Physical Development Committee Meeting — Agenda Packet
City of Lynchburg · Lynchburg City County · Physical Development Committee · meeting of Oct 10, 2023 · Agenda packets
Open the original document More from City of Lynchburg
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
PHYSICAL DEVELOPMENT COMMITTEE
City Council Committee
Tuesday, October 10, 2023 | 3:00 PM
2nd Floor Training Room- City Hall
900 Church Street
Lynchburg, VA 24504
PHYSICAL DEVELOPMENT COMMITTEE AGENDA
I. Welcome Councilmember Larry Taylor, Chair
II. Information Items
II.1. Hear an update on the construction of the Police Department Headquarters
III. General Business
IV. Roll Call
V. Next Regular Meeting
Page 1 of 13
POLICE DEPARTMENT UPDATEOctober 10, 2023
Page 2 of 13
PROJECT OVERVIEW
Project consists of land acquisition,design and construction of a modern,state of the art building to meet thecurrent and future law enforcementneeds for the City of Lynchburg.The main building is three stories talland will be 93,991 square feet in areaonce completed.
Page 3 of 13
FRONT (WEST) FAÇADE
The Notice To Proceed was issued onOctober 14, 2022 and provides 847 daysfor the completion of construction. Thiswould place the constructioncompletion on or about February 7,2025.Project is currently on schedule.
Page 4 of 13
NORTH FAÇADEThe scope of work includes the entiresite development – stormwater, utilityinfrastructure, site grading, parkingfacilities (including a separate rollingasset building), site security, lighting,landscaping, and building construction –foundation and structure to the roofincluding all systems and finishesnecessary to operate the building as aPolice Department upon completion.
Page 5 of 13
NORTH FAÇADEThe Notice To Proceed was issued onOctober 14, 2022 and provides 847 daysfor the completion of construction. Thiswould place the constructioncompletion on or about February 7,2025.Project is currently on schedule.
Page 6 of 13
ROLLING ASSETS BUILDINGThe project is currently well underwaywith site clearing/grading 95%complete, utilities (stormwater, waterand sewer) run to the site, buildingfoundation completed, structural slabs(all floors) 100% completed and steelerection 99% completed at this time.
Page 7 of 13
SOUTH/EAST FAÇADE
Framing and sheathing on the buildingexterior is underway as well as roofconstruction.Overall, we estimate the project to beapproximately 29% complete at thistime.
Page 8 of 13
ROOF PROGRESS
Page 9 of 13
INTERIOR PROGRESS
Page 10 of 13
INTERIOR PROGRESS
Page 11 of 13
INTERIOR PROGRESS
Page 12 of 13
Questions?
Page 13 of 13