FY27 Evaluating the Restaurant Permitting Process Study
Fairfax County · Fairfax County · Other
Open the original document More from Fairfax County
This document is no longer listed on Fairfax County's website. We kept the copy we read.
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
f
OFPA
Report
Jennifer Girard,
CFE, CIDA
Performance Auditor
to the Board
Office of Financial &
Program Audit
Fairfax County Land Development Services
Evaluating the Restaurant Permitting
Process
October 2026
Office of Financial & Program Audit Team
Jennifer Girard, Performance Auditor to the Board of Supervisors
Cara O’Connor, Deputy Auditor to the Board
Ryan Huang, Lead Analytics Auditor
Diana Davis, Board Auditor Intern
Jaden Riyu, Board Auditor Youth Leadership Intern
Audit Committee
Daniel Storck, Chairman, Board of Supervisors – Mount Vernon District
James Bierman, Board of Supervisors – Dranesville District
Pat Herrity, Board of Supervisors – Springfield District
Andres Jimenez, Board of Supervisors – Mason District
Lester A. Myers, At-large Representative
Jay Ramsey, At-large Representative
Cover Photo Source: Land Development Services, Fairfax County
Office of Financial & Program Audit
12000 Government Center Parkway, Suite 233
Fairfax, VA 22035
703-324-1501
Email: auditoroftheboard@fairfaxcounty.gov
You can obtain copies of this report by
contacting us or download and view an
electronic copy by visiting our website at:
www.fairfaxcounty.gov/boardauditor/
Auditor of the Board (fairfaxcounty.gov)
EXECUTIVE SUMMARY
WHY THIS MATTERS
Home to more than 2,500 restaurants, Fairfax County has a
substantial and growing restaurant industry. Improving the
effectiveness and efficiency of the permitting process can reduce
the financial strain on restaurant owners and support the County’s
economic vitality.
Evaluating the
Restaurant
Permitting
Process
Study
Report Issued:
October 2026
Fairfax County is home to more than 2,500 food establishments,
and the County has issued an average of 280 new food
establishment permits annually in recent years. Because opening a
restaurant in Fairfax County often requires multiple permits,
reviews, and inspections across agenciessuch as Land
Development Services, the Health Department and the Office of
the Fire Marshal, the permitting process can have a significant
impact on how quickly a restaurant can open and the costs it incurs
along the way. Amplifying this impact is the fact that across the
Commonwealth of Virginia, nine out of 10 restaurants are small
businesses.
Permitting challenges are not unique to Fairfax County.
Jurisdictions across the country are working to address the
complexity of commercial permitting and to find ways and tools to
make the processes work better for businesses trying to open. Our
review found that while the County has made improvements to the
permitting process over the years and provides some resources for
applicants, there is an opportunity to improve the process for
restaurants looking to open in Fairfax County. Restaurant owners
report concerns about lengthy and unpredictable timelines and
difficulty navigating the process. For the restaurants we tested, the
median time to open was 315 days for new establishments and 110
days for changes in ownership. Even when agencies meet their
review-time goals, the cumulative process can take a significant
amount of time (although not all of that time is within the County’s
control).
The County should build on the improvements already underway by
making the process more predictable and easier to navigate. OFPA
offers three recommendations to 1) improve the guidance and
support for restaurants, 2) address some workflow challenges, and
3) address concerns around the lengthy permitting process.
Management agreed with the responses and has offered cross-
agency solutions to address the issues.
Objective
To evaluate the timeliness,
efficiency, and overall
experience of the permitting
process for restaurants
opening in Fairfax County
Table of Contents
Background ................................ ................................ ................................ ...................... 1
Connection to the Countywide Strategic Plan................................ ................................ ...... 1
Summary of Work Performed ................................ ................................ ............................. 1
Scope of Review................................ ................................ ................................ ................ 2
Restaurant Permitting Process, Systems and Resources................................ ...................... 2
Data Analysis................................ ................................ ................................ .................... 8
Restaurant Interviews ................................ ................................ ................................ ......20
Economic Impact of Permitting Process for Restaurants................................ ..................... 24
Existing Efforts to Improve the Permitting Process................................ .............................. 26
Leading Practices to Streamline Restaurant Permitting................................ ....................... 28
Observations and Recommendations................................ ................................ ................33
Observation and Recommendation 1................................ ................................ ............33
Observation and Recommendation 2................................ ................................ ............36
Observation and Recommendation 3................................ ................................ ............37
Appendix 1................................ ................................ ................................ ....................... 40
Appendix 2................................ ................................ ................................ ....................... 41
Appendix 3................................ ................................ ................................ ....................... 42
Appendix 4................................ ................................ ................................ ....................... 43
Appendix 5................................ ................................ ................................ ....................... 44
Appendix 6................................ ................................ ................................ ....................... 47
1 | P a g e
Fairfax County is home to over 2,500 restaurants – more than any other
jurisdiction in the Commonwealth of Virginia. This number continues to
grow, with an average of 280 new restaurant health permits issued annually
in recent years in the County. Opening a new restaurant (or food
establishment, more broadly) often requires multiple permits and approvals
across various County departments, including Health, Zoning, Building, and
Fire. Delays in permitting can create financial strain for business owners and
discourage investment and hinder economic developmentin the County.
These impacts are particularly important given the restaurant industry’s
significant contribution to the broader economy. In Virginia, restaurants
generate $1.74 back into the state economy for every dollar invested in the
industry (National Restaurant Association, 2026). Furthermore, nine out of
10 restaurants in Virginia are small businesses(National Restaurant
Association, 2026). An efficient and predictable permitting process can help
reduce unnecessary costs for businesses while supporting the continued
growth and economic contributions of the restaurant industry. The Office of
Financial and Program Audit (OFPA) proposed this study to evaluate the
timeliness, efficiency, and overall experience of the permitting process for
new restaurants in Fairfax County. The Board of Supervisors approved this
study in FY26.
OFPA reviewed the Fairfax Countywide Strategic Plan (Revised June 2025) to
consider the connection of restaurant permitting to the 10 community
outcomes that the Board of Supervisors has identified as priority areas for
the County. Four outcome areas relate to restaurant permitting.
• Economic Opportunity: by fostering a thriving food service sectorthat
strengthens local economies,
• Healthy Communities: by ensuring food safety through Health
Department inspections and public health standards,
• Effective and Efficient Government: by streamlining county permitting
processes that help food establishments open efficiently,and
• Housing and Neighborhood Livability: by supporting local restaurants
that bring communities together and provide dining options that make
neighborhoods feel more welcoming.
The OFPA team conducted a review of restaurant permitting to assess the
timeliness, effectiveness and efficiency of the process. This work included
analyzing the Planning and Land Use System (PLUS) data and developing a
sample of restaurants for deeperreview. We examined county website
resources and instructions available to restaurant applicants to evaluate
resource availability.
Background
Summary of Work
Performed
Connection to the
Countywide
Strategic Plan
2 | P a g e
To gain insight into the customer experience around permitting, we
interviewed restaurant owners and managers as well as County reviewers,
inspectors, and other staff involved in permitting.
In addition, we examined practices used in other jurisdictions and
considered recognized leading practices that could inform improvements.
OFPA also reviewed associated fees to understand their impact on
applicants and overall process accessibility.
Our review examined the permitting process forrestaurants that received
Fairfax County Health Department food establishment permits between July
1, 2023, and August 3, 2026, focusing specifically on full-service
restaurants, carry-out restaurants, bakeries, breweries/wineries, and
fast-food establishments, while intentionally excluding other establishment
types such as grocery stores, school cafeterias, and hospitals.We examined
both new establishments as well as changes of ownership, which still
require a new food permit. We also looked at food establishments that were
in the process of a building renovation or a new build and had not yet
received their food establishment permit. We examined the process from
the start of permitting (for a renovation or new build) through a restaurant’s
opening.
Due to timeframe limitations, we focused on the permitting process after
any required zoning and site plan submissions and approvals, as most new
restaurants in the County do not go through those steps. Additionally, the
study’s timeframedid not allow for in-depth reviews of customer service
survey responses, the process for restaurants undergoing a change of
ownership, or the extent of identified workflow challenges within PLUS.
Restaurant Permitting Process
Opening a restaurant in Fairfax County begins (and the permitting
process effectively starts) once an owner identifies a suitable site
(such as a parcel of land or an existing structure). Fairfax County’s
zoning rules determine where different restaurant types (restaurants,
carryout establishments, drive-through restaurants, and
entertainment-oriented venues) can operate. Owners can consult
the County’s zoning district analyzer or speak with the Zoning
Permits Section in the Department of Planning and Development (DPD) to
learn whether the use is permitted by right or the County will require a
special permit or exception.
If zoning uncertainties exist, owners can meet with DPD. Staff review the
proposed restaurant concept, site characteristics, any existing conditions
Scope of Review
Restaurant Permitting
Process, Systems and
Resources
ZONING
3 | P a g e
on the land, and whether the County requires a Special Exception, Rezoning,
or Proffered Condition Amendment. If the County requires a zoning
application, owners must hire a licensed civil engineer to prepare required
materials. Owners submit all zoning applications through PLUS (the
County’s central integrated online platform, see PLUS – The County’s
Online Permitting Platform on page 5) and pay applicable fees. In special
exception cases (e.g., drive-through uses), the County requires public
hearings with the Planning Commission and Board of Supervisors. Rezoning
and Proffered Condition Amendment applications follow similar procedures
and may also involve negotiation of new conditions.
Once the zoning path is clear, the permitting process transitions
into the site-related and building plan stages. Site plans, required
for new buildings, demonstrate how land disturbance, grading,
stormwater management, and infrastructure changes will comply
with county regulations. For new construction or expansions,
which disturb 2,500 sq. ft. or more, the County usually requires a
full site plan. Smaller expansions or conversions may qualify for a
Minor Site Plan. Restaurant owners must hire Virginia-licensed professionals
(such as civil engineers, architects, and surveyors) to prepare the formal site
plans required for submissionto Fairfax County.
Applicants submit site plans electronically in PLUS, and multiple agencies,
including Land Development Services (LDS), the Department of Public
Works and Environmental Services (DPWES), the Fairfax County Health
Department, the Office of the Fire Marshal and the Virginia Department of
Transportation (VDOT), review the applications and site plans. Agency
reviewers identify non-compliance issues and provide comments to owners
for correction. Owners submit revisions, and the plans cycle through review
until the County approves the site planand issues a corresponding land
disturbance permit. Converting an existing restaurant space (already zoned
and built for food service) is typically the fastest route to opening a new
restaurant.
Owners (or their representatives) may submit building plans in
PLUS concurrently with site plans or afterward. Building plans for
new construction or alteration/addition must detail structural,
mechanical, electrical, plumbing, and life safety systems. LDS, the
Health Department, the Office of the Fire Marshal, and Zoning
review building plans concurrently and focus their reviews on
ensuring that the plans comply with all relevant state and local
codes. Fairfax County requires restaurants to comply with the
Virginia Uniform Statewide Building Code (USBC) and the Statewide Fire
Prevention Code (SFPC) as well as county regulations (e.g., ordinances, the
Public Facilities Manual, PFM). Health review ensures compliance with
state health codes and operational requirements. County agencies issue
BUILDING
G
SITE
Addition/Alteration
Commercial (ALT-C
Permit): A commercial
Addition/Alteration
permit is required
when you're modifying
an existing non-
residential structure.
Commercial New
(BLD-C Permit): A
commercial New
Building permit is
required when building
a new commercial
building or new,
detached structure.
4 | P a g e
comments and owners submit revisions until building plans receive
approval. Owners may begin work after the County approves the required
plans and corresponding permit for construction. Owners must also submit
applications for trade permits (mechanical, electrical, plumbing and fire
protection systems). As with building plan reviews, County agencies issue
comments and owners submit revisions until the County approves the trade
applications and issues the permits.
Note: This graphic provides a general visual overview of the steps involved in opening a
restaurant that must submit building plans. Steps 1-4 are shown with less detail since they
were not a focus of the study.
Applicants opening a food establishment also apply for the Food
Establishment Permit by submitting required plans and documents through
PLUS and paying applicable fees.
Owners must plan for inspections throughout construction; every
permit requires inspections before occupancy. For example, fire-
related permits, such as alarms and sprinklers, require separate
inspections. Once all construction-related inspections including
those for plumbing, mechanical, electrical, and fire protection
systems are completed/passed, the owner must schedule a pre-
occupancy inspection with the Office of the Fire Marshal, when
required, as well as the Health Department. After the
establishment has passed a Health Department pre-occupancy
inspection, Health issues the restauranta food establishment
permit. The owner will then apply for a Nonresidential Use Permit (Non-
RUP), which must be obtained before opening to the public.
Owners must register for the Fairfax County Food and Beverage Tax prior to
opening for business and the County’s Business, Professional, and
Occupational License (BPOL) within 75 days of starting business operations.
INSPECTIONS
5 | P a g e
Restaurants serving alcohol must obtain a local mixed beverage license
from the Commonwealth of Virginia.
PLUS – The County’s Online Permitting Platform
PLUS, formally known as the Planning and Land Use System, is Fairfax
County’s central integrated online platform. PLUS is a configurable,
commercially available software platform developed by Accela, Inc.It
consists of several systems, including ePermit Hub (plan review
application), CityGov (inspection application), and Virginia Interactive
(payment portal). More than 900 other government agencies use Accela.
The County implemented the first release of PLUSin October 2020, and the
most recent release (Release 4) launched in October 2022. PLUS eliminated
a number of older systems such as FIDO and PAWS and integrated the
County’s permitting process into one system.Importantly, it allowed the
County to introduce concurrent reviews, helping the review process to
proceed more efficiently.
Restaurant owners (or their representatives) use PLUS to submit permit
applications, pay fees, monitor status and receive electronic notifications
for zoning, building, environmental health and other land development
permits. DPD, LDS, the Office of the Fire Marshal and Health Department all
use PLUS to review applications, issue permits, send notifications, and
schedule inspections.
PLUS has several different sections, or modules, as seen in the screenshot
below. The modules represent different areas with separate record types
and data. Most restaurant applicants utilize Environmental Health, Building,
and Fire modules, though depending on their plans, they may need to utilize
the Planning, Site or Zoning modules.
PLUS Applicant Home Page
With the addition of
PLUS, Fairfax
County
decommissioned 25-
30 older systems.
6 | P a g e
Using PLUS starts with the owner (or their representatives) creating an
account and choosing the correct application type. The PLUS portal
includes guidance tools to help applicants identify the correct submission
path, but the County encourages applicants to review requirements
carefully before filing.
Applicants must format and submit plans, drawings, and supporting
materials according to the County’s digital submission requirements. The
County performs a preliminary quality assurance review and returns non-
compliant or incomplete submissions to applicants for revision before the
plan review process begins.
As stated above, manyprojects involve multiple reviews and approvals from
different agencies such as Zoning, Land Development Services, the Health
Department, and Office of the Fire Marshal, who provide comments on plan
reviews through PLUS. Applicants can see in PLUS which department is
reviewing their submission at any time.
A key component of navigating the system is understanding the review cycle
structure. Fairfax County typically reviews applications in rounds. After the
initial submission, reviewers provide comments in PLUS for the applicant.
Applicants then revise their plans to address the comments and resubmit
the plans through PLUS. Depending on the quality of the initial submission
and the complexity of the project, several review cycles may be required
before reviewers grant approval. Being thorough during the initial
submission and including all required documents and code-compliant
plans can reduce the number of review rounds and shorten the overall
timeline.
After the County approves the application, the permit is issued through
PLUS. Owners can begin construction and request the required inspections
at the appropriate stages(however, not all agencies use PLUS for inspection
scheduling). Inspectors record inspection results digitally, creating a
continuous record of compliance for the project. This integration ensures
that applicants, contractors, and County officials have access to consistent
project information throughout the life cycle of the project. Finally, the
County issues occupancy permits in PLUS.
Permitting Resources for Restaurant Applicants
Fairfax County provides a range of resources to help applicants navigate the
permitting process. Land Development Services (LDS) offers the PLUS
Permit Library, which includes more than 60 step-by-step guides covering
application requirements, required documents, review procedures, and
other permitting topics. LDS also provides over 120 instructional videos on
PLUS (including key videos in 8 languages) and publishes technical updates
7 | P a g e
through its Letters to the Industry. The Office of the Fire Marshal also
provides a PLUS Permit Library, and the Health Department provides
guidance on food-establishment requirements. Overall, County agencies
provide a substantial amount of guidance on their websites; however, the
information is dispersed across multiple department websites and exists
within numerous subpages, requiring extensive drilling down to locate key
details.
A coordinated start-to-finish workflow does not exist to guide prospective
restaurant owners through the full process. The County’s restaurant guide
“Opening a Restaurant in Fairfax County” (published in April 2022) likely
was intended to address that gap, butwhile it is posted on the Health
Department’s website as “Updated!, ” it pre-dates the implementation of
PLUS and is outdated and no longer reflects the current process. One
example, the guide provides a phone number for the “Fairfax County
Concierge on Opening a Restaurant”; however, when we called the number,
a recording stated that it was a non-working County number, and the call
was automatically disconnected.
The County’s published LDS metrics provide estimated turnaround times
for individual LDS tasks, but they do not give applicants a sense of how long
the full permitting process may take. The metrics outline target timeframes
for specific actions, such as reviewing resubmissionsand scheduling
inspections, but they do not provide the average number of resubmissions
or inspections. The Office of the Fire Marshal presents nine different metrics
on their website, including engineering plan review metrics, fire and
sprinkler metrics and acceptance testing metrics. However, these metrics
lack a consistent look and feel, and no accompanying explanations are
provided to help the public – and especially restaurant owners – interpret
how they relate to expected or actual processing times. Per conversations
with the Office of the Fire Marshal, they are collaborating with LDS to
develop comparable metrics that also will include project estimations.The
Health Department does not publish metrics on the County’s website.
Applicants can also obtain assistance through the Permitting and
Customer Support Center, which provides in-person, virtual, phone, and
email assistance with PLUS, applications, inspections, permit status, zoning
and code questions, and payments. Engineer of the Day and Planner of the
Day services associated with the Center provide additional technical
assistance. LDS staff also offer an online form to request a Pre/ Post
Building and Site Submission Conference.
The Department of Economic Initiatives (DEI) also provides small
businesses with technical assistance, training, and connections to outside
support organizations through their CORE program, while the County’s
Economic Development Authority works to bring large companies,
8 | P a g e
international firms, and high-growth industries to Fairfax County, helping
them locate office space, enter the U.S. market, connect to venture capital,
and navigate regulatory processes.
In addition to County resources, many applicants also rely on external
resources for guidance to navigate the permitting process. Those resources
may include architects, engineers, land use consultants, or other
professionals to prepare applications, plans and coordinate with the
County.
Additional Resources for Targetedor Expedited Support
Fairfax County offers several programs that may help eligible applicants
navigate or accelerate the permitting process. Tenant Support Services
(TSS), a pilot launched in April 2026, provides small-business tenants with a
single point of contact, early zoning and code guidance, coordinated
assistance, and expedited building permit review for eligible projects. So far,
25 businesses have requested participation, with 23 deemed eligible,
including one café. However, most restaurants that require a commercial
kitchen hood typically fall under additionalregulatory requirements, such as
Health Department permitting and enhanced fire code review, that extend
beyond the support TSS currently provides. The Project Management
Program provides targeted or long-term assistance to help applicants
navigate complex projects and resolve permitting issues.
For applicants seeking faster plan review, the Expedited Building Plan
Review (Peer Review) Program allows applicants—including restaurant
projects—to use County-certified private-sector reviewers. The County
prioritizes plans submitted by certified reviewers, with review times
generally targeted at approximately half of standard review times. Applicants
pay the peer reviewer directly. Fast Track Build Plan Reviewis available for
certain non-complex commercial projects but generally excludes
restaurants with commercial kitchens.
Permit expediters are private professionals who may assist with
applications, agency coordination, and resubmissions but have no official
affiliation with the County, and applicants pay permit expediters directly.
Overall, the County provides numerous resources and assistance options,
but they vary in applicability to restaurants, are not centrally located, are
largely not industry specific (such as the Restaurant Industry) and do not
provide a single source of guidance covering the full, multi-agency
restaurant permitting process.
OFPA obtained PLUS data from LDS, the Office of the Fire Marshal, and the
Health Department. We obtained this data to explore the timeliness and
Data Analysis
9 | P a g e
efficiency of the permitting process for food establishments.PLUS records
permit applications in separate modules, including Building, Environmental
Health, and Fire. Although applicants submit multiple permit applications
through PLUS for one process (such as opening a restaurant), the system
does not provide a universal identifier linking records across modules. As a
result, data from Health, LDS and the Office of the Fire Marshalfor the same
restaurant may appear under different business names or address formats
in the different modules. Connecting records across agencies required
significant manual review.
Restaurant Permitting Analysis
As of July 2026, Fairfax County had approximately 3,183 operating food
establishments. About 2,500 are included in the four categories OFPA
included in our analysis: full-service restaurants, carry-out establishments,
bakeries, and fast-food establishments (See Appendix 3 for a list of all
categories). Since the beginning of FY24, the Health Department has issued
841 food establishment permits for these types of businesses(about 280
per year). (See Appendix 6 for permits issued in each district since FY24.)
These permits include both new establishments (40%) and changes in
ownership (60%). In that same time period, approximately 390 food
establishments (out of 841) required a building permit for renovations (ALT-
C) or a new build (BLD-C), the vast majority of which were ALT-Cs.
OFPA sought to use the population of 841 food establishments to examine
how long it takes to open a restaurantstarting with the food establishment
application or building permit (whichever was submitted first by the
applicant) through opening day, what contributes to the duration, and what
the impact is on the food establishments.However, as noted above, PLUS
records cannot be easily linked across the agencies’ modules, so OFPA
could not reliably reconstruct the complete permitting timeline for all 841
food establishments. As a result, we selected a non-statistical sample of 34
food establishments for detailed analysis. The sample included both new
establishments and changes in ownership, as well as restaurants that did
and did not require renovations(ALT-C building applications). New builds
(BLD-C applications) for food establishments are less common in Fairfax
County, and there were no BLD-C applications in the sample of 34 food
establishments. See Appendix 1 - Data Integration and Sampling
Methodology.
It is important to note that the analysis measures the period after the
applicant begins interacting with the County(as shown in the graphic on
page 4). It does not include time spent selecting a location, designing the
project, securing financing, or other activities that occur before an applicant
begins the application process in PLUS. In addition, restaurants do not
Of the food
establishment
permits issued since
the beginning of
FY24, 99 have since
closed.
10 | P a g e
necessarily enter the permitting process at the same point or follow the
same sequence of steps.
We sought to answer three questions in our analysis:
1. How long does it take to open a restaurant in Fairfax County?
2. What drives the length of the permitting time frames?
3. What is the impact on restaurants and other food establishments?
1. How long does it take to open a restaurant inFairfax County?
Opening a restaurant typically requires multiple applications to and
approvals from several County agencies. For the restaurants in OFPA's
sample, the process generally involved a combination of applications,
reviews and inspections from LDS, the Health Department, and the Office of
the Fire Marshal.
OFPA calculated the overall duration for each restaurant in our sample to
calculate the time from the start of the first record in PLUS (related to the
restaurant’splans to open) to the last identifiable record associated with the
restaurant prior to opening. Based on the sample, the median time was 315
days, or approximately 10.5 months, for new establishments. For changes
in ownership, the median was 110 days, or approximately 3.7 months.
Duration (in Calendar Days) to Open a Restaurant (in PLUS)
Note: OFPA used median duration (calendar days) because processing times vary widely
across restaurants, often due to differences in project scope and complexity. Median is less
influenced by outliers than average.
These figures represent the total permitting period captured in PLUS (across
multiple applications needed to open a restaurant)and should not be
interpreted as the total time to open a restaurant(such as time by the
applicant to design plans or select a site). Furthermore, because they are
median values drawn from a non-statistical sample, they provide a general
indication of typical permitting process timelines.
2. What drives the length of the permitting time frames?
The overall time frames above reflect the processing time of multiple
applications, reviews, corrections, resubmissions, construction and
inspections, and the duration is driven by both the County and the food
establishment. The number and type of steps vary depending on the
complexity of the project and the quality of the application and submissions.
11 | P a g e
In this section, we review permitting durations by record type, with particular
attention to the permitting process duration associated with Commercial
Addition/Alteration (ALT-C) records. We also examine rounds of review and
inspections, and when possible, the time in the County’s control compared
to the applicant’s control, to better understand possible drivers behind the
timelines.
Record Types and Duration
In the 34 restaurants sampled, OFPA identified 15 different types of records
used in the permitting process (See Appendix 2 – Record/Application
Types for Sampled Restaurants). In PLUS, record types correspond to the
applications an applicant submits. For example, a Food Establishment
Application submitted in PLUS is considered a unique/distinct record type.
Not every restaurant required every record type. Most restaurants(20 of 34)
in our sample had 1-4 unique record types, while the remaining restaurants
were split between 5-8 unique record types (7 of 34 restaurants) and 9-12
unique record types (7 of 34 restaurants).
The table below provides the record (application) types with the median time
to complete each record type ranging from 1 day to 288 days, illustrating the
wide variation in the time to complete for the different types of records. The
record with the longest median time is the ALT-C, or Commercial
Addition/Alteration record, with a median of 288 days (which usually closes
after the final inspection). The time reflects the total duration the record
remained in process and includes periods when it was with the County and
the applicant; it does not distinguish how long the record spent with each
party.
Duration (in Calendar Days) by Record Type
Note: Occupancy Inspection record type refers to the pre-occupancy inspection conducted
by the Office of the Fire Marshal.
12 | P a g e
Since the ALT-C record had the longest median days and maximum days,
OFPA further explored the restaurants in our sample with ALT-C records. We
assigned generic names to these restaurants to protect their identities.
The table below shows the 14 food establishments in our sample with ALT-C
records and illustrates the duration of each of four phases of the ALT-C
application: Application Submittal, Plan Review, Construction and
Construction/Inspection. The Construction phase spans from the
completion of plan review to the completion of the first regulated milestone
requiring an inspection, which varies based on the approved scope of work.
Once the inspection is passed, the applicant proceeds with the
Construction/Inspection phase because additional inspections occur as
construction progresses until project completion. Among the four phases,
Construction/Inspection had the longest average duration at 148 days (47%
of all phase time), followed by Plan Review at 98 days (31% of all phase
time), Construction at 50 days, and Application Submittal at 16 days. This
indicates that most of the elapsed time for the 14 food establishments
occurred during the Plan Review and Construction/Inspection phases.
Permitting Process Duration (in Calendar Days)
for 14 Food Establishments with ALT-C Records
Note: 15 of 34 food establishments sampled had 17 Commercial Addition/Alteration (ALT-C)
records. We excluded 3 ALT-C records because they were for demolition-only work (2 records)
or stud-only work (1 record), resulting in 14 food establishments. OFPA used ALT-C workflow
records to calculate the total days for the ALT-C Application Submittal and Plan Review
phases, as well as all relevant records for each food establishment to calculate the
Construction (plan review approval to first inspection) and Construction/Inspection phases.
Total days exclude Certificate of Occupancy (Non-RUP) records because Non-RUP
processing may overlap with other permitting activities and therefore does not represent an
additional sequential phase of the process.
13 | P a g e
Applications, Plan Reviews and Inspections Overview
In addition to the multiple (and different) types of applications the County
may require before opening a restaurant, the reviews and inspections for
each application also varied among restaurants. During the application
review process, permit technicians review applications for completeness
and return incomplete applications to the applicant for correction and
resubmission. During the plan review process, applicants submit plans that
multiple County agencies and disciplinesreview, often concurrently. When
reviewers determine that any portion of the plans do not meet applicable
code requirements, reviewers return the plans to the applicant for
correction and resubmission. This creates a cycle of submission, review,
correction, resubmission, and review that may occur multiple times
before the County approves the plans. Likewise, during inspections, the
applicant may fail an inspection and need to make changes and then
undergo a follow-up inspection. See graphic below:
Multiple Rounds of Submissions, Plan Reviews and Inspections
Note: Inspections happen throughout the construction phase as different stages of work are
completed.
Plan Reviews
OFPA examined the number of rounds of plan reviews for the 14 restaurants
with ALT-Cs in the selected sample. We first looked at reviews for
restaurants applying for permits for an interior renovation (a more complex
application) and noted how many different types of reviews the County
required for the ALT-C application, as well as how many resubmissions the
County required (see graphic below). See Appendix 4 for a list of all review
types associated with the ALT-C record types in our sample of restaurants.
For the 14 ALT-C applications, OFPA calculated the number of distinct
reviews required (for example, ElectricalReview, Fire Marshal Review) and
also the number of plan submissions (initial submission) and resubmissions
(where the County had comments as a result of a review and sent the plans
back to the restaurant for correction). We noted that ALT-C applications
included between 6-9 types of plan reviews, depending on the project
complexity and the disciplines involved. Additionally, applicants typically
14 | P a g e
required between 2-6 submissions/resubmissions before the County
approved the application and issued the ALT-C permit allowing work to
begin. The total length of time for the plan reviews was between 46-169
calendar days (or 1.5 to 5.6 months).
Reviews and Submissions/Resubmissions (in Calendar Days)
for 14 Food Establishments with ALT-C Records
Next, OFPA compared the average number of days of each round of
submissions by Agency. In our sample data, the Health Department had the
highest average number of days for the first review at 18, followed by LDS at
15. Generally, first reviews takelonger than subsequent reviews, but the
cumulative effect of multiple rounds of reviews can have a significant
impact on the overall timeline, even when agencies are meeting their
individual review time metrics.
Average Calendar Days to Review Submissions Per Round Per Agency
for 14 Food Establishments with ALT-C Records
15 | P a g e
In addition, we reviewed the number of different reviewers per type of review
associated with an ALT-C (such as Electrical Review, Mechanical Review or
Fire Marshal Review). In other words, when an applicant had to submit and
resubmit multiple times, we explored whether different reviewers were
assigned to look at that submission each time it was resubmitted. We
examined this because some restaurants had expressed concern with
different reviewers in subsequent review rounds who provided conflicting
information compared to a previous reviewer’s comments.For the 68
reviews associated with one or more resubmissions across our sample of 14
restaurants, the vast majority maintained the same reviewer on those
multiple reviews. In the sample tested, 65 of 68 (96%) reviews were
performed by the same reviewers during subsequent resubmissions of the
same review type.
Inspections
OFPA also examined inspections and noted the number of inspections
required for the food establishments in our sample (See Appendix 4 for a list
of inspections). We looked at both required minimum number of inspections
(such as Health Inspection, Mechanical Inspection) compared to the total
number of inspections (including failed inspections) that occurred.
Number of Inspections and Re-inspections
for 14 Food Establishments with ALT-C Records
Note: Inspection types varied by project and included building, mechanical, plumbing,
electrical, fire protection, and occupancy inspections, such as framing, concealment,
ductwork, gas, fire alarm, sprinkler, hood suppression, and pre-occupancy/final inspections.
16 | P a g e
For the 14 sampled restaurants, OFPA calculated the number of distinct
inspections required (based on various regulated construction milestones)
and also the number of inspections and re-inspections (passes and fails).
We noted that the sampled restaurants had between 3-24 types of
inspections, and there were 6-35 inspections/re-inspections until the
County approved the construction workfor each restaurant in the sample.
The duration of the construction/inspection phase depends on the pace of
construction and contractor readiness for each inspection. In addition,
scheduling time is shared between the County and the applicant based on
the County’s available inspection dates and the applicant’s preferred dates.
The total length of time for construction and inspections was between 56-
374 calendar days (or 1.9 to 12.5 months).
Similar to the reviewers, we also examined the number of distinct inspectors
for the same type of inspection. For the 124 application records associated
with the 14 sampled restaurants, a number of these records (such as an ALT-
C) required different types of inspections. We wanted to understand how
many of the same type of inspection (such as Wall Concealment Inspection
on the Electrical Record) had multiple inspectors, since several restaurant
owners commented on the frustrations with multiple inspectors for the
same inspection. Thirteen records out of 124 (10%) were assigned different
inspectors for subsequent rounds of the same inspection.For example, one
Mechanical Permit Application for a single restaurant required a single
inspection, but each time the inspection failed, a different inspector
performed the subsequent inspection.
Time with County Compared to Time with Applicant- ALT-C Application
Submittal and Plan Review
For the 14 restaurants in the sample with an associated Commercial
Addition/Alteration (ALT-C) application, OFPA was able to analyze the time
spent by the applicant and County during the application submittal phase
and the plan review phase. We were unable to include the construction and
inspection phases in this analysis because the dates recorded in PLUS do
not indicate whether the durations were applicant-owned (performing
construction) or county-owned (such as scheduling).
As noted above, the application submission portion of the process, similar
to the review and inspection portions, may involve multiple rounds between
the applicant and County before the application is considered complete and
can be reviewed by the County. Permit technicians review applications for
completeness and return incomplete applications to the applicant for
correction and resubmission. Once the permit technician deems the
Inspector
Continuity: LDS,
Office of the Fire
Marshal and the
Health Department
aim to assign the
same inspector
across multiple
rounds for the same
project, while
allowing flexibility to
use another
inspector when
needed for efficiency
(for example, when
the assigned
inspector is on
leave).
17 | P a g e
application complete, the County begins the review phase for the
application.
The graphic below is for one restaurant in our sampleto illustrate the
back-and-forth between the applicant and the County for the application
submittal and plan review phases. The visualization presents the
application submissions and plan reviews (of which there were three for this
restaurant) and provides the number of days associated with each activity
for each party, offering a depiction of the iterative interactions.
Timeline for Application Submittal and Plan Review –
Time with County versus Time with Applicant for Food Establishment 34
Note: Agency-level review days may not sum to the total County review days shown in the bar
because agencies perform concurrent reviews or activities not attributed to a specific agency
that may include administrative processing, routing, coordination, and otherworkflow
activities.
The next two graphics summarize the division of time between the County
(shown in blue) and the applicant (shown in gray) for both the application
submittal and plan review phases for the 14 sampled food establishments
with ALT-C applications. Unlike the earlier graphic created for one
restaurant, the visuals below do not depict the iterative, back-and-forth
interactions between the County and the applicant. Instead, they aggregate
all County time and all applicant time across the sample to provide a
high-level view of how responsibility for each phase is distributed.
Across the application submittal phase, the County averaged 4 days, while
applicants averaged 12 days. During the plan review phase, across all
rounds of reviews, the County’s average total time was 52 days, and
applicants averaged 45 days. (Note that this time does not include any time
18 | P a g e
the applicant spent with designers, architects or engineers before beginning
the application process in PLUS.) These combined durations highlight the
shared responsibility for overall timeline length, as both County processing
time and applicant response time contribute meaningfully to the pace of
each phase.
Application Submittal – Time with County versus Time with Applicant
for 14 Food Establishments with ALT-C Records
Plan Review – Time with County versus Time with Applicant
for 14 Food Establishments with ALT-C Records
19 | P a g e
County staff emphasized that when restaurants hire experienced design
professionals, especially those familiar with Fairfax County requirements
and restaurant design, the likelihood of moving quickly through application
submission and plan review increases greatly.
OFPA could not perform the same analysis for construction and inspections
because the available data does not consistently identify when an
inspection-related item was awaiting action by the County versus the
applicant.
Fairfax County Plan Review Goals
The bar graphs above illustrate the total time ALT-C permit records spent
with both the County and the applicant. We also analyzed review times by
round and by agency to understand how these durations compare to the
metrics for each reviewing entity (see bar graph on page14). Currently, LDS,
the Health Department, and the Office of the Fire Marshal each establish
targets for review timelines, with expectations varying depending on whether
the review is an initial submission or a subsequent resubmission.
For example, LDS has a goal of 39 business days or less for the first plan
review (for all commercial building permits that are not fast-tracked), and 15
days for each subsequent submission. However, LDS does not provide
information on how many resubmissions applicants typically experience,
making it difficult for applicants to estimate the full timeline for plan reviews
and permitting. See Appendix 5 for an example of the LDS metrics.
Environmental Health does not provide metrics or goals on the County’s
website, but they shared with OFPA that their internal review goal is to
complete a plan review within 10-15 business days after fee payment.The
Office of the Fire Marshal posts their weekly and monthly plan review
averages for Class 4 or greater Architectural Reviews, which range from 30-
34 days per review. Sprinkler and Fire Alarm reviews have a slightly shorter
average review time. Overall, LDS plan reviews in our sample generally met
or exceeded their goals, while the Health Department’s average in our
sample was just slightly over the goal for the first round, and the Office of the
Fire Marshal also met or exceeded their metrics per round.
Taken together, our analysis illustrates the complexity of the restaurant
permitting process. An applicant seeking to open a new restaurant,
particularly one that involves renovations, may need to submit multiple
applications, move through several rounds of review, work with numerous
reviewers and inspectors, and repeatedly interact with the County before
they can open. Our analysis of the full permitting timeline for the sampled
food establishments shows that even when individual agencies generally
meet their established review-time targets, the cumulative sequence of
steps, handoffs and interdependencies can still result in substantial overall
The LDS 2025
Annual Report
indicates that in
FY25, Commercial
Alterations (ALT-Cs)
took 100 days on
average to issue the
permit (to begin
construction), with
an average of 3 plan
submissions.
20 | P a g e
durations. Currently, the County does not provide restaurant applicants
with readily accessible information about the total amount of time they
should expect to spend navigating the end-to-end process. Applicants are
left trying to calculate the full timeline by interpreting separate processing
metrics from LDS and the Office of the Fire Marshal, while the Health
Department does not publish processing time metrics.
3. What is the impact on restaurants and other food establishments?
The data does not indicate that every restaurant experiences a lengthy or
identical permitting process. Rather, it demonstrates that the process varies
substantially depending on the project and can involve a significant number
of applications, reviews, revisions, and inspections, all of which take time.
Even when agencies meet their individual goals forplan review days, the
cumulative effect of all the rounds of reviews and inspections is significant
and can be costly to the applicant. We explore the impact of costs and
delays in the section Economic Impact of Permitting Process for
Restaurants (page 24).
The analysis provides context for evaluating permitting effectiveness, not
only in terms of how quickly individual reviews are completed by County
agencies, but also how efficiently and effectively the full process moves a
restaurant toward opening throughmultiple agencies and applications.This
length of time (315 days for a new establishment to open and 110 days for a
change of ownership) was a primary concern voiced by restaurants in our
interviews; the results of which are in the following section.
OFPA interviewed 11 restaurant owners and restaurant groups that recently
opened, or were in the process of opening, restaurants in Fairfax County to
better understand their experiences navigating the County’s permitting
process. The interviewees included both first-time and experienced
restaurant operators, as well as small, independent restaurants and larger
restaurant groups.
Restaurant owners were very appreciative that the County was studying the
permitting process and seeking direct input from businesses. Overall, 60
percent of interviewees had a negative view of their permitting experience,
while 40 percent had a neutral view. Although experiences varied, several
recurring themes emerged.
1. Lengthy and Unpredictable Timelines
The most frequently cited concern was the length and unpredictability of the
permitting process. Interviewees reported typical timelines of approximately
four to seven months, with some projects taking substantially longer. One
Restaurant Interviews
21 | P a g e
owner who anticipated a three-month process ultimately waited
approximately seven months. Lengthy and unpredictable timelines were an
overarching concern because they often resulted from the other challenges
identified below, and in turn, drove up the overall cost of opening a
restaurant.
Indeed, these delays can have significant financial consequences. Two
owners had negotiated leases with six months of free rent while permits
were being obtained, but delays resulted in rent payments before their
restaurants could open. One first-time owner reported taking out a loan to
cover rent during the delay. Another estimated that unpredictable timelines
and delays resulted in approximately $45,000 in additional rent.
Owners attributed delays to multiple factors, including repeated review and
inspection cycles, changing or inconsistent comments, unclear
requirements and staffing availability. Several noted that the process was
particularly difficult to predict because the County would often send back
plans for resubmission without reviewing the entire plan, which added
multiple additional rounds of plan reviews.
2. Inconsistency Across Reviews and Inspections
Inconsistent direction from reviewers and inspectors was one of the most
significant concerns raised by interviewees. Several owners described
receiving new comments or requirements from different reviewers or
inspectors after addressing issues identified in earlier rounds. In some
cases, owners perceived the comments as contradictory or believed an
inspector was applying a different interpretation than the one reflected in
the approved plans.
For restaurant owners, these inconsistencies translate directly into
additional time and cost. One experienced restaurateur reported that
resolving a reviewer’s concern about the location of a sink—despite the
owner’s understanding that the location complied with code—delayed the
project by approximately three months because the County’s different
inspectors gave conflicting feedback on the sink location.
Several interviewees suggested assigning a single reviewer or County point
of contact to a project, particularly for smaller businesses. Others
recommended that the County conduct a more comprehensive review
before returning comments to an applicant, rather than identifying only a
portion of the issues in each round. They believed this would reduce the
number of review cycles and provide greater predictability on timelines.
22 | P a g e
3. Lack of Clear Guidance and Support for First-Time/Small Restaurant
Owners
Interviewees also noted that the permitting process was difficult to
understand, particularly for first-time business owners. None of the
interviewees were aware of the County’s 2022 Restaurant Guide, and only
one was aware of the County’s expedited peer-review option. Two additional
owners said they would have considered using peer review had they known
about it.
Several owners said they wanted clearer, restaurant-specific guidance on
what would be required for their particular type of establishment. One first-
time owner said the permitting process was the “most difficult and most
stressful” part of opening his business and encouraged the County to
consider the process from the perspective of a first-time business owner.
Owners also recalled that the County had previously provided more
comprehensive process information for commercial construction and
suggested that a similar, user-friendly roadmap for restaurant openings
would help applicants understand requirements, sequencing, and expected
timelines.
Several owners emphasized that both the County and applicants have a role
in keeping projects moving. Some acknowledged that applicants,
contractors, and design professionals may not fully understand County
requirements or may incorrectly attribute delays to the County when the
underlying issue is incomplete or incorrect work. Clearer guidance could
help reduce this confusion and allow both sides to identify responsibility for
delays more quickly.
4. Communication Challenges, Customer Service, and PLUS
Interviewees reported mixed experiences with County communication.
Several had difficulties reaching responsive staff at times, particularly when
staff were unavailable due to vacations or holidays. Many also said that key
aspects of the process, including the potential for multiple review cycles
and the time required to address comments, were not clearly
communicated at the outset.
Several owners described PLUS as cumbersome or difficult to navigate,
although others reported that it worked adequately. None of the
interviewees we asked were familiar with the County’s customer feedback
surveys, although most indicated they would be willing to provide feedback
if they were aware of the opportunity.
The interviews also revealed differences in how applicants experienced
interactions with County staff. Some owners described certain interactions
23 | P a g e
with LDS and fire inspectors as adversarial or expressed concern that raising
questions about an inspection decision could negatively affect their project.
In contrast, several owners specifically praised Health Department staff as
responsive, fair, and willing to work collaboratively to resolve issues. One
owner cited an instance in which County staff participated in a call with the
tenant’s landlord that helped resolve an issue and avoid additional delay.
5. Fees and Costs Associated with Delays
Fees
Larger restaurant groups generally considered County fees reasonable,
while newer and smaller restaurants were more likely to view fees as a
financial burden. Some interviewees specifically raised concerns about
resubmission fees and questioned whether those fees provide sufficient
value when reviews identify only a portion of the issues that ultimately need
to be addressed.
Several owners appreciated having the expedited services, like peer review
offered by the County, but others viewed the cost of expedited services as a
barrier for smaller businesses. One owner cited approximately $30,000 in
third-party expedited review costs.
Financial Impact of Delays
The financial consequences described by interviewees were substantial.
Owners cited additional rent, architectural and contractor costs, repeated
construction changes, expedited review fees, employee training costs, and
lost revenue associated with delayedopenings. One owner estimated that a
delayed opening could result in $70,000 to $100,000 in weekly losses for one
of his smaller restaurants and added that if staff had been hired, the losses
would increase an additional 50%.
While individual estimates varied and were not independently verified by
OFPA, the interviews demonstrate how even small delays in a permitting
process can become significant financial costs for businesses. As one
interviewee summarized, time ultimately becomes cost.In the next section
on Economic Impact, OFPA explores these costs further.
6. Collaboration as a Goal
Despite their frustrations, several restaurant owners expressed a broader
desire for a more collaborative relationship with the County. Some
suggested that the County should clarify whether attracting and supporting
new businesses, particularly restaurants, is a priority and, if so, work in
partnership with businesses to help them navigate the regulatory process
successfully. Another restaurant owner expressed frustrationbecause the
24 | P a g e
process did not feel collaborative and noted that he feared retaliation if he
pushed back on an inspection’s resultsthat he felt were incorrect.
Interviewees generally wanted the County and applicants to have a shared
goal of meeting requirements while moving projects forward as efficiently
and predictably as possible. From the owners’ perspective, clearer
expectations, duration transparency, consistent application of
requirements, and a designated, single point of contact could help establish
that partnership while maintaining the County’s regulatory responsibilities.
Overall, the interviews indicate that restaurant owners are not necessarily
seeking fewer requirements; they are seeking a process that is clearer, more
consistent, more predictable, and more collaborative. At the same time,
interviews with County staff indicated that sometimes applicants and their
contractors can also contribute to delays when requirements are
misunderstood, applications are incomplete, or work does not conform to
approved plans. Improving the process therefore requires attention to both
sides of the interaction.
Opening a food establishment is a major financial undertaking, requiring
substantial upfront investment in design and construction, permitting fees,
equipment purchases, and pre-opening staffing. These costs are generally
necessary to prepare and operate a restaurant and are not incurred solely
because of the permitting process. However, the longer the permitting
process takes, the longer an applicant must carry these costs as they wait
for the restaurant to generate revenue. The following sections review both
the direct costs of permitting and the costs associated with delays in the
permitting process.
Direct Permitting Costs
OFPA analyzed the County fees associated with the permits and approvals
identified for the 34 restaurants in its sample. The total cost varied
considerably depending on the type and scope of the project. Restaurants
requiring renovations (such as an ALT-C) generally incurred more fees
because they required additional building, trade, fire, and other permits.
Across the sample, the median County permitting fees were $6,234 for new
establishments (ranging from $175 - $77,554) and $168 for changes in
ownership (ranging from $80 - $15,893). Fees included charges associated
with the various permits required, including the fees to resubmit an
application after the County sends it back to the applicant for corrections.
Economic Impact of
Permitting Process for
Restaurants
25 | P a g e
Median County Fees by Permit/Record Type
for 14 Food Establishments with ALT-C Records
The Cost of Permitting Delays
The economic impact of the permitting process is not limited to County fees.
While waiting for permits, approvals, or inspections, owners continue to
incur pre-opening costs without generating revenue. These can include rent,
financing costs, contractor and construction expenses, insurance, and labor
costs associated with hiring and training staff.
The financial impact of extended timelines and delays varies by project. A
delay may not create new costs in every instance, but it does extend the
time during which the owner is paying expenses without restaurant revenue.
As noted in the Interviews section, several owners reported substantial
impacts: one estimated losses of $70,000–$150,000 per week due to
delayed permitting, while another needed to take out loans when the
process extended beyond six months.
Permit-related delays also affect County revenue. Once a restaurant opens,
it begins generating meals tax revenue. Delayed openings postpone these
payments. For example, a restaurant generating $30,000 in taxable weekly
sales (industry average reported by QSR Pro) would generate approximately
$1,200 in weekly County meals tax revenue. A one-month delay would defer
about $4,800. If even half of the 280 new food establishments opening each
year experienced a one-month delay, the County would forgo an estimated
$672,000 in meals tax revenue, as well as amounts received through the
local option tax (the 1% local portion of Virgina’s sales tax).
Overall Economic Impact
The cost of permitting should be understood within the broader investment
required to open a restaurant. County permitting fees represent a small
Restaurant revenue
varies significantly
per restaurant.
While pizza chain
Papa John’s
averages $22,000 a
week in sales,
steakhouse chain
LongHorn
Steakhouse
averages $155,000
in average weekly
sales.
26 | P a g e
share of that investment. Unexpected delays in the permitting process can
add meaningful financial pressure because an applicant may need to
continue carrying rent, financing, professional fees, construction expenses,
and labor costs until the business can open and begin generating revenue.
Applicants also may underestimate the amount of time needed for the
phases of permitting, as the County does not provide guidelines or
estimates for the typical duration of the end-to-end process. When a
restaurant underestimates the time required or experiences delays in the
permitting process, owners need to carry pre-opening costs for longer, and
additionally, the County’s meal tax revenueis postponed.
Over the years, LDS has worked to improve the parts of the permitting
process that they control. The Permitting Resourcesand Options for
Additional Support sections earlier in this report highlight a few of the
resources and processes available to applicants that LDS has created to
improve the process.
In addition to these resources, LDS has made other internal changes to
improve the process. The recent Economic Competitiveness Strategic
Roadmap, put together by the County’s Economic Competitiveness Task
Force, includes multiple agenciesfocused on addressing the economic
challenges faced by businesses in the County.The Roadmap includes
several initiatives to improve the permitting process. Although it does not
identify restaurant permitting as a standalone initiative, actions under
Strategic Area 3 are intended to streamline commercial development and
can assist applicants navigating restaurant‑related permits, including those
involving small‑business tenant spaces, commercial alterations, new
construction, building permits, and fire review.Through initiatives 3.7 - 3.9,
LDS aims to provide clearer project-based dashboards, dedicated
assistance for qualifying small-business and tenant projects through the
Tenant Support Services Pilot, and tiered building-plan review pathways
based on project complexity.Together, these efforts are intended to improve
timeline transparency, reduce unnecessary review steps and resubmissions,
and provide applicants with better access to project status and milestones.
Other planned initiatives focus on identifying issues earlier and reducing
delays during review and construction. These include multidisciplinary pre-
submission meetings, more opportunities for parallel review, approval of
certain minor code-compliant field changes without formal plan revisions,
and publication of common submission errors. The County is also working
on a two-phased digital modernization and automation initiative. The first
phase focuses on automating PLUS workflows, and the second phase would
work with the Department of Information Technology (DIT)to pilot AI-
enabled plan review tools. One last initiative aims to provide eligible
Existing Efforts to
Improve the
Permitting Process
27 | P a g e
projects with a single point of contact to provide guidance during the
process. These improvements could reduce conflicting guidance, correction
cycles, manual handoffs, and administrative delays, making the process
more predictable and efficient for restaurant applicants.
Although these initiatives are not limited to restaurants, they could improve
several permitting and review challenges commonly encountered by
restaurants opening in the County.
Additionally, the LDS Plan Review Quality Control Programregularly
reviews a selection of plan review comments to ensure they meet guidelines
and are clear, specific, actionable, referenced to applicable code or
policies, and are not repetitive.
Lastly, back in 2018, LDS began a customer service survey option for
customers. This process evolved over time and offers a way for customers
LDS customers to provide feedback on application submission, plan
uploading, building inspections and the Customer Experience Team.
However, OFPA learned that due to some technical glitches, the surveys
have not been easy to access for customers, leading to a sharp decline in
responses over the past few years. LDS provided us with customer survey
data dating back to 2020/2021, but most surveys have had no responses
since November 2024. Also, during our interviews, restaurant owners were
not familiar with the option to provide feedback but expressed interest in
having that option.
Permitting challenges are not unique to Fairfax County. To provide context
for the County’s permitting experience, we reviewed practices in nearby
jurisdictions, including permitting durations. This comparison is important
not only to identify relevant benchmarks, but also because restaurants and
restaurant groups have choices about where to locate their businesses.
Understanding how Fairfax County’s process compares with those of
neighboring jurisdictions can help the County assess its competitiveness.
The table below summarizes available permitting metrics for nearby
jurisdictions.
28 | P a g e
Permitting Timeline Jurisdiction Comparison:
Renovations and New Builds
Note: Most days listed above are business days, not calendar days, unless otherwise noted.
Prince William County did not specify calendar or business days.
We also reviewed leading practices and trends from jurisdictions across the
United States to identify approaches that may offer opportunities for Fairfax
County to make its permitting process more predictable, accessible,
transparent, and efficient.
Los Angeles, CA: Restaurant and Small Business Express Programand
Restaurant Beverage Program
The Los Angeles Department of Building and Safety (LADBS) Restaurant &
Small Business Express Program (RSBEP)is a free case-management
program designed to help restaurants and small businesses navigate the
permitting, plan review, inspection, and approval process. Restaurants,
bars, and outdoor dining projects can participate regardless of project
valuation, while other eligible small businesses generally must have
construction projects valued below $1 million.
Leading Practices to
Streamline Restaurant
Permitting
29 | P a g e
A key feature of the program is the assignment of a dedicated Case Manager
who serves as a single point of contact throughout the development
process. Case Managers can coordinate meetings with relevant agencies
during design, help resolve conflicts and monitor plan review during
permitting, coordinate inspections during construction, and assist with final
approvals and Certificates of Occupancy. The program can be accessed at
any stage of a project, allowing businesses to receive assistance before
plans are submitted or after permitting or construction has already begun.
City of Santa Rosa, CA: Business Concierge Program
The City of Santa Rosa’s Business Concierge Programprovides one-on-one
assistance to businesses navigating planning, permitting, licensing, and
construction. A Small Business Ombudsman serves as a central point of
contact for businesses by coordinating with City departments and providing
businesses with technical and financial resources and helping resolve
issues that may slow projects. Notably, Santa Rosa reported that the
program supported more than 150 entrepreneurs and small-business
owners and facilitated more than 250 service touchpoints from February
through August 2025, including assistance with permitting, licensing, and
other business needs.
The program does not replace the normal permitting process; instead, it
helps businesses navigate and coordinate that process more efficiently.
Santa Rosa’s Business Concierge Program is part of the city’s One-Stop-
Shop, which offers business owners a single, streamlined access point for
permits, licensing, and development support. Designed to “eliminate
guesswork and accelerate progress”, the One-Stop-Shop functions as both a
physical hub and an online resource that business owners, entrepreneurs
and developers can use to advance their projects.
San José, CA: Streamlined Restaurant Program (SRP) and Small
Business Ally Program
The City of San José’sStreamlined Restaurant Program (SRP)expedites
permitting for qualifying restaurant and food/beverage tenant
improvements, reducing review times toas little as 1–2 months compared
with the typical 4–6 months, with no additional expedited-review charge.
Projects generally must be3,000 square feet or less, have kitchens of1,000
square feet or less, include no more thanfour new kitchen hoods, and
involve no new construction, two-story spaces, mezzanines, or full façade
rebuilds. The process includes pre-qualification, a 1.5-hour kickoff
meeting with City reviewers and the applicant’s architect, and an expedited
plan review to identify and resolve issues early.
30 | P a g e
The City’s Small Business Ally Programcomplements the SRP by providing
step-by-step assistance with permitting, inspections, zoning, building
codes, and other City requirements. Bilingual Small Business Allies help
businesses navigate requirements and connect with appropriate City
departments. From July 2023 through June 2024, the program assisted 2,977
entrepreneurs, including 112 food-related businesses that received
streamlined assistance through the SRP . The program also conducts
multilingual outreach, workshops, and training, with Vietnamese and
Spanish translation support to help business owners understand regulatory
requirements.
San José also launched two initiatives to reduce permitting delays. The Best
Prepared Designer Programallows experienced design professionals and
contractors with a strong record of submitting code-compliant plans to
receive permits for eligible smaller projects within about five days,
compared with two to three months. By placing greater responsibility for
code compliance on qualified professionals, the program can also reduce
staff plan-review workload. The Self-Start Building Permits with Plan
Review Program allows applicants to upload plans directly and track permit
status and responsibility for next steps, reducing intake delays and
improving transparency.
Chicago, IL: Department of Business Affairs and Consumer Protection
(BACP) Neighborhood Business Development Centers (NBDCs)
In 2019, Chicago’s Department of Business Affairs and Consumer Protection
(BACP) aimed to expand its one-stop-shop model beyond City Hall and
make business assistance more accessible in Chicago neighborhoods
through a network of Neighborhood Business Development Centers
(NBDCs). The initiative was built on BACP’s Small Business Center, which
already served as a centralized location for business licensing, public-way
permits, and other resources. NBDCs extend the one-stop shop model into
neighborhoods by funding and partnering with local nonprofit organizations,
chambers of commerce, and community development organizations that
already work with area businesses.
NBDCs do not replace the City departments that issue licenses, permits, or
approvals. Instead of requiring entrepreneurs to rely solely on City Hall,
businesses can visit an NBDC in their community for free, individualized
assistance with starting, operating, or expanding a business. BACP operates
the NBDC program through contracts with these local organizations,
including organizations designated as NBDC “Generalists” or “Specialists. ”
While jurisdictions across the United States are taking a variety of
approaches to streamline permitting, emerging technologies such as AI also
31 | P a g e
offer opportunities to further improve the efficiency and consistency of the
process.
AI Tools Utilized in Leading Practices
AI tools are increasingly being used at the front end of the restaurant
permitting process to help restaurant applicants understand jurisdiction-
specific requirements and submit applications. Jacksonville, Florida, uses
an AI tool that screens permit materials before they reach a reviewer. The
tool analyzes review comments and identifies potential issues, helping staff
complete reviews more efficiently. Jacksonville reported that commercial
permit turnaround times decreased from 30 to 13 days, reducing delays
associated with construction and opening.
Austin, Texas, uses an AI-powered platform to compare building plans with
digitized planning, zoning, and building code requirements. The platform
provides immediate feedback on potential compliance issues, allowing
applicants to correct problems earlier and reducing the need for multiple
revisions.
AI plan review tools are also being used in other jurisdictions to scan
building plans for possible code violations that are later confirmed by staff.
These AI tools can help improve submission quality, reduce coordination
errors, and shorten review periods, with reported reductions of 80 percent in
peer-review time and 70 percent in coordination errors.
Key Takeaways from Other Jurisdictions and Leading Practices
Across the jurisdictions reviewed, the strongest approaches do not
necessarily eliminate regulatory requirements or require a complete
redesign of the permitting system. Instead, they focus on making existing
processes simpler to navigate, better coordinated, and more responsive to
the complexity of individual projects.
These approaches are consistent with broader recommendations for
improving business permitting. The Institute for Justice, for example,
analyzed barriers to starting a business across 20 cities and recommends
that local jurisdictions streamline rules for small businesses to “make it
cheaper, make it faster, and make it simpler.” Similarly, Virginia’s Permit
Transparency initiativeillustrates the value of making permitting information
easier for applicants to understand and track.In general, where possible,
online permitting systems (and supporting resources) should be intuitive
and guide applicants through the process rather than require them to
interpret the County’s processes and organizational structure and
determine the appropriate steps themselves.
32 | P a g e
Leading Practices Summary
Collectively, the research points to several practical principles for improving
restaurant permitting:
• Make the process easier to navigate: Give applicants a clear entry
point and guidance across agencies.Provide applicants with a single
point of contact across agencies.
• Coordinate earlier: Identify missing information and potential
conflicts before formal review generates multiple correction cycles.
• Tailor review to project complexity: Provide simpler or expedited
pathways for lower-risk projects rather than applying the same
process to every restaurant.
• Make technology work for the applicant: Online systems should be
intuitive, transparent, and actively guide applicants through
requirements and next steps.
• Look beyond individual review times: Improving the overall
customer experience and reducing unnecessary handoffs and
review/inspection cycles may be as important as meeting individual
departmental targets.
33 | P a g e
Observations and Recommendations
Observation a nd Rec ommendatio n 1
Observation 1
Fragmented, Outdated Guidance and Limited Support Dedicated to Restaurants
Restaurants in Fairfax County face a complex, multi-agency approval process, with multiple
applications, inspections and permits, yet there is no comprehensive, easy-to-find, end-to-end
guidance available to help them navigate it. Business owners must independently piece together
requirements from various departments, including Health, Fire Marshal, Land Development
Services, Planning and Development, and Tax Administration, and navigate different modules in
PLUS for the different record types (applications). The County’s only consolidated resourcetailored
to restaurants, “Opening a Restaurant in Fairfax County,” is outdated (published in April 2022,
prior to the implementation of PLUS) and does not reflect current workflows, requirements, or
expected durations.
The County recognizes that permitting is complex and can be burdensome for businesses and
therefore offers a variety of programs and services to support business owners, including
restaurants. However, information about these programs and services is dispersed across multiple
County websites with no centralized location to clearly communicate to restaurant owners what is
available and what they may be eligible for at no additional cost. Additionally, some private-sector
services, such as County-certified peer reviewers and expeditors who are not certified by the
County, can help owners navigate complex requirements. However, these services come at a cost
and may be prohibitive for some businesses.
As a result, restaurant owners and entrepreneurs looking to open a restaurantmust navigate a
fragmented and decentralized information landscape, making it difficult to identify required steps,
applications, expected timelines and available support programs or services. Larger restaurant
groups often offset this complexity by hiring expeditors, certified peer reviewers, and specialized
consultants, allowing them to move through multi-agency requirements more efficiently. Applying a
OneFairfax equity lens highlights that outdated guidance and decentralized information may
disproportionately affect small and first-time businesses, leading to longer timelines and increased
costs for businesses that may be least able to absorb them. A common theme in our restaurant
interviews is that restaurants noted the absence of a single point of contact for the permitting
process, which they believe could reduce confusion and improve coordination.
Finally, current feedback mechanisms, such as customer service surveys, are not functioning
effectively, making it difficult for the County to identify gaps in service and also address barriers
experienced by business owners, especially under-resourced business owners.
To address these challenges, OFPA offers the following recommendations.
Recommendations to Address Observation 1
To improve the efficiency, effectiveness and equity of the restaurant permitting process, the County
should consider the following actions:
34 | P a g e
1. Update (and maintain) a comprehensive restaurant guide(with input from all relevant
agencies, including Health, Office of the Fire Marshal, and Department of Economic
Initiatives) so it is aligned with current PLUS workflows. Work with other agencies (DEI, OPA)
to actively market it to business owners. The guide should include clear information on the
review and resubmission process(including duration expectations and total timelines for
different types of processes), inspections required, the value of utilizing available
resources, and the benefits of consulting the County before signing a lease.Where
possible, link the guide within PLUS so that any applicant beginning a food establishment
application (or potentially a commercial building permit application) can be directed to the
guide. Alternatively, if the option exists to automate emailing the guide to applicants who
identify as food establishments during the PLUS process(through a download or link), the
County may want to explore this option. The guide would be most effective when applicants
can readily access it or are proactively provided with it early in the permitting process.
2. A wide variety of individuals and commercial businesses, including small businesses, must
navigate the permitting process with the County.Agencies that provide guidance on the
permitting process (including LDS, Health and the Office of the Fire Marshal) should review
their permit-related County websites and related resources for clarity and
comprehensiveness. The County may want to establish permitting pages specific to key
audiences, such as the restaurant industry, so thatapplicants don’t need to hunt and peck
around to find resources (such as the Tenant Support Services program and the Expedited
Building Plan Review Program) that relate to their needs. Ensure county websites related to
permitting, small businesses and food establishments link to the updated restaurant guide.
3. Consider whether County resources can provide the option of a single point of contact
(such as a case manager or concierge) for first-time and small-business restaurant owners
navigating the complexities of the permit process. Based on our conversations with County
staff, this concept is being explored as part of the TSS Pilot.
4. Improve dashboards that provide permitting goals and current processing times. Either
present dashboards for the full end-to-end process or harmonize the dashboards for
Health, Land Development Services, Zoning and Fire Marshal so the presentation and
terminology are consistent. Consider tracking new metrics that may give the restaurant
applicant a better sense of the entire process, rather than just the expected time frames for
one review round. Based on our conversations with County staffand OFPA’s review of the
Economic Competitiveness Strategic Roadmap, dashboard improvements area planned
initiative of the Economic Competitiveness Task Force.
5. Update and improve the customer service survey and outreach to capture feedback and
identify barriers experienced by business owners, particularly small and first-time
businesses. Ensure there is a process to take action on issues that repeatedly arise.
6. Consider the feasibility of using AI and/or other automation and system tools to
accelerate initial plan review processes, especially to support small businesses that may
lack technical expertise. Based on our conversations with County staffand OFPA’s review
of the Economic Competitiveness Strategic Roadmap, evaluating AI and automation are a
planned initiative of the Economic Competitiveness Task Force.
35 | P a g e
Providing better,clearer resources to potential applicants can help reduce timelines and get
restaurants and other food establishments opened more quickly. OFPA recognizes the efforts
already underway through the Economic Competitiveness Strategic Roadmap, which, if
implemented, should help meet several of these recommendations.
Management Response:
Management agrees that the Restaurant Guide should be updated and agencies’ disparate
webpages/information could be consolidated to provide a focused entry for prospective restaurant
permittees. To this end, starting in November 2026, LDS will stand up a multiagency workgroup
with participant invitations to the Health Department, Office of the Fire Marshal, Department of
Economic Initiatives and Zoning to accomplish the following:
1. Inventory published information related to establishing (permitting) a restaurant in Fairfax
County. (Completed by March 2027)
2. Delineate a plan to consolidate and update this information. One likely place to
consolidate the information is in the permit library published on LDS’s webpage. The
agency developed this library to provide a single set of instructions for permittees, making it
a natural fit. (Completed by June 2027)
3. LDS is already working with the Office of the Fire Marshal to coordinate publicly facing
metrics / dashboards regarding permit review processing timelines. This work requires
adjustments to PLUS, PowerBI and website platforms. This should be completedby June
2027. Through the workgroup established in #1, staff will develop a plan of action for
similarly consolidated metrics for Health Department permit work by June 2027.
4. The County expects PLUS to migrate to the vendor cloud (SaaS) in late calendar year 2026.
Once complete, customer surveys can be reestablished as a part of the customer
experience. New surveys will launch by August 2027.
5. LDS and partner agencies seek PLUS vendor offerings to leverage AI within plan review. To
date, the current PLUSvendor’s offerings cannot perform this task. Simultaneously, LDS
monitors competitors’ offerings to augment or replace PLUS’s plan review component with
something that can leverage AI. (Ongoing – implementation dependent on market
availability, etc.)
Accountable Individual(s):
The LDS PACA Division Director in LDS will lead items 1, 2 & 3(currently Brandy Mueller)
The LDS Operations Division Director in LDS will lead items 4 & 5(currently Helman Castro)
Implementation Dates:
• Multi-agency workgroup - by November 2026
• Inventory of information - completed by March 2027
• Plan - completed by June 2027
• LDS and OFM dashboard platform work - completed by June 2027
o Develop a similar plan of action for Health Department - completed by June 2027
• PLUS migration - December 2026
o New surveys will launch - August 2027
36 | P a g e
• AI plan review - implementation dependent on market availability, etc. – Ongoing
Observation a nd Rec ommendatio n 2
Observation 2
Cross-Agency Workflow Challenges in Food Establishment Plan Reviews
When an applicant submits a building or alteration permit application in PLUS, LDS assigns plans to
the required review departments. According to staff interviews, at times, the applicant does not
correctly designate their business as a food establishment or LDS misses that the applicant is a
food establishment, and LDS does not add the Health Department as a reviewer of the plans. As a
result, the Health Department sometimes learns about the application late in the process,
sometimes after LDS has issued the building permit to the applicant. When the Health Department
is notified of the building permit (often because the applicant has submitted their food
establishment application), staff must still complete the plan review to ensure that the
construction complies with Health Department requirements, which can create delays for the
applicant and cause frustration.
Recommendation to Address Observation 2
LDS should review intake and routing procedures to ensure staff consistently identify food
establishment applications and add the Health Department as a required plan reviewer. LDS can
consider adding or updating prompts or mandatory fields in PLUSduring the building and alteration
application process to improve categorization, providing refresher training for staff, and
establishing a verification step before plans are assigned. The County might also explore the use of
AI tools that review plans could also help flag food establishmentprojects earlier in the process.
These improvements will help ensure the Health Department receives applications at the correct
stage, reduce delays and applicant frustration, and support more timely, coordinated plan review.
Management Response:
We acknowledge that this can occur. However, we believe this to be anomalous. Nonetheless, we
acknowledge that it does occur occasionally as first submission commercial projects are
distributed by the Building Division and the full distribution can be missed. We will task the
workgroup established in Observation #1 response,to consider options to prevent this error moving
forward, including possible PLUS automations to prevent user error upon distribution or moving this
task to PACA permit technicians as part of the initial QA/QC review. Notwithstanding the findings of
the workgroup, focused training for building plan review staffrepresents a no regrets option to move
forward. The Building Division training to improve distinguish restaurant applications manually
during review distribution will be implemented by December 2026. By March 2027, we will identify
any PLUS or process changes to remedy this issue.
Accountable Individual(s):
LDS PACA Division Director(currently Brandy Mueller)
37 | P a g e
Implementation Dates:
• Training - by December 2026
• PLUS or process changes to remedy the issue- by March 2027
Observation a nd Rec ommendatio n 3
Observation 3
Restaurants Report Inconsistent, Conflicting and Lengthy Permitting Processes
Interviews with restaurant owners and managers revealed concerns regarding the timeliness and
consistency of permitting reviews and inspections, with delays accumulating and significantly
affecting the end-to-end permitting process. Applicants reported that requirements sometimes
shift between review cycles, that different reviewers or inspectors provide conflicting guidance, and
that inspections often require multiple visits. These issues generate delays, rework, and additional
costs, including repeated plan revisions, resubmission fees, redoing completed work, and
prolonged periods during which restaurants cannot open and begin generating revenue.
When OFPA discussed these concerns with County staff, they offered reasonable explanations,
including that applicants may submit incomplete applications, misunderstand the code
requirements, or schedule inspections before the work was complete. These perspectives indicate
that some delays may reflect shared responsibility and an expectations gap between the County
and applicants. OFPA was not able to independently confirm the prevalence of these issues
through our analysis of permitting data; however, the consistency of feedback from restaurant
owners suggests challenges that the County has not fully addressed.
Restaurant owners also expressed concerns that some requirements may reflect individual
reviewer or inspector preferences rather than the consistent application of established codes. LDS
staff indicated that the department does not maintain standard operating procedures governing
reviews and inspections. Instead, staff rely ontraining as well as the Virginia Uniform Statewide
Building Code, the Statewide Fire Prevention Code, and the Public Facilities Manual, and reviewers
and inspectors may create their own checklists. This individualized approach increases the
potential for inconsistent expectations and contradictory guidance. Staff also described
challenges with inspection logistics, including difficulties using PLUS to efficiently route inspectors,
which may further contribute to extended timelines.
Combined, these issues demonstrate that the County may not have sufficient insight into the
restaurant applicant’s experience and where contradictions originate. These ongoing challenges
highlight the need for the County to examine the underlying causes of delays and inconsistencies to
determine whether they arise from misaligned expectations, insufficient visibility, unclear
communication, limited coordination, or gaps in execution in the permitting process.
Recommendation to Address Observation 3
To address the consistency and timeliness issues identified by restaurants and the cumulative
delays that affect the end-to-end permitting process, OFPA recommends the following:
38 | P a g e
1. Establish a cross-agency workgroup, with representation from LDS, the Health Department,
the Department of Economic Initiatives and the Office of the Fire Marshal, to gather and
analyze restaurant-applicant feedback, staff insight, and PLUS data to determine why
requirements shift, contradictory comments occur, inspections require multiple visits, and
overall timelines extend. The workgroup should use these insights to identify whether
challenges stem from a gap in expectations, or communication, coordination, or execution
issues; and implement improvements (that are within the County’s control)based on those
findings.
2. The County should strengthen consistency among reviewers and inspectors by clarifying
expectations, improving alignment in how code requirements are applied, and creating
internal mechanisms or escalation processes to resolve conflicting interpretations before
they reach applicants.
3. In addition, the County should explore options to improve inspection logistics by optimizing
scheduling and routing tools (available in PLUS).
4. Finally, where possible, these efforts should be coordinated with initiatives underway in the
Economic Competitiveness Strategy Roadmap to ensure consistency, avoid duplication,
and reinforce broader County goals related to business experience and economicgrowth.
Management Response:
As stated in the management response to Observation #1, LDS will stand up a multi-agency
workgroup to include staff from the Health Department, Office of the Fire Marshal, Department of
Economic Initiatives and Zoning by November 2026. Once the new customer surveys are
established (management response to Observation #1 – August 2027) this workgroup will review all
customer input to identify root causes and corrective measures. If input is received by
management ahead of these surveys, they will provide it to this workgroup.
The building inspections group in LDS will develop an inspection manual to cover all commercial
inspections. This will be directly applicable to restaurant establishments. This manual will be
finished by September 2027.
The routing tools for inspections in PLUS have not worked well. LDS inspection supervisors have
had to compensate by manually re-sorting work each morning. Staff are eager to find an automated
solution. Once PLUS is fully migrated to SaaS, the PLUS teamwill identify a path forward to resolve
this issue. The path forward will be identified by April 2027.
Accountable Individual(s):
Workgroup – LDS PACA Division Director(currently Brandy Mueller)
Inspection Manual – LDS Building Official (currently Jay Riat)
Routing Solution – LDS Operations Division Director(currently Helman Castro)
Implementation Dates:
• Multi-agency workgroup - by November 2026
• Review of customer service surveys - to begin after August 2027
39 | P a g e
• Inspection manual - September 2027
• Routing Toolsoptions identified - April 2027
40 | P a g e
Appendix 1
Data Integration and Sampling Methodology
We combined restaurant permitting data provided by the Health Department (HD) and Land
Development Services (LDS) to develop a more complete view of the permitting process.
1. We first combined HD food establishment application and permit data using restaurant
name and address as matching identifiers.
2. We then incorporated LDS Certificate of Occupancy (Non-RUP) and commercial
addition/alteration and new building (ALT-C/BLD-C) data using available identifiers,
including restaurant name and address, where available. However, certain records
contained different or incomplete identifying information. For example, ALT-C/BLD-C
(renovation and new build) records did not include restaurant names, and restaurant names
in food application records did not always match those in LDS Non-RUP records. As a
result, we standardized available identifying fields and used multiple identifiers to match
records as much as possible across the agencies' datasets.
3. Because the agencies were unable to provide complete workflow history data for the entire
population of restaurant permitting records, we used a sample to evaluate detailed
permitting workflows and processing timelines. Weused non-statistical sampling to select
34 food establishment applications with a closed status and LDS ALT-C/BLD-C records
dating from FY24 through FY26, and staff accessed PLUS to obtainthe corresponding
detailed workflow histories. The workflow histories provided task-level information,
including workflow tasks and statuses, status dates, responsible parties, and other record-
level details.
4. We used the combined data to analyze the sequence and timing of permitting activities and
to distinguish, where supported by the workflow data, agency processing time from other
portions of the overall permitting process.
41 | P a g e
Appendix 2
Record/Application Types for Sampled Restaurants
Note: The Occupancy Inspection record type shown above refers
to the pre-occupancy inspection.
42 | P a g e
Appendix 3
Food Establishments in Fairfax County as of July 21, 2026
Note: Food establishment types in grey are within the scope of this report.
43 | P a g e
Appendix 4
All Inspection Types Associated with
the ALT-C Record Type
in the Sample of Restaurants
Index Record Type Task
1 Commercial Addition/Alteration Ceiling Concealment
2 Concrete Pour
3 Final
4 Framing
5 Insulation
6 Routine
7 Slab
8 Wall
9 Wall Concealment
1 Commercial Electrical Ceiling Concealment
2 Concealment
3 Conduit Underground
4 Final
5 Wall Concealment
1 Commercial Mechanical Ceiling Concealment
2 Ductwork
3 Final
4 Grease Duct Light Test
5 Grease Duct Wrap
6 Hood Fire Suppression
7 Routine
1 Commercial Plumbing Ceiling Concealment
2 Concealment
3 Final
4 First Gas
5 Groundwork Sanitary Sewer
6 Routine
7 Wall Concealment
1 Fire Alarm Fire Alarm
2 Fire Alarm Visual
1 Food Establishment Application Pre-Occupancy
1 Occupancy Inspection Pre Occupancy
1 Sprinkler System or Standpipe System Dry Sys. Trip Perf. Test
2 Hydro Sprinklers
3 Main Drain Perf. Test
4 Sprinkler Final
5 Sprinkler Visual
All Review Types Associated with
the ALT-C Record Type
in the Sample of Restaurants
Note: Task fields can be found in PLUS workflow history.
44 | P a g e
Appendix 5
Examples of Permitting Dashboards and Metrics
Fairfax County, VA
Washington, DC
45 | P a g e
City of Fairfax, VA
Loudoun County, VA
46 | P a g e
Denver, CO
San Jose, CA
47 | P a g e
Appendix 6
Fairfax County Food Establishment Permits Issued by District
Note: The number of active food establishmentsas of July 2026. This includes establishments
classified as Bakery, Carry Out Food Service, Fast Food Restaurant, and Full-Service Restaurant.
District
Number of Active
Food Establishments
# of New Food Est.
Permits Issued since FY24
# of New Food Est. Permits
Issued Since FY24 Now Closed
BRADDOCK 169 59 8
DRANESVILLE 142 57 5
FRANCONIA 311 85 9
HUNTER MILL 264 91 9
MASON 408 128 12
MOUNT VERNON 209 70 7
PROVIDENCE 441 151 21
SPRINGFIELD 194 66 8
SULLY 361 134 20
Total 2,499 841 99
48 | P a g e
Office of Financial & Program Audit
The Audit Committee and the Office of Financial & Program Audit(OFPA) were created by the
Board of Supervisors, pursuant to Virginia Code §15.2-825. The Audit Committee consists of six
members – four Supervisors of the Board and two county residents. Working under the guidance
and direction of the Audit Committee, OFPA provides an independent means for determining the
manner in which operations, programs, and resources authorized by the Board of Supervisors (BOS)
are deployed by management, and whether they are consistent with the intent of the Board and
operating effectively and efficiently.
What We Do
OFPA designs and conducts reviews, studies, and evaluations of county agencies as assigned by
the BOS or the Audit Committee. OFPA activities can vary from a simple inquiry, a program study, or
long-term monitoring. We present the results of our work in reports that offer recommendations to
increase county revenues, reduce county expenditures, or otherwise improve the efficiency and
effectiveness of county resources. Results and recommendations are based on our analysis of
county data and other information and may not identify every risk, process gap, revenue
enhancement, or expense reduction.
Our Goals
• Review the effectiveness and efficiency of programs and operations of county departments,
agencies, and authorities.
• Identify cost savings and additional financial resources, as appropriate.
• Recommend ways to improve, promote, and increase accountability.
12000 Government Center Parkway, Suite 233
Fairfax, VA 22035
703-324-1501
www.fairfaxcounty.gov/boardauditor/
To request this information in an alternate format, callOFPA at 703-324-1501.