Route 5 and New Osborne Turnpike Public Meeting 2 Presentation
Henrico County · Henrico County · meeting of Apr 21, 2026 · Notices
Open the original document More from Henrico County
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
ROUTE 5 AND
NEW O SBORNE TUR NPIKE
IMPROV EMENT STUD Y
P UBL IC INF ORM ATION M EETIN G
2
M arc h 5, 20 26
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Agenda
• Study description and background
• Corridor study process and public engagement summary
• Potential intersection improvements
• Potential corridor-wide improvements
Objective
• Receive public feedback on potential improvements
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Study Description and Background
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Study Description
The County of Henrico is
conducting a study to evaluate
necessary safety and operational
improvements along the Route 5
and New Osborne Turnpike
corridors.
This study is being conducted in
partnership with the Virginia
Department of Transportation
(VDOT) and the City of Richmond.
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Background
The study will consider findings developed in:
• Route 5 Corridor Study, December 2011, Kimley-Horn
• Route 5 Corridor Study, December 2018, Henrico County
• Route 5 Traffic Operational & Safety Analysis, December 2024,
RK&K/VDOT
Purpose
• Identify multimodal strategies to help connect eastern Henrico
County and the City of Richmond
• Accommodate future traffic
• Address capacity-constrained roadways and relieve congestion
• Improve safety along the corridors
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Study Area
1. Williamsburg Rd and Hatcher St
2. Rt. 5 and New Osborne Tpke
3. Rt. 5 and Oakland Rd
4. Rt. 5 and Osborne Tpke
5. Rt. 5 and Midview Rd/Herman St
6. Rt. 5 and 1st Colonial Pkwy
7. Rt. 5 and Messer Rd
8. Rt. 5 and S Laburnum Ave
9. Rt. 5 and Wilson Rd/Varina St
10. Rt. 5 and Mill Rd
11. Rt. 5 and Strath Rd
12. Rt. 5 and Buffin Rd/Woodmill Dr
13. Rt. 5 and Doran Rd
14. Rt. 5 and Four Mile Run Pkwy
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Corridor Study Process
1. Kickoff Meeting
2. Steering Committee Meeting #1
3. Public Information Meeting #1
4. Public Survey
5. Data Analysis
6. Traffic Analysis and Concept Development
7. Steering Committee Meeting #2
8. Public Information Meeting #2 (We are here!)
9. Public Survey #2
10. Steering Committee Meeting #3
11. Finalize Study Document
12. Public Information Meeting #3
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Public Engagement Responses
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Public Engagement Summary
Traffic & Congestion
Intersection Safety
Bicycle & Pedestrian Safety
Speeding
Lighting
Future
Development
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Concept Development
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Potential Intersection Improvements
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Roundabout Overview
• Improved safety: Reduces number of conflict points
• Increased efficiency: Yield-controlled design means
fewer stops, fewer delays, and shorter queues
• Safer speeds: Promotes lower vehicle speeds
• Long-term cost effectiveness: No traffic signals
means lower long-term costs for operations and
maintenance
• Aesthetics: Allows for landscaping and beautification
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Successful Roundabout Installations
Woodman Road & Greenwood Road Doran Road & Four Mile Run Parkway
Shady Grove Road and Old Nuckols Road Francistown Road and Hungary Creek Middle School
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Williamsburg Road and Hatcher Street
Alternative 1: Do Nothing
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Williamsburg Road and Hatcher Street
Alternative 2: Roundabout
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Potential Intersection Improvements
Williamsburg Road and Hatcher Street
Alternative Improvements Pros Cons
#1: Do Nothing • Maintain one-way
stop control
• N/a • Northbound approach
operates with
excessive delay
#2: Roundabout • Construct a single-
lane roundabout
• Right-turn slip lanes
on all approaches
• Improved operations
• Improved safety
• Improved ped/bike
connectivity
• Increased delay for
major street through
movements
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Potential Intersection Improvements
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Route 5 and New Osborne Turnpike
Alternative 1: Do Nothing
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Route 5 and New Osborne Turnpike
Alternative 2: Realignment (Unsignalized)
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Route 5 and New Osborne Turnpike
Alternative 3: Roundabout
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Potential Intersection Improvements
Route 5 and New Osborne Turnpike
Alternative Improvements Pros Cons
#1: Do Nothing • Maintain skewed
one-way stop control
• N/a • Westbound approach
operates with
excessive delay
#2: Realignment
(Unsignalized)
• Realign New Osborne
Turnpike to intersect
Route 5 at a right-
angle
• Eliminates skew
• Improves sight
distance
• Improves safety
• Westbound approach
operates with
excessive delay
#3: Roundabout • Realign New Osborne
Turnpike and
construct a single-
lane roundabout
• Improved operations
• Improved safety
• Improved ped/bike
connectivity
• Increased delay for
major street through
movements
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Potential Intersection Improvements
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Route 5 and New Market Road/Osborne Turnpike
Alternative 1: Do Nothing
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Route 5 and New Market Road/Osborne Turnpike
Alternative 2: Realignment (Unsignalized)
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Route 5 and Osborne Turnpike/Lovey Lane
Alternative 3: Roundabout
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Potential Intersection Improvements
Route 5 and New Market Road/Osborne Turnpike
Alternative Improvements Pros Cons
#1: Do Nothing • Maintain skewed/offset
one-way stop control
• N/a • Eastbound approach
operates with excessive
delay
• Multiple trail crossings
#2: Realignment
(Unsignalized)
• Realign Osborne Turnpike
to intersect Route 5 at a
right-angle
• Eliminates skew/offset
• Improves sight distance
• Improves safety
• Consolidates trail crossings
• Eastbound approach
operates with excessive
delay
#3: Roundabout • Construct a single-lane
roundabout
• Improved operations
• Improved safety
• Improved ped/bike connectivity
• Increased delay for major
street through movements
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Potential Intersection Improvements
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Route 5 and Midview Road / Herman Street
Alternative 1: Do Nothing
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Route 5 and Midview Road / Herman Street
Alternative 2: Realignment (Unsignalized)
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Potential Intersection Improvements
Route 5 and Midview Road/Herman Street
Alternative Improvements Pros Cons
#1: Do Nothing • Maintain skewed/offset two-
way stop control
• N/a • Westbound approach
operates with
excessive delay
#2: Realignment
(Unsignalized)
• Realign Herman Street to
intersect Route 5 at a right-
angle at Midview Road
• Eliminates skew
• Improves sight
distance
• Improves safety
• Westbound approach
operates with
excessive delay
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Potential Corridor Improvement
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
New Osborne Turnpike/Newton Road/Hatcher Street Alternative 1: Do Nothing
New Osborne Turnpike/Newton Road/Hatcher Street
Alternative 1: Do Nothing
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
New Osborne Turnpike/Newton Road/Hatcher Street
Alternative 2: Realignment/Improvement
Potomac Street
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Potential Corridor Improvement
New Osborne Turnpike between Route 5 and Williamsburg Road
Alternative Improvements Pros Cons
#1: Do Nothing • Maintain narrow, single-
lane, crossing
• N/a • Narrow, dark, crossing
presents safety
concerns
#2: Realignment/
Improvement
• Provide bridge over
railroad
• Provide shared-use path
from Williamsburg Road
to Route 5
• Improved safety
• Improved ped/bike
connectivity
• Substantial
improvement costs
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Potential Intersection Improvements
• The following improvement concepts were identified in the
RK&K/VDOT study and will be included in the Build analysis
• Route 5 at Varina Road/Wilson Road
• Southbound right-turn lane installed as part of the Nelson Farm Residential
Development
• Route 5 at Mill Road
• Realign Mill Road and install a westbound left-turn lane
• Route 5 at Strath Road
• Construct a single-lane roundabout with right-turn slip lanes on all approaches
• Route 5 at Doran Road
• Realign Doran Road and construct a single-lane roundabout
RK&K/VDOT Study Conclusions
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Potential Intersection Improvements
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Potential Intersection Improvements
Route 5 at Varina Road/Wilson Road
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Potential Intersection Improvements
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Potential Intersection Improvements
Route 5 at Mill Road
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Potential Intersection Improvements
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Potential Intersection Improvements
Route 5 at Strath Road
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Potential Intersection Improvements
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Potential Intersection Improvements
Route 5 at Doran Road
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Potential Intersection Improvements
Intersection Lighting
1. Route 5 and Bickerstaff Road
2. Route 5 and McCoul Street
3. Route 5 and New Osborne Turnpike
4. Route 5 and Oakland Road
5. Route 5 and Lanier Avenue
6. Route 5 and Osborne Turnpike
7. Route 5 and McLean Street
8. Route 5 and N. James Estates
9. Route 5 and Midview Road/Herman Street
10. Route 5 and Hickory Avenue
11. Route 5 and 1st Colonial Parkway (existing)
12. Route 5 and Leeland Drive
13. Route 5 and Messer Road
14. Route 5 and Burning Tree Road
15. Route 5 and Varina Library
16. Route 5 and Battlefield Park Road
17. Route 5 and Willson Road/Varina Road
18. Route 5 and Mill Road (existing)
19. Route 5 and Strath Road
20. Route 5 and Buffin Road
21. Route 5 and Doran Road (existing)
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Potential Improvements
Additional Trail Crossings
1. Route 5 and McCoul Street
2. Route 5 and Oakland Road
3. Route 5 and Lanier Avenue
4. Route 5 and McLean Street
5. Route 5 and Hickory Avenue
6. Route 5 and Leeland Drive
7. Route 5 and Burning Tree
8. Route 5 and Battlefield Park Road
9. Route 5 and Recreation Road
10. From Four Mile Run to the Virginia Capital Trail
ROUTE 5 CORRIDOR STUDY
Public Information Meeting #2
Thank you for
coming!
Please share your feedback and questions
with a member of our technical team.
Scan QR Code
to Visit the Project Website!
Will be available until March 19th