Physical Development Committee Meeting — Agenda Packet
City of Lynchburg · Lynchburg City County · Physical Development Committee · meeting of Dec 12, 2023 · Agenda packets
Open the original document More from City of Lynchburg
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
PHYSICAL DEVELOPMENT COMMITTEE
City Council Committee
Tuesday, December 12, 2023 | 3:00 PM
2nd Floor Training Room- City Hall
900 Church Street
Lynchburg, VA 24504
PHYSICAL DEVELOPMENT COMMITTEE AGENDA
I. Welcome Councilmember Larry Taylor, Chair
II. Information Items
II.1. College Lake Dam Removal Update
III. General Business
IV. Roll Call
V. Next Regular Meeting
Page 1 of 27
Physical Development
Committee
Agenda Item II.1.
Information Only
AGENDA ITEM SUMMARY
MEETING DATE PRESENTED BY
December 12, 2023 Timothy Mitchell, Director of Water
Resources, Erin Hawkins, Water Quality
Manager
AGENDA ITEM # II.1
College Lake Dam Removal Update
RECOMMENDATION
Information Only.
SUMMARY
College Lake Dam is considered a high hazard dam and is not in compliance with the Department of
Conservation and Recreation's Dam Safety Regulations. In order to comply with the regulations,
either the dam would need to undergo major safety upgrades or be removed. In August 2018, the
College Lake Dam over-topped and nearly failed. The City of Lynchburg recently received bids for
the College Lake Dam Removal and Restoration Project and English Construction was the
successful low bidder with costs coming in on budget. Staff will provide an update of the project
status including purpose and goals, budget, construction activities, and long-term management.
PRIOR ACTION(S)
Previous Budget and Capital Improvement Plan authorizations.
Various City Council briefings and updates.
FISCAL IMPACT
Prior CIP appropriations totaling $22,500,000 have been authorized by City Council. The funding
sources include $5 million in DCR Dam Safety Grants, $10 million from Virginia Clean Water
Revolving Loan Fund with an additional $2.5 million in principal forgiveness with the remaining $5
million in General Obligation Bonds. Total project costs including contingencies equal $22,500,000.
CONTACT(S)
Timothy Mitchell, Director of Water Resources
ATTACHMENT(S)
1. Council PDC Mtg College Lake Update Dec 2023
REVIEWED BY
Page 2 of 27
Date: November 30, 2023
Timothy Mitchell, Director of Water Resources
Date: December 05, 2023
Gregory Patrick, Deputy City Manager
Date: December 07, 2023
Alicia Finney, Clerk of Council
Page 3 of 27
COLLEGE LAKE DAM REMOVAL
AND RESTORATION PROJECT
Physical Development Committee
December 12, 2023
Page 4 of 27
OVERVIEW
1. Project
2. Budget
3. Construction Activities
4. Long‐Term Management
Page 5 of 27
REMOVE RESTORE RECONNECT
Project Overview
Page 6 of 27
PROJECT OVERVIEW
PROJECT
PURPOSE
AND GOALS
Removal of a high‐
hazard dam to
provide protection of
life, property, and the
environment.
Preserve floodplain
capacity and
coordination with
FEMA on current
mapping.
Page 7 of 27
PROJECT OVERVIEW
PROJECT PURPOSE AND GOALS
Manage historical sediment accumulated
behind the dam in a way that minimizes
downstream water quality impacts.
Restore Blackwater Creek and its adjacent
tributaries that have been impacted by
the dam.
Provide wetland restoration and
establishment opportunities in the
former and adjacent floodplain.
Page 8 of 27
PROJECT OVERVIEW
BLACKWATER CREEK
–P R O P O S E D
IMPROVEMENTS
Armored cascade grade control
Toe wood bank protection
Page 9 of 27
Increased meandering
of Blackwater Creek
Log cross vane grade control
PROJECT OVERVIEW
BLACKWATER CREEK –
PROPOSED IMPROVEMENTS
Page 10 of 27
Boulder grade control vane
Dense native vegetation
PROJECT OVERVIEW
BLACKWATER CREEK –
PROPOSED IMPROVEMENTS
Page 11 of 27
REMOVE RESTORE RECONNECT
Budget
Page 12 of 27
BUDGET OVERVIEW
Funding Sources
$5M DCR Dam Safety Grant
$10M Virginia Clean Water Revolving
Loan Fund + $2.5M Principal Forgiveness
General Fund
Project Costs
Engineering $1,809,716.76
Land Acq/ROW $62,559
Construction Administration $1,587,680.80
Construction Base Bid $17,478,495.35
Misc $35,572.68
Contingency $1,525,975.41
Total 22,500,000.00
Page 13 of 27
REMOVE RESTORE RECONNECT
Construction Activities
Page 14 of 27
CONSTRUCTION ACTIVITIES
CONTRACTOR INTRODUCTION
Primary contractor: W. C. English, Incorporated
Subcontractor: Resource Environmental Solutions
Contractor qualifications:
Lynchburg company with local resources.
Experts in mass excavation.
Experience with dewatering.
Experience with erosion and sediment controls.
Experts in stream and wetland restoration.
Knowledgeable about history of College Lake and Dam
as well as stakeholder concerns.
Page 15 of 27
CONSTRUCTION ACTIVITIES
CONSTRUCTION SCHEDULE
Page 16 of 27
CONSTRUCTION ACTIVITIES
ANTICIPATED DAIL Y SCHEDULE
Monday – Friday
Work to be conducted 24‐hours a day on infrequent occasion for impacts
to dam itself (breaching and dewatering installation).
Expected hours: 7 AM – 5/6 PM
Saturdays and Sundays
Limited to required 24‐hour operations for dam breaching and dewatering
installation.
Limited to adhere to schedule and to overcome any delays.
Holidays
Work will be halted on the following holidays: Veterans Day,
Thanksgiving Day, Christmas Day, New Years Day, etc.
Page 17 of 27
CONSTRUCTION ACTIVITIES
CONSTRUCTION SIGNAGE
During construction, Creekside Trail
will be closed from Lakeside Drive
to Shirley Road.
Signage will be posted for duration
of project.
Close coordination with Parks &
Recreation and the University of
Lynchburg.
Page 18 of 27
CONSTRUCTION ACTIVITIES
CONSTRUCTION
TRAFFIC
Construction traffic will enter and exit Old Lakeside Drive via New Lakeside Drive
on the west and Hopwood Drive on the east.
Construction traffic will utilize Faculty Drive’s dead end for access to site.
Construction traffic will utilize Hopwood Drive and Westover Drive on University
of Lynchburg campus for site access by Wake Field House and Fox Field.
Routes to be refined as construction progresses.
Page 19 of 27
CONSTRUCTION ACTIVITIES
DEWATERING
Flexible water level management to facilitate
sediment management upstream
Slow, controlled rate of dewatering
Targeted seasonal dewatering
Page 20 of 27
CONSTRUCTION ACTIVITIES
RESTORATION & SEDIMENT MANAGEMENT
Sediment traps will be constructed to capture and transport
sediment to permanent stockpile areas
Impounded sediment will be removed by mechanical
methods with specialized equipment
Page 21 of 27
CONSTRUCTION ACTIVITIES
EXPECTED SITE CONDITIONS
DURING CONSTRUCTION
During construction, you may notice:
• Unpleasant odor
• Construction noise
• Unattractive view
• Murky water
Page 22 of 27
CONSTRUCTION ACTIVITIES
SEDIMENT STOCKPILES
• Sediment may be stored on site in designated, convenient stockpiles.
• Stockpiles are designed to blend into the valley and will be planted
with natural vegetation.
• Stockpiles will consist of up to approximately 150,000 cubic yards
spread across potentially 3 stockpile locations.
Post construction 30 days post construction
Erosion control matting and
coir logs will stabilize
stockpiles and slow run‐off
Page 23 of 27
CONSTRUCTION ACTIVITIES
DAM REMOVAL
• Install dewatering system & dewater College Lake.
• Excavate dam breach creating 15ft wide stream channel
(24‐hour continuous operation).
• Continue dam excavation to final stream elevations and
complete removal of earthen dam.
• Stabilize slopes and create proposed stream and banks
per design.
Page 24 of 27
CONSTRUCTION ACTIVITIES
MONITORING & CONSTRUCTION OVERSIGHT
Cellular alert monitoring of dissolved oxygen and turbidity
Construction operations will be observed by
engineers specializing in stream restoration,
sediment management, dam removal, and
geotechnical engineering
Page 25 of 27
REMOVE RESTORE RECONNECT
Long‐Term Management
Page 26 of 27
LONG‐TERM MANAGEMENT
COMPLIANCE
MONITORING
• Annual monitoring of physical stream and wetland stability
• Minimum of 5 years required by USACE
• Perpetual Stewardship will remain with the University
Page 27 of 27