Economic Development Authority — Agenda Minutes
Chesterfield County · Chesterfield County · Economic Development Authority · meeting of Mar 20, 2025 · Other
Open the original document More from Chesterfield County
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Economic Development Authority of Chesterfield County
Minutes
March 20, 2025
P a g e 1 | 4
Members Attending:
Terri Cofer Beirne* John V. Cogbill, III Faizan Habib
Danielle Fitz Hugh Jesse Calloway Robert Vaughn
John Hughes
Members Absent:
None
Others Attending:
John O'Neill, Hunton Andrews Kurt, LLP – Virtual Attendance
Mike Chernau, Chesterfield Attorney's Office
Mike Laing, ECI Development Management Services
Tim Davey, Timmons Group
Debbie Baicy, Chesterfield Accounting Department
Garrett Hart, Chesterfield Economic Development
Jake Elder, Chesterfield Economic Development
Matt McLaren, Chesterfield Economic Development
Samantha Furnish, Chesterfield Economic Development
Aiden Thompson, Chesterfield Budget & Management
Jerry Turner, Citizen
*Attended via Microsoft Teams
Danielle Fitz Hugh called the meeting to order at 3:06 p.m. and noted a quorum
was present for the March 20, 2025, Economic Development Authority meeting.
Other Updates:
Matt McLaren presented a Commonwealth Opportunity Fund Grant Agreement
for Super Radiator Coils to the Authority for consideration. He explained that the
expansion involves a $22 million investment with an additional 80,000 square feet
in the exciting facility. This project will generate 160 new jobs and is backed by a
state grant. Matt also outlined the local performance agreement, covering wage
requirements and tax incentives.
Robert Vaughn motioned to approve the Commonwealth Opportunity Fund grant
agreement for Super Radiator Coils expansion. Faizan Habib seconded, and all
members present voted in the affirmative.
Economic Development Authority of Chesterfield County
Minutes
March 20, 2025
P a g e 2 | 4
Approval of the Minutes:
Danielle Fitz Hugh requested the Authority approve the January 16, 2025,
meeting minutes. John Hughes motioned to approve the meeting minutes as
written. Robert Vaughn seconded, and all members present voted in the
affirmative.
Financial Statements Update:
Debbie Baicy provided the February financial report highlighting cash reserves
and project funding.
Springline at District 60 Update:
Mike Laing provided an update on Springline at District 60, including the progress
on the Collins building and the waitlist for apartments at The James. He said the
first move-ins are expected around May 1, with a full opening by June 30. He
shared that prospective tenant meetings with grocers and restaurants have been
held, indicating a growing interest in the site.
Mike presented new renderings of the hotel, highlighting changes in the bar area,
restaurant, and conference space. The building will have a glass facade, enhancing
its appearance and functionality. The James Two building is being planned, and
construction is expected to start soon. The new rendering shows the future of
Celebration Park and the James Two building, which will have a glass atrium and
retail space.
Mike presented a change order for the Authority to consider, which consists of
two parts. The first part, valued at $335,000, covers the hardscapes and site
amenities for Parcel 5. This includes the green space located just beside the
Collins building. The lighting was already part of a previous plan, but this change
order consists of trash cans, planters, sidewalks, one tent structure with
permanent footings and posts, and a metal tent area near the leasing office. The
second part of this change order is the landscaping, valued at $954,000. He said
they solicited three bids for this work, and James River Nurseries came in with the
lowest bid, approximately $60,000 less than the others.
Robert Vaughn moved to approve change order as presented to the Authority.
John Cogbill seconded, and all members present voted in the affirmative.
Economic Development Authority of Chesterfield County
Minutes
March 20, 2025
P a g e 3 | 4
Meadowville Technology Park Update:
Garrett Hart reported LEGO continues to make progress, and we should have
pictures in the next 30 to 60 days showing steel going up. They are using wood
beam construction for the main headquarters, and steel for the manufacturing
warehouses.
Upper Magnolia Green Update:
Jake Elder updated the EDA-initiated zoning cases for the Upper Mag and Watkins
Center. Community meetings were held for both cases and planning
commissioners and board members were present. Questions and comments have
been received on both cases, which have been addressed, and we've worked
closely with staff to prepare for the formal staff report. The zoning cases are
scheduled to be on the agenda for the Planning Commission meeting on April 15,
which will be one of the required public hearings. If the Planning Commission
takes action in April, the cases will move forward to the Board of Supervisors in
May.
Jake informed the Authority that staff is working with the Virginia Economic
Development Partnership (VEDP) through their Virginia Business Ready Sites
program to advance Upper Magnolia West to a Tier 4 site classification. We were
awarded a $13 million grant in the most recent round, which has been divided
into a $2 million grant for design and permitting and an $11 million grant for
other project needs.
Tim Davey reported we were awarded the grant in the fall, so we've known about
it for a while. There's been a lot of discussion around the terms, as they're starting
to impose more restrictions on many of these grants. The grant has been broken
down into phases; first, we need to complete the soft costs phase, which has
changed a bit due to some of the new requirements they've given us. After that,
we can move on to preparing the construction plans for bidding, at which point
we'll access the $11 million for construction. Over the past few months, we've
had to add a few things, so we'll ask you to amend a task order approved a few
months ago to get us moving. While we did get started, some aspects have
shifted along the way.
Economic Development Authority of Chesterfield County
Minutes
March 20, 2025
P a g e 4 | 4
This grant focuses on the infrastructure needed to support the larger pad site
we've been working on. When we applied for additional funds to complete the
rest of the infrastructure, the EDP suggested their approach to making the site
more marketable. The $13 million is intended to help us refine and develop the
site, bringing it to a point where we can fully reach the future pad site we're
planning. Over the last few months, one of the key changes they've asked us to
focus on is ensuring that we have a portion of the pad ready to market, located
near the 400-acre pad site we're developing.
Tim presented an amended task order for design and construction services for the
VEDP grant award for the Upper Mag road improvements not to exceed $2
million. The task order proposes to re-construct approximately 1,200' of existing
Duval Road as an improved two-lane roadway westward to where Duval Road
Extended would be re-aligned as a new two-lane industrial access roadway. A new
two-lane roadway connection to the south would be made to continue to serve
the existing Duval Road to the south and west. The design of an initial 10-acre site
pad and its access driveway are also included.
Robert Vaughn moved to approve the Timmons Group Amended Task Order for
professional design services for VEDP grant for Upper Magnolia Green road
improvements not to exceed $2 million and authorize the Chair and/or Vice-Chair
to sign. John Cogbill seconded, and all members present voted in the affirmative.
There being no further business, Danielle Fitz Hugh adjourned the meeting at 3:38
p.m.
Respectfully submitted,
Samantha Furnish
Recording Secretary