Board of Architectural Review Work Session — Minutes
City of Charlottesville · Charlottesville City County · Board of Architectural Review · meeting of Mar 18, 2025 · Minutes
Open the original document More from City of Charlottesville
This document is no longer listed on City of Charlottesville's website. We kept the copy we read.
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
1
Meeting Minutes
City of Charlottesville
Board of Architectural Review
Work Session
March 18, 2025 5:30 PM
In-person in the Neighborhood Development Conference Room
Welcome to th
is public work session of the Charlottesville Board of Architectural Review. The
primary goals of this session are to provide updates for BAR members regarding on-going projects and
applications, as well as to discuss staff workflows for the conduction of board business.
Members Present
: Ron Bailey, Roger Birle, Cheri Lewis, Jerry Rosenthal, Carl Schwarz, Kate
Tabony, David Timmerman, James Zehmer
Staff Prese
nt: Jeff Werner, Kate Richardson
5:30 PM - W
ork Session began. (No pre-meeting discussion.)
A. Matters from Public
Gen
evieve Keller addressed the members to urge vigilance when considering demolition requests.
B. Consent Agenda
1. Special Use Permit Request - Recommendation to City Council
Planning #PL-25-0027
Commercial Permit #BC-25-0033
401 Ridge Street, Tax Parcel 290132000
Ridge Street ADC District
Owner: Barbara S & Alan D. Jenkins
Applicant: Andrew
Jenkins
Request: Special Use Permit to allow commercial general lodging for up to 10 guest
rooms. Change of permitted use only. No exterior alterations proposed.
Mr. Zehmer asked for a motion to approve the consent agenda. Mr. Schwarz so
moved; Mr. Bailey seconded. Vote: 8-0
Finding of no adverse impact: Based on the information submitted addressing only the
proposed use, with no alterations associated with the SUP being currently proposed to the
site or to the exterior of the existing c1891 structure, I move to recommend to City
Council the requested Special Use Permit for 401 Ridge Street to allow operation of a
B&B will not adversely impact this property or the Ridge Street ADC District.
Furthermore, it should be understood that at any later exterior alterations at this p roperty--
with
or without this SUP--will require BAR review and approval, per Chapter 34,
Sections 5.2.6. and/or 5.2.7.
C. Work Session
2. Project Update
BAR #
HST24-0047
March 18, 2025 Meeting Minutes (3.20.25)
March 18, 2025 BAR Meeting Minutes (3.20.25)
2
1000 Wertland Street, TMP 100038000
(1010 Wertland St; 129 10th St NW; Portion of 1105 W. Main St.)
West Main Street ADC District
Owner: UVA Foundation
Applicant: Elizabeth Chapman; Grimm + Parker Architects
Project: Multi-story residential building
Ms.
Chapman from Grimm + Parker Architects gave a brief introduction of the
development team. Mr. Settles provided an overview of the project’s narrative and
status.
Note: Separate two-on-one meetings were held earlier in the day with four BAR
members and the development team at the Grimm + Parker office. A brief account of
the work session discussion follows:
• The development team summarized the numerous limiting factors and
c
onstraints on the project, most importantly impacting unit number and square
footage, which is a set parameter.
• In response to feedback from neighborhood meetings, the building’s inner
courtyard was specifically designed to be a private and safe space for the
community; “just for them”.
• BAR members expressed they did not see much responsiveness to their design
recommendations and comments over the past year of preliminary discussions,
specifically in regards to: massing, scale, and materiality.
• There was discussion that the alternating color scheme is utilized to camouflage
massing, and that this strategy is not very successful. This formula is seen
everywhere on similar buildings, and therefore this project could be anywhere,
in any city.
• The presence of the proposed structure on the Wertland street side remains of
particular concern and is generally out of step with the neighborhood and the
ADC district guidelines.
• The applicant will return with another design iteration in the coming month(s).
3. St
aff Consultation & Questions
Staff Documentation
a. Hyperlinks & Laserfiche (update)
The
City’s IT Department is looking into purchasing additional Laserfiche licenses
so that the archives for Boards and Commissions, as well as city historic surveys
and other cultural documentation, can have a more stable connection for public
access.
b. Min
utes, Action Memos, Applicant Materials: Dissemination and Archiving.
Mr. S
chwarz recommended utilizing the “other files” location within the Civic
Clerk application for any presentation materials or late submittals pertaining to a
CoA application that are not included in the official packet. This would allow for
better viewing when in Council Chamber (TV monitors near the dais are not ideal),
March 18, 2025 BAR Meeting Minutes (3.20.25)
3
and then those additional materials can be flagged for inclusion into the BAR
archives on Laserfiche.
4. A
pplication procedures & Workflows
a. Review of BAR Bylaws. (Agenda item added by staff.)
Discussion: Members expressed they were generally content with the document as
is, and that it does an outstanding job of summarizing procedures. Several minor
revisions and suggestions were discussed to maintain brevity and clarity, but no
major revision was undertaken.
[S
taff Note- March 20, 2025: Ms. Lewis communicated she will provide the
Bylaws edits as discussed in the work session to staff.]
b. P
re-Application Conferences
J
eff Werner: Development Code Ch. 34, 5.2.7-B.2.c requires Pre-application
Conferences with the entire board for projects and activities that meet certain
criteria (i.e.: development with projected construction costs of $350,000 or more.)
We should establish some basic requirements for what information an applicant
must provide prior to this pre-application conference. And we should distinguish
between what’s necessary for a multi-story office building versus a two-story
addition to someone’s house. We should have rules for how we treat those
discussions, and what’s expected from the applicants. Staff has the responsibility of
determining what constitutes as “complete” application but there are no precise
rules to define that, so it requires judgment on my part.
Discussion:
Staff provided an overview of the current development review processes. [See
appendix.]
T
he BAR suggested a two-step review for large-scale projects might be worth
evaluation
M
embers agreed there should be a clear path outlined for applicants, and that staff is
doing a good job of managing CoA requests, bringing applications forward, and
creating informative and detailed staff reports.
F
urther discussion centered on what constitutes a complete application. Staff
Referenced the ADC District Guidelines, Introduction, C. Desing Review Process.
[See Appendix.]
M
embers directed staff to outline the review procedures and to create a checklist
for applicant submittals.
J
eff Werner: For demolitions, should we establish that CoAs for significant
demolitions that have subsequent CoAs for new construction will only be
considered separately and not at the same meeting? Or, only after the demo CoA is
resolved, including if it gets appealed?
March 18, 2025 BAR Meeting Minutes (3.20.25)
4
Discussion:
General discussion on this process, and regarding the period of validity for
demolition CoAs including how or why they are renewed by the Administrator (the
NDS Director, or Board Staff). Staff raised the idea that perhaps any extension of a
demolition CoA be brought to the board for review prior to renewal.
5. C
ertified Local Government Training Requirements
M
embers fulfilled a portion of their CLG training by participating in this work session
regarding the BAR review process.
D. A
djourn
The meeting was adjourned at 7:56 PM.
Appendix:
D
evelopment Review Process – work session whiteboard (image)
CHARLOTTESVILLE ARCHITECTURAL DESIGN CONTROL DISTRICT DESIGN GUIDELINES 7
IntroductionI
C. Design Review Process
Design review is mandatory for exterior alterations to any
building and/or site in Charlottesville’s Architectural Design
Control (ADC) Districts and for any individually protected
properties. Please consult the individual map for each district
on the following pages to determine if your building or site
is located in one of these historic districts. Some districts
contain non-contributing buildings and sites, which do
not require BAR approval for demolitions. Otherwise, both
contributing and non-contributing buildings and sites follow
the same design review process.
Contributing buildings and sites are defined as those
individual properties that are listed on or eligible for
the National Register; listed by the City as individually
designated structures; or by their design, age (over 50 years),
and historic integrity meet generally agreed upon standards
of contributing buildings in historic districts. Buildings of
more recent construction whose form, materials, scale, and
overall design relate to the remaining traditional character of
the district, or that represent a unique or distinct architectural
style, are also included in this category.
Non-contributing buildings and sites are those whose age
(less than 50 years), design, scale, and materials do not relate
to the remaining traditional character of the district. Also
included are buildings whose age and original design might
make them eligible for the Contributing category, but because
of extensive alterations no longer retain their integrity;
and those buildings whose advanced level of deterioration
precludes their inclusion.
Once you have determined that your building and/or site
is located in an ADC district or is an individually protected
property, you must follow the steps below:
1. Obtain online or pick up a Certificate of Appropriateness
(COA) application at the Department of Neighborhood
Development Services (NDS) in City Hall. Staff can help you
determine if you need a COA.
2. Determine whether a pre-application conference is mandatory
for your project. Consult Zoning Ordinance Article II, Sec. 34-
282(e).
3. If not mandatory, you may still request a pre-application
conference which can provide informal input and helpful
technical information for completing the COA.
4. Consider presenting a conceptual design, particularly for an
addition or a new building, to the BAR before seeking formal
approval. Contact staff to be placed on an agenda.
5. Fill out the COA application and collect necessary information
and exhibits as listed in the Zoning Ordinance, Article II,
Section 34-282(d):
a. Detailed and clear depictions of any proposed changes in the
exterior features of the subject property, including but not limited to
the following: the general design, arrangement, texture, materials,
plantings and colors to be used, the type of windows, exterior doors,
lights, landscaping, parking, signs, and other exterior features
and appurtenances. The relationship of the proposed change to
surrounding properties will also be shown.
b. Photographs of the subject property and photographs of the
buildings on contiguous properties.
c. Samples to show the nature, texture and color of materials
proposed.
d. The history of an existing building or structure, if requested by
the BAR or staff.
e. For new construction and projects proposing expansion of the
footprint of an existing building: a three-dimensional model (in
physical or digital form) depicting the site, and all buildings and
structures to be located thereon, as it will appear upon completion
of the work that is the subject of the application.
f. In the case of a demolition request where structural integrity is
at issue, the applicant shall provide a structural evaluation and cost
estimates for rehabilitation, prepared by a professional engineer. The
BAR may waive the requirements for a structural evaluation and
cost estimates in the case of an emergency, or if it determines that
the building or structure proposed for demolition is not historically,
architecturally, or culturally significant under the criteria set forth
in Section 34-274.
6. Make ten copies of the application materials and return these
with the required fee to the Department of Neighborhood
Development Services in City Hall. Return this information
twenty-one calendar days before the next scheduled meeting of
the BAR, which is the third Tuesday of each month.
7. If the application is complete, your project will be placed on
the agenda of the next meeting or you will be informed that
additional information is needed. Y ou should plan to attend the
BAR meeting.
8. If the application is approved by the BAR, you will receive a
letter approving the application and issuing a COA or issuing
COA subject to certain conditions which will be stated in the
letter. After your COA is approved, you may apply for a building
permit, if needed.
9. If the BAR does not approve the application, you may appeal
to the City Council by filing an appeal within ten (10) working
days of the date of the decision; if they do not approve it, you
may appeal to the Circuit Court.