City Council Budget Work Session - Capital Improvement Program — Agenda Packet

City of Charlottesville · Charlottesville City County · City Council · meeting of Mar 27, 2025 · Agenda packets

Open the original document More from City of Charlottesville

This document is no longer listed on City of Charlottesville's website. We kept the copy we read.

Text

Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.

Budget Work Session Capital Improvement Program 5 Year Plan (FY26 – FY30) March 27, 2025 1 Agenda • CIP Review and Discussion • What’s New? • Parks and Recreation • School Projects • Transit Operations • Public Comment on CIP • Agency Funding Follow-up (if time allows) 2 CIP Summary 3 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 Totals Sources of Funds: General fund transfer 8,302,434$ 9,844,059 $ 7,994,393 $ 10,227,184$ 11,061,000 $ 47,429,069 $ CIP Contingency - 1,964,486 - 716,749 - 2,681,235$ Bond issues 23,445,252 27,044,309 48,565,680 26,301,813 12,678,915 138,035,969$ Contribution from Schools 200,000 200,000 200,000 200,000 200,000 1,000,000$ Other 40,000 40,000 40,000 40,000 40,000 200,000$ Total sources 31,987,686 $ 39,092,854 $ 56,800,073 $ 37,485,746 $ 23,979,915 $ 189,346,273$ Us e s of funds : Education $6,007,489 $9,150,000 $31,150,000 $5,150,000 $3,650,000 $55,107,489 Facilities Capital Projects $3,146,794 $3,566,264 $2,743,930 $12,443,950 $1,792,165 $23,693,102 Public safety and justice $1,208,918 $1,885,065 $909,864 $1,900,806 $1,176,958 $7,081,611 Transportation and access $6,037,285 $9, 123,625 $10,250,179 $8,289,190 $7,805,792 $41,506,071 Parks and recreation $2,415,000 $1,200,000 $1,200,000 $1,200,000 $1,200,000 $7,215,000 Affordable Housing $12,732,200 $13,727,900 $10,256,100 $8,211,800 $8,065,000 $52,993,000 Technology Infrastructure $440,000 $440,000 $290,000 $290,000 $290,000 $1,750,000 Total uses 31,987,686 $ 39,092,854 $ 56,800,073 $ 37,485,746 $ 23,979,915 $ $189,346,273 Funding Gap $0 $0 $0 $0 $0 $0 CITY MANAGER PROPOSED 5-YEAR PLAN Education 29% Facilities Capital Projects 12% Public safety and justice 4% Transportation and access 22% Parks and recreation 4% Affordable Housing 28% Technology Infrastructure 1% 5-Year Plan Education 19% Facilities Capital Projects 10% Public safety and justice 4% Transportation and access 19% Parks and recreation 7% Affordable Housing 40% Technology Infrastructure 1% FY 26 CIP CIP Revenues 4 FY 2026 Sources of Funds: G eneral fund transfer 8,302,434$ Bond issues 23,445,252 Contribution from Schools 200,000 Other 40,000 Total sources 31,987,686 $ General fund transfer 26% Bond issues 73% Other 1% FY 26 CIP Revenues Budget Guideline/Policy – transfer at least 3% of general fund budget to CIP as “pay-go” What’s New in the 5-Year CIP? 5 Education • Lump Sum to Schools - $500,000 increase ($100k per year) • City School Priority Improvements - $750,000 increase ($150k per year) Facilities Capital Projects • City Facility HVAC Repair/Replacement - $1.25M increase ($250k per year) Public Safety and Justice • Replacement Fire Apparatus - $130,000 reduction and FY 29 replacement was moved from FY 28 • Bypass Fire Station (old building) Repurpose/Upfit - $100,000 increase • Police Car Portable Radio Replacement – new project - $340,000 added Transportation and Access • New Sidewalks - $4.8M added to address Priority Sidewalk List • Sidewalk Repair - $500,000 reduction in FY 26 to better align existing funding with planned work • ADA Transition Plan – new project - $8.7M added • Safe Routes to School – new project - $1M added Additional CIP Changes 6 Parks and Recreation • Parks and Schools Playground Renovations - $460,000 increase ($88k per year) • Urban Tree Planting - $125,000 increase ($25k per year) • Oakwood Cemetery Drainage and Road Issues – new project - $150,000 added • Hazard and Liability Ash Tree Removal - $400,000 decrease – funds reallocated to Urban Tree Planting and Invasive Plant Removal • Invasive Plant Removal - $375,000 increase ($75k per year) • Downtown Mall Tree Management Plan – new project - $315,000 added • Parks Master Plan Implementation – new project - $500,000 added • Riverview Park Access Management – new project - $250,000 added Affordable Housing • Carlton Mobile Home Park – new project - $7.8M added Parks and Recreation Update 7 School Projects 8 Walker Pre-K Center Requested Budget Amendment  Move $4M for project design from FY27 to FY26  Move $26M for project construction from FY28 to FY27 Priority Improvement Program  Budget includes increased funding from $1.25M to $1.4M annually through FY30 Schools Lump Sum Funding  CHS and CATEC will receive rekeying projects from FY26 lump sum funding  CHS will also have select doors replaced. This work responds to the results of the CCS security audit CAT Route Frequency and Ridership – Pre-COVID 9 Fall 2019 - WEEKDAY SERVICE LEVEL Route # Route Name 6:00 AM 7:00 AM 8:00 AM 9:00 AM 10:00 AM 11:00 AM 12:00 PM 1:00 PM 2:00 PM 3:00 PM 4:00 PM 5:00 PM 6:00 PM 7:00 PM 8:00 PM 9:00 PM 10:00 PM 11:0 0 PM 1 PVCC and Woolen Mills 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 2 5 t h S t r e e t S t a t i o n 3 03 03 03 03 03 03 03 03 03 03 03 03 03 03 03 03 03 0 3 S o u t h w e s t & B e l m o n t 3 03 03 06 06 06 06 06 06 03 03 03 03 06 06 06 06 06 0 4 Cherry Ave & Harris Rd 23 23 23 23 45 70 70 70 70 23 23 23 45 70 70 70 70 70 5 Commonwealth Dr 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 6 R i d g e S t & P r o s p e c t A v e 6 06 06 06 06 06 06 06 06 06 06 06 06 06 06 06 06 06 0 7 E m m e t S t & S e m i n o l e T r l 2 02 02 02 02 02 02 02 02 02 02 02 02 02 03 03 03 03 0 8 Preston Ave & Emmet St 30 30 30 60 60 60 60 60 60 30 30 30 30 9 The Health Dept & YMCA 70 70 70 70 70 70 70 70 70 70 70 70 70 70 1 0 P a n t o p s 6 06 06 06 06 06 06 06 06 06 06 06 06 06 06 06 06 06 0 11 Locust Ave & Rio Rd 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 T r o l l e y F r e e T r o l l e y 1 51 51 51 51 51 51 51 51 51 51 51 51 51 51 51 51 51 5 FY 2020 31-Jul 31-Aug 30-Sep 31-Oct 30-Nov 31-Dec 31-Jan 29-Feb 31-Mar 30-Apr 31-May 30-Jun 140,151 150,065 173,615 184,251 148,323 127,361 124,323 102,453 70,728 29,355 33,967 38,584 1,323,176 Summer 2020 - WEEKDAY SERVICE LEVEL Weekday 6:00 AM 7:00 AM 8:00 AM 9:00 AM 10:00 AM 11:00 AM 12:00 PM 1:00 PM 2:00 PM 3:00 PM 4:00 PM 5:00 PM 6:00 PM 7:00 PM 8:00 PM 9:00 PM 10:00 PM 11:0 0 PM 1 PVCC and Woolen Mills 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 2 5 t h S t r e e t S t a t i o n 3 03 03 03 03 03 03 03 03 03 03 03 03 03 03 0 3 S o i t h w e s t & B e l m o n t 3 03 03 06 06 06 06 06 06 03 03 03 03 06 06 0 4 Cherry Ave & Harris Rd 30 30 30 60 60 60 60 60 60 60 60 60 60 60 60 5 Commonwealth Dr 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 6 R i d g e S t & P r o s p e c t A v e 6 06 06 06 06 06 06 06 06 06 06 06 06 06 06 0 7 E m m e t S t & S e m i n o l e T r l 3 03 03 03 03 03 03 03 03 03 03 03 03 03 03 0 8 Preston Ave & Emmet St 60 60 60 60 60 60 60 60 60 60 60 60 60 9 The Health Dept & YMCA 70 70 70 70 70 70 70 70 70 70 70 70 70 70 1 0 P a n t o p s 6 06 06 06 06 06 06 06 06 06 06 06 06 06 06 0 11 Locust Ave & Rio Rd 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 T r o l l e y F r e e T r o l l e y 2 52 52 52 52 52 52 52 52 52 52 52 52 52 52 5 FY 2021 31-Jul 31-Aug 30-Sep 31-Oct 30-Nov 31-Dec 31-Jan 28-Feb 31-Mar 30-Apr 31-May 30-Jun 53,453 55,370 55,129 58,927 51,709 49,587 46,096 36,379 57,027 50,168 45,153 58,012 617,010 FY 2022 31-Jul 31-Aug 30-Sep 31-Oct 30-Nov 31-Dec 31-Jan 28-Feb 31-Mar 30-Apr 31-May 30-Jun 88,509 98,344 107,215 104,462 94,791 90,011 84,820 91,971 101,985 103,004 93,766 97,636 1,156,514 CAT Route Frequency and Ridership – Now 10 Pre-November 9, 2024 - WEEKDAY SERVICE LEVEL Route # Route Name 6:00 AM 7:00 AM 8:00 AM 9:00 AM 10:00 AM 11:00 AM 12:00 PM 1:00 PM 2:00 PM 3:00 PM 4:00 PM 5:00 PM 6:00 PM 7:00 PM 8:00 PM 9:00 PM 10:00 PM 11:0 0 PM 1 P V C C a n d W o o l e n M i l l s6 06 06 06 06 06 06 06 06 06 06 06 06 06 06 06 06 0 2 5 t h S t r e e t S t a t i o n 3 03 03 03 03 03 03 03 03 03 03 03 03 03 03 03 03 0 3 S o u t h w e s t & B e l m o n t 6 06 06 06 06 06 06 06 06 06 06 06 06 06 06 06 0 4 Cherry Ave & Harris Rd 30 30 30 30 60 60 60 60 60 60 60 60 60 60 60 60 5 Commonwealth Dr 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 6 R i d g e S t & P r o s p e c t A v e 6 06 06 06 06 06 06 06 06 06 06 06 03 06 06 06 0 7 E m m e t S t & S e m i n o l e T r l 3 03 03 03 03 03 03 03 03 03 03 03 03 03 03 03 03 0 8 Preston Ave & Emmet St 60 60 60 60 60 60 60 60 60 60 60 60 9 The Health Dept & YMCA 30 30 30 60 60 60 60 30 30 30 30 60 60 60 60 1 0 P a n t o p s 6 06 06 06 06 06 06 06 06 06 06 06 06 06 06 06 0 11 Locust Ave & Rio Rd 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 T r o l l e y F r e e T r o l l e y 2 52 52 52 52 52 52 52 52 52 52 52 52 52 52 52 5 FY 2023 31-Jul 31-Aug 30-Sep 31-Oct 30-Nov 31-Dec 31-Jan 28-Feb 31-Mar 30-Apr 31-May 30-Jun 88,509 98,344 107,215 104,462 94,791 90,011 84,820 91,971 101,985 103,004 93,766 97,636 1,156,514 FY 2024 31-Jul 31-Aug 30-Sep 31-Oct 30-Nov 31-Dec 31-Jan 29-Feb 31-Mar 30-Apr 31-May 30-Jun 100,496 116,609 117,720 115,974 105,881 97,921 106,481 114,015 116,306 123,586 122,504 115,566 1,353,059 Post-November 9, 2024 - WEEKDAY SERVICE LEVEL Route # Route Name 6:00 AM 7:00 AM 8:00 AM 9:00 AM 10:00 AM 11:00 AM 12:00 PM 1:00 PM 2:00 PM 3:00 PM 4:00 PM 5:00 PM 6:00 PM 7:00 PM 8:00 PM 9:00 PM 10:00 PM 11:0 0 PM 1 P V C C a n d W o o l e n M i l l s6 06 06 06 06 06 06 06 06 06 06 06 06 06 06 06 06 0 2 5 t h S t r e e t S t a t i o n 3 03 03 03 03 03 03 03 03 03 03 03 03 03 03 03 0 3 S o u t h w e s t & B e l m o n t 6 06 06 06 06 06 06 06 06 06 06 06 06 06 06 06 06 0 4 Cherry Ave & Harris Rd 30 30 30 30 30 30 30 30 30 30 30 30 30 60 60 60 5 Commonwealth Dr 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 6 R i d g e S t & P r o s p e c t A v e 3 03 03 03 03 03 03 03 03 03 03 03 03 06 06 06 0 7 E m m e t S t & S e m i n o l e T r l 3 03 03 03 03 03 03 03 03 03 03 03 03 03 03 03 03 0 8 Preston Ave & Emmet St 60 60 60 60 60 60 60 60 60 60 60 60 9 The Health Dept & YMCA 30 30 30 30 30 30 30 30 30 30 30 60 60 60 60 1 0 P a n t o p s 6 06 06 06 06 06 06 06 06 06 06 06 06 06 06 06 06 0 11 Locust Ave & Rio Rd 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 T r o l l e y F r e e T r o l l e y 2 52 52 52 52 52 52 52 52 52 52 52 52 52 52 52 5 FY 2024 31-Jul 31-Aug 30-Sep 31-Oct 30-Nov 31-Dec 31-Jan 28-Feb 31-Mar 30-Apr 31-May 30-Jun 117,639 116,982 122,025 133,310 114,885 101,217 112,723 102,891 - - - - 921,672 Council Discretionary Funds $1,002,001 11  $250,000 BRACH (Replacement of Lost Grant for Homeless Services)  $162,000 PHA (Eviction Prevention – Staff Salaries)  $50,000 PHA (Eviction Prevention – Cash Assistance)  $43,150 Boys & Girls Club (Total Funding: $116,000)  $28,800 Lighthouse Studios [2 programs] (Total Funding: $40,000)  $6,000 Loaves & Fishes (Total Funding: $50,000)  $1,200 Piedmont CASA (Total Funding: $10,000)  $6,600 LiveArts (Total Funding: $16,000)  $7,100 Legal Aid Justice Center (Total Funding: $40,000)  $1,500 SARA (Total Funding: $25,000) $556,350 TOTAL ALLOCATED $104,261 REDIRECTED CIP FUNDS: Dogwood Veterans Memorial $660,611 TOTAL EXPENDED $341,390 BALANCE REMAINING Remove $4,200 from Fralin and redistribute to Arts/Events Sponsorships Add $37,040 BridgeLine due to Calculation Error (Total Funding: $56,780) Add $137,000 CRHA Resident Services Important Budget Dates Work Sessions March 6 March 13 March 27 April 10 Public  Hearings March 20  (Budget) April 7   (Tax Rates) Community  Budget Forum March 20 Budget  Adoption April 14 12 Questions and Discussion www.Charlottesville.gov/budget 13 Appendix 14 Council-Directed Funding Opportunity  $500,000 Strategic Initiatives Fund  $234,860 Reduction in Financing for ACRJ Project  $41,500 HOPS Balance  $35,000 CAHF Balance  $86,381 CDBG Balance  $104,260.65 Available CIP Unspent Balance $1,002,001 Total Available for Council Allocation 15 Transportation Infrastructure  Staff reviewed proposed and historic Transportation CIP projects to determine how the balance of investments were supporting Council and Comp Plan goals for mode options  Reviewed “available” existing funds, last year’s adopted CIP , and this year’s proposed CIP Major findings of analysis:  The City has been investing in bike/pedestrian focused- projects at a much higher rate than automobile-focused investments  The trend is toward more spending on bike/pedestrian projects, largely driven by the major increases in funding for New Sidewalks and ADA-compliance projects  The City is not adding automobile capacity with its projects, most of these are maintenance, repair, and upgrades  Local capital contributions to transit make up a small portion of what is spent on transit 16 Increased Funding from FY 25 Decreased funding from FY 25 New Project Added FY 26 Proposed FY26 Projected FY27 Projected FY28 Projected FY29 Projected FY30 5 Year Total Revenues Transfer from General Fund 7,627,434 9,169,059 7,319,393 9,552,184 10,386,000 44,054,070 Transfer from General Fund - Mall Vendor Fees 100,000 100,000 100,000 100,000 100,000 500,000 Transfer from General Fund - VCF Allocation 575,000 575,000 575,000 575,000 575,000 2,875,000 Contribution from Schools (Small Cap Program) 200,000 200,000 200,000 200,000 200,000 1,000,000 CIP Contingency (from prior year surplus) 0 1,964,486 0 716,749 2,681,235 PEG Fee Revenue 40,000 40,000 40,000 40,000 40,000 200,000 CY 2026 Bond Issue 23,445,252 0 0 23,445,252 CY 2027 Bond Issue 0 27,044,309 0 27,044,309 CY 2028 Bond Issue 0 0 48,565,680 48,565,680 CY 2029 Bond Issue 26,301,813 26,301,813 CY 2030 Bond Issue 12,678,915 12,678,915 TOTAL AVAILABLE REVENUES $31,987,686 $39,092,854 $56,800,073 $37,485,746 $23,979,915 $189,346,274 Expenditures EDUCATION Proposed Projected Projected Projected Projected 5 Year Project FY26 FY27 FY28 FY29 FY30 Total Lump Sum to Schools (City Contribution) 1,300,000 1,300,000 1,300,000 1,300, 000 1,300,000 6,500,000 City Schools HVAC Repair 750,000 750,000 750,000 750,000 750,000 3,750,000 City Schools Priority Improvement Projects 1,400,000 1,400,000 1,400,000 1,400,000 1,400,000 7,000,000 Charlottesville High School Roof Replacement 2,357,48 9000 0 2 , 357,489 Charlottesville City School Reconfigu r a t i o n 0000 0 0 Charlottesville Walker School Pre-K Center 0 4,000,000 26,000,000 0 0 30,000,000 Clark Elementar y School Windows Replacement 0000 0 0 Burnley-Moran Elementary School Roof Replacement 0 1,500,000 0 0 0 1,500,000 Jackson-Via Elementary School Roof Replacement 0 0 1,500,000 0 0 1,500,000 Johnson Elementary School Roof Replacement 0 0 0 1,500,000 0 1,500,000 School Small Capital Improvements Program 200,000 200,000 200,000 200,000 200,000 1,000,000 SUBTOTAL $6,007,489 $9,150,000 $31,150,000 $5,150,000 $3,650,000 $55,107,489 FACILITIES CAPITAL PROJECTS Proposed Proj ected Projected Projected Projected 5 Year Project FY26 FY27 FY28 FY29 FY30 Total Lump Sum to Facilities Capital Projects 1,319,956 1,159,155 1,193,930 1,217,809 1,242,165 6,133,014 City Facility HVAC Replacement 500,000 500,000 500,000 500,000 500,000 2,500,0 00 City and Schools Solar PV Program 75,000 0 0 0 0 75,000 General District Court - FFE and Hearing Room 201,83 8000 0 201,838 Proposed Capital Improvement Program FY 2026-2030 Increased Funding from FY 25 Decreased funding from FY 25 New Project Added FY 26 Proposed FY26 Projected FY27 Projected FY28 Projected FY29 Projected FY30 5 Year Total Proposed Capital Improvement Program FY 2026-2030 Climate Action Initiatives 1,000,000 1,000,000 1,000,000 1,000,000 0 4,000,000 Jefferson-Madison Regional Library Renovations 0 857,109 0 9,676,141 0 10,533,250 HVAC Contingency Fund - City and School Facilities 50,000 50,000 50,000 50,000 50,000 250,000 SUBTOTAL 3,146,794 3,566,264 2,743,930 12,443,950 1,792,165 23,693,102 PUBLIC SAFETY AND JUSTICE Proposed Proj ected Projected Projected Projected 5 Year Project FY26 FY27 FY28 FY29 FY30 Total Replacement Fire Apparatus 0 1,334,065 0 1,470,806 0 2,804,871 Replacement EMS Apparatus 458,918 0 481,864 0 505,958 1,446,740 Bypass Fire Station (old building) Repurpose/Upfit 200,00 0000 0 200,000 Police Mobile Data Terminals 82,000 83,000 85,000 87,000 88,000 425,000 Police Portable Radio Replacement 75,000 75,000 75,000 75,000 75,000 375,000 Police Car Portable Radio Replacement 68,000 68,000 68,000 68,000 68,000 340,000 Fire Portable Radio Replacement 75,000 75,000 75,000 75,000 75,000 375,000 Sheriff Portable Radio Replacement 40,000 40,000 40,000 40,000 40,000 200,000 Fire - Self-Contained Breathing Apparatus Replacement s 150,000 150,000 25,000 25,000 25,000 375,000 Fire - Protective Clothing/Turnout Gear Replacement 60,000 60,000 60,000 60,000 300,000 540,000 SUBTOTAL $1,208,918 $1,885,065 $909,864 $1,900,806 $1,176,958 $7,081,611 TRANSPORTATION AND ACCESS Proposed Project ed Projected Projected Projected 5 Year Project FY26 FY27 FY28 FY29 FY30 Total New Sidewalks 1,217,051 1,128,980 974,886 1,387,057 630,792 5,338,766 Sidewalk Repair 0 500,000 650,000 700,000 700,000 2,550,000 SIA Immediate Implementation 200,000 200,000 200,000 200,000 200,000 1,000,000 Small Area Plans 150,000 150,000 150,000 150,000 150,000 750,000 Street Milling and Paving 1,250,000 1,500,000 1,700,000 1,750,000 2,000,000 8,200,000 ADA Pedestrian Signal Upgrades 240,000 240,000 240,000 0 0 720,000 Minor Bridge Repairs 225,000 225,000 225,000 0 0 675,000 Traffic Signal Infrastructure Replacement 250,000 2,000,000 3,000,000 1,000,000 1,000,000 7,250,000 Stribling Avenue Sidewalk 600,00 0000 0 600,000 ADA Transition Plan 700,000 2,000,000 2,000,000 2,000,000 2,000,000 8,700,000 Safe Routes to School 200,000 200,000 200,000 200,000 200,000 1,000,000 State Bridge and Highway Inspections 100,000 100,000 100,000 100,000 100,000 500,000 CAT Transit Bus Replacement Match 245,234 169,645 150,293 77,133 150,000 792,305 Intelligent Transportation System 185,000 185,000 185,000 200,000 200,000 955,000 City Wide Traffic Engineering Improvements 150,000 150,000 150,000 150,000 150,000 750,000 Neighborhood Transportation Improvements 100,000 100,000 100,000 100,000 100,000 500,000 Increased Funding from FY 25 Decreased funding from FY 25 New Project Added FY 26 Proposed FY26 Projected FY27 Projected FY28 Projected FY29 Projected FY30 5 Year Total Proposed Capital Improvement Program FY 2026-2030 Bicycle Infrastructure 100,000 100,000 100,000 100,000 100,000 500,000 Right of Way Appurtenance 100,000 100,000 100,000 100,000 100,000 500,000 Traffic Sign Retro Reflective Compliance 25,000 25,000 25,000 25,000 25,000 125,000 Historic District and Entrance Corridor Design Guideline s 0 50,000 0 50,000 0 100,000 SUBTOTAL $6,037,285 $9,123,625 $10,250,179 $8,289,190 $7,805,792 $41,506,071 PARKS AND RECREATION Proposed Projected Projected Projected Projected 5 Year Project FY26 FY27 FY28 FY29 FY30 Total Downtown Mall Infrastructure Repairs 100,000 100,000 100,000 100,000 100,000 500,000 Parks and Recreation Lump Sum Account 400,000 400,000 400,000 400,000 400,000 2,000,000 Parks and Schools Playground Renovations 200,000 200,000 200,000 200,000 200,000 1,000,000 Urban Tree Planting 125,000 125,000 125,000 125,000 125,000 625,000 Parkland and Trails Acquisition and Development 125,000 125,000 125,000 125,000 125,000 625,000 Oakwood Cemetery Drainage and Road Issues 150,00 0000 0 150,000 Hazard and Liability Ash Tree Removal 0000 0 0 Downtown Mall Trees Active Lifecycle Management 100,000 100,000 100,000 100,000 100,000 500,000 Invasive Plant Removal 150,000 150,000 150,000 150,000 150,000 750,000 Downtown Mall Tree Management Plan 315,00 0000 0 315,000 Parks Master Plan Implementation 500,00 0000 0 500,000 Riverview Park Access Management (name change ) 250,000000 0 250,000 SUBTOTAL $2,415,000 $1,200,000 $1,200,000 $1,200,000 $1,200,000 $7,215,000 TECHNOLOGY INFRASTRUCTURE Proposed Projected Projected Projected Projected 5 Year Project FY26 FY27 FY28 FY29 FY30 Total Communications Technology Account/Public Access 40,000 40,000 40,000 40,000 40,000 200,000 City Wide IT Strategic Infrastructure 250,000 250,000 250,000 250,000 250,000 1,250,000 Voting Equipment Replacement 150,000 150,000 0 0 0 300,000 SUBTOTAL $440,000 $440,000 $290,000 $290,000 $290,000 $1,750,000 AFFORDABLE HOUSING Proposed Projected Projected Projected Projected 5 Year Project FY26 FY27 FY28 FY29 FY30 Total Public Housing Redevelopment - (CRHA) 3,000,000000 0 3 , 000,000 Westhaven Redevelopment 5,000,000 5,000,000 5,000,000 0 0 15,000,000 Charlottesville Affordable Housin g Fund (CAHF) 1,500,000 1,500,000 1,500,000 1,500,000 1,500,000 7,500,000 Increased Funding from FY 25 Decreased funding from FY 25 New Project Added FY 26 Proposed FY26 Projected FY27 Projected FY28 Projected FY29 Projected FY30 5 Year Total Proposed Capital Improvement Program FY 2026-2030 Supplemental Rental Assistance (CSRAP) 900,000 900,000 900,000 900,000 900,000 4,500,000 Friendship Court Infrastructure Improvements 0 650,000 350,000 1,560,000 840,000 3,400,000 Friendship Court Redevelopment - Phase 3 0 2,047,500 1,102,500 0 0 3,150,000 Friendship Court Redevelopment - Phase 4 0 0 0 2,925,000 1,575,000 4,500,000 PHA - 501 Cherr y Avenue 1,000,000 2,150,000 0 0 0 3,150,000 Carlton Mobile Home Park 1,332,200 1,230,400 1,153,600 1,076,800 3,000,000 7,793,000 Salvation Arm y Low Barrier Shelter Operations Subsidy 0 250,000 250,000 250,000 250,000 1,000,000 SUBTOTAL $12,732,200 $13,727,900 $10,256,100 $8,211,800 $8,065,000 $52,993,000 TOTAL PROJECTS $31,987,686 $39,092,854 $56,800,073 $37,485,746 $23,979,915 $189,346,273 Funding Gap $0 $0 $0 $0 $0 $1

Source: City of Charlottesville website. First collected Nov 15, 2026.