County Manager's Proposed
FY 2025 Budget
County Board Work Session
April 4, 2025| 3:00 p.m.
FY 2025 Capital Program
Budget
PAYG, GO Bonds &
Short-term Finance
2
Measured approach
Mindful of continued
recovery in near-term,
impacts of debt service
on operating budget,
uncertain external
pressures (e.g. inflation /
interest rates)
Maintaining
County’s Current
Asset Inventory
e.g., facilities, trails and
bridges, technology
systems, and roofs
Meet Regional,
Legal, and
Regulatory
Obligations
e.g., Metro
Responding to
Emerging Service
Demands
Addressing
Environment &
Resiliency
Planning for
the Future
Principles Guiding Capital Investment
3
FY 2025 Capital Program Budget
$137.8 million
TO PRIORITIZED CAPITAL INVESTMENTS
PUBLIC/GOVERNMENT
FACILITIES
PARKS &
RECREATION
TECHNOLOGY &
PUBLIC SAFETY
MAINTENANCE
CAPITAL
TRANSPORTATION
& ROADS
COMMUNITY
CONSERVATION
4
$137.8
million
4%
General Obligation
Bonds (County)
$4.8 million
Funds are derived from the public sale of municipal
bonds for which principal and interest (debt service)
is paid to investors for the use of the money. Used
to fund large capital infrastructure with average
useful life of 10 years or more.
44%
State, Federal and
Regional Grants
$58 million
State, federal and regional grant funds restricted
in use to transportation activities.
Overall Funding Sources for the Capital Program
5%
Crystal City Tax Increment
Fund
$6.5 million
Fund source is portion of the incremental real estate tax
revenue which is used to pay for infrastructure
improvements to further the revitalization of these
areas.
7%
Short-term Finance
$9.2 million
Fund source is capital financing to acquire equipment and technology,
and to perform certain capital maintenance projects that have an
average useful life between three and ten years.
17%
PAY-AS-YOU-GO
$23.2 million
Funded by a transfer of net tax support, restricted bond premium
and, other miscellaneous fees and charges.
27%
Transportation Capital Fund (TCF)
$36.1 million
C&I Tax ($24.4 million)
NVTA Local ($11.8 million)
Tax revenue dedicated to support transportation infrastructure projects
throughout the County. Comprised of local Commercial and Industrial
(C&I) Tax and NVTA Local (30% allocation).
5
PAYG Overview
• $23.2 million from various sources
• General fund transfer, one-time funds- $20 million
• Bond premium (legally restricted in use to capital projects) - $3.2
million
• Funds assets with an average useful life of 10 years or less
• Continued focus on ‘must-have’ maintenance
• Assets at end of useful life
• Lifecycle replacement of equipment
• Rating agency expectation to have PAYG funding as a flexible
funding source for capital investment
6
PAYG Funding Over Time
6,875 5,322
8,646
3,832 1,180 4,000 6,000 6,000
3,000
14,643
6,645
5,650
12,651
12,000
3,225
6,695 1,331
6,995
1,991 11,049
8,846 7,969
20,000
0
5000
10000
15000
20000
25000
30000
35000
FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 FY 2024 FY 2025
HISTORY OF PAYG FUNDING SOURCES
One-Time Funds
Bond Premium
Ongoing Funds
Ongoing Fund
Trend
7
Spending Previously Authorized GO Bond Balances
• $4.8 million GO Bonds
• Authorized but Unissued GO bonds ($2.3 million)
• Issued but Unspent GO bond balances ($2.5 million)
• Funds assets with an average useful life of 10+ years
• Historically used for large replacement or renovation projects
• Debt service appropriated in General Fund
8
Short-term Finance Overview
• $9.2 million in short-maturity financed dollars
• Funds assets with an average useful life of 3-10 years
• Debt service appropriated in General Fund
• Historically used for equipment and systems replacement:
• ACE/CAPP (Treasurer Revenue and Collection System
Enhancement)
• Server Program
• Public Safety Radios
9
Key Budget Considerations
• Affordability of projects based on continued inflationary and supply
chain pressures
• Competing priorities require hard choices for funding
• Maintaining balance of improving and upgrading existing assets and
funding new projects for program efficiencies and to meet various
stakeholder expectations
10
• DHS - Social Solutions/Efforts To Outcomes/Homeless Management
Information System Replacement
Replacement of the current system to manage the Economic
Independence Division (EID) Customer Service Center - Customer
Service/Case Management functionality and replace the current
Homeless Management Information System (HMIS).
• Electoral Board - Voting Machines
Replacement of the Arlington Electoral Board voting system.
Other Projects
County Manager's Proposed
FY 2025 Budget
County Board Work Session
April 4, 2025| 3:00 p.m..
FY 2025 Capital Program
Budget
PAYG, GO Bonds &
Short-term Finance