Economic Development Authority — Agenda Minutes
Chesterfield County · Chesterfield County · Economic Development Authority · meeting of Aug 20, 2026 · Other
Open the original document More from Chesterfield County
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Economic Development Authority of Chesterfield County
Meeting Minutes
August 20, 2026
P a g e 1 | 4
Members Attending:
Robert Vaughn Terri Cofer Beirne
Faizan Habib John Hughes
John V. Cogbill, III Jesse Calloway
Members Absent:
Danielle Fitz Hugh
Others Attending:
John O'Neill, Hunton Andrews Kurth, LLP
Brendan Staley, Hunton Andrews Kurth, LLP
Tim Davey, Timmons Group
Garrett Hart, Chesterfield Economic Development
Matt McLaren, Chesterfield Economic Development
Debbie Baicy, Chesterfield Accounting Department
Samantha Furnish, Chesterfield Economic Development
Susan Beals - Resident
Robert Vaughn called the meeting to order at 3:03 pm and noted that a quorum was present for the
Economic Development Authority meeting on August 20, 2026.
Approval of the Minutes:
Robert Vaughn requested approval of the minutes of the July 16, 2026, meeting. John Hughes
motioned to approve the meeting minutes as written. John Cogbill seconded, and all members
present voted in the affirmative.
Financial Statements Update:
Debbie Baicy provided the July financial report, highlighting cash reserves and project funding.
Debbie reported that the auditors began their work this week and that the audit is progressing
smoothly.
Springline at District 60 Update:
Garrett Hart provided an update on the Springline development. He said a topping-out ceremony
for the Mondelle hotel was held this week, with approximately 100 to 150 attendees participating
and signing the ceremonial beam before it was placed on top of the building.
Construction will now move into the next phase, with work beginning to enclose the building. The
exterior will include the existing white concrete elements as well as a significant amount of glass.
Once the exterior skin is completed, much of the remaining construction activity will take place
inside the building and will be less visible from the surrounding area.
Meadowville Technology Park Update:
Garrett Hart provided an update on Henricus Access Road, officially named Dutch Gap Parkway.
He said the project is necessary due to Dominion Energy's fly ash project, which will impact the
existing roadway into Henricus. The project is a County-funded initiative, with the Economic
Development Authority (EDA) responsible for constructing a portion of the roadway. The County is
responsible for the portion on the opposite side of Interstate 295, including the bridge component.
Economic Development Authority of Chesterfield County
Meeting Minutes
August 20, 2026
P a g e 2 | 4
The County has awarded a contract for its portion and will manage that work separately from the
EDA's construction activities.
The roadway will provide access to Henricus Historical Park and Adeline Acres, as well as
surrounding properties. The roadway also provides access around the LEGO campus and the large
development pad.
Construction of the stormwater management facilities required for the roadway is nearing
completion. Work depended on relocating a sewer line, which is now complete and approved by
the Department of Utilities. After completing the stormwater facilities, the contractor is expected
to begin placing the roadway gravel base during the first week of September. The EDA's portion of
the project is anticipated to be completed in early December.
Garrett reported that the wetlands permit associated with the Dutch Gap Parkway is scheduled to
expire this month and will need to be renewed. Renewal will require field verification to confirm that
wetlands and related environmental features remain appropriately documented and covered under
the permit. Due to weather-related delays and the revised project completion date, additional
engineering testing and construction management services will also be required.
Garrett presented an amended task order from Timmons Group for the Authority to consider. The
task order covers construction management services and renewal of the wetlands permit. The task
order has a fixed fee of $90,000.
John Cogbill motioned to approve the Timmons Group Amended Task Order for extended CA & CEI
services for a fixed fee of $90,000. Faizan Habib seconded, and all members present voted in the
affirmative.
Garrett reported that, as part of the LEGO site development package, Meadowville Technology
Parkway is being widened, and a new entrance is being constructed at the existing T-intersection
shown in the project plans. The intersection will be fully signalized and will provide right-in/right-out
and left-in/left-out access for employees once the LEGO facility is operational.
The project is funded through the Transportation Partnership Opportunity Fund (TPOF) as part of
the State's incentive package associated with the LEGO project. The EDA will make the
improvements and be reimbursed by the State through the TPOF program.
Upper Magnolia Green Update:
Garrett Hart provided an update on two major infrastructure projects associated with the Upper
Magnolia development: the Duval Road Realignment and the Western Area Arterial Connector
(WAAC), which will provide two lanes of the Powhite Parkway extension.
Garrett said Duval Road currently extends across the area and connects to Skinquarter Road and
Otterdale Road. Under the proposed realignment, Duval Road will be relocated to a new traffic
circle, providing access into the Upper Magnolia Industrial Park. The portion of the existing Duval
Road affected by the future Powhite Parkway interchange will ultimately become a cul-de-sac.
Economic Development Authority of Chesterfield County
Meeting Minutes
August 20, 2026
P a g e 3 | 4
At the end of the new roadway, the EDA is constructing a 10-acre development pad to give
prospective businesses a clear view of and understanding of the larger Upper Magnolia site. The
pad is part of the grant-funded site development program through the Virginia Economic
Development Partnership (VEDP). Grant funds will reimburse the EDA for eligible project costs to
prepare the site for marketing.
The 10-acre pad will be cleared, stabilized, and planted with grass and will be accessible from the
new Duval Road realignment. A cul-de-sac will provide access at the end of the roadway. He noted
that significant rainfall has delayed the project, requiring repairs and reestablishment of erosion
and sediment control measures after severe storms.
Garrett said the Western Area Arterial Connector (WAAC) project, also referred to as the Powhite
Parkway project, involves constructing approximately two lanes of the Powhite Parkway from Hull
Street Road north toward Westerleigh. The project has received all required permits and is
currently in final design. Funding includes a $35 million Transportation Partnership Opportunity
Fund (TPOF) award and approximately $10 million in VSRP Program funding to initiate construction.
He reported that bid packages are currently being prepared, with construction anticipated to begin
in October or November 2026.
Other Updates:
None
Closed Session:
John Cogbill motioned that the Authority meeting be closed (1) Pursuant to Section 2.2-3711(A)(3)
Code of Virginia, for discussion or consideration of the acquisition of real property for a public
purpose, or of the disposition of publicly held real property, where discussion in an open meeting
would adversely affect the bargaining position or negotiating strategy of the public body, (2)
Pursuant to Section 2.2-3711(A)(5) for discussion concerning a prospective business or industry or
the expansion of an existing business or industry where no previous announcement has been made
of the business' or industry's interest in locating or expanding its facilities in the County. Jesse
Calloway seconded, and all members present voted in the affirmative.
EXIT:
John Cogbill motioned that the Authority leave the closed session held (1) Pursuant to Section 2.2-
3711(A)(3) for discussion or consideration of the acquisition of real property for a public purpose,
or of the disposition of publicly held real property, where discussion in an open meeting would
adversely affect the bargaining position or negotiating strategy of the public body, (2) Pursuant to
Section 2.2-3711(A)(5) for discussion concerning a prospective business or industry or the
expansion of an existing business or industry where no previous announcement has been made of
the business' or industry's interest in locating or expanding its facilities in the community.
Robert Vaughn called for a vote certifying that to the best of each member's knowledge, (i) only
public business matters lawfully exempted from open meeting requirements under Va. Code § 2.2-
3711 (A)(3) and (A)(5), and (ii) only such public business matters as were identified in the motion by
which the closed meeting was convened were heard, discussed, or considered. All members
present voted in the affirmative.
Economic Development Authority of Chesterfield County
Meeting Minutes
August 20, 2026
P a g e 4 | 4
Director Attendance
(Present/Absent)
Vote
(Aye/Nay/Abstain)
Terri Cofer Beirne Present Aye
Robert Vaughn Present Aye
John Cogbill Present Aye
Danielle Fitz Hugh Absent
Faizan Habib Present Aye
John Hughes Present Aye
Jesse Calloway Present Aye
John Cogbill motioned to authorize the Chair and Vice Chair, or either of them, to execute all
documents necessary to provide an easement to Vepco/Dominion Power. Terri Cofer Beirne
seconded, and all members present voted in the affirmative.
With no further business, Faizan Habib motioned to conclude the meeting at 4:30 pm. Terri Cofer
Beirne seconded, and all members present voted in the affirmative.
Respectfully submitted,
Samantha Furnish
Recording Secretary
Next Meeting: September 17, 2026, at 3 pm