1
Historic Preservation Commission
Minutes of May 20, 2024
MEMBERS PRESENT:
Julie Arrington
Michael Erquiaga, Vice-Chair
Shanda Horner, Chair
Tracey Langseth
Emmett Lifsey
Dr. Gerry Sherayko
MEMBERS ABSENT:
Peter Alexander
OTHERS PRESENT:
Ms. Eve Mergenthaler, Secretary to the Historic Preservation Commission; and the public.
ROLL CALL:
After a quorum was established, Chair Horner called the meeting to order at 4:00 p.m.
1. CONSENT AGENDA:
Commissioner Lifsey made a motion to accept the consent agenda, which was seconded by Commissioner
Erquiaga, and passed by a unanimous vote.
2. NEW BUSINESS
a) ACTION (Advocate-Lifsey): Request of Randolph College to convert a window into a door,
install a ramp, and relocate a mechanical unit at 2500 Rivermont Avenue (Presser Hall).
(HPC2405-0001)
Mr. Greg McCann of Jamerson-Lewis Construction and Mr. Jonathan Tyree, Vice President of Finance and
Administration at Randolph College were present to represent the application. The Presser Hall building is
located at the front of the campus in the historic district. The basement level was previously used for offices
but will be converted to host the new robotics and mechatronics engineering program. This will include a
new lab, machine shop, and faculty offices. The basement level is not currently handicap accessible. The
proposed modifications will make the building accessible. A side window will be removed and converted
into a door. Additional sidewalk, at an appropriate grade, will be adde d to access the new door. A
mechanical HVAC unit will be removed and replaced on the other side of the building where other HVAC
units are already located.
Commissioner Erquiaga asked about the design of the new door. It does not match the existing doors.
Mr. McCann responded that making the design of the new door match the existing doors has been discussed
as an option. It would still be an aluminum store front door but it would have mullions/muntins to match.
Commissioner Lifsey made a motion to approve the application as submitted with the stipulation
that the new door have exterior mullions/muntins to match existing doors . The motion was
seconded by Commissioner Sherayko and passed by the following vote:
AYES: Erquiaga, Horner, Langseth, Lifsey, Sherayko 5
NOES: 0
ABSTENTIONS: 0
ABSENT: Alexander, Arrington 2
2
b) ACTION (Advocate-Horner): Request of Kristina Brumme to replace wood siding, soffit,
fascia, and trim at 301 Cabell Street. (HPC2405-0002)
Ms. Kristina Brumme was not present to represent the application.
Chair Horner stated that the applicants want to replace exterior elements of the house. It is not in good
shape and has a lot of rotten wood.
Commissioner Lifsey noted that the intent is to replace all of the siding. The application noted using hardie
plank with a grain. That would not be appropriate as the house would have had a smooth finished surface.
Smooth hardie plank should be utilized.
Commissioner Sherayko noted that applicants don’t typically request to replace all of the siding unless it is
necessary.
Chair Horner added that she visited the house in person and replacement is necessary.
Commissioner Lifsey reiterated that the hardie plank needs to be smooth, not grained.
Commissioner Sherayko asked if the decorative trim would be replaced.
Commissioner Lifsey made a motion to approve the application as submitted with the following
stipulations: the hardie plank be smooth rather than grained and match the existing exposure;
the decorative trim remain; and all replacement trim match existing profile and size. The motion
was seconded by Commissioner Langseth and passed by the following vote:
AYES: Arrington, Erquiaga, Horner, Langseth, Lifsey, Sherayko 6
NOES: 0
ABSTENTIONS: 0
ABSENT: Alexander 1
c) ACTION (Advocate-Erquiaga): Request of Adam White to install two types of fencing with
gates at 210/212 Harrison Street. (HPC2405-0003)
Mr. Adam White was present to represent the application. He would like to install two (2) types of fencing.
Both styles of fencing will be consistent with neighboring fences. On the left side of the house, a diamond
lattice style fence will be used. On the right side, a black, baked enamel aluminum, medium to heavy gauge
style fence will be used. The aluminum fencing will adjoin the porch. Both fences will not be visible at the
same time and the lattice fence will not be visible from the street. The fence heights will be per the
submitted drawing.
Commissioner Erquiaga asked about the visibility of the lattice fencing.
Mr. White responded that the lattice style gates will not be visible from the street as they will be located
behind the house.
Commissioner Erquiaga made a motion to approve the application as su bmitted. The motion was
seconded by Commissioner Langseth and passed by the following vote:
AYES: Arrington, Erquiaga, Horner, Langseth, Lifsey, Sherayko 6
NOES: 0
ABSTENTIONS: 0
ABSENT: Alexander 1
3
d) ACTION (Advocate-Alexander): Request of James Jean Louis Jeune to replace windows
at 1014 Jackson Street. (HPC2405-0004)
Mr. Myvens Jean Louis was present to represent the application on behalf of Mr. James Jean Louis Jeune
who was present via cell phone. The application is to replace all of the windows and he has submitted a
window quote for review. The windows will be simulated divided li te clad wood windows with exterior
muntins. There has been some difficulty in finding an appropriate replacement for the large window in the
living room so he would like to request two (2) double hung windows instead of replacing in-kind.
Commissioner Lifsey asked if the replacement windows are the same size as the original windows.
Mr. Louis replied that the tallest windows could not be replicated at the same h eight and would be a few
inches shorter. The tallest window is eighty-one (81) inches tall but the tallest wooden clad window that
can be ordered is seventy-seven (77) inches tall due to a couple of factors.
Commissioner Lifsey asked for clarification that the head height would remain the same but the sill would
come up about four (4) inches. He als o asked if the window width and the outside trim would match the
original.
Mr. Louis replied that was correct.
Commissioner Lifsey asked if the windows at the sides would also be replaced.
Mr. Louis replied that was correct.
Commissioner Lifsey asked if the replacement windows will be divided lite.
Mr. Louis replied that was correct.
Commissioner Sherayko asked if the windows at the sides and rear would be returned to the original size
and location to match the originals since some of those were previously removed or changed location.
Mr. Louis replied that was correct.
Commissioner Erquiaga asked for clarification regarding the large front window.
Mr. Louis responded that he would like to install two ( 2) double hung windows in place of an in-kind
replacement. He is not sure how long it would take to get an in-kind replacement window.
Commissioner Lifsey stated that a living room window would not be required to have the same egress that
a bedroom window would. The middle portion of that window needs to be nine-over-nine.
Commissioner Lifs ey made a motion to approve the arch top windows with the following
stipulations: a reduced height as submitted is allowed but the head height must match the
originals; replacement windows must match the originals in width, details (lites), and
location; and the exterior trim must match the originals in size and profile.
Commissioner Lifsey noted that the large window in the living room should be nine-over-nine but could be
a single or double hung window. It should retain the same trim and opening.
Commissioner Langseth asked about the side components of the large front window.
Mr. Louis responded that the intent is to remove those and have two (2) double hung windows in place of
the original. The manufacturer wasn’t able to find an exact match for the original so there is no exact time
frame for replacing it.
4
Commissioner Lifsey noted that the window in the quote does not match the original window. The original
window had four-over-four panels at the top of the side panels.
Commissioner Sherayko noted that large window is an outstanding architectural feature.
Ms. Eve Mergenthaler stated that the window was removed and is no longer in the applicant’s possession.
Chair Horner noted that the window should have been restored but since it is gone, it should be rebuilt to
match the original.
Commissioner Lifsey shared agreement and noted it is a very distinctive feature. It needs to be replaced
in-kind.
Commissioner Sherayko shared agreement.
The motion to conditionally approve the arch top windows was seconded by Commissioner Erquiaga and
passed by the following vote:
AYES: Arrington, Erquiaga, Horner, Langseth, Lifsey, Sherayko 6
NOES: 0
ABSTENTIONS: 0
ABSENT: Alexander 1
Commissioner Lifsey made a motion to approve the replacement of the large living room window
with the sti pulation that it match the original in height, width, detail, and location but the
middle window ma y be double hung or single hung . The motion was seconded by Commissioner
Sherayko and passed by the following vote:
AYES: Arrington, Erquiaga, Horner, Langseth, Lifsey, Sherayko 6
NOES: 0
ABSTENTIONS: 0
ABSENT: Alexander 1
Commissioner Lifsey made a motion to approve the rectangular window replacements at the rear
and side s with the stip ulation that they match the original s in height, width, details, and
location and have exterior trim that matches the original in size and profile. The motion was
seconded by Commissioner Arrington and passed by the following vote:
AYES: Arrington, Erquiaga, Horner, Langseth, Lifsey, Sherayko 6
NOES: 0
ABSTENTIONS: 0
ABSENT: Alexander 1
Commissioner Erquiaga reiterated what was approved and noted that if anything differs from the approval,
it will require a new application and approval.
e) ACTION (Advocate-Sherayko): Request of Evelyn Luann Owens to do extensive work at
711 Roslyn Place. (HPC2405-0005)
Ms. Ashlee Glen was present to represent the ap plication on behalf of Ms. Evelyn Luann Owens. A wood
privacy fence will be installed at the rear and side of the house. A cement pad will be installed and will
wrap around the house. It will serve as a front and back patio and a driveway. The rear two (2) windows
were missing when the house was purchased but new wood windows will be installed to match the existing
side windows. One existing window was too rotten to be restored and will need to be replaced in-kind. The
5
other windows have been restored. Dark green awnings will be added to the back of the house, the front
two (2) windows, and the front and side door. The color will match the trim and the roof.
Commissioner Erquiaga asked for clarification on the material of the awning and hardscapes.
Ms. Glen replied that the awnings will be canvas and the hardscapes will be cement.
Commissioner Sherayko noted that the proposed work will be an improvement.
Commissioner Erquiaga shared agreement.
Commissioner Sherayko made a motion to approve the applicat ion as submitte d. The motion was
seconded by Commissioner Arrington and passed by the following vote:
AYES: Arrington, Erquiaga, Horner, Langseth, Lifsey, Sherayko 6
NOES: 0
ABSTENTIONS: 0
ABSENT: Alexander 1
f) ACTION (Advocate-Arrington): Request of Henry Branstetter to do extensive work at
2117 Rivermont Avenue. (HPC2405-0006)
Mr. Henry Branstetter and Mr. Tom McCoy were present to represent the application. They would like to
repair the failed hidden gutters and roof; extend an existing wooden, six-foot-tall privacy fence; and install
a new garage door that matches others in the neighborhood. They would also like to replace dormer
windows that had previously been removed and stored in the attic and repaint the house in a new color
scheme.
Commissioner Lifsey asked if the brick foundation and chimneys are already painted.
Mr. Branstetter replied that they are.
Commissioner Sherayko asked about removing and storing the shutters.
Mr. McCoy responded that the shutters are not all intact. Many have pieces or hardware missing. Some
shutters are completely missing.
Mr. Branstetter added that the shutters are original and will be stored. The roof is currently gray shingles
but will be replaced with new shingles in a “resawn shake” color.
Commissioner Lifsey noted that the shingles might emulate the original slate better in a black color.
Mr. Branstetter noted that there are no photos to show whether the roof was originally slate or cedar shake
shingles.
Commissioner Sherayko noted that the new colors, garage door, and restoration of the windows are
appropriate.
Commissioner Lifsey shared agreement.
Commissioner Sherayko made a motion to approve the application as submitted. The motion was
seconded by Commissioner Lifsey and passed by the following vote:
AYES: Arrington, Erquiaga, Horner, Langseth, Lifsey, Sherayko 6
NOES: 0
6
ABSTENTIONS: 0
ABSENT: Alexander 1
g) ACTION (Advocate-Arrington): Request of Casey Servis of Servis Architecture Co., on
behalf of Across the Bridge, LLC, to do extensive work at 480 Rivermont Avenue.
(HPC2405-0007)
Mr. Casey Servis of Servis Architecture Co. was present to represent the applicati on. The house has wood
lap siding on the first floor and wood shingles on the second floor. The wood lap siding will be reused on
the front and the street side. It will be replaced with hardie plank on the rear and interior side. The request
is the same for the shingles but there may not be enough in good enough shape to salvage. If there isn’t
enough, they will replace all four (4) sides with hardie shingle.
Commissioner Sherayko asked if the second floor originally had a large round window.
Mr. Servis responded that he is not sure . The plan is to keep the existing window . If that changes, they
will submit another application. The rest of the windows are one-over-one and many are missing or in bad
shape. They will repair what they can and replace with wood or aluminum clad wood windows to match
existing windows.
Commissioner Lifsey asked about the plans for the stairs.
Mr. Servis replied that the left concrete staircase will be removed and replaced with a railing . The side
porch will serve as entry to one (1) unit so a new wood staircase will be added at the rear. The front porch
concrete stairs will serve as entry for several units. The concrete staircase will be removed and rebuilt in
the same foot print with wood. The porch railings will continue down the staircase from the columns . A
concrete parking area will be added at the back off of the alley. There will be four (4) parking spaces. The
exterior of the house will be painted in a new color scheme.
Commissioner Sherayko asked if the lower staircase from the sidewalk will also be removed.
Mr. Servis responded that they will remove it and return it to grass.
Commissioner Lifsey noted that the hardie plank lap siding should be smooth and not grained.
Commissioner Langseth asked what color the replacement steps will be.
Mr. Servis responded that they will be a dark brown color.
Commissioner Lifsey asked about the color for the window sashes.
Mr. Servis replied that they will be a different color.
Commissioner Lifsey noted that this area of Rivermont is going to look dramatically better once all of the
work is done.
Commissioner Sherayko agreed and noted that the before and after should be documented.
Commissioner Langseth made a motion to approve the application as submitted . The motion was
seconded by Commissioner Lifsey and passed by the following vote:
AYES: Arrington, Erquiaga, Horner, Langseth, Lifsey, Sherayko 6
NOES: 0
ABSTENTIONS: 0
ABSENT: Alexander 1
7
3. NEXT MEETING DAY:
The next regular meeting is scheduled for June 17, 2024.
4. ADJOURNMENT:
There being no further business, the meeting was adjourned at 5:08 p.m.
ATTEST: ____________________________________ ATTEST: _________________________________