Planning Commission Meeting Agenda
September 22, 2026
100 5th Street Northeast
City Space Conference Room
Charlottesville, Virginia 22902
Carl Schwarz, Chair
Danny Yoder, Vice Chair
Ross Harness
Hosea Mitchell
Betsy Roettger
Lyle Solla-Yates
Josh Carp
Michael Joy
I. Commission Work Session
Beginning: 5:00 p.m. Location: (Cityspace, 100 5th Street NE, Charlottesville, VA 22902)
1. Comprehensive Plan Five Year Review
II. Future Meeting Schedule/Adjournment
Tuesday October 13 - 5:30 PM - Regular Meeting
Individuals with disabilities who require assistance or special arrangements to participate in the
public meeting may call the ADA Coordinator at (434) 970-3185 or submit a request via email
to ada@charlottesville.gov. The City of Charlottesville requests that you provide a 48 hour notice
so that proper arrangements may be made.
Planning Commission pre-meeting and regular meetings are held in person and by Zoom webinar.
The webinar is broadcast on Comcast Channel 10 and on all the City's streaming platforms
including: Facebook, Twitter, and www.charlottesville.gov/streaming. Public hearings and other
matters from the public will be heard via the Zoom webinar which requires advanced registration
here: www.charlottesville.gov/zoom . You may also participate via telephone and a number is
provided with the Zoom registration or by contacting staff at 434-970-3182 to ask for the dial in
number for each meeting. Written comments may be submitted via email to
planningcommission@charlottesville.gov.
Page 1 of 39
City of Charlottesville
Neighborhood Development Services Department
PLANNING COMMISSION WORK SESSION
Subject: Comprehensive Plan 5-Year Review Draft Scope
Staff Contacts: Tori Kanellopoulos, NDS Long-Range Principal Planner
Date: September 22, 2026
Background
In November 2021, City Council formally adopted the City’s Comprehensive Plan
(“Comp Plan”). Since then, there have been several amendments thereto, including
adopting the Climate Action Plan and the Parks & Recreation Master Plan.
Per Virginia State Code §15.2-2230, each locality must review its Comprehensive Plan
at least every five years to determine whether it is advisable to amend the Comp Plan.
While there have been several amendments to the City’s Comp Plan to date, it is best
practice to complete a review of the Comp Plan every five years and determine if
additional changes are needed.
The purpose of this work session is to share an overview of the draft scope of work for
the City’s Comp Plan 5-year review process and ask for the Planning Commission’s
feedback to inform the final scope.
Staff Analysis
The attached presentation provides an overview of the general expectations for the
content of Virginia localities’ Comp Plans and their reviews, the City’s draft process and
approach for reviewing the City’s Comp Plan, initial existing conditions data, and project
objectives. The Comp Plan review is an opportunity to evaluate and respond to
challenges, opportunities, and emerging issues that have been identified since the City
adopted the updated Comp Plan in 2021.
Page 2 of 39
The Comp Plan review will be informed by feedback and expertise from City staff,
community members, the Planning Commission, and City Council, along with qualitative
and quantitative data, State Code requirements, and best practices. This will include:
• Updating existing conditions data and trends
• Incorporating any new State Code requirements
• Alignment with City plans that have been completed since November 2021 and
coordinating with in-progress plans that are moving in parallel
• Evaluating strategies and priorities and where changes are needed
• Opportunities for community input and information-sharing throughout the process
The existing conditions data that is provided in the attached presentation is a summary
of initial findings on regional trends, development patterns, and affordable housing. As
staff continues to scope the Comp Plan, staff will continue to collect and analyze data to
inform the Comp Plan review.
The community, Planning Commission, and Council will be informed throughout the
project, and will be engaged at key points to ask for input and feedback. Staff will provide
regular project status updates and share upcoming opportunities for engagement,
including through a future Connect Charlottesville page. Staff will hold work sessions with
the Planning Commission and will share the Commission’s recommendations and
feedback with Council at corresponding work sessions.
This work session is an early step in the process to ask for Planning Commission
feedback on the draft scope. Staff will hold a work session with Council later this fall to
ask the same questions and will share a summary of the Commission’s feedback from
today’s work session. Staff would anticipate the 5-year review process to formally kick off
in early 2027.
Staff Recommendation
Staff is asking for the Planning Commission’s feedback on key questions to determine
the Comp Plan 5-year review scope, which are on presentation slides 35 and 36.
Attachments
A. Presentation for September 22, 2026
Page 3 of 39
Comprehensive Plan
5-Year Review
Planning Commission
Work Session
September 22, 2026
Page 4 of 39
Agenda
• Review of the Cville Plans Together process
• Comprehensive Plans: purpose, how implemented, topics included
• 5-year review of Comp Plans for Virginia localities
• Draft process and approach for how the City will review the 2021
Comprehensive Plan
• Initial existing conditions data
• Project objectives for the 5-year review
• Planning Commission input: key questions to determine the project scope
Page 5 of 39
Cville Plans Together
• Affordable Housing Plan
• Comprehensive Plan
• Development Code
Page 6 of 39
Cville Plans Together Process
(March 2021)
(Nov 2021)
(In effect as of
Feb 2024)
Was a community process for
updating the future vision for the
city, with a focus on equity and
affordability.
Page 7 of 39
Cville Plans Together Process: Affordable Housing Plan
Vision: The City of Charlottesville will achieve a local housing
market that is healthy,high quality, affordable, and above all,
equitable.
Guiding Principles:
• Racial Equity
• Regional Collaboration
• Comprehensive Approach
Major Initiatives:
• Dedicate $10M annually to affordable housing
• Build inclusive governance at all levels
• Adopt progressive and inclusionary zoning reforms
Recommendations related to:
• Funding, Governance, Land Use, Tenants' Rights, and Subsidy
Page 8 of 39
Cville Plans Together Process: Comprehensive Plan
Five Guiding Principles
These are community-input-driven priorities that apply to
the entire Plan.
Equity & Opportunity
Community Culture & Unity
Local & Regional Collaboration
Environmental Stewardship & Sustainability
Connections & Access
Page 9 of 39
Comprehensive Plan Priority Areas
Six Priority Areas For Implementation
• Support the development of more housing throughout the city,
with a focus on creation of more housing that is affordable to
more people, especially those with the greatest need.
• Make sure all people have access to shelter, food,
job opportunities, and other resources they need to thrive
and succeed.
• Work to both mitigate and prepare for theimpacts of climate
change.
• Make it safer, easier, and more desirable towalk, ride a bicycle,
utilize public transportation, or use other non-single-occupancy
vehicle transportation options.
• Keep Charlottesville green, make it greener, and protect the
natural environment and the many benefits it provides.
• Continue to evolve and improvecommunication
and collaboration.
Page 10 of 39
Comprehensive Plan Future Land Use Objectives
• Build upon land use recommendations from other plans.
• Ensure citywide, equitable opportunities
for additional housing.
• Increase opportunities for development near community hubs
and amenities, to maximize access.
• Explore the potential of vacant or underutilized properties.
• Establish correlations between the City’s land uses, UVA, and
the County’s Urban Ring.
• Increase access to transit, as well as walking and
biking infrastructure.
• Protect, preserve, and enhance natural and
cultural resources.
• Ensure long term economic sustainability of the City
by planning for a wide range of commercial land use types.
Page 11 of 39
Cville Plans Together Process: Development Code
• Informed by guidance and recommendations in the
Comprehensive Plan
• Changes from the previous ordinance (2003) include:
• Allowing more 'missing middle' and multifamily
housing by-right
• No minimum parking requirements
• Updated affordable housing requirements that
apply to projects with 10 or more units
• More focused on form and urban design
Page 12 of 39
Draft Approach and Scope
for the Comprehensive Plan
5- Year Review
Page 13 of 39
What is a Comprehensive Plan?
• Establishes a 20-year vision with
recommendations to guide growth,
development, and public infrastructure,
amenities, and services.
• Comp Plans have recommendations for how
and where localities should grow, supporting
local economic development, protecting and
restoring natural and historic resources, and
guiding decisions on providing public
infrastructure (such as schools, roads,
sidewalks, parks, and utilities).
• Recommendations in the Comprehensive Plan
are used to guide:
• Initiating and evaluating plans, policies,
and programs
• Developing the capital improvement
program (CIP)
• Evaluating and developing local ordinance
changes (e.g. zoning, water protection)
• Review of certain applications
Page 14 of 39
What topic areas does a Comprehensive Plan provide guidance for?
Comp Plan recommendations support the City's Vision Statement: To be a place where everyone thrives, by
guiding how and where the city should accommodate projected population and employment growth and the
delivery of the infrastructure, amenities, and services to provide current and future community members
with a high quality of life.
State Code provides a framework of requirements to include in Comprehensive Plans, and localities can
then choose how to meet those requirements and how to organize their plan. Topics typically include:
Page 15 of 39
How often are Comprehensive Plans reviewed or updated?
• Virginia State Code requires localities to review their Comprehensive Plans every 5 years and
leaves it up to each locality to determine what level of changes (if any) are needed to their Plans.
• For example, some localities may only update one chapter or review their Plan and decide no
changes are needed, while others may rewrite the whole Plan. Localities also need to review
Virginia State Code to determine if there are any new State Code provisions that are applicable to
incorporate into their Comp Plan review.
• This review is an important opportunity to evaluate changing conditions, emerging issues,
updated priorities, any revised population and employment projections, and progress on current
Plan implementation.
Page 16 of 39
What is the City's process for reviewing the Comp Plan?
The process is still being scoped, and an initial outline is provided below. There will be opportunities
for community participation throughout the process, along with work sessions and finally public
hearings with the Planning Commission and City Council.
Page 17 of 39
How is the City approaching this Comp Plan review?
The Comp Plan review is an opportunity to evaluate and respond to challenges, opportunities, and
emerging issues that have been identified since the 2021 Comp Plan and subsequent Development Code.
• Recent (past 6-12 months) community feedback shows support for previously identified values and
goals, such as housing affordability and multimodal transportation, but differing opinions on the best
ways to achieve those outcomes.
• Larger projects close to "core neighborhoods" have drawn concerns especially regarding the potential for
displacement and neighborhood change.
• There is limited information to date on Development Code implementation, as the Code has only been in
effect since February 2024 and development applications have had limited time to fully move through
the process.
• There is continued community interest in topics that relate to and support land use and housing,
including transportation, protecting the natural environment and historic resources, and
parks/recreation.
Page 18 of 39
How is the City approaching this Comp Plan review?
The Comp Plan review is an opportunity to coordinate with the range of parallel City projects that are either
completed or in progress, which cover many of the 2021 Plan chapters.
Page 19 of 39
How is the City approaching this Comp Plan review?
Updated data and existing conditions analysis is needed to inform this project and respond to challenges,
opportunities, and emerging issues. An overview of the in-progress initial existing conditions analysis is
provided below and additional data for other topics will be gathered and analyzed throughout the project.
• Where have development and redevelopment been occurring?
• Types of development being built (including types of housing units) and distribution across the city
• How many affordable housing units have been built, and where?
• Including comparison of on-site vs paying in-lieu fees
• Where are development and redevelopment likely to occur moving forward?
• Buildout analysis
• Noting constraining factors, including financial feasibility and property owner decisions
on whether or not to develop
• What are the changing demographics of our community?
• Who is at most risk of displacement (e.g. cost-burdened households)
Page 20 of 39
Initial Data:
Existing Conditions
Analysis
Page 21 of 39
Regional Considerations
The following data and key takeaways were provided
by Hamilton Lombard (Demographer):
• For housing costs: Charlottesville metropolitan
statistical area (MSA) has become one of the
most expensive metro areas in the Eastern U.S.
• Growth in upper-income households in
Charlottesville MSA has increased at a faster pace
than in the U.S. overall.
• Few U.S. metro areas rely more on the Education
and Health employment sectors than
Charlottesville.
From the 2026 'State of the Community' Presentation: Median home value by
MSA, American Community Survey (ACS) 2023 (1-year
estimates); Charlottesville area highlighted with navy blue circle
Page 22 of 39
Regional Considerations
The following data and key takeaways were provided by
Hamilton Lombard (Demographer):
• An increasing share of the Charlottesville region's workers
live outside of Albemarle County and the City of
Charlottesville. Of the 352 U.S. urban areas with 100,000+
population, only the Boulder MSA has a higher % of
daytime population change, which is from in-commuters;
Charlottesville MSA is second highest.
• The availability of relatively higher income jobs within the
Charlottesville area (e.g. healthcare, finance, biotech)
along with the relatively lower cost of housing in
surrounding localities and regions, is one of the reasons for
this trend. This is occurring along with workers who are
unable to afford the cost of housing in the Charlottesville
area and therefore live further away.
2010
2023
Change in median household
income
From the 2026 'State of the Community' Presentation:American
Community Survey (ACS) 2010 and 2023 (1-year estimates)
Page 23 of 39
Where have development and redevelopment been occurring?
• Total completed residential units 2021-2025:
approx. 744 units
• Staff were able to estimate the total number of units
completed in the past 5 years and anticipate having
10+ years of completed units in future iterations of
this data analysis
Completed units by type of unit
2021-2025
Single-family detached (red) 108
Single-family attached (blue) 47
Two family dwelling (purple) 17
Additional dwelling unit (orange) 14
Multifamily (apartment, condo,
multistory unit) (green)
558
Manufactured housing unit 0
Approximate distribution of completed units by type 2021-
2025, using Cityworks permit data
Page 24 of 39
2023 Development Code: Projects Approved, In Progress, or Under Review
2023 Development Code
Completed
permits
(built)
Permits in
progress / under
construction
Permits under
review
47 47 27
• Development Dashboard (left) shows
projects that are approved, under review,
and under construction. This snapshot only
shows projects that are moving forward
under the 2023 Development Code, as of
August 2026
• Since the Dashboard is pulling from permit
data, there are several non-residential
projects included on the map as they have
associated permits/plans (e.g. building
modifications, bus stops, hotels)
Access the dashboard here:
https://www.charlottesville.gov/1902/Development-Map
Page 25 of 39
2023 Development Code: Completed Projects
Map and Pie Chart: Completed residential permits by
unit type that were approved under the 2023
Development Code
Page 26 of 39
Affordable Housing Units Estimates
• Total Affordable Units Completed 2009-2026: 561
• 85% of completed affordable units built in three neighborhoods: Belmont-Carlton, Ridge Street, & North Downtown
• 83% of affordable units in pipeline in three neighborhoods: North Downtown, 10th & Page, & Ridge Street
Affordable Units by Neighborhood
2009-2026
Belmont-Carlton 212
Ridge Street 160
North Downtown 106
Starr Hill 62
10th & Page 15
Fry's Spring 4
Woolen Mills 2
Total 561
Affordable Units Under Construction,
Approved, and Under Review by Neighborhood
North Downtown 288
10th & Page 264
Ridge Street 157
Fifeville 71
Locust Grove 53
The Meadows 19
Total 852
Page 27 of 39
Affordable Housing In Lieu Fees
• Total Affordable Housing In Lieu Fees (for completed projects) 2009-2026: $2,702,304
• In Lieu Fees for projects Under Construction: $11,103,080
• In Lieu Fees for projects Under Review: $8,160,685
Page 28 of 39
Measuring Neighborhood and Demographic Change
• There are multiple ways to estimate which areas may be at a greater risk of future
displacement and to measure where neighborhood change has been occurring. Examples of
data that can be used include:
• Cost-burdened households (spending more than 30% of income on housing costs)
• Demographics (e.g. age, race/ethnicity)
• Median household income
• Poverty rate and ALICE (Asset Limited, Income Constrained, Employed)
• Lack of health insurance
• Health indicators and outcomes
• Educational attainment
• Limited English Proficiency
Page 29 of 39
Measuring Neighborhood and Demographic Change
• The 2021 Comp Plan uses the designation of 'Sensitive Communities' to identify areas estimated to be at
a greater risk of displacement
• Comp Plan used the following criteria to identify which Census Block Groups were designated:
• Areas that are General Residential on the Future Land Use Map, and
• Have a relatively high proportion of households with income less than $30,000/year (which was
about 30% Area Median Family Income or 50% Area Median Household Income) and Black
residents, Hispanic residents, and other residents who do not identify as White and Non-
Hispanic (ACS 2018 5-year estimates)
• Comp Plan recommends revisiting the methodology for identifying communities at risk of
displacement with each 5-year Plan review
• This information can be used to help inform Comp Plan recommendations and priorities
• The next two slides include updated income distribution and housing cost-burdened data for
Charlottesville. Additional data sources to measure change and displacement risks will be identified
during the Comp Plan review process
Page 30 of 39
Charlottesville: Change in Income Distribution
• Consistent with Hamilton
Lombard's regional
findings, the
income distribution
is shifting towards higher
incomes
• This data does include
University of Virginia
students that live in
Charlottesville.
American Community Survey (ACS) 5-year Census data for 2015-2019 and 2020-2024. Incomes are not adjusted
for inflation.
Page 31 of 39
Charlottesville: Housing Costs
• Using 2024 5-Year American Community Survey data, approximately 40% of all Charlottesville
households are considered cost-burdened (paying more than 30% of household income toward
housing costs), including:
• 21.3% of homeowner households and
• 55.5% of renter households
Page 32 of 39
Example: Charlotte NC Comprehensive Plan
• The City is reviewing Comp Plans from a variety of localities to inform best practices, including
Charlotte, NC
• As part of their Comprehensive Plan update, the City of Charlotte developed an Equitable Growth
Framework with a variety of mapping and data analysis tools, including a 'populations vulnerable to
displacement overlay'
• Charlotte used this data analysis to identify areas where residents and businesses may not have
access to daily needs, choices for housing, a diversity of employment, or safe and healthy
environments
1. Informed the development of Goals and supporting Policies, Projects and Programs in the
Comprehensive Plan
2. Identified priorities for Community Planning Areas for subsequent mapping and planning efforts
within sub-geographies throughout the community
3. Assessing and tracking progress towards becoming a more equitable, fair and just city over the
next 20 years
Page 33 of 39
Example: Charlotte NC Comprehensive Plan
• Populations vulnerable to displacement overlay map
shown to the right. The analysis identifies residents
that have characteristics that tend to make them
more vulnerable to potential displacement. This map
was one in a series of Charlotte's Equitable Growth
Framework.
• Four measures have been documented as major
contributors to vulnerability to displacement and are
used to identify the areas with the most vulnerable
populations across Charlotte:
• Poverty Rate;
• Educational Attainment;
• Race; and
• Age
Page 34 of 39
Determining the Scope for
the Comp Plan 5-Year
Review
Page 35 of 39
Comprehensive Plan 5-Year Review: Objectives
The City's approach to this Comp Plan review informed the project
objectives, which are outlined on this and the following slide:
• Review and potentially update the City's Comprehensive Plan to
meet the State Code requirement for the 5-year review
• Update existing conditions and trends data, including updated
population and employment projections
• Incorporate any new (since Nov 2021) State Code requirements
for Comp Plans that apply to the City
• Align any Comp Plan updates with City plans that have
been completed since Nov 2021 (e.g. Climate Action Plan, Parks
and Rec Master Plan)
Page 36 of 39
Comprehensive Plan 5-Year Review: Objectives
• Evaluate current Plan strategies and priorities and where
changes are needed
• This would include any potential major policy or other
substantive Plan changes
• The community will be informed throughout the Comp Plan
review process and will be asked to provide feedback at key
points; this is an area where community feedback will be
especially important
• Establish a process for regular tracking and reporting on Plan
metrics and implementation progress, in coordination with the
City's Strategy Office
• Establish a framework and approach for Small Area Planning
• Coordinate across related projects that will be moving in parallel
(e.g. Mobility Plan)
Page 37 of 39
Questions for Determining the Comp Plan Review Scope
• Does the 2021 Comp Plan land use vision still align with today's community priorities and meet
current community needs? If changes are needed, what outcomes are desired and what
should they address?
• Would you anticipate the need to significantly change the Comp Plan and/or Development
Code approaches?
Page 38 of 39
Questions for Determining the Comp Plan Review Scope
• What are the main challenges, opportunities, and emerging issues that should be addressed with
the Comp Plan review? Staff would recommend building on the initial list as outlined in this
presentation and summarized below:
• Address continued concern about displacement and neighborhood change, especially
in/around 'core neighborhoods'.
• Increase multimodal transportation options to support new development and redevelopment
(noting that the Comp Plan review will be coordinated with the Mobility Plan).
• Address barriers to housing development (esp. missing middle housing) while protecting the
natural environment, ensuring the city has high quality public infrastructure and buildings,
and supporting walkability and quality of place.
• Align Comp Plan with new (since 2021) plans, streamlining and updating Comp Plan
strategies where possible.
• Revisit limited and smaller-scale commercial uses in residential districts.
• Provide opportunities for community members to learn and understand how the City makes
decisions and what tools are available, building on the Community Engagement chapter.