2/27/24 Citizens’ Budget Advisory Committee (CBAC)
Meeting Notes
Commitee Members Present: Mr. Gene Johnson, Mr. Chip Hughey, Mr. Robert Vaughn, Mr. Chris Eudailey, Ms.
Shelia Walters
County Staff Present: Mat Harris – Deputy County Administrator, Shane Hill – Budget Manager, Riane Reiss –
Budget Manager, Stephanie Davis – Budget Analyst, Josh Davis – CCPS Chief Opera�ng Officer, Robert Meister –
CCPS Chief Financial Officer
The mee�ng was brought to order at 12:10 pm
1. Welcome
2. Approval of November 30, 2023 Minutes
a. November 30, 2023 minutes were approved.
3. Schools Update
a. Mr. Davis began the mee�ng by sharing a general overview of schools.
b. Enrollment has grown since the pandemic. The County StratIS model is predic�ng an addi�onal
2,000 students by August of 2028. Chesterfield is on pace to surpass Virginia Beach in enrollment to
become the fourth largest district in the state of Virginia.
c. A �meline of schools’ development projects was shared highligh�ng proposed comple�on dates to
provide new buildings and new seats to address school capacity needs.
d. A new project has been added in the Dale district at the request of the School Board Representa�ve
Ms. Chaters to expand the LC Byrd gymnasium. Mr. Johnson asked what the expansion of the
gymnasium would entail. Mr. Davis shared the design and floorplan associated with the proposed
expansion. Mr. Harris stated that the design will be like Midlothian and Monacan High Schools.
e. Mr. Eudailey asked about the cost of projects that are in the upcoming years. Mr. Davis responded
that the cost associated with the two middle schools was approximately $100 million and AM Davis
will cost approximately $60 million. The next two elementary schools and high school will be bid on
this year. Mr. Davis stated Infla�on has had an impact on costs and previous cost es�mates may not
accurately reflect current market values.
f. Mr. Vaughn asked if the proposed projects were covered by the bond referendum. Mr. Davis
explained that some costs are associated with the $375 million referendum but funding for other
projects is being determined. Mr. Meister shared that the cost es�mates for the next three schools’
bids will be important in determining how much remaining referendum dollars will be available for
use on other schools’ projects.
g. Mr. Eudailey asked what the capacity will be for the new high school. Mr. Davis shared that the
expected capacity is 2,400 students. When the project was developed for the referendum the
es�mated cost of the high school was $135 million. It is now expected to cost approximately $200
million. Mr. Vaughn inquired about whether the land was given to schools for the construc�on of
the schools. Mr. Davis responded that the land was provided by the Economic Development
Authority (EDA). Mr. Meister explained that land cost was not included in the ini�al es�mate.
h. Mr. Harris further detailed that when the Upper Magnolia land was purchased there was a vision
that infrastructure would be included there including schools. Quite o�en the County does not
include land acquisi�on in bond issuances because land can be purchased in cash prior to
infrastructure development. Referendum projects are a star�ng point, but the demographic
informa�on will drive future projects.
i. Mr. Davis con�nued his presenta�on by providing the number of seats that each new project will
provide the school district by school type. If all projects are completed, capacity is expected to
increase by 8,000 seats. Mr. Eudailey inquired about how many of the 274 modular units will be
eliminated with the addi�on of the planned schools’ projects. Mr. Davis shared that it would help
eliminate some but not all need for the units.
j. Mr. Vaughn inquired about how the new schools’ projects correspond with popula�on growth
projec�ons. Mr. Harris stated that from a capacity level the County will be in good shape. Mr. Davis
returned to his presenta�on on schools’ capacity. Detailing the capacity for each new elementary
(3), middle (2), and high school (1).
k. Mr. Johnson inquired about why Matoaca Middle School was reducing its student capacity. Mr.
Davis shared that the rebuild will be a smaller school that will s�ll be able to accommodate growth
within the area.
l. Mr. Davis shared that the current school district capacity is 67,000 students and the County is at 93
percent of its capacity. In five years, the County is projected to be at 96 percent capacity. If all
projects are completed, capacity is projected to decrease to 85 percent.
m. Mr. Hughey asked if there are any common themes in the popula�on growth that has been
projected that provide a picture about why popula�on growth is stronger in the County. Mr. Davis
encouraged the commitee to read the Weldon Cooper report to get addi�onal informa�on about
migra�on within the state, sta�ng that since 2020 the County has grown by about 20,000 ci�zens
contribu�ng to student growth.
n. Mr. Davis transi�oned to discussing the impact of housing developments on school planning. Mr.
Harris shared that data is collected on student genera�on factors to es�mate impacts of the
housing impacts pipeline. Mr. Harris detailed the types of housing developments coming up in
Chesterfield sta�ng that apartments are the lowest genera�on factor housing type in the County for
school age children.
o. Ms. Walters inquired about if there is an assump�on that a certain amount of land is going to be
developed for schools based on proximity to housing developments. Mr. Harris stated that the
County looks at the number of units and historical trends to be able to predict what will need to
happen.
p. Mr. Eudailey asked how many units can be built without the approval of the Board of Supervisors.
Mr. Harris responded that addi�onal research would have to be done to provide an answer.
q. Mr. Davis discussed the design plan for Falling Creek Middle, Western Area Middle School, and the
two elementary schools opening in 2026. AM Davis Elementary, which is a Title I school, is being
built to account for smaller classes sizes and one to one instruc�on. Bensley Elementary students
will be moved to the current Falling Creek Middle school building as their school is being rebuilt.
Western Area High School will be the first brand new high school in the County in approximately 20
years and construc�on is expected to begin in 2026. Redistric�ng efforts may be u�lized for each
school to address capacity. Addi�onally, there will be some road infrastructure built alongside the
new school developments.
r. Mr. Davis began discussing non-referendum facility projects. The Dale District Elementary school
project could open at the earliest in August 2027. The district has five schools with 69 classrooms in
trailers. The County would like schools in this area to have smaller class sizes and is looking at
proper�es for the new elementary school. Old Hundred Elementary school is currently unfunded,
but it is an an�cipated need for the County if Roseland and Hallsley con�nue to be developed.
Midlothian Middle has been added onto over the years but now sites are being discussed for a
replacement facility that could open as early as August 2028. Mr. Harris discussed scenarios that
have impacted the project moving forward. Grange Hall Elementary enrollment will decrease when
the Western Area Elementary school is opened. Grange Hall Elementary and Midlothian Middle are
100-year-old buildings that require constant maintenance. Thomas Dale main campus will receive
an expansion, and at the request of School Board Representa�ve Ann Coker, the logis�cs of
combining the main campus with the west campus are being explored. Matoaca Middle School
opened its most recent wing in December 2019. The proposed addi�on to the school would model
Manchester Middle School.
s. Mr. Meister discussed VPSA and CIP funding associated with the construc�on of the new schools.
Mr. Johnson asked how VPSA funding works. Mr. Harris shared that it is received through an
applica�on process and the bond issuance is an appropria�on-backed credit that is more expensive
than a General Obliga�on bond but avoids having a referendum. Mr. Vaughn inquired if there is a
cap on how much the County can receive in VPSA funding. Mr. Harris stated that the County is
under that threshold.
t. Mr. Eudailey asked what the County’s capacity is to borrow money. Mr. Harris responded that the
County did not exceed its capacity with the referendum as there will always be addi�onal projects.
u. Mr. Hughey asked if the new schools’ projects would impact the need for more teachers. Mr. Harris
stated that there are discussions about capacity needs.
v. Mr. Davis began to discuss schools’ major maintenance. Mr. Johnson asked if Schools sets aside 2.5
percent for major maintenance each year. Mr. Davis stated that the County has made tremendous
strides in major maintenance in. August 2020, $57 million was dedicated to major maintenance
efforts. Addi�onal revenue received during the pandemic was helpful in the comple�on of projects,
especially HVAC.
w. Mr. Hughey asked what falls into the life safety category. Mr. Davis responded that it is related to
roofs.
x. Mr. Davis shared that the opera�ng fund transfer is below 10 figures. Bonds and grants have been
the main revenue sources for schools’ major maintenance. By 2026, without addi�onal funding, the
balance will be depleted. Mr. Meister shared there is a $6.5 million transfer from the County
annually for major maintenance. Mr. Harris stated that the solu�on to increasing the transfer is to
get pay-go funding where it needs to be. Mr. Davis con�nued his presenta�on sta�ng that the
current replacement value is at 1.5percent and an addi�onal $30 million would be needed to reach
1.5 percent.
y. Mr. Eudailey asked about the maintenance of facili�es prior to 2020. Mr. Harris stated that 2008-
2012 funding was reduced because the maintenance could be deferred. When County revenue
began to grow the funding was increased; however, the number of major maintenance needs had
built up but there are great strides being made to close the gap.
4. FY2025 Budget Update
a. Mr. Harris began his presenta�on on the FY2025 Budget update.
b. County Board of Supervisors will receive the proposed budget on March 13th. A period of
community dialog will ensue for a month a�er. There are two new board members for the FY2025
cycle.
c. Mr. Harris shared that there are three sources that generate significant revenue for the County of
which schools receives 35-40%: 1) Real estate, 2) personal property local, and 3) sales and use
taxes.
d. Mr. Harris provided an overview of land book revalua�ons detailing areas that the County is doing
well in as well as long run assessment data.
e. Mr. Harris provided an update on the mul�-family market, sharing that apartment assessments
went down in 2024 but have gone up over 44 percent over the past three years. Mr. Vaughn
inquired about how assessments are determined for apartments. Mr. Harris stated that it is
calculated using an income-based approach.
f. Mr. Harris con�nued the presenta�on discussing student genera�on factors, sharing that the
County es�mates one child per 10 apartment units. The total permit base for County is
approximately 40 percent mul�-family. Mr. Johnson inquired if condos were a part of calcula�on.
Mr. Harris stated the County does not include condos.
g. Mr. Harris stated that personal property is s�ll experiencing market correc�on, and local sales tax
has been up and down since 2022.
h. Ms. Walters asked how the County compares to other locali�es. Mr. Harris stated that in the post
Covid world the status of the County is not abnormal but makes determining how to alleviate the
burden of the assessment issue more difficult.
i. Mr. Vaughn inquired about what the County gets for every one percent of sales taxes. Mr. Harris
stated that is approximately $70 million and meals tax would be approximately $30 million. The
County has not explored taxing digital streaming services.
j. Mr. Harris shared data from the Virginia Department of Auditor of Public Accounts to detail the
County revenue per capita and the overall tax burden.
k. Mr. Harris reviewed the projected expenditure increase for FY2025.
l. Mr. Vaughn asked whether personal property will be more or less than $117 million. Mr. Harris
stated that there will be less personal property taxes received in in FY2024. In FY2025, growth is
expected but there will be a smaller increase due to the informa�on received from the
Commissioner of Revenue.
m. Mr. Johnson asked of the 8.8 percent real estate increase how much is real estate growth. Mr. Harris
stated less than 10 percent is from commercial residen�al growth because the exis�ng residen�al
base is large.
n. Mr. Vaughn inquired about when the County will see a benefit from the addi�on of the Lego. Mr.
Harris responded that by the end of the five-year plan there should be some dividends. There was
an incen�ve package struck with Lego so some taxes were taken off. Mr. Harris stated that the
County assumes a percentage increase in real estate assuming we have $350 million in commercial
value and will watch the trend. Chesterfield is 80 percent residen�al and 20 percent commercial
and Henrico is 70% percent residen�al and 30 percent commercial. Apartments are commercial
under building code which skews Henrico’s ra�o.
o. Ms. Walters asked what the trend has been in real estate value. Mr. Harris responded that the
County budgets between 3.5-4 percent.
p. Mr. Harris detailed the County’s plans for FY2024 sharing that a $47 million increase in revenue was
expected prior to receiving the personal property numbers from the Commissioner of Revenue.
q. Mr. Eudailey asked that Fire and EMS provide and update to the group. Mr. Harris stated that he
would request the department come and share with the commitee.
r. Mr. Harris con�nued his presenta�on on expenditures highligh�ng base changes to expenditures
such as personnel and five-year plan enhancements.
s. Mr. Harris stated that in the next mee�ng Fire will provide an update, mul�year opera�ng priori�es
will be reviewed as well as a look at the CIP .
t. Central Virginia Transit Authority (CVTA) put 0.07 percent on sales tax and spans Central Virginia
and will use the revenue source for the largest road program in Chesterfield County’s history. It
must be used specifically for transporta�on projects which are mostly funded by pay-go. It will be a
revenue bond and payments will be made to the Economic Development Authority (EDA). It could
poten�ally be a $300 million road program. Ms. Walters inquired about the �ming related to ge�ng
funds for the road projects. Mr. Harris stated he would like to move forward by July 1, 2024.
Mee�ng adjourned at 1:54 pm