNTY DEBT SERVICE (4) 75,214,123 78,886,834 84,203,678 88,191,588 85,750,178 84,081,110 79,106,077 74,872,136 72,770,213 70,05 3,699
TOTAL TAX SUPPORTED DEBT SERVICE 133,709,676 138,913,407 147,260,911 155,180,691 150,099,146 150,111,137 138,966,421 129,879,677 125,988 ,858 120,298,035
% GROWTH N TAX-SUPPORTED DEBT SERVICE 6.5% 4.9% 6.7% 4.7% -2.8% -1.9% -5 9% -5.4% -2 8% -3.7%
COUNTY ONLY -0.1%
% GROWTH N TAX-SUPPORTED DEBT SERVICE 6.3% 3.9% 6 0% 5.4% -3.3% 0.0% -7.4% -6 5% -3 0% -4.5%
COUNTY / SCHOOLS -0.4%
GENERAL GOVERNMENT EXPENDITURES (5) 1,543,403,639 1,558,837,676 1,574,426,052 1,598,042,443 1,630,003,292 1,670,753,374 1,712,522,209 1,755,335,264 1,799,218,646 1,844,199,112
DEBT SERVICE AS % OF EXPENDITURES 8.66% 8 91% 9.35% 9.71% 9.21% 8.98% 8.11% 7.40% 7.00% 6.52%
MARKET VALUATION OF TAXABLE PROPERTY (6) 84,366,622,713 86,391,421,658 88,464,815,778 90,764,900,988 93,124,788,414 95,918,532,066 98,796,088,028 101,759,970,669 104,812,769,789 107,957,152,883
NET TAX SUPPORTED DEBT AS % OF MARKET VALUATION (3%) 1.5% 1.4% 1.4% 1.3% 1.1% 1.0% 0 9% 0 8% 0 6% 0.5%
POPULATION (7) 241,322 243,562 245,802 248,042 250,392 252,742 255,092 257,442 259,792 262,142
DEBT PER CAPITA $5,152 $5,114 $5,052 $4,645 $4,233 $3,816 $3,397 $3,004 $2,619 $2,248
INCOME PER CAPITA (8) $101,594 $103,829 $106,113 $108,448 $110,834 $113,272 $115,764 $118,311 $120,914 $123,574
NET TAX-SUPPORTED GENERAL OBLIGATION
DEBT TO INCOME (NOT TO EXCEED 6%) 5.1% 4.9% 4 8% 4.3% 3.8% 3.4% 2 9% 2 5% 2 2% 1.8%
(1) Updated for 2021 GO Bond Issuance. 5% coupon rate assumed on all other bond issuance. Includes bonds planned in APS' Adopted FY 2022 - FY 2024 CIP
(2) Excludes General Obligation bonds issued for the Utilities Fund
(3) Excludes credit support commitments on revenue bonds or lease-backed bond financings. Includes subject to appropriation bonds supported by the County's General Fund. For all subject to appropriation debts, see Chart C.
(4) Includes both General Obligation and Subject to Appropriation debt service. Excludes Utilities Fund and Transportation Capital Fund Debt Service and other debt costs. Includes AHIF bonds
(5) Includes expenditures of General Fund and certain Special Revenue Funds of the County and School Board. Assumes 1.0% growth in FY 2023 and FY 2024, increasing to 2.5% in FY2027 and beyond
(6) Includes real, personal property, and public property. Assumes 2.4% growth in FY 2023, increasing up to 3 0% in FY2027 and beyond
(7) Population as of July 1, 2019 from the US Census 2019 ACS 1-Year Estimate with growth as estimated by MWCOG Round 8.4 Forecasts.
(8) Source: Bureau of Economic Analysis 2019 estimates, with growth of 2 2% consistent with PCPI annual growth in Virginia from 2006 - 2016
Arlington County, Virginia
Debt Ratio Forecast
Adopted FY 2022 - FY 2024 CIP
B - 5
Chart C
FY 2022 FY 2023 FY 2024 FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031
Proposed
Tax-Supported General Obligation Debt $1,148,610,029 $1,157,034,829 $1,159,286,929 $1,075,953,535 $988,847,240 $898,666,785 $805,806, 329 $718,110,873 $630,540,418 $544,964,962
Tax-Supported Subject to Appropriation ("STA") Debt
Capital Equipment Short Term Financing (2) 12,615,805 10,899,541 17,438,976 29,742,415 22,586,974 16,304,555 10,667,946 5,818,696 2,236, 495 0
Industrial Development Authority (IDA) Bonds (3) 90,200,000 84,290,000 78,330,000 72,300,000 67,350,000 62,315,000 57,195,000 62,315,000 57,195,000 57,195,001
Subtotal $102,815,805 $95,189,541 $95,768,976 $102,042,415 $89,936,974 $78,619,555 $67,862,946 $68,133,696 $59,431,495 $57,195,001
Project-Supported Subject to Appropriation ("STA") Debt (4)
IDA Revenue Refunding Bonds (Ballston Skating Facility) (5) 18,155,000 16,760,000 15,290,000 13,740,000 12,100,000 10,365,000 8,525,000 10,365,000 8,525,000 8,525,001
Gates of Ballston (6) 23,000,000
Subtotal 41,155,000 16,760,000 15,290,000 13,740,000 12,100,000 10,365,000 8,525,000 10,365,000 8,525,000 8,525,001
Total Tax-Supported General Obligation (GO) & ALL STA Financings 1,292,580,834 1,268,984,370 1,270,345,905 1,191,735,950 1,090,884,2 14 987,651,340 882,194,275 796,609,569 698,496,913 610,684,964
Total Tax-Supported GO and Tax-Supported STA Financings 1,251,425,834 1,252,224,370 1,255,055,905 1,177,995,950 1,078,784,214 977,286,340 873,669,275 786,244,569 689,971,913 602,159,963
Total Project-Supported STA Financings 41,155,000 16,760,000 15,290,000 13,740,000 12,100,000 10,365,000 8,525,000 10,365,000 8,525,000 8,525,001
Market Value of Taxable Property 84,366,622,713 86,391,421,658 88,464,815,778 90,764,900,988 93,124,788,414 95,918,532,066 98,796,088,028 101,759,970,669 104,812,769,789 107,957,152,883
Total Tax-Supported GO & ALL STA Financings
as Percent of Market Value (Not to Exceed 4%) 1.53% 1.47% 1.44% 1.31% 1.17% 1 03% 0.89% 0.78% 0.67% 0.57%
Total Tax-Supported GO & Tax-Supported STA Financings
as Percent of Market Value 1.48% 1.45% 1.42% 1.30% 1.16% 1 02% 0.88% 0.77% 0.66% 0.56%
Total Project-Supported STA Financings (Credit Enhancement)
as Percent of Market Value (2) 0.05% 0.02% 0.02% 0.02% 0.01% 0 01% 0.01% 0 01% 0.01% 0.01%
(1) Excludes Self-supporting debt in the Utility Fund
(2) Includes existing and planned capital equipment short term financing in the General Fund, Auto Fund, Utilities Fund and Schools Fund
(3) Includes the Series 2013, 2017 IDA Bonds, the 2020A IDA Bonds, and $11.23MM of Series 2020B IDA bonds issued to refund the Series 2011 IDA bonds
(4) Debt service on these financings is intended to be repaid by user fees or tenant rental income, not by County General Fund revenues.
(5) Includes $19.71 million of Series 2020B IDA revenue refunding bonds issued to refinance the construction of two ice rinks, the office space, and the training facility on top of he 8 h Level at he Ballston Parking Garage.
(6) The County Board approved the credit support for the long-term financing of the Gates of Ballston for an amount not to exce ed $23.0 million.
Summary of Tax‐Supported General Obligation Bonds & Subject To Appropriation‐Type Financings (1)
Ratio of Outstanding Debt to Market Value
Adopted FY 2022 ‐ FY 2024 Capital Improvement Plan
As of June 30
B - 7
Program Area Summary
Regional Partnerships And Contingencies
Funding Source 2022 2023 2024 Three Year Total
New Funding $1,732 $1,059 $1,069 $3,860
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG $1,732 $1,059 $1,069 $3,860
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $452 -- -- $452
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $452 -- -- $452
Grand Total $2,184 $1,059 $1,069 $4,312
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
Projected Staffing 2022 2023 2024 Three Year Total
Anticipated FTE Change -- -- -- --
Grand Total -- -- -- --
C - 1
Return to Table of Contents
Program Area Program Area Overview
Regional Partnerships And Contingencies
Category Funding Sources 2022 2023 2024 Three Year Total
Contingency $1,405 $270 $270 $1,945
Regional Partnerships $779 $789 $799 $2,367
Grand Total $2,184 $1,059 $1,069 $4,312
Category Projected Ongoing Costs 2022 2023 2024 Three Year Total
Contingency -- -- -- --
Regional Partnerships -- -- -- --
Grand Total -- -- -- --
Program Area Projects by Category
Regional Partnerships And Contingencies
Category / Project 2022 2023 2024 Three Year Total
Contingency $1,405 $270 $270 $1,945
Capital Contingency $1,405 $270 $270 $1,945
Regional Partnerships $779 $789 $799 $2,367
Northern Virginia Criminal Justice Academy $137 $139 $139 $415
Northern Virginia Regional Park Authority $642 $650 $660 $1,952
Grand Total $2,184 $1,059 $1,069 $4,312
C - 2
Return to Table of Contents
Program Area Category
Regional Partnerships And Contingencies Contingency
Project
Capital Contingency
Funding Source 2022 2023 2024 Three Year Total
New Funding $953 $270 $270 $1,493
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG $953 $270 $270 $1,493
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $452 -- -- $452
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $452 -- -- $452
Grand Total $1,405 $270 $270 $1,945
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
One-time funds are available as contingent for unforseen capital project costs or pending capital requirements.
C - 3
Return to Table of Contents
Program Area Category
Regional Partnerships And Contingencies Regional Partnerships
Project
Northern Virginia Criminal Justice Academy
Funding Source 2022 2023 2024 Three Year Total
New Funding $137 $139 $139 $415
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG $137 $139 $139 $415
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total $137 $139 $139 $415
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
In 2006, the principal members agreed to fund the construction of the Emergency Vehicle Operations Center (EVOC). The bond
financing contributions towards the NVCJTA partnership continues through 2026.
C - 4
Return to Table of Contents
Program Area Category
Regional Partnerships And Contingencies Regional Partnerships
Project
Northern Virginia Regional Park Authority
Funding Source 2022 2023 2024 Three Year Total
New Funding $642 $650 $660 $1,952
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG $642 $650 $660 $1,952
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total $642 $650 $660 $1,952
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
Northern Virginia Regional Park Authority owns and protects more than 10,000 acres of land in 19 parks, including Potomac
Overlook, Upton Hill and the W&OD Regional Parks in Arlington. Funds are used to preserve, improve, expand, renovate and
enhance the parks and facilities.
C - 5
Return to Table of Contents
Program Area Category Overview
Local Parks And Recreation Programs
Maintenance Capital Category
Funding Source 2022 2023 2024 Three Year Total
New Funding $100 $7,105 $1,395 $8,600
01 Federal ‐‐ ‐‐ ‐‐ ‐‐
02 State ‐‐ ‐‐ ‐‐ ‐‐
03 Developer ‐‐ ‐‐ ‐‐ ‐‐
04 New Bonds ‐‐ $5,000 ‐‐ $5,000
05 PAYG ‐‐ $1,390 $1,395 $2,785
06 Short‐term Financing $100 $715 ‐‐ $815
07 Sanitary Tax ‐‐ ‐‐ ‐‐ ‐‐
08 Other ‐‐ ‐‐ ‐‐ ‐‐
09 Transportation Capital C&I ‐‐ ‐‐ ‐‐ ‐‐
10 Transportation Capital NVTA Local ‐‐ ‐‐ ‐‐ ‐‐
11 Regional ‐‐ ‐‐ ‐‐ ‐‐
12 Crystal City TIF ‐‐ ‐‐ ‐‐ ‐‐
Previous Funding $3,601 ‐‐ ‐‐ $3,601
13 Authorized Unissued Bonds ‐‐ ‐‐ ‐‐ ‐‐
14 Issued Unspent Bonds ‐‐ ‐‐ ‐‐ ‐‐
15 Transportation Capital C&I ‐‐ ‐‐ ‐‐ ‐‐
16 Transportation Capital NVTA Local ‐‐ ‐‐ ‐‐ ‐‐
17 Regional ‐‐ ‐‐ ‐‐ ‐‐
18 Crystal City TIF ‐‐ ‐‐ ‐‐ ‐‐
19 Other $3,601 ‐‐ ‐‐ $3,601
Grand Total $3,701 $7,105 $1,395 $12,201
Category / Project 2022 2023 2024 Three Year Total
Maintenance Capital $3,701 $7,105 $1,395 $12,201
Alcova Heights Park Phase 2 $1,695 ‐‐ ‐‐ $1,695
Alcova Heights Park Phase 3 ‐‐ ‐‐ ‐‐ ‐‐
Assessment Management Tool $200 ‐‐ ‐‐ $200
Bluemont Park Tennis Complex Replacement $1,282 $5,000 ‐‐ $6,282
Capital Asset Manager $165 $165 $170 $500
Douglas Park Phase 1 ‐‐ ‐‐ ‐‐ ‐‐
Drew Park ‐‐ ‐‐ ‐‐ ‐‐
Greenbrier Park Track Replacement ‐‐ $715 ‐‐ $715
James Hunter Park Canine Turf Replacement ‐‐ ‐‐ ‐‐ ‐‐
Monroe Park Playground Replacement ‐‐ ‐‐ ‐‐ ‐‐
Parks Maintenance Capital Program ‐‐ $1,000 $1,000 $2,000
Grand Total $3,701 $7,105 $1,395 $12,201
C - 9
Return to Table of Contents
Program Area Category
Local Parks And Recreation Programs Maintenance Capital
Project
Alcova Heights Park Phase 2
Funding Source 2022 2023 2024 Three Year Total
New Funding -- -- -- --
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $1,695 -- -- $1,695
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $1,695 -- -- $1,695
Grand Total $1,695 -- -- $1,695
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
This project will fund Phase 2 of the redevelopment of the Alcova Heights Park and will include accessibility renovations to the
restroom building, replacement of the basketball court and associated walkway, signage and landscaping improvements.
Architectural and engineering services for the design was previously funded under Phase 1.
C - 10
Return to Table of Contents
Program Area Category
Local Parks And Recreation Programs Maintenance Capital
Project
Assessment Management Tool
Funding Source 2022 2023 2024 Three Year Total
New Funding -- -- -- --
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $200 -- -- $200
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $200 -- -- $200
Grand Total $200 -- -- $200
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
This project will fund the third and final year of consultant review and update of DPR's capital asset inventory listing.
C - 11
Return to Table of Contents
Program Area Category
Local Parks And Recreation Programs Maintenance Capital
Project
Bluemont Park Tennis Complex Replacement
Funding Source 2022 2023 2024 Three Year Total
New Funding -- $5,000 -- $5,000
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- $5,000 -- $5,000
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $1,282 -- -- $1,282
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $1,282 -- -- $1,282
Grand Total $1,282 $5,000 -- $6,282
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- $350 $350
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- $350 $350
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- $350 $350
Design and construction of the tennis courts, court lighting, restroom building, picnic shelter, parking lot, site amenities,
walkways, landscaping, stormwater and other associated park amenities located at the Bluemont Park Tennis Complex.
C - 12
Return to Table of Contents
Program Area Category
Local Parks And Recreation Programs Maintenance Capital
Project
Equipment at DPR Facilities
Funding Source 2022 2023 2024 Three Year Total
New Funding $100 -- -- $100
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing $100 -- -- $100
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total $100 -- -- $100
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- $16 $16 $32
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short-term Financing Costs -- $16 $16 $32
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- $16 $16 $32
Ongoing needs for the purchase and replacement of equipment at DPR facilities.
C - 14
Return to Table of Contents
Local Parks And Recreation Programs Maintenance Capital
Project
Feasibility Studies
Funding Source 2022 2023 2024 Three Year Total
New Funding -- -- -- --
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $134 -- -- $134
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $134 -- -- $134
Grand Total $134 -- -- $134
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
Master planning and feasibility studies provide program funds that allow the County to address strategies and analysis for park
and recreation facilities and other public spaces. Funding is used to conduct feasibility, impact or other analytical studies and
conceptual plans as the need arises.
C - 15
Return to Table of Contents
Program Area Category
Local Parks And Recreation Programs Maintenance Capital
Project
Field Fund
Funding Source 2022 2023 2024 Three Year Total
New Funding -- $225 $225 $450
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- $225 $225 $450
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $125 -- -- $125
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $125 -- -- $125
Grand Total $125 $225 $225 $575
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
The Parks Field Fund is supported by an annual fee assessed on official affiliated youth and adult sports teams playing on
Arlington County rectangular and diamond fields. The fees assessed for rectangular fields are directed to support replacement
and construction of synthetic turf fields in the County. The fees assessed on diamond fields are to be used each year for specific
diamond field enhancements, such as improved irrigation, batting cages or accelerated sod replacement. The FY 2022 funding
reflects the projected annual revenue from FY 2021 fees.
C - 16
Return to Table of Contents
Program Area Category
Local Parks And Recreation Programs Maintenance Capital
Project
Greenbrier Park Track Replacement
Funding Source 2022 2023 2024 Three Year Total
New Funding -- $715 -- $715
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- $715 -- $715
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total -- $715 -- $715
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- $115 $115
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short-term Financing Costs -- -- $115 $115
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- $115 $115
Design and construction for the replacement of the running track surfacing and long jump pit within the stadium field complex at
Greenbrier Park/Yorktown High School. The running track was last replaced in 2007 and Arlington County Public Schools do not
cost share in this project.
C - 17
Return to Table of Contents
Program Area Category
Local Parks And Recreation Programs Maintenance Capital
Project
Parks Maintenance Capital Program
Funding Source 2022 2023 2024 Three Year Total
New Funding -- $1,000 $1,000 $2,000
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- $1,000 $1,000 $2,000
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total -- $1,000 $1,000 $2,000
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs $296 $302 $307 $905
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs $296 $302 $307 $905
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total $296 $302 $307 $905
The Parks Maintenance Capital Program provides for recurring, systematic reinvestment in existing outdoor facilities to ensure
efficient, safe, high-quality park and recreation facilities for the community to enjoy. The program funds the replacement or
major renovation of outdoor park and recreation facility assets, including athletic fields and courts, field and court lighting,
playgrounds, picnic shelters, restrooms, parking lots and other park amenities. The program also addresses bringing facilities up
to current standards for accessibility, safety requirements, storm water improvements and the protection of natural resources
that are complementary to renovating the assets. The County utilizes a base level of pay-as-you-go (PAYG) allocations and local
parks and recreation bonds to fund the program. Two years of total project funding (FY2023 & FY2024) appear below.
C - 18
Return to Table of Contents
Program Area Category Overview
Local Parks And Recreation Programs
Park Master Plans Category
Funding Source 2022 2023 2024 Three Year Total
New Funding $800 $400 $8,130 $9,830
01 Federal
02 State
03 Developer $500 $300 $300 $1,100
04 New Bonds $800 $3,955 $4,755
05 PAYG
06 Short-term Financing
07 Sanitary Tax
08 Other
09 Transportation Capital C&I
10 Transportation Capital NVTA Local
11 Regional
12 Crystal City TIF $100 $3,875 $3,975
Previous Funding
13 Authorized Unissued Bonds
14 Issued Unspent Bonds
15 Transportation Capital C&I
16 Transportation Capital NVTA Local
17 Regional
18 Crystal City TIF
19 Other
Grand Total $800 $400 $8,130 $9,830
Category/ Project 2022 2023 2024 Three Year Total
Park Master Plans $800 $400 $8,130 $9,830
Arlington Boathouse $800 $3,955 $4,755
Crystal City Parks and Public Space $500 $400 $4,175 $5,075
Grand Total $1,300 $400 $8,130 $9,830
Return to Table of Contents C-19
Program Area Category
Local Parks And Recreation Programs Park Master Plans
Project
Arlington Boathouse
Funding Source 2022 2023 2024 Three Year Total
New Funding $800 ‐‐ $3,955 $4,755
01 Federal ‐‐ ‐‐ ‐‐ ‐‐
02 State ‐‐ ‐‐ ‐‐ ‐‐
03 Developer ‐‐ ‐‐ ‐‐ ‐‐
04 New Bonds $800 ‐‐ $3,955 $4,755
05 PAYG ‐‐ ‐‐ ‐‐ ‐‐
06 Short‐term Financing ‐‐ ‐‐ ‐‐ ‐‐
07 Sanitary Tax ‐‐ ‐‐ ‐‐ ‐‐
08 Other ‐‐ ‐‐ ‐‐ ‐‐
09 Transportation Capital C&I ‐‐ ‐‐ ‐‐ ‐‐
10 Transportation Capital NVTA Local ‐‐ ‐‐ ‐‐ ‐‐
11 Regional ‐‐ ‐‐ ‐‐ ‐‐
12 Crystal City TIF ‐‐ ‐‐ ‐‐ ‐‐
Previous Funding ‐‐ ‐‐ ‐‐ ‐‐
13 Authorized Unissued Bonds ‐‐ ‐‐ ‐‐ ‐‐
14 Issued Unspent Bonds ‐‐ ‐‐ ‐‐ ‐‐
15 Transportation Capital C&I ‐‐ ‐‐ ‐‐ ‐‐
16 Transportation Capital NVTA Local ‐‐ ‐‐ ‐‐ ‐‐
17 Regional ‐‐ ‐‐ ‐‐ ‐‐
18 Crystal City TIF ‐‐ ‐‐ ‐‐ ‐‐
19 Other ‐‐ ‐‐ ‐‐ ‐‐
Grand Total $800 ‐‐ $3,955 $4,755
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs ‐‐ $56 $71 $127
01 Personnel ‐‐ ‐‐ ‐‐ ‐‐
02 Non‐Personnel ‐‐ ‐‐ ‐‐ ‐‐
03 Bond Financing Costs ‐‐ $56 $71 $127
04 Short‐term Financing Costs ‐‐ ‐‐ ‐‐ ‐‐
05 Facilities Costs ‐‐ ‐‐ ‐‐ ‐‐
06 Operations Costs ‐‐ ‐‐ ‐‐ ‐‐
07 Maintenance Capital Costs ‐‐ ‐‐ ‐‐ ‐‐
02 Fees ‐‐ ‐‐ ‐‐ ‐‐
08 Less Fees ‐‐ ‐‐ ‐‐ ‐‐
Grand Total ‐‐ $56 $71 $127
C - 21
Return to Table of Contents
Program Area Category Overview
Local Parks And Recreation Programs
Parks Land Acquisition and Open Space Category
Funding Source 2022 2023 2024 Three Year Total
New Funding -- -- -- --
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total -- -- -- --
Category / Project 2022 2023 2024 Three Year Total
Parks Land Acquisition and Open Space -- -- -- --
Parks Land Acquisition and Public Space Program -- -- -- --
Grand Total -- -- -- --
C - 24
Return to Table of Contents
Program Area Category
Local Parks And Recreation Programs Parks Land Acquisition and Open Space
Project
Parks Land Acquisition and Public Space Program
Funding Source 2022 2023 2024 Three Year Total
New Funding -- -- -- --
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total -- -- -- --
Arlington County is nationally recognized for the quality and diversity of its public spaces and recreational opportunities.
Maintaining that high level of stewardship and responsiveness to community needs is a continual challenge because of the
County's small size, its increasing population density, and the pressures and impacts of urban growth on remaining natural areas
and park land. One of the priority actions in the Public Spaces Master Plan, adopted by the Arlington County Board on April 25,
2019, is a recommendation that 30 acres of new public space be added to County park and public space inventory over the next
ten (10) years (Priority Action 1, Recommendation 1.1). The Public Spaces Master Plan provides comprehensive criteria and a
methodology to objectively evaluate potential acquisition opportunities for making recommendations to the County Board. The
document also includes a series of maps identifying potential sites for future acquisitions. These maps represent aspirational
acquisition targets for either expansion of existing or creation of new public spaces and the protection of natural or historic
resources. The purpose of the Parks Land Acquisition and Public Space Program is to have reserves on hand that allow the County
to strategically acquire real property for parks and public spaces based on recommendations in the Public Spaces Master Plan.
Additionally, the County uses different ways to acquire land and provide public space to its residents. Land may also be acquired
through site plan contributions, form-based code requirements, Transfer of Development Rights, property transfers or other land
exchanges and property donations. Over the course of the last year the County Board has approved at least 5 private
developments whose approvals required the creation of privately owned public spaces. Residents' access to these spaces are
ensured through public access easements. These spaces range from .17 acres at the future Ames center to 1.4 acres at the Crystal
City Water Park. Last year alone the County added 3.46 acres to its public space inventory via these privately owned public spaces.
Vulnerable properties adjacent to parks that are prone to flooding may also present an opportunity to expand parks and public
space areas.
C - 25
Return to Table of Contents
Program Area Category
Local Parks And Recreation Programs Parks Land Acquisition and Open Space
Project
Parks Land Acquisition and Public Space Program
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs $6 $6 $7 $19
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs $6 $6 $7 $19
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total $6 $6 $7 $19
C - 26
Return to Table of Contents
Program Area Category Overview
Local Parks And Recreation Programs
Synthetic Turf Program Category
Funding Source 2022 2023 2024 Three Year Total
New Funding $268 $982 $2,837 $4,087
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing $268 $491 $1,750 $2,509
07 Sanitary Tax -- -- -- --
08 Other -- $491 $1,087 $1,578
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $1,262 -- -- $1,262
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $1,262 -- -- $1,262
Grand Total $1,530 $982 $2,837 $5,349
Category / Project 2022 2023 2024 Three Year Total
Synthetic Turf Program $1,530 $982 $2,837 $5,349
Barcroft Park Community Field Replacement $489 -- -- $489
Rocky Run Park Synthetic Field Replacement $268 -- -- $268
Synthetic Turf Program -- -- $2,837 $2,837
TJ Upper Field Conversion $773 -- -- $773
Wakefield High School Stadium Field Replacement -- $982 -- $982
Grand Total $1,530 $982 $2,837 $5,349
C - 27
Return to Table of Contents
Program Area Category
Local Parks And Recreation Programs Synthetic Turf Program
Project
Barcroft Park Community Field Replacement
Funding Source 2022 2023 2024 Three Year Total
New Funding -- -- -- --
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $489 -- -- $489
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $489 -- -- $489
Grand Total $489 -- -- $489
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
Design and construction for the replacement of the synthetic turf surfacing on the athletic field. Costs include design
development, replacement of the synthetic turf and infill, repairs to the base layer and under-drain system, replacement of
field amenities, and construction administration.
C - 28
Return to Table of Contents
Program Area Category
Local Parks And Recreation Programs Synthetic Turf Program
Project
Rocky Run Park Synthetic Field Replacement
Funding Source 2022 2023 2024 Three Year Total
New Funding $268 -- -- $268
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing $268 -- -- $268
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total $268 -- -- $268
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- $43 $43 $86
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short-term Financing Costs -- $43 $43 $86
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- $43 $43 $86
Design and construction for the replacement of the synthetic turf surfacing on the athletic field. Costs include design
development, replacement of the synthetic turf and infill, repairs to the base layer and under-drain system, replacement of field
amenities, and construction administration.
C - 29
Return to Table of Contents
Program Area Category
Local Parks And Recreation Programs Synthetic Turf Program
Project
Wakefield High School Stadium Field Replacement
Funding Source 2022 2023 2024 Three Year Total
New Funding -- $982 -- $982
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- $491 -- $491
07 Sanitary Tax -- -- -- --
08 Other -- $491 -- $491
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total -- $982 -- $982
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- $79 $79
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short-term Financing Costs -- -- $79 $79
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- $79 $79
Design and construction for the replacement of the synthetic turf surfacing on the stadium athletic field. Costs include design
development, replacement of the synthetic turf and infill, repairs to the base layer and under-drain system, replacement of field
amenities, and construction administration.
C - 32
Return to Table of Contents
Program Area Category Overview
Local Parks And Recreation Programs
Trail Modernization Category
Funding Source 2022 2023 2024 Three Year Total
New Funding $1,000 $1,000 $2,500 $4,500
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds $1,000 $1,000 $2,500 $4,500
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $2,935 -- -- $2,935
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds $2,935 -- -- $2,935
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total $3,935 $1,000 $2,500 $7,435
Category / Project 2022 2023 2024 Three Year Total
Trail Modernization $3,935 $1,000 $2,500 $7,435
Trail and Bridge Modernization Program $3,935 $1,000 $2,500 $7,435
Grand Total $3,935 $1,000 $2,500 $7,435
C - 33
Return to Table of Contents
Program Area Category
Local Parks And Recreation Programs Trail Modernization
Project
Trail and Bridge Modernization Program
Funding Source 2022 2023 2024 Three Year Total
New Funding $1,000 $1,000 $2,500 $4,500
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds $1,000 $1,000 $2,500 $4,500
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $2,935 -- -- $2,935
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds $2,935 -- -- $2,935
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total $3,935 $1,000 $2,500 $7,435
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs $13 $84 $173 $270
01 Personnel -- -- -- --
02 Non-Personnel $13 $14 $14 $41
03 Bond Financing Costs -- $70 $159 $229
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total $13 $84 $173 $270
The Trail and Bridge Modernization Program is largely focused on replacement and major renovation of the County's 39.7 miles of
off-street, multi-purpose trails that are approaching the end of their useful life. Trails will be brought up to current standards,
including appropriate sub-base, replacement or repaving of asphalt surfacing, striping, drainage, signage, safety markers and site
furnishings. The program also replaces existing trail lighting with energy-efficient lighting and adds new areas of trail lighting as
guided by the Public Spaces Master Plan. The other component of this program focuses on the replacement of pedestrian bridges
and low-water fords on multi-purpose trails and hiking trails. Recently completed trail work under this program includes milling
and repaving or full replacement of several segments of the Four Mile Run Trail, renovation of a section of the Custis Trail near
McCoy Park, and replacement of the western portion of the Four Mile Run Trail in Benjamin Banneker Park. Recently completed
bridge work under this program includes the replacement of a pedestrian bridge at Lubber Run Park and design efforts for the
replacement of a bridge at Glencarlyn as well as a second bridge at Lubber Run Park. In addition to specific projects identified
during the FY 2022 - FY 2024 CIP, outside consultants will conduct studies to assess trail and pedestrian bridge conditions in order
to determine a prioritized list for upcoming program maintenance needs.
C - 34
Return to Table of Contents
Program Area Summary
Community Conservation
Funding Source 2022 2023 2024 Three Year Total
New Funding $2,000 $2,500 $2,500 $7,000
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds $2,000 $2,000 $2,000 $6,000
05 PAYG -- $500 $500 $1,000
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $5,500 $6,000 $5,000 $16,500
13 Authorized Unissued Bonds $2,000 $6,000 $5,000 $13,000
14 Issued Unspent Bonds $3,000 -- -- $3,000
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $500 -- -- $500
Grand Total $7,500 $8,500 $7,500 $23,500
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- $140 $318 $458
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- $140 $318 $458
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- $140 $318 $458
Projected Staffing 2022 2023 2024 Three Year Total
Anticipated FTE Change -- -- -- --
Grand Total -- -- -- --
This program will improve the quality and appearance of public areas in Arlington's residential areas and neighborhood
commercial districts, which are critical in order to achieve the vision of a world class urban community. The program
develops infrastructure and community within neighborhoods and creates viable, attractive neighborhood business districts.
C - 35
Return to Table of Contents
Program Area Program Area Overview
Community Conservation
Category Funding Sources 2022 2023 2024 Three Year Total
Neighborhood Conservation $7,500 $8,500 $7,500 $23,500
Grand Total $7,500 $8,500 $7,500 $23,500
Category Projected Ongoing Costs 2022 2023 2024 Three Year Total
Neighborhood Conservation -- $140 $318 $458
Grand Total -- $140 $318 $458
The Neighborhood Conservation (NC) program enhances residential areas by providing citizen-initiated public improvements
based upon regularly updated neighborhood plans. Projects include street improvements, residential traffic management, park
enhancements, street lighting, beautification and landscaping projects.
Program Area Projects by Category
Community Conservation
Category / Project 2022 2023 2024 Three Year Total
Neighborhood Conservation $7,500 $8,500 $7,500 $23,500
Neighborhood Conservation $7,500 $8,500 $7,500 $23,500
Grand Total $7,500 $8,500 $7,500 $23,500
C - 36
Return to Table of Contents
Program Area Summary
Public And Government Facilities
Funding Source 2022 2023 2024 Three Year Total
New Funding $10,855 $10,500 $3,000 $24,355
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds $7,535 $7,500 -- $15,035
05 PAYG $2,246 $2,500 $2,500 $7,246
06 Short-term Financing $974 -- -- $974
07 Sanitary Tax -- -- -- --
08 Other $100 $500 $500 $1,100
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $12,990 -- -- $12,990
13 Authorized Unissued Bonds $800 -- -- $800
14 Issued Unspent Bonds $1,270 -- -- $1,270
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $10,920 -- -- $10,920
Grand Total $23,845 $10,500 $3,000 $37,345
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs $348 $476 $2,611 $3,435
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs $297 $424 $2,558 $3,279
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs $51 $52 $53 $156
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total $348 $476 $2,611 $3,435
Projected Staffing 2022 2023 2024 Three Year Total
Anticipated FTE Change -- -- -- --
Grand Total -- -- -- --
This program provides facilities for both existing and evolving services and programs. It encompasses both significant
modernization and planned replacement of facilities, based upon facility life cycles and changing program demands and
services. It serves to provide a consistent, sustainable inventory of quality public facilities through systematic investment.
The program is carefully integrated with the Facilities Maintenance Capital program by planning for adequate maintenance
of facilities through their life cycle, periodic renovation, and eventual replacement of obsolete facilities at the appropriate
points in the life cycle.
C - 38
Return to Table of Contents
Program Area Projects by Category
Public And Government Facilities
Category / Project 2022 2023 2024 Three Year Total
Design and Construction $15,475 $7,000 $500 $22,975
26th and Old Dominion Stormwater $1,200 -- -- $1,200
Ballston Public Parking Garage Floors 1 - 7 $100 $500 $500 $1,100
Courthouse Complex Renovations & Infrastructure $1,500 $6,500 -- $8,000
Courts/Police Building Improvements $10,000 -- -- $10,000
Crystal City Library $1,160 -- -- $1,160
Facility Planning & Feasibility Studies $544 -- -- $544
Gender Neutral Restroom Signage $145 -- -- $145
Police Women's Locker Room Expansion $126 -- -- $126
Quincy Site Design $700 -- -- $700
Facilities Maintenance $8,370 $3,500 $2,500 $14,370
Public Facilities Maintenance Program -- $2,500 $2,500 $5,000
Central Library MEP Replacement $2,355 -- -- $2,355
Communication Facility Repairs $160 -- -- $160
Court Square West Structural Concrete Repair $500 -- -- $500
Detention Facility VAV Replacements $1,935 $1,000 -- $2,935
Detention Facility Ventilation System $625 -- -- $625
Equipment Bureau Roof Replacement $1,670 -- -- $1,670
Fire Station 2 HVAC Replacement $325 -- -- $325
Fire Station 5 HVAC Replacement $300 -- -- $300
Water-Sewer-Street Admin Restroom Refresh $500 -- -- $500
Grand Total $23,845 $10,500 $3,000 $37,345
C - 40
Return to Table of Contents
Program Area Category Overview
Public And Government Facilities
Design and Construction Category
Funding Source 2022 2023 2024 Three Year Total
New Funding $5,461 $7,000 $500 $12,961
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds $3,930 $6,500 -- $10,430
05 PAYG $1,431 -- -- $1,431
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other $100 $500 $500 $1,100
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $10,014 -- -- $10,014
13 Authorized Unissued Bonds $800 -- -- $800
14 Issued Unspent Bonds $1,270 -- -- $1,270
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $7,944 -- -- $7,944
Grand Total $15,475 $7,000 $500 $22,975
Category / Project 2022 2023 2024 Three Year Total
Design and Construction $15,475 $7,000 $500 $22,975
26th and Old Dominion Stormwater $1,200 -- -- $1,200
Ballston Public Parking Garage Floors 1 - 7 $100 $500 $500 $1,100
Courthouse Complex Renovations & Infrastructure $1,500 $6,500 -- $8,000
Courts/Police Building Improvements $10,000 -- -- $10,000
Crystal City Library $1,160 -- -- $1,160
Facility Planning & Feasibility Studies $544 -- -- $544
Gender Neutral Restroom Signage $145 -- -- $145
Police Women's Locker Room Expansion $126 -- -- $126
Quincy Site Design $700 -- -- $700
Grand Total $15,475 $7,000 $500 $22,975
C - 41
Return to Table of Contents
Program Area Category
Public And Government Facilities Design and Construction
Project
Courthouse Complex Renovations & Infrastructure
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
C - 45
Return to Table of Contents
Program Area Category
Public And Government Facilities Design and Construction
Project
Courts/Police Building Improvements
Funding Source 2022 2023 2024 Three Year Total
New Funding $1,730 -- -- $1,730
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds $1,730 -- -- $1,730
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $8,270 -- -- $8,270
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds $1,270 -- -- $1,270
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $7,000 -- -- $7,000
Grand Total $10,000 -- -- $10,000
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
C - 47
Return to Table of Contents
Program Area Category
Public And Government Facilities Design and Construction
Project
Crystal City Library
Funding Source 2022 2023 2024 Three Year Total
New Funding $1,160 -- -- $1,160
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG $1,160 -- -- $1,160
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total $1,160 -- -- $1,160
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
As part of the site plan approval for 1901 S. Ball Street in Crystal City (#56 Site Plan), the developer agreed to execute a 10-year
lease with Arlington County for 7,200 SF of space to provide for a new library facility in Crystal City. This project will include the
design and construction of the interior space for the Library.
C - 48
Return to Table of Contents
Program Area Category
Public And Government Facilities Design and Construction
Project
Facility Planning & Feasibility Studies
Funding Source 2022 2023 2024 Three Year Total
New Funding -- -- -- --
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $544 -- -- $544
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $544 -- -- $544
Grand Total $544 -- -- $544
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
Facility master planning provides an integrated approach that addresses short, intermediate, and long-term needs for County
facilities. Planning proceeds in phases, and balances short-term deficiencies with long-range objectives for space management
and efficiencies, often with emphasis on a particular site, or a certain subgroup of facilities. The outcome is an evolving, flexible
project list that is capable of taking advantage of new opportunities, while simultaneously working to resolve known
deficiencies, all at a funding level and timing consistent with debt capacity and future years funding allocations. Periodic
reevaluation and updating of space deficiencies will help to provide a relevant baseline context for site-specific decisions and
strategies. Feasibility studies will allow an integrated approach to proper scoping and project feasibility for Board,
departmental, and community initiated projects.
C - 49
Return to Table of Contents
Program Area Category
Public And Government Facilities Design and Construction
Project
Police Women's Locker Room Expansion
Funding Source 2022 2023 2024 Three Year Total
New Funding $126 -- -- $126
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG $126 -- -- $126
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total $126 -- -- $126
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
The Police Women's Locker Room is undersized for the current and future complement of female staffing in the Courts Police
building located at 1425 N. Courthouse Road. Currently, there are only two spare lockers for existing female staff. This project
will expand the current locker space into the adjacent underutilized bunk room to allow for an additional 15-20 lockers.
C - 51
Return to Table of Contents
Program Area Category
Public And Government Facilities Design and Construction
Project
Quincy Site Design
Funding Source 2022 2023 2024 Three Year Total
New Funding $700 -- -- $700
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds $700 -- -- $700
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total $700 -- -- $700
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs $297 $289 $282 $868
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs $297 $289 $282 $868
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total $297 $289 $282 $868
The County is currently implementing an interim solution for relocation of the Police Emergency Vehicles from the SEEC building
located along Four-Mile Run which was demolished as part of the Jennie Dean Park construction. This funding provides for the
design on the N. Quincy Street property (building 1) to allow for the relocation of the Fire Reserve Vehicles and related fire
materials from a temporary building at Water Pollution Control Plant (WPCP). Relocating Fire vehicles and related materials is
needed to avoid delay in the start of the WPCP construction in CY 2025 for the Solids Master Plan expansion. The design will result
in the ability to house both Fire and Police vehicles without inhibiting the longer-term plan to accommodate additional police and
fire vehicle storage and logistics needs at the Quincy site. Given limited funds, this proposal does not include funding for the
construction associated with the design nor relocation of additional programs or facility upgrades to the remaining three buildings.
C - 52
Return to Table of Contents
Program Area Category Overview
Public And Government Facilities
Facilities Maintenance Category
Funding Source 2022 2023 2024 Three Year Total
New Funding $5,394 $3,500 $2,500 $11,394
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds $3,605 $1,000 -- $4,605
05 PAYG $815 $2,500 $2,500 $5,815
06 Short-term Financing $974 -- -- $974
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $2,976 -- -- $2,976
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $2,976 -- -- $2,976
Grand Total $8,370 $3,500 $2,500 $14,370
Category / Project 2022 2023 2024 Three Year Total
Facilities Maintenance $8,370 $3,500 $2,500 $14,370
Public Facilities Maintenance Program -- $2,500 $2,500 $5,000
Central Library MEP Replacement $2,355 -- -- $2,355
Communication Facility Repairs $160 -- -- $160
Court Square West Structural Concrete Repair $500 -- -- $500
Detention Facility VAV Replacements $1,935 $1,000 -- $2,935
Detention Facility Ventilation System $625 -- -- $625
Equipment Bureau Roof Replacement $1,670 -- -- $1,670
Fire Station 2 HVAC Replacement $325 -- -- $325
Fire Station 5 HVAC Replacement $300 -- -- $300
Water-Sewer-Street Admin Restroom Refresh $500 -- -- $500
Grand Total $8,370 $3,500 $2,500 $14,370
C - 53
Return to Table of Contents
Program Area Category
Public And Government Facilities Facilities Maintenance
Project
Central Library MEP Replacement
Funding Source 2022 2023 2024 Three Year Total
New Funding $1,189 -- -- $1,189
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG $715 -- -- $715
06 Short-term Financing $474 -- -- $474
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $1,166 -- -- $1,166
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $1,166 -- -- $1,166
Grand Total $2,355 -- -- $2,355
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
This project includes a restroom refresh, replacing the generator and transfer switch, elevator modernization and replacing the
air handling unit in the Virginia Room and Auditorium. The refreshed bathrooms will be energy-efficient reducing future utility
expenses.
Air handling units, generator, and elevators have reached the end of their useful lives and more frequent repairs and the
potential for failure could cause closure of the facility if not refreshed. The existing generator is no longer supported by the
manufacturer. The restroom finishes are in poor condition. The air handler is resulting in humidity issues that could damage
documents in the Virginia Room if not replaced.
C - 55
Return to Table of Contents
Program Area Category
Public And Government Facilities Facilities Maintenance
Project
Communication Facility Repairs
Funding Source 2022 2023 2024 Three Year Total
New Funding -- -- -- --
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $160 -- -- $160
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $160 -- -- $160
Grand Total $160 -- -- $160
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
This project will provide for structural concrete repairs and generator/transfer switch replacements for an emergency
communications facility located at N. 24th Street and Emerson Street.
C - 56
Return to Table of Contents
Program Area Category
Public And Government Facilities Facilities Maintenance
Project
Court Square West Structural Concrete Repair
Funding Source 2022 2023 2024 Three Year Total
New Funding -- -- -- --
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $500 -- -- $500
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $500 -- -- $500
Grand Total $500 -- -- $500
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
This project will provide for structural concrete repairs to supporting beams and slab in the parking garage under the building
located at 1400 N. Uhle Street. This is a safety concern and the project will address loose concrete that has fallen on cars due to
major structural cracks in the beams and slab.
C - 57
Return to Table of Contents
Program Area Category
Public And Government Facilities Facilities Maintenance
Project
Detention Facility VAV Replacements
Funding Source 2022 2023 2024 Three Year Total
New Funding $1,935 $1,000 -- $2,935
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds $1,935 $1,000 -- $2,935
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total $1,935 $1,000 -- $2,935
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- $135 $242 $377
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- $135 $242 $377
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- $135 $242 $377
Replace existing pneumatic variable air volume (VAV) units and upgrade the building automation system (BAS) for new VAV
units. The VAVs are not providing the proper cooling or heating in cells due to their age and outdated technology. In addition,
they are no longer supported by the existing BAS.
C - 58
Return to Table of Contents
Program Area Category
Public And Government Facilities Facilities Maintenance
Project
Detention Facility Ventilation System
Funding Source 2022 2023 2024 Three Year Total
New Funding -- -- -- --
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $625 -- -- $625
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $625 -- -- $625
Grand Total $625 -- -- $625
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
Replace the existing ventilation systems in the Medical unit and loading dock in the County's Detention Facility located at 1435
N. Courthouse Road. The ventilation system has reached the end of its useful life and requires frequent repairs. The potential
for failure could cause facility closures in these areas.
C - 59
Return to Table of Contents
Program Area Category
Public And Government Facilities Facilities Maintenance
Project
Equipment Bureau Roof Replacement
Funding Source 2022 2023 2024 Three Year Total
New Funding $1,670 -- -- $1,670
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds $1,670 -- -- $1,670
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total $1,670 -- -- $1,670
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
The project includes replacement of the Equipment Bureau roof, which is at the end of its useful life, installation of solar panels,
and replacing bay light fixtures with LED's. The roof is experiencing more frequent leaks resulting in increased repairs. The
existing bay lighting does not provide sufficient lighting for the Equipment Bureau technicians and is not energy efficient.
C - 60
Return to Table of Contents
Program Area Category
Public And Government Facilities Facilities Maintenance
Project
Fire Station 2 HVAC Replacement
Funding Source 2022 2023 2024 Three Year Total
New Funding -- -- -- --
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $325 -- -- $325
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $325 -- -- $325
Grand Total $325 -- -- $325
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
Replace the HVAC components (rooftop units, exhaust fans) and the building automation system at Fire Station 2. The rooftop
units and exhaust fans are requiring more frequent repairs and have the potential for failure that would closure of the facility.
C - 61
Return to Table of Contents
Program Area Category
Public And Government Facilities Facilities Maintenance
Project
Fire Station 5 HVAC Replacement
Funding Source 2022 2023 2024 Three Year Total
New Funding $100 -- -- $100
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG $100 -- -- $100
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $200 -- -- $200
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $200 -- -- $200
Grand Total $300 -- -- $300
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
Replace five rooftop units and three pumps for first floor HVAC in Fire Station 5 which have reached the end of their useful
lives. The HVAC system is requiring more frequent repairs and has the potential for failure that would cause closure of the
facility.
C - 62
Return to Table of Contents
Program Area Category
Public And Government Facilities Facilities Maintenance
Project
Water-Sewer-Street Admin Restroom Refresh
Funding Source 2022 2023 2024 Three Year Total
New Funding $500 -- -- $500
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing $500 -- -- $500
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total $500 -- -- $500
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
Refreshment of the restroom facilities in the Water Sewer Streets (WSS) administrative building located at 4200 S. 28th Street.
The restrooms are heavily used and need to be refreshed.
C - 63
Return to Table of Contents
Program Area Summary
Information Technology/Equipment
The information technology (IT) and equipment maintenance capital program maintains the County's technology assets in
order to 1) sustain the County's existing business systems so they remain useful, operable and responsive to business need
2) best leverage the existing infrastructure to support the business needs of the entire County as well as department
specific applications, 3) reduce operating and support costs associated with aging hardware, and 4) provide a reliable and
secure environment for the operation of County's systems while furthering County's goals for energy efficiency and worker
productivity.
Funding Source 2022 2023 2024 Three Year Total
New Funding $13,843 $19,047 $17,088 $49,978
01 Fede ral
02 State
03 Developer
04 New Bonds
05 PAYG $1,733 $1,383 $133 $3,249
06 Short-term Financing $12,110 $17,664 $16,380 $46,154
07 Sanitary Tax
08 Other $575 $575
09 Transportation Capital C&I
10 Transportation Capital NVTA Local
11 Regional
12 Crystal City TIF
Previous Funding $4,088 $7,815 $7,000 $18,903
13 Authorized Unissued Bonds
14 Issued Unspent Bonds $685 $815
15 Transportation Capital C&I
16 Transportation Capital NVTA Local
17 Regional
18 Crystal City TIF
19 Other $3,473 $7,000 $7,000 $18,903
Grand Total $17,931 $26,862 $24,088 $68,881
: . •
01 Operating Costs $375 $500 $650 $1,525
01 Personnel
02 Non-Personnel
03 Bond Financing Costs
04 Short Term Financing Costs
05 Facilities Costs
06 Operations Costs $375 $500 $650 $1,525
07 Maintenance capital Costs
02 Fees
08 Less Fees
Grand Total $375 $500 $650 $1,525
Anticipated FTE Change
Grand Total
Return to Table of Contents D-1
Program Area Program Area Overview
Information Technology/Equipment
The Information Technology (IT) systems, software, and hardware which serve departments typically reach the end
of their useful life in three to ten years. At that point, the systems become increasingly costly to maintain and
difficult to exchange information with other systems. Priorities for determining which applications to replace first are
driven by age, criticality of the system to operations, and availability of ongoing support from the application's
vendor. The IT systems and equipment are paid for through a combination of PAYG and short-term financing, with
operating impacts through principal and interest payments on the short-term finance as described in the Capital
Financing section of the CIP.
IT and equipment maintenance capital falls into three major program areas: Enterprise Information Technology (EIT),
Information Technology/Other, and Public Safety Technology.
The EIT capital improvement program funds two categories:
• Maintenance Capital - Equipment includes the ongoing replacement of aging desktop computers, laptops and
tablets, servers, networks, and other equipment, both employee and public facing. Tools to support
enhanced virtual government services and employee mobility.
• Hardware and Application Refreshment includes refreshment/replacement of software and management
systems that provide key resources to meet the County's internal and external demands. This includes
upgrade of the revenue and collection system and the human resources and financial system.
Information Technology/Other Equipment include special systems and equipment that is required for a department
to maintain its specific operations and services. This CIP funds replacement of existing line of business applications
such as land records, and real estate assessment. It also includes technology upgrades and new systems that the
Department of Human Services requires to manage mandated health services.
The Public Safety capital improvement program consists of key projects t hat will keep existing IT systems refreshed or
replaced on a reasonably expected life-cycle so that the systems remain useful, operable and responsive to public
safety needs. Special concerns for forecasting publi
c safety technology requirements include: rapid technology
advances that require upgrades and/or replacement
s; the need to maintain interoperability within the regio n; the
need to maintain redundancies that are required for safety and to avoid system failures; and, responding to the
changing needs of the workforce and the com
munity. These issues may impact not only the needs of public safety,
but also the t
iming and scope of future projects. These pro
jects are managed by the four public safety agencies. The
useful life of these projects range from three to ten years and must be refreshed to maintain operability.
D-2
Return to Table of Contents
Program Area Program Area Overview
Information Technology/Equipment
Category Funding Sources 2022 2023 2024 Three Year Total
Enterprise Information Technology $9,378 $13,120 $15,105 $37,603
IT/Other $550 $3,250 $2,000 $5,800
Fire $4,370 $7,609 $3,500 $15,479
Police $3,633 $133 $133 $3,899
Public Safety Communications and Emergency Mgmt. -- $1,750 $2,850 $4,600
Sheriff -- $1,000 $500 $1,500
Grand Total $17,931 $26,862 $24,088 $68,881
Category Projected Ongoing Costs 2022 2023 2024 Three Year Total
Enterprise Information Technology $375 $1,275 $3,020 $4,670
IT/Other -- -- $322 $322
Fire -- -- $579 $579
Police -- -- -- --
Public Safety Communications and Emergency Mgmt. -- -- $281 $281
Sheriff -- -- $161 $161
Grand Total $375 $1,275 $4,363 $6,013
D-3
Return to Table of Contents
Program Area Projects by Category
Information Technology/Equipment
Category / Project 2022 2023 2024 Three Year Total
Enterprise Information Technology $9,378 $13,120 $15,105 $37,603
Audio Visual Equipment for Conference Rooms $1,000 -- -- $1,000
Connect Arlington $685 $815 $575 $2,075
Courtroom Upgrades to support Body Worn Cameras $210 -- -- $210
Enterprise Records Management System Modernization $300 $1,000 $1,000 $2,300
Human Resources and Financial System Refreshment -- $7,000 $7,000 $14,000
Network Equipment, Worker Mobility, Power Systems $2,646 $1,020 $1,480 $5,146
PC Replacement $3,272 $2,000 $1,800 $7,072
Revenue and Collection System Enhancement -- -- $1,200 $1,200
Security and Software -- $200 $200 $400
Server Hardware & Data Storage $965 $585 $850 $2,400
Telephone System Study & Refreshment $300 $500 $1,000 $1,800
IT/Other $550 $3,250 $2,000 $5,800
Child Welfare Purchase of Service Software $300 $950 -- $1,250
Day Care Ctr./In-home Child Care Licensing System $250 $300 -- $550
Land Record System -- $1,000 -- $1,000
Real Estate Assessment System -- $1,000 $2,000 $3,000
Fire $4,370 $7,609 $3,500 $15,479
Fire Defibrillators -- -- $3,500 $3,500
Fire Portable Radios -- $3,609 -- $3,609
Fire Vehicle Apparatus $4,370 $4,000 -- $8,370
Police $3,633 $133 $133 $3,899
Mobile Data Computers $3,500 -- -- $3,500
Police IT: E-Summons System $133 $133 $133 $399
Public Safety Communications and Emergency Mgmt. -- $1,750 $2,850 $4,600
Public Safety Radios -- -- $2,850 $2,850
Radio Base Station and System Replacement -- $1,750 -- $1,750
Sheriff -- $1,000 $500 $1,500
Courthouse Magnetometer / X-Ray Machine -- -- $300 $300
Justice Center Security System -- $1,000 $200 $1,200
Grand Total $17,931 $26,862 $24,088 $68,881
D-4
Return to Table of Contents
Program Area Category Overview
Information Technology/Equipment
Enterprise Information Technology Category
Funding Source 2022 2023 2024 Three Year Total
New funding $6,840 $5,305 $8,105 $20 250
01 Federal
02 State
03 Developer
04 New Bonds
05 PAYG $1,600 $1,600
06 Short-term Financing $5,240 $5,305 $7,530 $18,075
07 Sanitary Tax
08 Other $575 $575
09 Transportation Capital C&I
10 Transportation Capital NVTA Local
11 Regional
12 Crystal City TIF
Previous Funding $2,538 $7,815 $7,000 $17,353
13 Authorized Unissued Bonds
14 Issued Unspent Bonds
15 Transportation Capital C&I
16 Transportation Capital NVTA Local
17 Regional
18 Crystal City TIF
19 Other $2,538 $7,815 $7,000 $17,353
Grand Total $9,378 $13,120 $15,105 $37,603
Category/ Project 2022 2023 2024 Three Year Total
Enterprise Information Technology $9,378 $13,120 $15,105 $37,603
Audio Visual Equipment for Conference Rooms $1,000 $1,000
Connect Arlington $685 $815 $575 $2,075
Courtroom Upgrades to support Body Worn Cameras $210 $210
Enterprise Records Management System Modernization $300 $1,000 $1,000 $2,300
Human Resources and Financial System Refreshment $7,000 $7,000 $14,000
Network Equipment, Worker Mobility, Power Systems $2,646 $1,020 $1,480 $5,146
PC Replacement $3,272 $2,000 $1,800 $7,072
Revenue and Collection System Enhancement $1,200 $1,200
Security and Software $200 $200 $400
Server Hardware & Data Storage $965 $585 $850 $2,400
Telephone System Study & Refreshment $300 $500 $r,mm $1,800
Grand Total $9,378 $13,120 $15,105 $37,603
Return to Table of Contents D-5
� 5" n o' ::r �
:, 3 Q. Q)
0 :r.
OQ 0 -< ::,
Program Area Category
Information Technology/Equipment Enterprise Information Technology
Project
Audio Visual Equipment for Conference Rooms
Funding Source 2022 2023 2024 Three Year Total
New Funding $1,000 -- -- $1,000
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG $1,000 -- -- $1,000
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total $1,000 -- -- $1,000
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
This project is to provide new or enhanced audio/visual capabilities to conference rooms across the County with particular
emphasis on making in-person meetings accessible virtually by others unable to participate in person.
D-6
Return to Table of Contents
Program Area
Information Technology/Equipment
Project
Connect Arlington
Category
Enterprise Information Technology
Connect Arlington (CA) is the County's Fiber Optic Network. It covers approximately 70 route miles and currently connects
90+ structures, roughly 50% of which are County structures and 50% are County Schools (APS) structures. CA also supports
the County's advanced traffic signals, video surveillance, and certain utilities. CA was constructed in three major (3) phases.
Funding Source 2022 2023 2024 Three Year Total
New Funding $575 $575
01 Federal
02 State
03 Developer
04 New Bonds
05 PAYG
06 Short-term Financing
07 Sanitary Tax
08 Other $575 $575
09 Transportation capital C&I
10 Transportation capital NVTA Local
11 Regional
12 Crystal City TIF
Previous Funding $685 $815 $1,500
13 Authorized Unissued Bonds
14 Issued Unspent Bonds $685 $815
15 Transportation Capital C&I
16 Transportation Capital NVTA Local
17 Regional
18 Crystal City TIF
19 Other $685 $815 $1,500
Grand Total $685 $815 $575 $2,075
P-ro·ected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs
01 Personnel
02 Non-Personnel
03 Bond Financing Costs
04 Short Term Financing Costs
05 Facilities Costs
06 Operations Costs
07 Maintenance Capital Costs
02 Fees
08 Less Fees
Grand Total
Return to Table of Contents D-7
� 5"
n o' ::r
3
0 :r.
0 -< ::,
Program Area Category
Information Technology/Equipment Enterprise Information Technology
Project
Courtroom Upgrades to support Body Worn Cameras
Funding Source 2022 2023 2024 Three Year Total
New Funding $210 -- -- $210
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing $210 -- -- $210
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total $210 -- -- $210
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
Upgrade two (2) additional courtrooms to support the display of digital evidence from Body Worn Cameras.
D-8
Return to Table of Contents
Program Area
Information Technology/Equipment
Project
Category
Enterprise Information Technology
Enterprise Records Management System Modernization
The Enterprise Records Management System (ERMS) is a set of solutions and a software platform for managing content and
processes designed to track and store records. The software can be used to manage the creation and maintenance of records
with classification schemes, apply retention and disposal schedules, and control access and use. The system was
implemented in 2004. The first year of funding is for an ERMS Roadmap study to determine guidelines for application
development, identify technical infrastructure needed and review the existing portfolio of applications to develop a
comprehensive budget and implementation plan.
Funding Source 2022 2023 2024 Three Year Total
New Funding $300 $1,000 $1,000 $2,300
01 Federal
02 State
03 Developer
04 New Bonds
05 PAYG $300 $300
06 Short-term Financing $1,000 $1,000 $2,000
07 Sanitary Tax
08 Other
09 Transportation Capital C&I
10 Transportation Capital NVTA Local
11 Regional
12 Crystal City Tl F
Previous Funding
13 Authorized Unissued Bonds
14 Issued Unspent Bonds
15 Transportation Capital C&I
16 Transportation Capital NVTA Local
17 Regional
18 Crystal City TIF
19 Other
Grand Total $300 $1,000 $1,000 $2,300
P.ro·ected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs
01 Personnel
02 Non-Personnel
03 Bond Financing Costs
04 Short Term Financing Costs
05 Facilities Costs
06 Operations Costs
07 Maintenance capital Costs
02 Fees
08 Less Fees
Grand Total
Return to Table of Contents D-9
Program Area
Information Technology/Equipment
Project
Category
Enterprise Information Technology
Human Resources and Financial System Refreshment
Upgrade/replacement of the current Oracle e-Business System to the cloud based solution. The current system was
implemented in 2006 and has had technical upgrades to retain vendor support but has not upgraded functionality. An upgraded
system will provide improved experience, interfaces, mobility, and workflow to streamline process execution. It will provide
improved data analytics, visualization, and reporting capabilities to aid in faster decision making and service delivery.
Additionally, the project will implement functionality not in the existing system such as Projects Accounting & Management,
Grants Management, Contracts Managements, Employee Performance Management, and Talent Management.
Funding Source 2022 2023 2024 Three Year Total
New Funding
01 Federal
02 State
03 Developer
04 New Bonds
05 PAYG
06 Short-term Financing
07 Sanitary Tax
08 Other
09 Transportation Capital C&I
10 Transportation Capital NVTA Local
11 Regional
12 Crystal City Tl F
Previous Funding $7,000 $7,000 $14,000
13 Authorized Unissued Bonds
14 Issued Unspent Bonds
15 Transportation Capital C&I
16 Transportation Capital NVTA Local
17 Regional
18 Crystal City TIF
19 Other $7,000 $7,000 $14,000
Grand Total $7,000 $7,000 $14,000
P.ro·ected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs
01 Personnel
02 Non-Personnel
03 Bond Financing Costs
04 Short Term Financing Costs
05 Facilities Costs
06 Operations Costs
07 Maintenance capital Costs
02 Fees
08 Less Fees
Grand Total
Return to Table of Contents D-10
Program Area
Information Technology/Equipment
Project
Category
Enterprise Information Technology
Network Equipment, Worker Mobility, Power Systems
This program supports the County network including cyclical refreshment of County network equipment; software and
hardware systems supporting worker mobility and telework technology; replacement of end-of-life power protection
equipment supporting data center infrastructure and in-building digital infrastructure throughout the County; refreshment
of equipment and cabling supporting the data center infrastructure, and; software and monitoring tools supporting
network access and access security.
Funding Source 2022 2023 2024 Three Year Total
New Funding $1,782 $1,020 $1,480 $4,282
01 Federal
02 State
03 Developer
04 New Bonds
05 PAYG
06 Short-term Financing $1,782 $1,020 $1,480 $4,282
07 Sanitary Tax
08 Other
09 Transportation Capital C&I
10 Transportation Capital NVTA Local
11 Regional
12 Crystal City TIF
Previous Funding $864 $864
13 Authorized Unissued Bonds
14 Issued Unspent Bonds
15 Transportation Capital C&I
16 Transportation Capital NVTA Local
17 Regional
18 Crystal City TIF
19 Other $864 $864
Grand Total $2,646 $1,020 $1,480 $5,146
P.ro·ected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs
01 Personnel
02 Non-Personnel
03 Bond Financing Costs
04 Short Term Financing Costs
05 Facilities Costs
06 Operations Costs
07 Maintenance capital Costs
02 Fees
08 Less Fees
Grand Total
Return to Table of Contents D-11
Program Area Category
Information Technology/Equipment Enterprise Information Technology
Project
PC Replacement
Funding Source 2022 2023 2024 Three Year Total
New Funding $3,248 $2,000 $1,800 $7,048
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing $3,248 $2,000 $1,800 $7,048
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $24 -- -- $24
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $24 -- -- $24
Grand Total $3,272 $2,000 $1,800 $7,072
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
This program supports the cyclical replacement and refreshment of end user computing devices (laptops, desktops, tablets,
etc.) that have reached the end of their usable life. End user devices have a usable life of three years or four years, depending
on device type. The program also includes products and services which supplement monitoring, maintenance, application
mobility, and security in the technology workplace.
D-12
Return to Table of Contents
Program Area Category
Information Technology/Equipment Enterprise Information Technology
Project
Revenue and Collection System Enhancement
Funding Source 2022 2023 2024 Three Year Total
New Funding -- -- $1,200 $1,200
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- -- $1,200 $1,200
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total -- -- $1,200 $1,200
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
The Revenue and Collection System is the application used by the offices of the Commissioner of Revenue and the Treasurer to
perform assessment and collection activities. The systems functionality includes all business tax and vehicle personal property
tax assessments, tax billings, production of tax letters and notices, tax enforcement activities, collections actions, revenue
accounting, and the majority of assessment and revenue reporting. This system requires refreshment/upgrading on a periodic
basis. Funding in FY 2024 is the first year of a two year project to upgrade the system.
D-13
Return to Table of Contents
Program Area Category
Information Technology/Equipment Enterprise Information Technology
Project
Security and Software
Funding Source 2022 2023 2024 Three Year Total
New Funding -- $200 $200 $400
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- $200 $200 $400
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total -- $200 $200 $400
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
Funds to augment and enhance the software used to monitor and manage the network, data traffic, and security posture of the
network.
D-14
Return to Table of Contents
Program Area
Information Technology/Equipment
Project
Server Hardware & Data Storage
Category
Enterprise Information Technology
This program supports the annual refreshment, enhancement, and expansion of County servers, hosts, storage devices,
as they reach the end of their useful life.
Funding Source 2022 2023 2024 Three Year Total
New Funding $585 $850 $1,435
01 Federal
02 State
03 Developer
04 New Bonds
05 PAYG
06 Short-term Financing $585 $850 $1,435
07 Sanitary Tax
08 Other
09 Transportation Capital C&I
10 Transportation Capital NVTA Local
11 Regional
12 Crystal City TIF
Previous Funding $965 $965
13 Authorized Unissued Bonds
14 Issued Unspent Bonds
15 Transportation Capital C&I
16 Transportation Capital NVTA Local
17 Regional
18 Crystal City TIF
19 Other $965 $965
Grand Total $965 $585 $850 $2,400
01 Operating Costs $375 $500 $650 $1,525
01 Personnel
02 Non-Personnel
03 Bond Financing Costs
04 Short Term
Financing Costs
05 Facilities Costs
06 Operations Costs $375 $500 $650 $1,525
07 Maintenance Capital Costs
02 Fees
08 Less Fees
Grand Total $375 $500 $650 $1,525
Return to Table of Contents D-15
Program Area Category
Information Technology/Equipment Enterprise Information Technology
Project
Telephone System Study & Refreshment
Funding Source 2022 2023 2024 Three Year Total
New Funding $300 $500 $1,000 $1,800
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG $300 -- -- $300
06 Short-term Financing -- $500 $1,000 $1,500
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total $300 $500 $1,000 $1,800
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
The County telephone system was acquired in 2008. Since that time, voice system technology and the County's need for
desktop telephones has drastically changed. The upgrade will allow the County to adopt a hybrid voice model where parts of
the system will be located on site in the County but the bulk of the process takes place in the Cloud.
D-16
Return to Table of Contents
Program Area Category Overview
Information Technology/Equipment
IT/Other Category
Funding Source 2022 2023 2024 Three Year Total
New Funding -- $3,250 $2,000 $5,250
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- $1,250 -- $1,250
06 Short-term Financing -- $2,000 $2,000 $4,000
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $550 -- -- $550
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $550 -- -- $550
Grand Total $550 $3,250 $2,000 $5,800
Category / Project 2022 2023 2024 Three Year Total
IT/Other $550 $3,250 $2,000 $5,800
Child Welfare Purchase of Service Software $300 $950 -- $1,250
Day Care Ctr./In-home Child Care Licensing System $250 $300 -- $550
Land Record System -- $1,000 -- $1,000
Real Estate Assessment System -- $1,000 $2,000 $3,000
Grand Total $550 $3,250 $2,000 $5,800
D-17
Return to Table of Contents
Program Area Category
Information Technology/Equipment IT/Other
Project
Child Welfare Purchase of Service Software
Funding Source 2022 2023 2024 Three Year Total
New Funding -- $950 -- $950
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- $950 -- $950
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $300 -- -- $300
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $300 -- -- $300
Grand Total $300 $950 -- $1,250
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
The internally managed system is configured to connect Arlington Child and Family Services with third party service providers to
facilitate the purchase of their services in accordance with the child's individualized service plan. Users of this system will be
clients, vendors, DHS Staff, and staff from Arlington County Courts and Public Schools. A majority of clients using the system
will be enrolled in the County's foster care and adoption programs. The system will connect service authorizations to the
County's financial system and to the state's reimbursement systems.
D-18
Return to Table of Contents
Program Area Category
Information Technology/Equipment IT/Other
Project
Day Care Ctr./In-home Child Care Licensing System
Funding Source 2022 2023 2024 Three Year Total
New Funding -- $300 -- $300
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- $300 -- $300
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $250 -- -- $250
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $250 -- -- $250
Grand Total $250 $300 -- $550
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
Acquire a comprehensive, integrated, day care center and in-home child care licensing management system for Arlington
County Department of Human Services. This system will support child care licensing operations and serve as a portal for clients,
parents and the public. The management system will include components for program inspections, document management,
program enrollment and waitlist management, and staff training.
D-19
Return to Table of Contents
Program Area Category
Information Technology/Equipment IT/Other
Project
Land Record System
Funding Source 2022 2023 2024 Three Year Total
New Funding -- $1,000 -- $1,000
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- $1,000 -- $1,000
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total -- $1,000 -- $1,000
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
This project is for the replacement of the Clerk of the Circuit Court's Land Record system. The Clerk of the Circuit Court records
and maintains the official record of documents affecting the title to real property located in Arlington County and the City of
Falls Church. The land records system supports recording of land records documents, judgments and financing statements; fee
calculation and collection; storage of the digital images and indexing information; e-recording; and providing public access to
land records.
D-20
Return to Table of Contents
Program Area
Information Technology/Equipment
Project
Real Estate Assessment System
Category
IT/Other
The Department of Real Estate Assessments is responsible for valuing approximately 66,000 parcels annually, consisting of
commercial, single-family and condominiums. The current system was initially implemented twenty years ago and a custom
in-house system was built eight years ago to supplement missing functionality at the time. A new system will provide
significant functional
enhancements with greater analytical and reporting capabilities as well as integration with other
systems.
Funding Source 2022 2023 2024 Three Year Total
� � New Funding $1,000 $2,000 $3,000 3 3
0 Q)
01 Federal -- � g---------------------------------------------- -<::,
02 State
03 Developer
04 New Bonds
05 PAYG
06 Short-term Financing $1,000 $2,000 $3,000
07 Sanitary Tax
08 Other
09 Transportation Capital C&I
10 Transportation Capital NVT A Local
11 Regional
12 Crystal City TIF
Previous Funding
13 Authorized Unissued Bonds
14 Issued Unspent Bonds
15 Transportation Capital C&I
16 Transportation Capital NVTA Local
17 Regional
18 Crystal City TIF
19 Other
Grand Total $1,000 $2,000 $3,000
P.ro·ected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs
01 Personnel
02 Non-Personnel
03 Bond Financing Costs
04 Short Term Financing Costs
05 Facilities Costs
06 Operations Costs
07 Maintenance Capital Costs
02 Fees
08 Less Fees
Grand Total
Return to Table of Contents D-21
Program Area Category Overview
Information Technology/Equipment
Funding Source 2022 2023 2024 Three Year Total
New Funding $4,370 $7,609 $3,500 $15,479
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing $4,370 $7,609 $3,500 $15,479
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total $4,370 $7,609 $3,500 $15,479
Category / Project 2022 2023 2024 Three Year Total
Fire $4,370 $7,609 $3,500 $15,479
Fire Defibrillators -- -- $3,500 $3,500
Fire Portable Radios -- $3,609 -- $3,609
Fire Vehicle Apparatus $4,370 $4,000 -- $8,370
Grand Total $4,370 $7,609 $3,500 $15,479
Fire Category
D-22
Return to Table of Contents
Program Area Category
Information Technology/Equipment Fire
Project
Fire Defibrillators
Funding Source 2022 2023 2024 Three Year Total
New Funding -- -- $3,500 $3,500
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- -- $3,500 $3,500
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total -- -- $3,500 $3,500
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
Defibrillators are carried on all Fire Department response vehicles and allow the Fire Department to treat many medical
emergencies using the best technologies available. An example is its ability to monitor critical blood gasses and to transmit
critical information directly to hospitals when a patient is diagnosed as having a possible heart attack. This dramatically reduces
the hospital wait time as medical staff are notified of the patient's critical condition as early as possible.
D-23
Return to Table of Contents
Program Area Category
Information Technology/Equipment Fire
Project
Fire Portable Radios
Funding Source 2022 2023 2024 Three Year Total
New Funding -- $3,609 -- $3,609
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- $3,609 -- $3,609
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total -- $3,609 -- $3,609
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
Fire portable radios are hand-held radios that allow for two-way communication with the Emergency Communications Center
and all public safety agencies throughout the National Capital Region. The radios will be replaced as they near end of life as
equipment failure could result in communication delays that increase response time to critical events. When public safety
portable radios are replaced, they are transitioned to non-public safety departments for continued use.
D-24
Return to Table of Contents
Program Area Category
Information Technology/Equipment Fire
Project
Fire Vehicle Apparatus
Funding Source 2022 2023 2024 Three Year Total
New Funding $4,370 $4,000 -- $8,370
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing $4,370 $4,000 -- $8,370
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total $4,370 $4,000 -- $8,370
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
The Fire Apparatus refreshment program is an on-going program that refreshes the various emergency vehicles used by the Fire
Department. The inventory includes but is not limited to fire pumpers, rescue vehicles, truck lifts and ladder trucks. As fire
emergency vehicles reach their end of useful life, they need to be refreshed to continue providing fire operational services.
Certain apparatuses include buy-back incentive programs where the County is able to acquire new equipment less the trade-in
value for the existing equipment at a lower net cost to the County.
D-25
Return to Table of Contents
Program Area Category Overview
Information Technology/Equipment
Police Category
Funding Source 2022 2023 2024 Three Year Total
New Funding $2,633 $133 $133 $2,899
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG $133 $133 $133 $399
06 Short-term Financing $2,500 -- -- $2,500
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $1,000 -- -- $1,000
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $1,000 -- -- $1,000
Grand Total $3,633 $133 $133 $3,899
Category / Project 2022 2023 2024 Three Year Total
Police $3,633 $133 $133 $3,899
Mobile Data Computers $3,500 -- -- $3,500
Police IT: E-Summons System $133 $133 $133 $399
Grand Total $3,633 $133 $133 $3,899
D-26
Return to Table of Contents
Program Area
Information Technology/Equipment
Project
Mobile Data Computers
Category
Police
The Mobile Data Computer (MDC) project includes refreshment of the hardware, software, servers and vehicle docking
stations required for police vehicles to utilize mobile computing technology in public safety vehicles. These terminals or
laptops permit data exchange via wireless technology to the Police, Fire and Sheriff's Departments and are located in public
safety vehicles. The use of these devices increases the efficiency of information sharing, investigations, records management
and all forms of communications.
Funding Source 2022 2023 2024 Three Year Total
New Funding
01 Federal
02 State
03 Developer
04 New Bonds
05 PAYG
06 Short-term Financing
07 Sanitary Tax
08 Other
09 Transportation Capital C&I
10 Transportation Capital NVTA Local
11 Regional
12 Crystal City TIF
Previous Funding
13 Authorized Unissued Bonds
14 Issued Unspent Bonds
15 Transportation Capital C&I
16 Transportation Capital NVTA Local
17 Regional
18 Crystal City TIF
19 Other
Grand Total
01 Operating Costs
01 Personnel
02 Non-Personnel
03 Bond Financing Costs
04 Short Term Financing Costs
05 Facilities Costs
06 Operations Costs
07 Maintenance capital Costs
02 Fees
08 Less Fees
Grand Total
Return to Table of Contents
$2,500 $2,500
$2,500 $2,500
$1,000 $1,000
$1,000 $1,000
$3,500 $3,500
D-27
Program Area
Information Technology/Equipment
Project
Police IT: E-Summons System
Category
Police
In FY 2015, the County began assessing a $5.00 fee as part of the cost of each criminal or traffic case in the District and/or
Circuit Courts for the use of purchasing and implementing an electronic summons system. The budget reflects the projected
annual revenue from the fees. The system was implemented in early CY 2021. The balance of existing revenue and future
revenue will be used to fund software, hardware and equipment costs associated with maintaining the system as allowed by
State Code.
Funding Source 2022 2023 2024 Three Year Total
New Funding $133 $133 $133 $399
01 Federal
02 State
03 Developer
04New Bonds
05 PAYG $133 $133 $133 $399
06 Short-term Financing
07 Sanitary Tax
08 Other
09 Transportation Capital C&I
10 Transportation Capital NVTA Local
11 Regional
12 Crystal City Tl F
Previous Funding
13 Authorized Unissued Bonds
14 Issued Unspent Bonds
15 Transportation Capital C&I
16 Transportation Capital NVTA Local
17 Regional
18 Crystal City TIF
19 Other
Grand Total $133 $133 $133 $399
Pro·ected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs
01 Personnel
02 Non-Personnel
03 Bond Financing Costs
04 Short Term Financing Costs
05 Facilities Costs
06 Operations Costs
07 Maintenance capital Costs
02 Fees
08 Less Fees
Grand Total
Return to Table of Contents D-28
Program Area Category Overview
Information Technology/Equipment
Funding Source 2022 2023 2024 Three Year Total
New Funding -- $1,750 $2,850 $4,600
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- $1,750 $2,850 $4,600
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total -- $1,750 $2,850 $4,600
Category / Project 2022 2023 2024 Three Year Total
Public Safety Communications and Emergency Mgmt. -- $1,750 $2,850 $4,600
Public Safety Radios -- -- $2,850 $2,850
Radio Base Station and System Replacement -- $1,750 -- $1,750
Grand Total -- $1,750 $2,850 $4,600
Public Safety Communications and Emergency
Mgmt. Category
D-29
Return to Table of Contents
Program Area Category
Information Technology/Equipment Public Safety Communications and Emergency Mgmt.
Project
Public Safety Radios
Funding Source 2022 2023 2024 Three Year Total
New Funding -- -- $2,850 $2,850
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- -- $2,850 $2,850
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total -- -- $2,850 $2,850
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
The Public Safety Radios being recommended for replacement are mobile and portable radios. Police and Sheriff mobile radios
are installed in County vehicles and provide two-way communication between the Emergency Communication Center and
public safety vehicles. Police and Sheriff portable radios are hand-held radios that allow for two-way communication with the
Emergency Communications Center and all public safety agencies throughout the National Capital Region.
D-30
Return to Table of Contents
Program Area Category
Information Technology/Equipment Public Safety Communications and Emergency Mgmt.
Project
Radio Base Station and System Replacement
Funding Source 2022 2023 2024 Three Year Total
New Funding -- $1,750 -- $1,750
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- $1,750 -- $1,750
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total -- $1,750 -- $1,750
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
The Emergency Radio system is used to transmit public safety and other critical public safety communications via portable and
mobile radios. In order to have a fully operational and interoperable system, components such as the system base stations must
be refreshed to support new technologies and aging hardware.
D-31
Return to Table of Contents
Program Area Category Overview
Information Technology/Equipment
Sheriff Category
Funding Source 2022 2023 2024 Three Year Total
New Funding -- $1,000 $500 $1,500
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- $1,000 $500 $1,500
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total -- $1,000 $500 $1,500
Category / Project 2022 2023 2024 Three Year Total
Sheriff -- $1,000 $500 $1,500
Courthouse Magnetometer / X-Ray Machine -- -- $300 $300
Justice Center Security System -- $1,000 $200 $1,200
Grand Total -- $1,000 $500 $1,500
D-32
Return to Table of Contents
Program Area Category
Information Technology/Equipment Sheriff
Project
Courthouse Magnetometer / X-Ray Machine
Funding Source 2022 2023 2024 Three Year Total
New Funding -- -- $300 $300
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- -- $300 $300
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total -- -- $300 $300
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
The Sheriff's Office magnetometer and X-ray machines reside in the Courts Building. These assets screen all visitors to the building
for potentially threatening items and assist in maintaining security in the Courthouse.
D-33
Return to Table of Contents
Program Area Category
Information Technology/Equipment Sheriff
Project
Justice Center Security System
Funding Source 2022 2023 2024 Three Year Total
New Funding -- $1,000 $200 $1,200
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- $1,000 $200 $1,200
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total -- $1,000 $200 $1,200
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
The Detention Facility Security System is used to monitor and control access to Detention Facility areas for the protection of staff,
inmates and the public. This equipment includes cameras, touch screens, and other equipment that control all doors, alarms, and
intercoms.
D-34
Return to Table of Contents
Program Area Summary
Metro
Funding Source 2022 2023 2024 Three Year Total
New Funding $30,200 $31,100 $31,900 $93,200
01 Federal -- -- -- --
02 State $9,500 $10,000 $10,400 $29,900
03 Developer -- -- -- --
04 New Bonds $20,700 $21,100 $21,500 $63,300
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local $0 $0 $0 $0
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total $30,200 $31,100 $31,900 $93,200
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- $1,449 $3,319 $4,768
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- $1,449 $3,319 $4,768
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- $1,449 $3,319 $4,768
Projected Staffing 2022 2023 2024 Three Year Total
Anticipated FTE Change -- -- -- --
Grand Total -- -- -- --
The Washington Metropolitan Area Transit Authority (WMATA/Metro) is a unique federal-state-local partnership formed to
provide mass transit service to the Washington Metropolitan region. WMATA's Adopted FY 2022 - FY 2027 Capital Budget
consists of $13.6 billion of critical system projects necessary to maintain the safety, reliability, and state of good repair of
Metro's infrastructure, equipment, and assets over the next six years. The program focuses heavily on ongoing projects and
prioritized system preservation and renewal needs identified in WMATA's Capital Needs Inventory. This includes
replacement / rehab of the system's aging rail infrastructure, funding for bus and railcar rehabilitation, replacement of bus,
rail, and paratransit vehicles, rail power system improvements, technology system improvements, and radio and wireless
communication system upgrades.
E-1
Return to Table of Contents
Program Area Category
Metro Metro
Project
Metro Funding
Funding Source 2022 2023 2024 Three Year Total
New Funding $30,200 $31,100 $31,900 $93,200
01 Federal -- -- -- --
02 State $9,500 $10,000 $10,400 $29,900
03 Developer -- -- -- --
04 New Bonds $20,700 $21,100 $21,500 $63,300
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local $0 $0 $0 $0
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total $30,200 $31,100 $31,900 $93,200
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- $1,449 $3,319 $4,768
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- $1,449 $3,319 $4,768
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- $1,449 $3,319 $4,768
Compared to previous plans, WMATA's Adopted FY 2022 - FY 2027 Capital Budget represents a significant funding increase.
Previous funding levels were approximately $1.3 billion - $1.5 billion annually, which has now risen to $2.0 billion - $2.6 billion
annually, an average increase of over 60%. To meet this significant funding request, Maryland, Virginia, and the District of
Columbia each passed legislation in 2018 which secures a combined $500 million annually of "dedicated funding" for WMATA
beginning in FY 2019. In Virginia, the share is $154 million and is funded by a combination of redirected state revenues, a
redirection of regional grantors and transient occupancy taxes previously collected by the Northern Virginia Transportation
Authority (NVTA), a gain from a floor on regional gas tax revenues, and an additional local funding commitment of $27.1 million
dollars.
For Arlington, the estimated funding requirement over ten years in the Adopted FY 2022 - FY 2027 CIP is $196 million. This
consists of $151 million of annual local jurisdictional subsidy payments, and $45 million for Arlington's share of the local
funding commitment portion of Virginia's new WMATA "dedicated funding". A combination of general obligation bonds, state
grants, regional gas tax, and transportation capital funds, are used to fund Arlington's share of the WMATA capital subsidy.
Arlington's proportional share of jurisdictional capital subsidy is outlined in the WMATA Capital Funding Agreement (CFA). The
current CFA was adopted in 2021 covering FY 2022 - FY 2027.
E-2
Program Area Summary
Transportation
The FY 2022 - FY 2024 Transportation Capital Improvement Plan (CIP) continues Arlington County's commitment to
developing, maintaining and managing a multimodal transportation system that expands travel choices and provides equal
access for all users. During the next 3 years, Arlington plans to invest close to $0.6 billion in a range of capital improvements
to enhance the quality of life and economic well-being of its residents, workers and visitors. The plan balances maintenance
of existing infrastructure with investment in projects that have long-term positive community impact. The program includes
a broad range of complete street projects to enhance accessibility for all modes, Metrorail station projects to improve
accessibility and safety for users, investments in the ART bus fleet and maintenance facilities, expansion of transit service in
key travel corridors such as Columbia Pike, continued maintenance and reconstruction of County bridges and roadways,
improvements to street lights and signals,
and enhancements to parking. The CIP program reflects the goals and objectives
set forth in Arlington's Master Transportation Plan and other County planning efforts.
Funding Source 2022 2023 2024 Three Year Total
New Funding $42,313 $83,206 $215,265 $340,784
01 Federal $1,544 $14,715 $27,992 $44,251
02 State $10,039 $13,908 $57,391 $81,338
03 Developer $0 $0
04 New Bonds $8,000 $11,750 $17,840 $37,590
05 PAYG $214 $4,310 $5,744 $10,268
06 Short-term Financing
07 Sanitary Tax
08 Other $1,809 $6,909 $4,557 $13,275
09 Transportation Capital C&I $11,896 $20,492 $57,263 $89,651
10 Transportation Capital NVTA Local $7,975 $7,135 $13,957 $29,067
11 Regional $0 $515 $25,737 $26,252
12 Crystal City TIF $836 $3,472 $4,784 $9,092
Previous Funding $123,386 $174,508 $71,450 $369,544
13 Authorized Unissued Bonds $3,000 $3,000
14 Issued Unspent Bonds $4,372 $2,437 $212 $7,021
15 Transportation Capital C&I $25,043 $44,481 $8,063 $77,587
16 Transportation Capital NVTA Local $9,549 $8,963 $4,949 $23,461
17 Regional $29,909 $52,441 $29,876 $112,226
18 Crystal City TIF $5,990 $6,622 $3,372 $15,984
19 Other $45,723 $59,564 $24,978 $130,265
Grand Total $165,899 $257,714 $286,715 $710,328
* Implementation Adjustment ($33,140) ($51,543) ($57,343) ($142,026)
Adjusted CIP $132,559 $206,171 $229,372 $568,102
* Reflects a budget adjustment to include risk of project execution to more accurately forecast annual expenditures.
Return to Table of Contents E-3
C
'l'
Program Area Summary
Transportation
Pro·ected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs
01 Personnel
02 Non-Personnel
03 Bond Financing Costs
04 Short Term Financing Costs
05 Facilities Costs
06 Operations Costs
07 Maintenance Capital Costs
02 Fees
08 Less Fees
Grand Total
* Anticipated FTE Change 7
Grand Total 7
* Seven (7) FTES for the Transportation Capital Fund are requested to support implementation of an almost $600 million
three-year CIP. No general fund support is required.
Return to Table of Contents E-4
7
7
Program Area Program Area Overview
Transportation
Funding for the Transportation CIP program comes from a mix of federal, state, regional, and local sources. Two
primary sources of local revenues for this program are the Commercial and Industrial (C&I) Tax (a component of
the Transportation Capital Fund (TCF or Transportation Capital)) and Crystal City, Potomac Yard, and Pentagon
City Tax Increment Financing (TIF). The C&I tax is funded by an additional real estate tax on commercial and
industrial properties for transportation initiatives; the rate is currently set at $0.125 per $100 of assessed value.
Eligible uses of these dedicated transportation funds are outlined in the state code, enacted through House Bill
3202 by the 2007 Virginia General Assembly (and as amended by the 2018 Virginia General Assembly), and
through the adoption of the tax by the County Board in 2008. The TIF uses a portion of incremental property tax
revenue generated by new development and property appreciation in Crystal City, Potomac Yard, and Pentagon
City to fund infrastructure improvements in those areas. The TIF was initiated by the County Board in 2010 at an
increment of 33 percent; the increment used in the CIP is 25 percent, consistent with the County Board action as
part of the FY 2019 Adopted Budget.
Arlington's Transportation CIP program also benefits from transportation funding legislation (House Bill 2313)
enacted by the 2013 Virginia General Assembly. This legislation raises transportation revenues for Northern
Virginia localities through a state-imposed regional sales tax. Revenues are collected by the state and distributed
to the Northern Virginia Transportation Authority (NVTA). Of these revenues, 70 percent (NVTA Regional) are
retained by the NVTA to fund regional transportation projects through a competitive selection process. The
remaining 30 percent (NVTA Local) is returned to the member localities, based on the amount of revenue
generated by the sales tax within the locality. NVTA Local funds, a component of the Transportation Capital Fund
(TCF or Transportation Capital), may be used for locally selected transportation projects that comply with eligible
uses outlined in the state code.
Consistent with the FY 2021 CIP and FY 2019 CIP, the availability of local sources of funds, including pay-as-you-go
(PAYG) and general obligation (GO) bonds, is constrained. As a result, rather than major improvements and
expansions, the use of these funds in this CIP is primarily focused on maintaining the County's transportation
infrastructure in a State of Good Repair (SGR) - paving roadways, repairing and replacing bridges, traffic signals
and streetlights. Some of these funds are also used to improve safety and accessibility in pursuit of the County's
Vision Zero goal. We seek to ensure that our existing transportation assets are maintained in good working
condition and continue the ongoing sustainability of our transportation programs.
This CIP continues investments from the previous CIP to create a Premium Transit Network that will offer faster,
more reliable and easier-to
-use bus service connecting Columbia Pike, Pentagon City, Crystal City and Potomac
Yard, which are major areas of growth and economic development in the County. Upon completion of capital
improvements and services enhancements, this network will include a combination of local and limited-stop
service and a new one-seat ride between Columbia Pike and Crystal City. Each segment will feature a variety of
passenger amenities to improve travel times and attract new riders. Amenities may include high quality transit
stations, exclusive bus lanes, off-vehicle fare collection, transit signal priority, low-floor boarding, and branded
vehicles and information. Projects supporting this effort include street improvements such as dedicated bus lanes
and transit signal priority, new transit stations, real-time bus arrival information, bus purchases and development
of bus maintenance/parking facilities. This adotped CIP includes funding for the full capital and operating costs of
implementing the ART service improvements outlined in the County Board-approved Transit Development Plan
(TDP) by using multiple dedicated funding sources, including TCF and funds from external agencies.
E-5
Return to Table of Contents
-
'l'
Program Area Program Area Overview
Transportation
The CIP also anticipates a variety of external funding sources over the 3-year period. These include several state sources - transit
capital and maintenance funding from the Virginia Department of Rail and Public Transportation (DRPT); and Smart Scale, state
funding that is highly competitive and available for roadway and transit projects. Both of those sources are programmed by the
Commonwealth Transportation Board (CTB). Additionally, both the 1-66 Express Lanes and 1-395 Express Lanes have associated
grant programs to allocate revenues resulting from the tolled facilities. Both of those programs are managed by the Northern
Virginia Transportation Commission (NVTC) with oversight by the CTB. The program also includes a small amount of federal
funding, from programs focused on safety (Highway Safety Improvement Program), bicycle and pedestrian improvements
(Transportation Alternatives Program), as well as large, nationally competitive programs (Rebuilding American Infrastructure with
Sustainability and Equity (RAISE)).
Category Funding Sources 2022 2023 2024 Three Year Total
Arlington Transit Program
Complete Arlington Streets
Maintenance capital
Transportation Capital Program Administration
Operating Costs
Grand Total
* Implementation Adjustment
$61,757 $115,525 $143,541 $320,823
$81,644 $118,975 $118,141 $318,760
$14,079 $13,591 $13,802 $41,472
$3,324 $3,574 $3,682 $10,580
$5,095 $6,049 $7,549 $18,693
$165,899 $257,714 $286,715 $710,328
($33,140) ($51,543) ($57,343) ($142,026)
Adjusted CIP $132,559 $206,171 $229,372 $568,102 --------------------------
* Reflects a budget adjustment to include risk of project execution to more accurately forecast annual expenditures.
Ongoing Costs 2022 2023 2024 Three Year Total
Arlington Transit Program
Complete Arlington Streets
Maintenance Capital
Transportation Capital Program Administration
Debt Service
Grand Total
Return to Table of Contents E-6
Program Area Projects by Category
Transportation
Category/ Project 2022 2023 2024 Three Year Total
Arlington Transit Program $61,757 $115,525 $143,541 $320,823
Army Navy Drive Transit Center $1,809 $6,463 $8,272
ART Facilities $9,573 $23,413 $23,993 $56,979
ART Fleet & Equipment Replacement $13,660 $10,590 $24,250
Ballston Multimodal Improvements $3,619 $3,619
Ballston-MU Metrorail Station West Entrance $2,038 $9,090 $56,623 $67,751
Bus Bay Expansion-East Falls Church Metro Station $1,312 $2,033 $3,258 $6,603
Bus Stop Accessibility Improvements $735 $711 $739 $2,185
Bus Stop and Shelter Program $550 $481 $506 $1,537
Court House Metro Station Second Elevator $543 $885 $1,428
Crystal City Metro Station East Entrance $10,822 $43,705 $36,744 $91,271
Pentagon City Metro Station Second Elevator $2,238 $6,175 $8,413
PrTN: Columbia Pike Transit Stations $4,723 $3,539 $2,868 $11,130
PrTN: Off Vehicle Fare Collection $36 $114 $150
PrTN: Transit ITS and Security Program $3,293 $1,177 $553 $5,023
PrTN: Transitway Extension to Pentagon City $7,349 $13,461 $5,242 $26,052
PrTN: Transitway Extension(Potomac Ave-Alexandria) $36 $4,318 $399 $4,753
Shirlington Bus Station Expansion $108 $108
Transit Strategic Plan Updates $272 $1,027 $1,299
Complete Arlington Streets $81,644 $118,975 $118,141 $318,760
Army Navy Country Club Trail $117 $309 $265 $691
Army Navy Drive Complete Street $2,297 $5,000 $5,000 $12,297
Bl KEArlington $2,296 $2,802 $7,783 $12,881
Boundary Channel Drive Interchange $4,337 $2,181 $25 $6,543
Bridge Renovation / Replacement $11,292 $12,890 $19,586 $43,768
Capital Bikeshare $1,426 $1,090 $1,160 $3,676
Columbia Pike Streets $17,511 $40,994 $36,909 $95,414
Crystal City, Pentagon City, Potomac Yard Streets $9,790 $17,870 $16,136 $43,796
Improvements Outside Major Corridors $5,747 $7,880 $5,592 $19,219
Intelligent Transportation Systems $6,257 $3,689 $3,789 $13,735
Lee Highway Multimodal Improvements $265 $265
Neighborhood Complete Streets $2,185 $1,016 $1,332 $4,533
Parking Meters $190 $700 $470 $1,360
Parking Technology $2,050 $2,250 $545 $4,845
Rosslyn-Ballston Arterial Street Improvements $4,290 $10,183 $11,663 $26,136
Strategic Network Analysis and Planning $769 $593 $610 $1,972
Street Lighting $2,514 $2,144 $1,341 $5,999
Street Safety Improvements (SSI) $1,831 $1,554 $1,601 $4,986
Transportation Asset Management $250 $258 $265 $773
Transportation Systems & Traffic Signals $4,479 $5,163 $3,383 $13,025
WALKArl i ngton $2,016 $409 $421 $2,846
Return to Table of Contents E-7
:1
'3.
C
'l'
Program Area Projects by Category
Transportation
Category/ Project 2022 2023 2024 Three Year Total
Maintenance Capital $14,079 $13,591 $13,802 $41,472
Bridge Maintenance $1,545 $1,535 $1,400 $4,480
Curb & Gutter Missing Links $115 $120 $125 $360
ITS Device Replacement $200 $165 $454 $819
Paving $12,169 $11,719 $11,770 $35,658
Trail Light Maintenance Program $50 $52 $53 $155
Program Administration / Operating Costs $8,419 $9,623 $11,231 $29,273
Program Administration $3,324 $3,574 $3,682 $10,580
Operating Costs $5,095 $6,049 $7,549 $18,693
Grand Total $165,899 $257,714 $286,715 $710,328
* Implementation Adjustment ($33,140) ($51,543) ($57,343) ($142,026)
Adjusted CIP $132,559 $206,171 $229,372 $568,102
* Reflects a budget adjustment to include risk of project execution to more accurately forecast annual expenditures.
Return to Table of Contents E-8
Program Area
Transportation
Arlington Transit Program Category
Category Overview
Funding Source 2022 2023 2024 Three Year Total
New Funding $16,159 $29,048 $105,509
01 Federal $6,761 $25,050
$150,716
$31,811
02 State $10,039 $13,908 $53,238 $77,185
03 Developer
04 New Bonds
OS PAYG
06 Short-term Financing
07 Sanitary Tax
08 Other $1,809 $6,463 $8,272
09 Transportation Capital C&I $184 $1,666 $3,343 $5,193
10 Transportation Capital NVTA Local $4,127 $250 $3,796 $8,173
11 Regional $20,082 $20,082
12 Crystal City TIF
Previous Funding $45,598 $86,441 $37,298 $169,337
13 Authorized Unissued Bonds
14 Issued Unspent Bonds $481 $126 $607
15 Transportation Capital C&I $6,024 $6,791 $1,643 $14,458
16 Transportation Capital NVTA Local $1,324 $409 $843 $2,576
17 Regional $18,192 $33,136 $20,129 $71,457
18 Crystal City TIF $36 $734 $770
19 Other $19,577 $45,979 $14,683 $80,239
Grand Total $61,757 $115,525 $143,541 $320,823
Category/ Project 2022 2023 2024 Three Year Total
Arlington Transit Program $61,757 $115,525 $143,541
Army Navy Drive Transit Center $1,809 $6,463
ART Facilities $9,573 $23,413 $23,993
$320,823
$8,272
$56,979
ART Fleet & Equipment Replacement $13,660 $10,590 $24,250
Ballston Multimodal Improvements $3,619 $3,619
Ballston-MU Metrorail Station West Entrance $2,038 $9,090 $56,623 $67,751
Bus Bay Expansion-East Falls Church Metro Station $1,312 $2,033 $3,258 $6,603
Bus Stop Accessibility Improvements $735 $711 $739 $2,185
Bus Stop and Shelter Program $550 $481 $506 $1,537
Court House Metro Station Second Elevator $543 $885 $1,428
Crystal City Metro Station East Entrance $10,822 $43,705 $36,744 $91,271
Pentagon City Metro Station Second Elevator $2,238 $6,175 $8,413
PrTN: Columbia Pike Transit Stations $4,723 $3,539 $2,868 $11,130
PrTN: Off Vehicle Fare Collection $36 $114 $150
PrTN: Transit ITS and Security Program $3,293 $1,177 $553 $5,023
PrTN: Transitway Extension to Pentagon City $7,349 $13,461 $5,242 $26,052
PrTN: Transitway Extension(Potomac Ave-Alexandria) $36 $4,318 $399 $4,753
Shirlington Bus Station Expansion $108 $108
Transit Strategic Plan Updates $272 $1,027 $1,299
Grand Total $61,757 $115,525 $143,541 $320,823
Return to Table of Contents E-9
'3.
Program Area Category
Transportation Arlington Transit Program
Project
Army Navy Drive Transit Center
Funding Source 2022 2023 2024 Three Year Total
New Funding $1,809 $6,463 -- $8,272
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other $1,809 $6,463 -- $8,272
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding -- -- -- --
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total $1,809 $6,463 -- $8,272
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
This project involves the planning, design and construction of the new Army Navy Drive Transit Center. This project will create a
new multi-modal, multi-jurisdictional facility near the Pentagon that will fill a critical void in the regional transportation system.
This project will enhance regional connectivity; the northern anchor of the Transitway connecting Pentagon City to the City of
Alexandria, serving ART bus, WMATA Metrobus service, DOD shuttles and tour buses by establishing a central bus route
connection and transfer hub in the busy Pentagon and Pentagon City travel markets. This facility will facilitate safe movement
of people transferring between different services or in route to their destinations in the Pentagon City area and serve as
important alternate to the Pentagon Transit Center, Northern Virginia's largest bus transfer center, during emergency closures.
E-10
Return to Table of Contents
Program Area Category
Transportation Arlington Transit Program
Project
ART Facilities
Funding Source 2022 2023 2024 Three Year Total
New Funding -- $6,301 $11,996 $18,297
01 Federal -- -- -- --
02 State -- $6,301 $11,996 $18,297
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $9,573 $17,112 $11,997 $38,682
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I $694 $2,265 -- $2,959
16 Transportation Capital NVTA Local -- -- -- --
17 Regional $8,726 $14,847 $11,997 $35,570
18 Crystal City TIF -- -- -- --
19 Other $153 -- -- $153
Grand Total $9,573 $23,413 $23,993 $56,979
This project addresses the need for an administration, operation and maintenance facility for Arlington's growing fleet of
Arlington Transit (ART) buses in the County. The facility is essential for ART's long-term sustainability as it will save ART's cost to
deadhead (non-revenue travel) to and from the existing warehouse maintenance facility in Alexandria, VA, improve service
reliability, eliminate the need for leased space, and ensure ART is able to deliver high quality service in the future. The County
has acquired three adjacent parcels of land on Shirlington Road to construct the required facilities to house and perform
administration, operations, and maintenance for ART. The facility will also include parking for buses as well as parking for ART's
administration, operations, and maintenance staff.
ART currently operates out of 4 facilities, two of which are not designed to support transit administration, operations, and
maintenance. One is a leased facility that is a converted warehouse in Alexandria, VA, located 9 miles south. The facility is not
designed for maintenance of transit buses and getting buses into and out of service from the facility is a major challenge for
ART. The other is a warehouse facility located on S Eads St across from the ART Light Maintenance Facility. This facility serves as
ART's administration and operations base and is also not designed for this purpose.
In addition, the County's local transit service has increased the number of routes and hours of service significantly over the past
ten years. The local bus fleet currently totals 78 buses. The plan is for ART to continue to increase over the next 20 years
requiring a fleet of over 100 buses. The new facility is designed to accommodate this expected growth. The facility is also being
designed with considerations for future electrification of the bus fleet and on-site charging.
E-11
Return to Table of Contents
Program Area Category
Transportation Arlington Transit Program
Project
ART Facilities
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
E-12
Return to Table of Contents
Program Area Category
Transportation Arlington Transit Program
Project
ART Fleet & Equipment Replacement
Funding Source 2022 2023 2024 Three Year Total
New Funding $13,232 -- $10,590 $23,822
01 Federal -- -- -- --
02 State $9,289 -- $7,201 $16,490
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local $3,943 -- $3,389 $7,332
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $428 -- -- $428
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I $31 -- -- $31
16 Transportation Capital NVTA Local $397 -- -- $397
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other -- -- -- --
Grand Total $13,660 -- $10,590 $24,250
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
This project is for the replacement of aging buses that have completed their useful life in accordance with public transit
standards. Arlington County's local bus system, ART, has a fleet of 78 buses of three different sizes. All existing buses are low-
floor vehicles powered by compressed natural gas (CNG) and heavy-duty with a vehicle life of 12 years. Many of these buses will
need to be replaced during the next ten fiscal years. A study is underway to review potential fleet conversion to EV to gain a
fulsome understanding of both the operational and capital impacts of this over time.
E-13
Return to Table of Contents
Program Area Category
Transportation Arlington Transit Program
Project
Ballston Multimodal Improvements
Funding Source 2022 2023 2024 Three Year Total
New Funding -- -- -- --
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $3,619 -- -- $3,619
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I $3,036 -- -- $3,036
16 Transportation Capital NVTA Local -- -- -- --
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $583 -- -- $583
Grand Total $3,619 -- -- $3,619
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
This project involves the planning, design and construction of a variety of surface level transportation facilities, street
improvements, and sidewalk improvements around the Ballston-MU Metrorail station. County staff finalized the design plans in
FY2019 for the project which included improvements to the pedestrian plaza area, curbside uses, street operational
improvements, and multi-modal facility accommodation. Specifically, the County's multimodal plan for this area is to modify
the curb-use plan, reconstruct and add bus bays, replace bus shelters and benches with newer, more modern structures,
improve pedestrian amenities, add more bicycle parking, design and install real time information displays, revise and improve
the landscaping, preserve and/or expand dedicated spaces for taxis and car-sharing, and add dedicated short-term spaces for
private shuttles and Kiss-n-Ride users. In December 2019, a construction contract was awarded for this project. Construction
started in spring 2020 and is expected to be complete in FY 2022.
E-14
Return to Table of Contents
Program Area Category
Transportation Arlington Transit Program
Project
Ballston-MU Metrorail Station West Entrance
Funding Source 2022 2023 2024 Three Year Total
New Funding -- -- $43,592 $43,592
01 Federal -- -- -- --
02 State -- -- $23,510 $23,510
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- $20,082 $20,082
12 Crystal City TIF -- -- -- --
Previous Funding $2,038 $9,090 $13,031 $24,159
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local -- -- -- --
17 Regional $2,038 $7,553 -- $9,591
18 Crystal City TIF -- -- -- --
19 Other -- $1,537 $13,031 $14,568
Grand Total $2,038 $9,090 $56,623 $67,751
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
The new Ballston West Entrance will be located at the intersection of N. Fairfax Drive and N. Vermont Street. This entrance will
be owned and operated by WMATA and will include two street-level elevators, escalators and/or stairs connecting to an
underground passageway and new mezzanine with stairs and elevators to the train platform. The new entrance will have fare
gates, fare vending machines, and a station manager kiosk. Additionally, the new entrance will improve access from the Glebe
Road area and the growing development in the western part of Ballston and improve egress in the event of an emergency
incident requiring evacuation from the station and train platforms.
E-15
Return to Table of Contents
Program Area Category
Transportation Arlington Transit Program
Project
Bus Bay Expansion-East Falls Church Metro Station
Funding Source 2022 2023 2024 Three Year Total
New Funding -- -- -- --
01 Federal -- -- -- --
02 State -- -- -- --
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- -- -- --
10 Transportation Capital NVTA Local -- -- -- --
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $1,312 $2,033 $3,258 $6,603
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I -- -- -- --
16 Transportation Capital NVTA Local $117 -- -- $117
17 Regional $539 $1,017 $2,890 $4,446
18 Crystal City TIF -- -- -- --
19 Other $656 $1,016 $368 $2,040
Grand Total $1,312 $2,033 $3,258 $6,603
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
The East Falls Church Metrorail station currently has four bus bays that are at maximum capacity. The project will expand bus
bay capacity by adding up to three new bus bays and replacing the existing shelters in the off-street bus loop at the East Falls
Church Metrorail station. The project also includes pedestrian access improvements from the Metro park-and-ride lot,
improvements to the accessible parking access, and evaluation of a new signal and crosswalk at the entrance to the park-and-
ride lot on Washington Boulevard. The project will be coordinated with Arlington County's complete streets project and signal
improvements on Sycamore Street as well as a Capital Bikeshare expansion project in the area in both Arlington and City of Falls
Church. Arlington County is sponsoring and leading the bus bay expansion project in coordination with WMATA that owns the
Metrorail station, the bus loop, and park-and-ride lot. Arlington County owns and operates the traffic signals in the project area.
E-16
Return to Table of Contents
Program Area Category
Transportation Arlington Transit Program
Project
Bus Stop Accessibility Improvements
Funding Source 2022 2023 2024 Three Year Total
New Funding $368 $711 $739 $1,818
01 Federal -- -- -- --
02 State -- $483 $503 $986
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I $184 $114 $118 $416
10 Transportation Capital NVTA Local $184 $114 $118 $416
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $367 -- -- $367
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I $298 -- -- $298
16 Transportation Capital NVTA Local $24 -- -- $24
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $45 -- -- $45
Grand Total $735 $711 $739 $2,185
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees -- -- -- --
08 Less Fees -- -- -- --
Grand Total -- -- -- --
The Bus Stop Accessibility Improvements program is an on-going program to address 554 of the County's bus stops previously
identified as being non-compliant with the Americans with Disabilities Act (ADA). Since FY 2014, approximately 271 bus stops
have been made ADA compliant. Bus stop improvements provided under this program include: ADA-compliant bus boarding
areas, pedestrian and accessible facilities that connect passengers to bus stops (sidewalks, crosswalks, ramps), and waiting areas
for wheelchair users inside bus shelters. Construction work is being accomplished through a combination of County crews,
other County streetscape projects, and Job Order Contracts, in addition to existing County contracting vehicles. The combined
use of County resources and external contractors minimizes procurement lead time allowing faster construction milestone
completions. The Transit Bureau works with the County's Real Estate Bureau to resolve right of way issues.
E-17
Return to Table of Contents
Program Area Category
Transportation Arlington Transit Program
Project
Bus Stop and Shelter Program
Funding Source 2022 2023 2024 Three Year Total
New Funding -- $392 $506 $898
01 Federal -- -- -- --
02 State -- $327 $344 $671
03 Developer -- -- -- --
04 New Bonds -- -- -- --
05 PAYG -- -- -- --
06 Short-term Financing -- -- -- --
07 Sanitary Tax -- -- -- --
08 Other -- -- -- --
09 Transportation Capital C&I -- $65 $81 $146
10 Transportation Capital NVTA Local -- -- $81 $81
11 Regional -- -- -- --
12 Crystal City TIF -- -- -- --
Previous Funding $550 $89 -- $639
13 Authorized Unissued Bonds -- -- -- --
14 Issued Unspent Bonds -- -- -- --
15 Transportation Capital C&I $316 $89 -- $405
16 Transportation Capital NVTA Local $57 -- -- $57
17 Regional -- -- -- --
18 Crystal City TIF -- -- -- --
19 Other $177 -- -- $177
Grand Total $550 $481 $506 $1,537
Projected Ongoing Costs 2022 2023 2024 Three Year Total
01 Operating Costs -- -- -- --
01 Personnel -- -- -- --
02 Non-Personnel -- -- -- --
03 Bond Financing Costs -- -- -- --
04 Short Term Financing Costs -- -- -- --
05 Facilities Costs -- -- -- --
06 Operations Costs -- -- -- --
07 Maintenance Capital Costs -- -- -- --
02 Fees --
Text truncated. Open the original for the full document.