Planning Commission Meeting Agenda
July 28, 2026
100 5th Street Northeast
City Space Conference Room
Charlottesville, Virginia 22902
Carl Schwarz, Chair
Danny Yoder, Vice Chair
Ross Harness
Hosea Mitchell
Betsy Roettger
Lyle Solla-Yates
Josh Carp
Michael Joy
I. Commission Work Session
Beginning: 5:00 p.m. Location: (Cityspace, 100 5th Street NE, Charlottesville, VA 22902)
1. Development Code Cleanup Discussion
II. Future Meeting Schedule/Adjournment
Tuesday August 11 - 5:00 PM - Pre-Meeting Tuesday August 11 - 5:30 PM - Regular Meeting
Individuals with disabilities who require assistance or special arrangements to participate in the
public meeting may call the ADA Coordinator at (434) 970-3185 or submit a request via email
to ada@charlottesville.gov. The City of Charlottesville requests that you provide a 48 hour notice
so that proper arrangements may be made.
Planning Commission pre-meeting and regular meetings are held in person and by Zoom webinar.
The webinar is broadcast on Comcast Channel 10 and on all the City's streaming platforms
including: Facebook, Twitter, and www.charlottesville.gov/streaming. Public hearings and other
matters from the public will be heard via the Zoom webinar which requires advanced registration
here: www.charlottesville.gov/zoom . You may also participate via telephone and a number is
provided with the Zoom registration or by contacting staff at 434-970-3182 to ask for the dial in
number for each meeting. Written comments may be submitted via email to
planningcommission@charlottesville.gov.
Page 1 of 22
Page 1 of 2
TO: Charlottesville Planning Commission
FROM: Matthew Alfele, Development Planning Manager
DATE: July 28, 2026
SUBJECT: Development Code Clean-Up: Follow-Up Discussion on Active Depth, Setbacks, and
Build-To
Tonight’s Work Session continues the Planning Commission’s engagement in the 2026 Development
Code Clean-Up effort following the July 9th Subcommittee Meeting. Staff is bringing forward a set of
interrelated topics—Active Depth, Setbacks, and Build-To (which might be more of a conversation
around Nonconformity)—for full Commission discussion. These topics represent areas where
technical refinements may improve clarity, resolve internal inconsistencies, and provide more
predictable outcomes for applicants and reviewers. As with all items in this year’s Clean-Up cycle, the
focus remains on small, technical adjustments rather than major policy changes. Larger policy
questions raised through community feedback or prior Commission discussions will continue to be
tracked separately as part of long-range planning efforts, consistent with the established Clean-Up
framework described in the June 23rd Listening Session Memo.
Below is a brief recap from the Planning Commission’s Work Session from June 23rd framed around
receiving feedback form local builders and developers; and the Subcommittees work from July 9th.
At the June 23rd Work Session, the Commission engaged directly with local builders and design
professionals to hear how the Development Code functions in practice. Several key themes emerged
from that session:
• Conflicts between minimum Build-To widths and maximum building widths, especially for
townhouse or multifamily configurations.
• Requests for clearer interpretation of attached dwellings and building massing relationships.
• Interest in better defining how covenants or external conditions interact with Code standards.
During the Subcommittee’s July 9th work meeting, committee members focused directly on three
technical areas slated for refinement in the Clean-Up cycle:
1. Active Depth Standards
o Existing depth requirements in the different Zoning Districts may not reflect functional
realities—especially the upper-story 30’ requirement for DX.
CITY OF CHARLOTTESVILLE
Department of Neighborhood Development Services
City Hall Post Office Box 911
Charlottesville, Virginia 22902
Telephone 434-970-3182
Fax 434-970-3359
www.charlottesville.gov
Page 2 of 22
Page 2 of 2
o Subcommittee members noted that it might better serve the intent of the code to
allow a wider variety of uses to count towards “active space” and only call out what
should not be permitted.
o Discussions included exempting interior residential spaces while preserving ground-
level activation and transparency requirements.
2. Setbacks
o The group examined how Setbacks interact with Build-To, especially on constrained
sites, nonconforming lots, and locations where utility or environmental constraints
limit placement options.
o Consideration included whether technical flexibility could better support code intent
without creating loopholes.
3. Build-To
o The Subcommittee raised several instances where strict Build-To compliance
unintentionally prevents additions to nonconforming buildings—because a property
owner would need to first build new frontage solely to meet Build-To before adding to
the side or rear.
o Members encouraged framing options that maintain the street-engagement goals of
Build-To while allowing reasonable improvements to existing nonconforming
structures.
These topics directly set the agenda for tonight’s discussion and reflect the Commission’s expressed
interest in receiving practical feedback from practitioners before moving toward draft language.
Staff recommends the Commission focus on four key questions during the Work Session:
1. Active Depth
• Are current depth standards achieving activation goals?
• Should depth requirements differ between ground stories and upper stories?
• Should interior residential (regardless of Zoning District) spaces be exempted?
• Would adjusting the definition achieve many of these goals?
2. Build-To and Setbacks
• How should the Code treat nonconforming buildings where strict Build-To prevents functional
additions?
• Should alternative compliance pathways be created for existing structures?
• What technical tweaks might balance flexibility with urban design intent?
3. Integration Across Standards
• Active Depth, Setbacks, and Build-To function in combination—not isolation. Staff encourages
the Commission to articulate guiding principles for how these standards should relate and
support each other.
Attachments and Links:
• City's Development Review Webpage and Current Development Code
• Connect Charlottesville Development Code Clean-Up Page
• Code Amendment Working Document Updated July 21, 2026
Page 3 of 22
Development Code Proposed Amendments Working and Tracking Document 2026 (UPDATE July 21, 2026)
Page 1 of 19
UPDATED July 21, 2026
This is a working document and is ONLY INTENDED to log of Development Code issues and proposed amendments to the City’s 2023 Development Code (Chapter 34). The outline is divided
into three categories to help distinguish different issues and is not intended as a priority list.
Clarifications & Technical Fixes (A)
This category includes grammatical edits and minor changes. Public engagement should be limited to Public Hearings at Planning Commission and City Council. This will also include updates to the Development Code
required to stay in compliance with State enabling legislation changes.
Refinements (B)
This category includes edits and/or changes to sections of the code that will better reflect the intent statement of each section. Public engagement should be limited to Public Hearings at Planning Commission and City
Council. This sections also include changes to supporting documents such as the Neighborhood Development Services (NDS) Fee Schedule.
Policy Changes or Major Amendments (C)
This category includes edits, additions, and/or removal of language that could change the intent of the code and/or change established policy. These changes require dedicated study and analysis. Public engagement should
involve community outreach and inclusion through Long Range Planning.
Additional Categories
The additional categories that fall after “C” are intended to capture comments and suggestions from other sources. The “source” is indicated in the title of each section.
Key Point of Housing Keeping. Once an issue is assigned a number, i.e. A.1 or B.11 it should not be moved. When new issues are added or more spaces is needed on a
Tier ALWAYS ADD THE NEW ROW TO THE END OF THE TIER. If an issue is moved or removed from a tier, only strike through the issue and do not delete the row.
Example: Planning Commission wants to move “Existing structure preservation bonus does not specify a timeframe to qualify as an existing structure.” From Tier 3 to
Tier 2. The issue is being “crossed out” on C.8 and added to B.70 (as that was the next open row in Tier 2.
Clarifications & Technical Fixes (A)
Number Page Code
Section
Current Language/Issue Suggested Language/Change Respons
ible Staff
Date
Adopted by
CC
A.1 5-41 5.2.10.A.1 The Tree Removal Permit does not distinguish between a stand alone permit to remove a tree and
tree removal related to a larger site development (going through Development Review). This is
causing two applications for Development Plans and FSP .
Add a “b. Trees being removed as part of a project required to go
through Development Review.”
Carrie
A.2 Private Streets do not clearly indicate they must be on dedicated property and not easements over
underling private property. This is creating issues as the code uses a lot of “street side lot line”
which does not work well with easements.
2/10/26: Move to Tier 1 (needs to be addressed with the 2026 updates). Moved from B.11
Staff suggests updating the definition of Street under section 7 to
clearly state a street (public or private) is an independent parcel or
ROW.
Street: A street is a public or private way that provides a principal
means of access to abutting property and includes the roadway
and associated streetscape elements. Streets shall meet the
following criteria:
• Public Street: A street located entirely within a publicly
dedicated and accepted right-of-way, under the ownership
Carrie
Page 4 of 22
Development Code Proposed Amendments Working and Tracking Document 2026 (UPDATE July 21, 2026)
Page 2 of 19
and maintenance of a governmental entity and design per
the City’s Standards and Design Manual.
Private Street: A street located on a separate, recorded lot or tract
that is not part of any abutting property. Private streets shall not
be established solely by easement across private property and
must comply with the City’s Standards and Design Manual and be
bonded to the same standards as a Public Street during
construction. Ownership and maintenance shall be the
responsibility of a private entity such as a homeowners’
association or other legally binding documents.
A.3 Yard designation details
This could be a Tier 1 as the change might only involve including “primary building”.
2/10/26: PC moved to Tier 1. Moved from C.4.
6/16/2026: Reviewed by staff and this is not an issue due to the updated language from 2025
regarding primary structures and uses.
This section refers to primary structures, but we should consider
changing to primary buildings. If structures, a raised deck (etc.)
would qualify and we should work through implications.
A.4 4-17 4.4.5.A.1 The Street Typology Map needs revision. The Local designation is not in the legend, and the green
marking on the Mall needs to be removed as it is not a category on the map.
2/10/26: PC moved from C.9.
6/16/2026: The paper map will be worked on with the goal of embedding the map into the GIS
viewer. No text amendment is needed but should be pointed out during adoption.
Map quality is also substandard. Not a code change, but we need a
better map.
Dannan
A.5 5-9 5.1.6.B.2 Add Special Exception Permits The Administrator reviews and provides a recommendation on
Special Exception Permits per 5.1.1.
Carrie
A.6 4-20 4.4.5.D.9.c Add “RN-” districts RN- districts were left out of several sections of the code where R-
districts are referenced
Carrie
A.7 6-13 6.7.1.A.2.a.iv Remove “Provision of expertise and technical assistance to the Planning Commission.” The Planning Commission no longer has authority over
subdivisions per changes to state code.
Carrie
A.8 Review all new state regulations post July 1st. Full Team
and CAO
A.9 2.10.6 Build-
To
When permitted by the Zoning District, a project utilizing the Existing Structure. Preservation
Bonus for density will be deemed to comply with the Build-To requirements.
Update “utilizing” to “eligible”. Carrie
A.10 2-98 2.10.1.D B.10 on the 2025 list (did not move forward).
Yard designation details graphics.
2/10/26: No Comments from PC
6/16/2026: This is just a graphic fixt as the existing graphic shows a façade at 15’ that is not part of
the front yard. The graphic needs to be update to show the façade OVER 15’ away to not be part of
the front yard.
The text bases yard on street-facing facades, which are within 50-ft
of the lot line. It uses "the primary building's street-facing facade"
but it is not clear if it is the primary building or the primary facade
and how that is defined. So, the text reads that the yard is between
lot line and any facade which meets the street-facing facade
standard, or any facade within 15-ft of a street-facing facade. This
is inconsistent with the graphic.
Carrie
A.11 5-58 5.2.16.C.4 B.23 on the 2025 list (did not move forward).
City Council Decision details
“The City Council will conduct a public meeting on the application. The City Council may hold a joint
public meeting with the Planning Commission.”
8/12/2025: Staff note. Add this to next year’s (2026) review. Change Critical Slopes Planning
Commission and City Council action to match that of Special Exception Permit and/or what comes
out of the Long Range Planning Environmental study.
This language matches items such as SUPs which require a public
hearing, but not items like SEPs which require a public meeting
same as the Critical Slope SEP .
Carrie
Page 5 of 22
Development Code Proposed Amendments Working and Tracking Document 2026 (UPDATE July 21, 2026)
Page 3 of 19
2/10/26: PC would like staff to have more administrative authority but also wants to see the
results of the Long Range Planning Environmental study to see what is says regarding Critical
Slopes.
6/16/2026: To match of permit types that do not require a Public Hearing, remove 5.2.16.C.2.
A.12 2-101,
2-126,
2-127
See G.1 for more details. This is a graphic fix to show finished grade over existing grade. Update the graphics. Carrie
A.13 The Development Code only speaks to Width limitations when it comes to a Lot that is split Zoned.
We need to establish the governing standards
Draft language: when a lot has more than one Zoning designation
the more restrictive District standards apply to the lot as a whole.
If we make this update, we should remove the section (34-
.2.10.10.A.3.a) as the “general” language would capture this too.
Matt
A.14 5-37 5.2.9.A.2.a New construction or addition activities for any project with no public improvements exept
Streetscape improvements…
New construction or addition activities for any project with no
public improvements except Streetscape improvements…
Carrie
A.15 5-70 5.4.4.A.d Contributing structures and protected properties are not allowed to fall into a state of disrepair
that could result in the deterioration of any exterior appurtenance or architectural feature so as to
produce a detrimental effect upon the character of a design district of the life and character of a
contributing structure or protected property.
Contributing structures and protected properties are not allowed
to fall into a state of disrepair that could result in the deterioration
of any exterior appurtenance or architectural feature so as to
produce a detrimental effect upon the character of a design district
or the life and character of a contributing structure or protected
property.
A.16
Refinements (B)
Number Page Code
Section
Current Language or Problem Suggested Language or Issue in Question Respons
ible Staff
Date
Adopted by
CC
B.1 Sight
Distance
NA B.6 on the 2025 list (did not move forward).
Nothing in the new code provides details on a sight distance triangle.
May 27, 2025, Planning Commission Work Session: This needs more study as PC would not want
VDOT regs as it would create too large of a triangle.
9/9/2025: Due to timing this will be moved to the 2026 list.
2/10/26: No Comments from Planning Commission
Could use the section from the 2003 Code (Sec. 34-1121. - Sight
distance—Required sight triangle.) Collaboration with the City
Traffic Engineer before any change is made.
Brennen
B.2 2-98 2.10.1.D Moved to A.10
B.3 4-24 4.5.1.C.3 B.20 on the 2025 list (did not move forward).
Provides “linking” requirements before “direct” requirements, but this should be reversed to
match 4.5.1.C.2. Also not clear why we need a Type 1 and direct when they are one and the same
and vice versa.
10/7/2025: This amendment is not ready to move forward and will be placed on the 2026 list.
2/10/26: No Comments from PC
Reverse order and reconsider categories. Carrie
B.4 7-15 7.2 B.22 on the 2025 list (did not move forward).
Grade, finished.
9/9/2025: This needs additional study and will be moved to the 2026 list.
2/10/26: PC would like to know how the terrain of the City is taken into account. Is the issue
related to graphics within the code, or is it a larger issue related to terrain?
6/16/2026: This might just need a better definition of “Finished Grade”.
Additional clarifying language is needed. Is the intent to measure
at building footprint?
BK
B.5 5-58 5.2.16.C.4 Moved to A.11
B.6 5-37 5.2.9 B.37 on the 2025 list (did not move forward). We are looking at two options. 1 would keep our current policy of
allowing one and two units to go straight to Building permit review
Page 6 of 22
Development Code Proposed Amendments Working and Tracking Document 2026 (UPDATE July 21, 2026)
Page 4 of 19
Changes to the Development Code Process to allow more types of development to go straight to
Building Permit review
9/9/25 (more information will be provided after we meet with different departments and get
additional feedback).
2/10/26: PC is supportive and wants to see what comes out of the Missing Middle Round Table
discussions.
6/16/2026: This will not be worked on until after conclusion of the Missing Middle Working Group.
(codifying it). The other option (which is the one we are moving
forward) would allow development within the R districts (provided
certain standards are met) to go straight to Building Permit review
B.7 2-85 to
2-87
2.9.3.B Moved to ADC.1
B.8 4-27 4.5.2.C.1 B.41 on the 2025 list (did not move forward).
Required Bicycle Parking. The code is requiring Hotels to be treated as Commercial which is in turn
requires a unreasonable amount of bicycle parking.
2/10/26: Important issue to PC, but no guidance yet.
Staff reached out to Code Studio to make sure we were reading the
code section correctly and they responded in an email on
November 6, 2025 with: “Great question, under the current code
language, you are interpreting this correctly that a lodging use is a
commercial use and would be calculated as you have outlined.
This could be an opportunity for administrative relief, or a potential
text amendment where lodging uses get listed as a new line on the
bicycle parking table with lesser requirements. This could be per SF
or per room, for example, in Raleigh, NC we specified long-term
bike parking as 1 space per 20 rooms (4 min) and short-term bike
parking as 1 space per 40 rooms (4 min).Happy to brainstorm more
as needed, Christy”
Matt
B.9 Food truck courts (places in the City where multiple food trucks could gather. This came out of a
conversation that under the current Temporary Use section only one food truck is permitted per
lot. This is an issue, but it also prevents something like a food court for food trucks.
2/10/26: This is important to PC and something they want to be involved in (subcommittee)
An idea to address this is 1. Amend the temporary sections, and 2.
Look into the idea of an Alternant Form section for Food Truck
Courts.
PC/Sub/
Team/Cr
aig
B.10 2-108 2.10.4.C Outdoor Amenity Space. The requirements for outdoor amenity space is just a flat percentage and
does not take into account the quality of the space.
2/10/26: Not a priority to PC.
Could allow for less percentage if the amenity space is active
instead of passive. This is used in other localities and would take
some research.
B.11 7-21 7.2 Moved to A.2
B.12 2-9, 2-
13, and
3-4
2.2.2.A.B.1,
2.2.4.B.1, and
3.2.2
(3/13/2026) In the R districts (R-A and R-B) height is only restricted for Buildings with “units”. There
is no stated height for nonresidential uses and there are some nonresidential uses allowed in these
districts (Religious assemble and Day care,
Matt
B.13 4-11 4.3.2.B.2 Mid-block pedestrian pathways
2/10/26: PC would like to see more study. moved from Tier 3 (from C.7)
This section is set up on the assumption there is only 1 primary
street frontage, which is often not the case. Needs revision/study.
B.14 5-54 5.2.15.A A Special Exception Permits may be granted for physical dimensional standards described in the
following Division... needs revision to account for the determination that parking location and
other potential locations are permitted modifications allowed under SEP.
May 27, 2025, Planning Commission Work Session: PC did not feel removing or adjusting the SEP is
appropriate at this time.
The other issue is that Special Exception Permits are only for “physical dimensional standards” and
not the regulation for the standard. The example being a SEP could be requested to change the
dimensional standards of a bike parking space, but it could not be used to reduce the number of
spaces required.
2/10/26: PC moved this to Tier 2 (Moved from C.11).
Also consider removal of 5.2.15.A.2.a (Div 2.10 Rules for Zoning
Districts) per input from Freas on requiring a ZMA instead.
Staff would recommend changing 5.2.15.A.1 to state “The City
Council may grant a modification of any physical dimensional or
numerical standard of this Development Code by Special Exception
Permit.”
Matt
B.15 7-10 7.1.2.E.3.b Sublot access
2/10/26: PC moved to Tier 2 (C.15).
Add clarifying language that easement may be through other
zoning lots.
Carrie
Page 7 of 22
Development Code Proposed Amendments Working and Tracking Document 2026 (UPDATE July 21, 2026)
Page 5 of 19
B.16 2-133 2.10.10B.2 Active Depth Applicability
Planning Commission has expressed an interest to reexamine active depth. They would like to have
a better definition and look at where active depth is needed and where it is not needed. An
example would be the current requirement on the mall that active depth is the full height of the
building along the façade.
2/10/26: This is a priority to PC and they moved to Tier 2. They would like to look at the required
depth, definition, should it be in the residential districts at all, should it be on all stories of a
building. This is their #1 priority for Tier 2. This is something for the subcommittee and could move
back to Tier 3 if it proves to be too complicated and needs community engagement. Gagrages
need to be part of this study too (from C. 18) Moved from C.16.
This section prevents structured parking as a standalone use, but
the structured parking section (4.5.5.C.7) provides screening
requirements which may imply the standalone use is okay.
Language on 2-133 is contradictory regarding ground floor. The
section states Active Depth is for the portion of the building use to
meet the minimum build to width requirement. But that
requirement is only for ground stories of a building.
PC/Sub/
Team
B.17 2.10.5 and
2.10.6
Setbacks and Build-to. Planning Commission would like to do a deeper dive into the current
regulations related to Build-to and Setbacks.
2/10/26: This is number 2 priority to PC and something for the subcommittee to look into. Moved
to Tier 3. Moved from C.22.
Build-to width is creating a lot of issues. Utility requirements is a big issue as it takes away from
what can be done with sublots.
(October 14, PC work session)
2/10/26: This is creating a lot of issues, and we need to find a way to allow administrative relief. PC
moved to Tier 3 (Moved from G.14).
The new Development Code relies heavily on Build-to
requirements. This is very different from our old code, and it is
creating a lot of issues. It would be a big lift to redo the code to
remove Build-to regulations, but it might be worth studying where
there can be relief from the regulations. In 2025 we updated
sections of the code to allow relief for developments taking
advantage of the existing structure bonus. There might be an
opportunity to look at other such reliefs (buildings that are IPPs or
Contributing structures in the Design Districts).
PC/Sub/
Team
B.18 2-132 2.10.10.A.5 2.10.10.A.5: Building Width Exception. “The depth of the open space must be at least equal to the
width of the open space or 30’, whichever is less.” I propose reducing that minimum depth to 25’.
A building built over a parking garage is 60’ wide (1’+18’+22’+18’+1’). If you have a double-loaded
corridor building above the parking garage, a 30’ deep open space will cut into the corridor. The
depth should be no deeper than an apartment depth.
2/10/26: PC wants this on Tier 2. Moved from D.5.
PC/Sub/
Team
B.19 4-103 4.12 Nothing in the Lighting section addresses athletic field lighting. The maximum fixture height is 15’
and that would not work for ball fields.
2/10/26: This is not a priority to PC at this time but should be looked at latter.
6/16/2026: There is room to permit field lighting, but we should update the code to be clear that
filed lights are permitted in Parks (public use).
Language in city's Standards & Design Manual should be inclusive. Dannan
B.20 2-102 2.10.1.G This section defines average grade as calculated from the highest and lower elevation of existing
grade but should be set by finished grade.
Change “existing grade” to “finished grade.” Carrie
B.21
Policy Changes or Major Amendments (C)
Number Page Code
Section
Current Language Staff Notes
*Community Engagement and analysis will be required.
C.1 2-9
(etc.)
2.2.2.B.1
(etc.)
11/12/25: PC Work Session moved this back to Tier 3 as there needs to be a deeper dive into what
a Building is and if it is the Lot or the Building that needs to have more than one unit in it to get the
bonus height.
2/10/26: This could be a deeper conversation with PC.
Building height is for the number of units within the building. If you have one building and it
has more than one unit within the building, you get the additional height. If you have multiple
units on a site, but they are each in their own individual unit, you do not get the additional
height. This is problematic for R-A, R-B, and R-C.
C.2 2.10.10
Massing
11/12/25: PC Work Session moved this back to Tier 3 as there needs to be a deeper dive into what
a Building is and if it is the Lot or the Building that needs to have more than one unit in it to get the
bonus height.
Resolved 2025 with B.5 Accessory Uses/Structures and Nonconformity Build-to
Building is not clearly defined when it comes to “Height” and “Massing”. The example is: If I
have seven townhomes along a primary street in the R-B, the massing and height is all
dependent on where the property lines are for each unit. If it is seven townhomes with no
property line at the shared wall (all seven are on one lot in a condo) the “building’ can only be
60’ long on the primary street, but it is a building with seven units in it and can be 3 stories
(and 40’). But, if there are property lines running through the shared walls, each unit is a
Page 8 of 22
Development Code Proposed Amendments Working and Tracking Document 2026 (UPDATE July 21, 2026)
Page 6 of 19
2/10/26: Staff explained to PC that this was resolved with B.5 for buildings that cross a property
line (duplexes and townhomes) but not resolved for multiple buildings on one lot (building a large
SFD in the backyard of an existing SFD and getting the height bonus).
building and can, individually, be 60’ long, but only 2.5 stories (35’). From the outside they
would present very differently but the only difference is where the invisible property line is.
Staff believes this was resolved with the B.5 amendment as it added the definition of Primary
Building: “Building, Primary- The building or buildings occupied or designated for the
primary/principal use on a lot or site.” By adding “site” a building can now cross a property line
(duplex or townhouse) and be considered one “building” on a site for the purpose of bonus
height.
C.3 2-40 2.5.6.A.6 Will eventually reference Type B and D (in Category 1 as well).
Resolved 2025 with A.16
See Downtown Mall Management Plan for recommendations on transitions.
C.4 2-97 2.10.1.D Moved to A.3
C.5 2-104 2.10.2.B.3.c Lots having vehicular access from any street other than a primary street, or not having vehicular
access at all, must meet the minimum width required for lots with other vehicular access specified
by the zoning district.
2/10/26: More information is needed, but this could be a Tier 1.
Assuming this is meant to describe the "side/rear access" width in the districts, should this say:
"...from any side street, alley, easement, or other right-of-way not designated a primary
street..."? This seems confusing because it only says "from a street or no access" which leaves
out everything I listed out.
C.6 Various Various Structure, accessory structure, etc.
Resolved 2025 with B.5 Accessory Uses/Structures and Nonconformity Build-to
Deeper dive on structure, accessory structure, and associated requirements. Consistency
issues, as well as intent (interior non-conforming lots vs corner non-conforming lots).
C.7 4-11 4.3.2.B.2 Moved to B.13
C.8 4-5 4.2.1 Existing structure preservation bonus does not specify a timeframe to qualify as an existing
structure.
Moved to Tier 1 (A.70) by Planning Commission at the work session on May 27, 2025
Moved to Tier 2 (B. 42) by Planning Commission at the Work Session on November 12, 2025
Resolved 2025 with B.42
Code Studio has verbally stated that this is for structures pre-dating the code, but that is not
specified here. As written, someone can build a structure and then immediately use it to get
the bonus as an existing structure.
C.9 NA 4.4 Moved to A.4 Map quality is also substandard.
C.10 4-27 4.5.2.B.2 Projects with 1 to 4 dwelling units are not required to provide short-term or long-term bicycle
parking.
2/10/26: Not a priority to PC.
Consider whether this should be applied per lot or per project. Tie to discussion of definition of
project. Do we want project with 4 or fewer dwelling units to be exempt from short and long
term bicycle parking?
C.11 5-54 5.2.15.A Moved to B.14
C.12 7-19 7.2 Project Any activity, including subdivisions, new construction, additions, site modifications, façade
modifications, changes of use, renovations, and maintenance and repair, on a parcel that is
controlled by this Development Code.
Staff determined that this is not an issue due to section 7.1.1.K.1.d Tenses and Plurals
2/10/26: Not an issue for PC.
Language implies this is only upon one parcel. Discuss intention and revision.
C.13 7-8 7.1.2.C.4 Site Modification
2/10/26: PC would like staff to look at this more, it is a little confusing and might not be an issue.
If you read this with what a "site" is under E on page 7-9, a Site Modification is only a change to
the land and not what is on it. We need something more like our old Site Plan Amendment.
Site: A single lot or group of connected lots owned or functionally controlled by the same
person or entity, assembled for the purpose of development.
Lot: A parcel, tract, or area of land established by a plat or other means as permitted by law,
which is to be used, developed, or built upon.
Site Modification: Any modification of an existing site that affects less than 50% of the existing
site area, up to 25,000 square feet of affected site area.
Staff recommends changing the definition of a Site to “A single lot, group of connected lots , or
improvements, owned or functionally controlled by the same person or entity, assembled for
the purpose of development.” Additional study is suggested.
C.14 7-9 7.1.2.E.2 Defining a lot
Staff determined that this is not an issue due to section 7.1.1.K.1.d Tenses and Plurals
2/10/26: Not an issue for PC.
This and the definition of parcel should be considered together.
Parcel. A contiguous portion of land that is assigned a unique identification number by the
Office of the Assessor. (7-19)
Page 9 of 22
Development Code Proposed Amendments Working and Tracking Document 2026 (UPDATE July 21, 2026)
Page 7 of 19
Lot: A parcel, tract, or area of land established by a plat or other means as permitted by law,
which is to be used, developed, or built upon. (7-9)
C.15 7-10 7.1.2.E.3.b Moved to B.15
C.16 2-133 2.10.10B.2 Moved to B.16
C.17 2-148 2.10.13 Entrances
2/10/26: Keep here and look at in the future.
Update to match previous determinations or better clarify.
C.18 4-43 4.5.7.C Moved to B.16
C.19 4-103 4.12 Move to B.19 Language in city's Standards & Design Manual should be inclusive.
C.20 4-32 4.5.3.D.2 This section contradicts 4.5.1.C.a.i.d which calls for all pedestrian paths to be physically separated
from the motor vehicle use.
2/10/26: Not an issue or priority for PC. They do not see small scale development having
pedestrian and vehicular traffic overlapping. Look at this in the future.
C.21 4-80 4.10.1.B.1 Critical Slope regulations are redundant given current VESMP regulations for larger developments,
which require engineered erosion and stormwater plans to be approved for land disturbance
greater than 6,000 square feet.
This is being studied as part of the Comprehensive Environmental Study and Update by NDS Long-
range Planning Division as part of the Department’s 2025/2026 Work Plan.
Add language: “Critical slope requirements apply to project sites not subject to Erosion and
Stormwater Management (ESM) Plans that include any portion of sloped area that has all of
the following criteria:”
C.22 2.10.5 and
2.10.6
Moved to B.17
C.23 Moved to B.17 and added to the setback issues.
C.24 The 6' Min/Max determination for ground story is too limiting for the topography in this area
leading to a need to break larger buildings into many modules which is very inefficient from a
construction perspective
Revert to the previous ground story definition of 50% of the floor above/below grade to define
ground story or provide administrative alleviation for larger sites on hills
Dan Bracey – Two Street Studio October 2025
2/10/26: PC believes the terrain of the City needs to be taken into consideration. Not a priority
now, but moved to Tier 3 (Moved from G.18).
C.25 2/10/26: PC would like to do a deep study of “Nonconformity” (such as lots, uses, and buildings).
To see what can really be achieved with our current built environment. Not a priority now, but in
the future.
Clarify Nonconformities. Clarify Expansions (any addition) 7.1.2.c "Project Activity". What are
BAR definitions- these should be stated. Additon (ok), façade modification, but nowhere is
there 'Alteration', rehabilitation, maintenance and repair, restored (restoration)... Anything that
is not subdivision, new construction, or change of use. Under 5.3.3.b.2- If the activity
associated with a nonconforming structure is not a subdivision, new construction, or a change
of use, per 7.1.2.c, is also a contributing structure in an ADC district, HC District or an IPP
(remove double comma) then that structure is not required to meet any development standard
that would require modifications to the existing structure to make it conforming, and that
activity requires an approved CoA. Part II of this: Definitions are inconsistent. Ex: Renovation
can be rehabilitation and vice versa. Planning suggestion: what you are working on must
become conforming/must meet current standards. Suggests new section under
nonconformities that addresses rehabilitation/restoration. Parallel w/ historic signage.
C.26
C.27
C.28
C.29
Architectural Design Control
Page 10 of 22
Development Code Proposed Amendments Working and Tracking Document 2026 (UPDATE July 21, 2026)
Page 8 of 19
ADC.1 2-85 to
2-87
2.9.3.B-C.1 B.39 on the 2025 list (did not move forward).
Individually Protected Properties are represented as both a chart and an overlay on the official
Zoning map. This creates issues as any change (adding an IPP or removing and IPP) requires both a
Zoning Map amendment and a Zoning Text amendment
2/10/26: No Comments from PC
Staff recommends removing the chart and only using the overlay on the official Zoning Map.
Update June 2026: Leave IPP chart in Code. (No change requested)
ADC.2 5-34 5.2.8.a.c.i Under Applicability for Corridor Review, C. “Regardless of whether a building permit is required:”, i.
“Site modifications;” with no noted exceptions could be interpreted to mean all properties where
there are proposed site modifications (including residential less than 2 units) must be reviewed by
design staff or the ERB.
Insert similar language as written under 5.2.8.a.c.iii “other than those on projects with up to 2
dwelling units.”
Suggested change for 5.2.8.a.c.i - “Site modifications, excepting those for residential projects
with 2 dwelling units or less per lot;”
ADC.3 4-82 4.11.3.a.2 Current language: For signs within an ADC District, HC District, Entrance Corridor, or an IPP , a
Certificate of Appropriateness will be issued in lieu of a Sign Permit according to 5.2.6 Minor
Historic Review, 5.2.7 Major Historic Review, and 5.2.8 Corridor Review. Issue: In practice, design
review is accomplished as a review task within the sign permit workflow and issued by zoning.
Modify text to state a Sign Permit application is in lieu of CoA application and approval of the
sign permit constitutes an approved CoA. Because a sign must meet the sign regs (zoning)
elevating the CoA implies that it confers zoning approval, which we stress it does not for other
CoA requests. Design staff only reviews an application after zoning determines it meets code.
Resolve with 5.2.7.E.2.b
ADC.4 4-90 4.11.9.C Table for Maximum Sign Area; Issue #1) HC Districts & IPPs are not identified under Overlay
Districts in the Zoning Districts column, nor is a Total Sign Area (max) assigned for HC Districts or
IPPs.
Amend the row under Overlay Districts to include HC Districts and IPPs as having a maximum
total sign area of 12 square feet. HC Districts and the majority of IPPs are within residential
neighborhoods; the total sign area should therefore not exceed 12 SF.
ADC.5 4-90 4.11.9.C Table for Maximum Sign Area; Issue #2) Clarify max sign area where width of the building limits the
size, regardless of the maximum size permitted.
Confer with zoning on possible language
ADC.6 4-86 4.11.5.F.1 Regarding signs in ADC Districts, HC Districts, Entrance Corridors, and IPPs, this section does not
reference the applicable Design Guidelines (3 different sets) as adopted by Council.
Suggested revision: 4.11.5.F.1 “The character of all signs must be harmonious with the
character of the structure on which they are to be placed. Among other things, consideration
will be given to the following, including the appliable Design Guidelines:” [begin list a.-e.]
ADC.7 5-3; 5-4 5.1.1 Table for Review Authority: 1) Sign Permit has no designation under BAR. 2) ZTA & ZMA have no
designations under BAR. 3) SEP & SUP have no designations under BAR.
Amend the table to include BAR authority designations as appropriate: 1) “A” for Sign Permit;
2) “R” for ZTA & ZMA; 3) “R” for SEP & SUP .
ADC.8 2-112 2.10.5.C.3.a Existing Setback Range- When the zoning district specifies the primary street setback as “Existing
Range” the minimum and maximum primary street setback defining the build-to zone may be
modified as follows: a) The required primary street setback may be met within the range of existing
primary street setbacks, no closer than the smallest setback in the range and no further than the
largest setback in the range. Issue: As stated, this requirement conflicts with summary of districts
and subareas.
Setbacks and summary of districts. Applies only in Residential, remedy is SEP or remove the
building. On corners, this is especially problematic. Suggest BAR should be allowed to do its job
in overlay districts regarding setbacks as each sub-area of a district is unique and should be
addressed on a case-by-case basis. Suggested language: In ADC/HC/IPP design overlays,
minimum and maximum setbacks are determined by BAR review using the City's Design
Guidelines per 2.10.9.3.a.3
ADC.9 2-84;2-
90
2.9.2.C.3/
2.9.3.B/
2.9.4.E
Clarity is needed/redefine “contributing structures”. 1)Refer to maps in Design Guidelines 2) Add language: Unless designated by Council no
structure less than 50 years old shall be a contributing structure. (This would alleviate BAR
review for demolitions of recent/modern buildings within an ADC/HC/IPP districts.) 3.
Alternately, work towards automatically identifying any building 100 years old as contributing
(formerly the City’s process, especially for IPP designations).
ADC.10 5-32 5.2.7.E Period of Validity, refine language; an update may be necessary regarding City Council’s or a court’s
approval. (Is that approval a CoA, and does it have a period of validity?)
See language from City Attorney's Office; update pending.
ADC.11 5-34 5.2.8 There is no Period of Validity for Entrance Corridor CoAs. See language from City Attorney's Office; insert new section as in 5.2.7.E
ADC.12 5-28 5.2.7.C City Council may approve a CoA. There is no provision in this section. Insert 5.2.7.C.3 City Council Review. Staff note: Also look at where "Must Approve" is
mentioned.
ADC.13 2-85 2.9.3/2.9.2 Naming conventions: Individually Protected Properties (-IPP); Architectural Design Control District
(-ADC). Within the IPP section there is no reference to the ADC District Design Guidelines.
Suggest referring to IPPs as Minor ADC Districts (and ADC Districts as Major ADC Districts), to
imply application of the ADC District Design Guidelines under 2.9.3.D
ADC.14 2-85 2.9.3.B Established Individually Protected Properties – the current table of IPPs should reflect recent
updates.
1)Update IPP table to match City Council Adoption in 2023; 2)Update IPP table to include 801
West Street (pending CC ZTA/ZMA on CC Agenda July 20)
ADC.15 2-85 2.9.3 The current TMP and Zoning Map designations for the IPPs are missing important historical
context; there should be definitions for what the overlay applies to. Example: where a “(portion)”
of a parcel is being referenced within the IPP table.
Historic documents (deeds, plats, etc.) along with the CC Resolution of Adoption should be
referenced as the definitive source of the IPP overlay. Methodologies and recordation
technologies advance, therefore the Zoning Map Overlay layers evolve, especially when parcel
Page 11 of 22
Development Code Proposed Amendments Working and Tracking Document 2026 (UPDATE July 21, 2026)
Page 9 of 19
data is updated. Defining the boundary as TMP on day of adoption (or similar), with reference
to NDS archives (as primary source documentation) should alleviate questions and concerns
when the Overlay and TMP do not exactly align, or where gaps or excluded portions exist.
ADC.16 2-125 2.10.9.A.3.a.ii In Downtown Mixed Use (DX), where the BAR has authority, the maximum height is determined
based on BAR review using their design guidelines. In areas outside of BAR authority, the maximum
height is determined by the maximum number of stories and feet allowed by the zoning district.
Issue: refine reference to the Design Guidelines; clarify intent.
Change “their design guidelines” to City Council’s adopted ADC District Design Guidelines.
Building height: Areas outside of BAR authority. This was intended to state heights in an EC
cannot be reduced by ERB. Is this intent clear?
ADC.17 5-7 5.1.5.B.5.c-d Composition (BAR seats) c. 2 owners of businesses or commercial property...; 1 owner of
residential property...
Is it necessary to clarify if these criteria include condominiums within a building?
ADC.18 The definition of expansions complicates development review applications for historic structures. See Preservation & Design Planner notes regarding expansions and project activities.
ADC.19
ADC.20
ADC.21
ADC.22
Department of Utilities
Util 1. 4.6.3.A Refers to Standards and Design Manual (SADM) but should also reference the SADM “and
Appendices.”
Util 2. 4.6.3.C Consider clearing up “public service line” to the “public portion of the utility extensions.”
Util 3. 4.6.5 Add a statement like 4.6.3 A to this section that references SADM and Appendices, and easements
for public stormwater systems as well.
Util 4. 4.6.7 First sentence, add Sanitary Sewer and Storm Sewer.
4.6.7 C, add Sanitary Sewer and Storm Sewer.
4.6.7 E convey easements
• Add the project developer must convey easements to #3
• the City for public utilities to serve sublot as defined in Dev Code
• Add the project developer must convey easements to #4
• private property owners, and/or common interest communities being served.
Util 5. 6.1.2.B o Standards and Design Manual add “and Appendices”
o Utilities’ standard drawings should also be referenced.
Util 6. 6.1.4 • Off-site improvement contributions (further legal review and discussion)
o As it reads, the developer pays the City to make the improvements, but there are
issues with this precedence. This obligates City resources to make improvements
for private development. Theres a timing issue with this too, if we go too early and
the development fails, or the developer moves too quickly, and we can’t meet their
timeline. Also, developer plans change too frequently to comport with City design,
bidding, and contracting processes to complete work.
▪ SADM Appendix Part 3.01 A6 says offsite changes must be considered to
serve the entire watershed of the subdivision or development.
o The developer should be responsible for the offsite improvements necessary, and
the City can contribute to betterments, if we deem the betterments necessary.
▪ Sewer and Water Capacity models will be developed by the end of the year
and will provide guidance when off-site improvement may be necessary to
support the added demands.
o Further review of State Code
Page 12 of 22
Development Code Proposed Amendments Working and Tracking Document 2026 (UPDATE July 21, 2026)
Page 10 of 19
▪ § 15.2-2243. Payment by subdivider of the pro rata share of the cost of
certain facilities.
▪ How the state code interacts with off-site requirements needs some more
consideration and what obligations could be.
▪ We should have legal review of the State code as part of these discussions.
o Do we have any City ordinances already about offsite development and costs to
the developer or City?
▪ Do we need develop an ordinance or can we write it in the code at this Tier
level for code cleanup? Could these obligations require a public hearing
over a code cleanup?
o Should gas be mentioned in this section.
▪ Developer would not install but would reimburse the City to install gas
services if part of the development needs.
Util 7. 6.1.5.B • “sewerage system”, is inconsistent language with other areas. Please use Sanitary Sewer
and Storm Sewer
• What is a “public access street”, no definitions for this term?
Util 8. 6.1.5.C • Change Certificate to “Certification” of Completion (CoC) is for Utilities, what do streets
use?
• Consider rewording to reference Utilities only with the CoC
Util 9. 6.2.1.B • Permanent Access Easement also needs to include permanent water and sewer easement
at the very least. This could create islands where the back lot wants to develop first but
can’t get an easement sorted out with the lots in front and prevent access to water and
sewer and future occupancy. This would render the lot undevelopable if water and sewer
cannot be provided due to adjacent landowners that may not have been aware that their
lot needed to provide someone with sewer and water access.
• Water and sewer easements are mentioned in 6.2.2 A 2, but it doesn’t designate it as
Permanent or requirement for the sublot.
Util 10. 6.2.2.A • #1 add “whether immediately proposed or necessary for adequate service in the future”
• Doesn’t specify gas currently. Needs to add Gas Service to easements.
• Does not currently specify public or private storm drainage facilities.
Util 11. 6.2.2.B Something to reflect access within the easement should be added
Util 12. 6.6.1.A “sewerage system”, is inconsistent language with other areas. Please use Sanitary Sewer and
Storm Sewer
Util 13. 6.6.1.B This should include Gas easements.
Util 14. 6.6.1.B.3 • Our understanding is after the Subdivision Plat is complete there will not be a Final Plat.
Currently, the deeds are being written along with the Subdivision Plat and recorded as part
of site plan approval processes.
• Do we expect to see Final Plats? How or when does this current language become
applicable?
Util 15. 6.6.1.C.1 This should be clarified to make the distinction between required “private” infrastructure and
“public” infrastructure that is necessary to drain ROW and/or public property. The ownership and
maintenance responsibility needs to be clarified in the easement language and noted on the plat.
Util 16. 6.6.1.C.2 • We have not been recording easements along streams since I have been here. We like this
requirement but are not sure how to implement, or to what extent along the stream the
Page 13 of 22
Development Code Proposed Amendments Working and Tracking Document 2026 (UPDATE July 21, 2026)
Page 11 of 19
easement would/should cover. Consider further discussion with Dan Frisbee and Brennen
Duncan.
• This should be expanded to clarify ownership and maintenance responsibilities. The
easement should be for city access, inspection and possible reconstruction. Long term day
to day maintenance should be the property owner’s responsibility. This and 6.6.1(C)(3)
should be worded to be in line with each other. Ownership and maintenance are also
referenced in 6.6.1(C)(6). All three should support each other.
Util 17. 6.6.1.C.6 • Our understanding is after the Subdivision Plat is complete there will not be a Final Plat.
Currently, the deeds are being written along with the Subdivision Plat and recorded as part
of site plan approval processes.
• Do we expect to see Final Plats? How or when does this current language become
applicable?
Util 18. 6.6.2 “Semipublic” is not a defined term. Please define or reword this.
Util 19. 6.6.4 • Needs cleaned up.
• Better reference to acceptance process.
• Gas is not mentioned.
Util 20. 6.7 • Plats and processes could use more direction.
• Permit portal has 5 different types of plats that can be submitted.
Planning Commission
Number Page Section Notes Staff Notes
D.1. 4-18 4.4.5.A.3 Before the code was approved, I had asked James what happens if you can’t fit the required greenscape and walk zones in
the right of way, and my understanding was that the building setbacks would be moved back to allow for them to be
installed. For example, if you have a maximum setback of 10’, and due to site constraints, the streetscape can’t fit, that
maximum setback would be moved back enough to allow it to fit. That’s how I interpret section 4.4.5.A.3. “When there is
not enough room in the public right of way for the required streetscape, the clear walk zone and greenscape zone must be
provided on-site as a permanent public access easement.” Are we enforcing this? In preliminary discussions with applicants
to the BAR, we’ve had some say they spoke to staff and are unable to provide the required street trees because of the
maximum setbacks.
After reviewing with staff and the code. This interpretation is correct
and has been utilized by Planning staff. Other types of easements
such as utilities is not contemplated in the code but is being
addressed with this batch of amendments.
D.2. Doors swinging over the ROW. The building code actually prohibits this, but there have been instances where it has been
excused by our code officials because there’s not life safety issue. Can we add to the zoning code that doors should not swing
over the public sidewalk?
2/10/26: PC Chair would like this not to happen, but not a priority to the PC. No movement at this time.
D.3. Definition of an entry: I think you all are on this after the apartment project at 1609 Gordon Ave. Does an entrance have to
open to an active space? Should it be allowed to go to a garage, internal courtyard, or exterior stair? We should add some
clarity to the code on this.
2.10.13 Entrances (page 2-148) The Street-Facing Entry Spacing
states “A maximum distance between street-facing doors providing
access from the public realm to the interior of a building.” For this
project (RX-5) the code requires an “Entry Feature” and “A street
facing entry every 40’ or 60’ depending on the type of street. This
section of the code is very confusing and convoluted. It would need a
lot of thought and work. Alternate Viewpoint: Can we discuss the
intent of this provision? Why is this a requirement? Does an
entrance have to open onto an empty space? It seems to add a layer
of red tape, and is unnecessary aesthetically. Single use buildings
have controlled access. We want to avoid false elements in design.
Garden apartments should not have an entrance every x amount of
feet... they are designed as a one entrance plaza.
Page 14 of 22
Development Code Proposed Amendments Working and Tracking Document 2026 (UPDATE July 21, 2026)
Page 12 of 19
D.4. Active Depth – this seems to keep coming up as preventing buildings from providing internal parking. Is it too deep? Do we
need to consider some exceptions or methods for providing internal parking?
D.5. 2-132 2.10.10.A.5 2.10.10.A.5: Building Width Exception. “The depth of the open space must be at least equal to the width of the open space
or 30’, whichever is less.” I propose reducing that minimum depth to 25’. A building built over a parking garage is 60’ wide
(1’+18’+22’+18’+1’). If you have a double-loaded corridor building above the parking garage, a 30’ deep open space will cut
into the corridor. The depth should be no deeper than an apartment depth.
2/10/26: PC wants this on Tier 2. Moved to B.18.
D.6. Ground floor definitions seem to keep tripping people up on sloping sites. Are ours too strict?
D.7. 4-31 4.5.3.D.1.a.vii Driveway widths – there seem to be no regulations for driveway widths for single family and duplex lots. 4.5.3.D.1.vii seems
to show maximum widths, but I understand that staff interprets the code as there being no maximum width for single family
or duplex parcels.
Staff does enforce this requirement. The issue can arise from the
fact that “parking” space are not defined for any lot with less than
6 spaces.
D.8. Fences vs guardrails (I assume you all are already on this).
D.9. Existing buildings under BAR review – what changes are allowed: There seems to be a debate about the level to which
contributing buildings in ADCDs are subject to the zoning code. Under the nonconformities section 5.3.3.B.2:
“If the nonconforming structure to be expanded is also a contributing structure in an ADC District or HC District, or an
Individually Protected Property, then that structure is not required to meet any development standard that would require
modification of the structure itself, and the Board of Architectural Review must approve a Certificate of Appropriateness for
the proposed expansion.”
I read that section as saying that if you add onto a contributing structure, the existing structure doesn’t need to be modified
to meet the zoning code. In a couple of cases, it appears that staff has interpreted that as saying that the existing building
can also be modified in ways that are counter to the zoning code. This could be making it less compliant with transparency
requirements by removing windows or removing required entry features for instance. Can we clarify exactly what is allowed
to happen when a non-conforming contributing structure is modified and/or added onto?
Please let the BAR do their job. Nonconformities are linked in part
to our comments under C.25… we believe this is more of a concern
related to BAR and limited authority to address height in some
locations. (And we have a mechanism for that with very clear
instructions.)
D.10. See B.1: Side lot line (min) 4’
(R-A, RN-A, R-B, and R-C). This section is preventing single-family attached style housing on abutting Zoning lots.
May 27, 2025, PC work session: PC does not like the Alternate Form approach and finds that it could be cumbersome. Staff
will keep this in mind but is still focused on the Alternate Form as the best solution.
D.11. See A.70: Existing structure preservation bonus does not specify a timeframe to qualify as an existing structure.
Moved by PC to Tire 2 (from Tire 3) at the May 27, 2025 Work Session. They want to use CodeStudio date of the code
adoption as the preservation date.
Remove preservation from the document (substitute as existing
structure retention bonus?) Utilize language consistent with the
profession; NRHP guidance is at least 50 years of age.
D.12. See B.6: Nothing in the new code provides details on a sight distance triangle.
May 27, 2025 Planning Commission Work Session: This needs more study as PC would not want VDOT regs as it would create
too large of a triangle.
D.13. See B.4: Lots with 1 dwelling unit do not have to provide street-facing entries.
May 27, 2025, Planning Commission Work Session: PC does not see this as an issue and suggests something more in line with
a street facing feature and not a entry.
Staff originally placed this on the list to highlight that “lots” with
only one dwelling do not need a street-facing entry. This is
regardless of Zoning District and a little ambiguous. Is this stating
that a lot with a commercial building AND one dwelling unit would
not need a street-facing entry? Staff may suggest:
“Lots in the R-A, RN-A, R-B, and R-C Zoning Districts do not have to
provide street-facing entries on a single unit residential dwelling
provided no additional dwellings or uses are provided.”
D.14. See B.13: Vehicle Access.
May 27, 2025, Planning Commission Work Session: PC does not see an issue with what is in the Development Code, and it
should not be changed to satisfy PWE or Fire.
D.15. See B.15: This section is only about Unit Bonus allowances in residential districts, but R-C also has a Height Bonus which is
not detailed.
Page 15 of 22
Development Code Proposed Amendments Working and Tracking Document 2026 (UPDATE July 21, 2026)
Page 13 of 19
May 27, 2025, Planning Commission Work Session: PC did not think the 50% AMI should apply and that this section is not in
line with the intent of the code.
D.16. See B.27: Canopy set at 10 years
May 27, 2025, Planning Commission Work Session: PC brought this up, but only acknowledged it was an issue with no more
explanation.
D.17. See C.11: A Special Exception Permits may be granted for physical dimensional standards described in the following
Division... needs revision to account for the determination that parking location and other potential locations are permitted
modifications allowed under SEP .
May 27, 2025, Planning Commission Work Session: PC did not feel removing or adjusting the SEP is appropriate at this time.
D.18. See B.14: Fence. A constructed vertical barrier of wood, masonry, wire, metal, or other manufactured material, or
combination of materials erected to enclose, screen, or separate areas. A fence differs from a wall in not having a solid
foundation along its entire length.
May 27, 2025, Planning Commission Work Session: PC thinks we could exclude guardrails or measure fence from floor
surface and allow 42-inch everywhere (should satisfy ABC). Also guardrail on a wall is exempt, use for elevated surfaces as
well (café example, elevated deck). B.17- confusing. There seems to be some standard that needs to apply. B.21- Fence type
x, think its about storage fencing? Or is this supposed to be landscape/transition requirement instead?
D.19. See B.17: Where existing streetscapes are determined to be in good condition by the Administrator, they may be used to
comply with clear walk zone and greenscape zone requirements provided they comply with all standards in this Division.
May 27, 2025, Planning Commission Work Session: PC found this language to be confusing and believes there needs to be a
standard.
D.20. See B.21: Fence Type X
May 27, 2025, Planning Commission Work Session: PC is not sure what this is for, fencing for storage, or for landscaping and
transition requirements.
D.21. See B.26: No building located on a lot may be wider than the maximum building width allowed by the zoning district.
May 27, 2025, Planning Commission Work Session: PC recommended requiring the owner to rezone the lots into one zoning
designation.
D.22. See B.5: At the November 12, 2026 PC work session, the PC wanted to add this (allowing more primary buildings on a lot
without first bringing it up to conformity in regards to Build-to) to a the list to look at in the future.
D.23. 11/12/25 PC Work Session: PC would like to look into this more as active space and active depth created a lot of conversation
(with a lot of it around the term “hall”). For now PC is okay with staff language, but they would like to revisit the concept and
where is should be used. (B.24)
D.24. 1/12/26: PC Chair would like to look into more opportunities to find existing structures “in compliance” when it comes to
build-to and setbacks. This came out of B.38 which states “When permitted by the Zoning District, a project eligible for the
Existing Structure Preservation Bonus for density will be deemed to comply with the Building Setback requirements.” And
“When permitted by the Zoning District, a project utilizing the Existing Structure. Preservation Bonus for density will be
deemed to comply with the Build-To requirements.” The Chair would like to see this expanded to the Design Control Districts.
D.25. 6/23/26: Evergreen Builders – Building width requirements can conflict with Build-to requirements.
D.26. 6/23/26: Gennie Keller – Reminder that Historic Preservation is part of Development. R-B is confusing and scattered
throughout the City and might not make sense.
D.27. 6/23/26: Neil Williamson - Affordable units should be for 30-years and not 99-years. SWM regulations need to go from 6,000
SF to 10,000 SF.
D.28. 6/23/26: Nicole Scro – Sublots should be allowed in the Corridor Districts (X) districts. Development review needs to be
predictable. Need reasonable easement requirements for things like utilities (current requirements call for too large of
easements). Front yard parking regulations should be relaxed.
D.29. 6/23/26: Valerie Long – Development Plans should not require a CoA. That should come during Final Site Plan approval.
D.30.
D.31.
Page 16 of 22
Development Code Proposed Amendments Working and Tracking Document 2026 (UPDATE July 21, 2026)
Page 14 of 19
D.32.
D.33.
D.34.
D.35.
D.36.
D.37.
D.38.
Tree Commission
Number Page Section Notes Staff Notes
E.1. Incentives for Tree Preservation - Reevaluate the city's current incentive structure for tree preservation to reward developers
who retain healthy, large trees on-site and to ensure that preservation of mature trees is seen not as an obstacle but as a
shared value and goal. The current incentive structure—where existing trees are allowed to contribute 1.50-4x canopy area
toward meeting minimum canopy requirements—is not effective at promoting overall tree canopy cover in the city. Consider,
for example, an incentive structure to reduce or waive stormwater fees as an incentive to preserve mature trees.
E.2. Bonds for Existing Plantings - Expand circumstances for when a bond is required to cover existing trees indicated for
preservation in site plans for 1 year after the completion of construction (see the cities of Falls Church, Fairfax, and Vienna for
precedents).
E.3. Tree Preservation Plans - Further define the existing preservation plan requirements to include tree canopies, trunks, critical
root zones, and tree protection measures drawn to scale (reference “Best Management Practices for Tree Preservation,
Transplanting, Removal, and Replacement”). Support a second Urban Forester position focused on plan review and
enforcement of preservation plans.
E.4.
E.5.
E.6.
E.7.
EV Charging Plan
Number Page Section Notes Staff Notes
F.1 What: The City can make several changes to the current zoning ordinance to streamline the EV charger permitting process. It
can permit chargers as an allowable accessory use to parking lots in all zoning districts for both private and public charging.
Why: Public charging stations are accessory use in most instances. However, land use and zoning codes often do not
reference or properly categorize EVSE. Subjecting EV charger applications to a conditional or special use permit process
requiring additional approvals can add significant staff time to projects and create delays. Explicit directives can increase
efficiency to the process by which new EV charging infrastructure can be approved. Providing this information to the public
will not only clarify whether a type of charger can be installed but also show that the City supports public EV charging.
How: The City can amend Charlottesville Development Code Div. 3.5. Accessory Uses and Structures to establish
requirements concerning the siting of EV charging systems for Level 1 and Level 2 charging. The City can codify in the zoning
ordinance that EV charging stations are allowed by right in parking lots as an accessory use across residential, commercial,
industrial, and other major zoning categories. For DCFC installations, the City may wish to adopt specific provisions, explicitly
detailing when EV charging is considered a primary use.
The City may require that EV charging in City historic districts, architectural control districts (Figure 41), and entrance
corridors be conditional on a Certificate of Appropriateness to ensure that infrastructure additions, landscaping, and related
elements will complement the existing area. Providing specific guidance about what types of charging installations the City
permits in these zones and any project criteria will aid installation projects and preserve the character of protected areas.
See the CV Charging Plan and look at the City of Fairfax Link to
what they are doing
Page 17 of 22
Development Code Proposed Amendments Working and Tracking Document 2026 (UPDATE July 21, 2026)
Page 15 of 19
F.2
F.3
F.4
Builders and Developers
Number Page Section Notes Staff Notes
G.1 2-101 2.10.1.F Kevin Riddle: On a project at Cabell Avenue, we encountered a question about ground story interpretation. (See the attached
PDF for a graphic.)
A question arose about which building level should be classified as the ground level. The doors at the top of the metal stairs
are too far above grade— over 6 feet— to count as the ground story. So I determined the level below— accessed from the
terrace at the 994’ elevation— should be the ground story. Our architecture and civil engineering team debated this. Some
people read the Code to say that the lowest allowable floor elevation in RX-5 is 0’ above existing grade. I argued that it
should be interpreted as 0’ above finished grade, based on the language in Division 2.10.1.F.1.a and 2.10.1.F.1.b. (page 2-
101). I think the confusion arose in part because the supporting graphic in this section refers to existing grade. It’s in a very
small font, but it’s there, and it appears to conflict with the superseding language in the Code’s text.
(As an aside, I realize that the use of finished grade to define ground story could conceivably allow a strange— and typically
undesirable— scenario where finished grade at building face is very far below the adjacent right-of-way. I think, however,
such a scenario is exceedingly unlikely, because almost no owner would gain anything by creating this condition… and the
obvious downside of using existing grade at building face to define ground story in a hilly town like ours would be the far
more common scenario of a parcel where grade rises from the street: if an owner modified existing grade down to make a
front door accessible to a disabled resident, the ground floor would be out of compliance— more than 0’ below existing
grade. To instead locate the ground floor elevation at 0’ or higher above existing grade would create the need to ramp up to
the front door, which in many situations would be a significant burden, especially where a building face is very close to the
sidewalk. Allowing residents to define ground stories based on modified— ie, finished— grades seems entirely reasonable.)
Long story short, I assume the Code should be edited so the notes on the Ground Story graphic read finished grade.
Dannan O’Connell was part of this discussion, if you want to check in with him for his take.
(by email)
6/16/2026: Moved to A.12 as a graphic update.
Staff believes this is a Tier 1 (grammatical issue and can be address
with the current round of amendments or in the future). Staff
believes the code is clear that words outweighs graphical
information per section XXX
G.2 2-132K 2.10.10.A.5 Kevin Riddle: We’ve studied several projects recently where new development is being considered on a parcel— or parcels--
that make up an entire block. In these cases, a single building may have streets on four sides, and all four sides are longer
than the building width maximum. In such a case, should one open space exception (page 2-132) be allowed on each street
face of the building rather just one exception for the entire building? With only one exception per building, as the Code
currently prescribes, an owner would have to separate one building into multiple buildings. While there may be upsides to
multiple buildings, it’s not obvious that a single building with nice fenestration, massing, materials, etc… would be worse than
multiple buildings… and wouldn’t multiple open space exceptions safeguard against a perception of a building looking too
massive?
(by email)
Staff does not believe this is an issue and the intent of the code is
to require developers to shrink their developments or to provide
new streets or other elements to breakup large projects. More
consideration may we warranted, but this would need to be a Tier
3 discussion.
G.3 Bicycle parking regulations need to be looked at. Currently the code calls form a lot of bicycle parking in areas that are not
bike friendly
(October 14, PC work session)
G.4 BAR is an issue and does not work with by-right. Active depth is an issue as although parking is not required, it is needed due
to financing. Administrative Modification need to be made larger (more than 10%). If you want more housing it needs to be
easy as posable and very standard. Developers need to know what they can do. Take away BAR authority and make as much
as possible not go to PC or CC.
(October 14, PC work session)
Page 18 of 22
Development Code Proposed Amendments Working and Tracking Document 2026 (UPDATE July 21, 2026)
Page 16 of 19
G.5 The code is too complicated. We need to think more about what lots are left in the City for development. Stormwater
regulations ae an issue and the affordability regulations need to be looked at on a yearly basis so they can be adjusted based
on real world changes.
(October 14, PC work session)
G.6 Max coverage regulations and max heights are an issue. Although parking is not required it is an issue for small lots as people
(Habitat) will have cars. Think about bringing back allowing front facing garages.
(October 14, PC work session)
2/10/26: More study is needed, but not at this time. Max coverage is an issue.
staff believes the max height issue will be resolved with the current
round of amendments).
G.7 From a Historic Preservation perspective, make existing buildings in the Historic District conforming. This would help with
preventing teardowns.
(October 14, PC work session)
This could be something to look at. Staff is already proposing that if
someone is using the “existing structure preservation” allowance,
things like build-to and setbacks are “conforming”. This could be
looked at for something broader in the Historic districts.
G.8 Changing the zoning along West Main to CX-3. Remove the pay for affordable housing and provide affordable within student
housing buildings.
(October 14, PC work session)
G.9 Up the amount of disturbed area for stormwater from 6,000 to 10,000. Change the major SD. Change the inclusionary
requirements. What we have is not working.
(October 14, PC work session)
2/10/26: This is being studied as part of Long Range Planning Environmental Study.
Under the current code we do not have major and minor SDs. We
only have SDs and staff is recommending a new application for
Sublots.
G.10 Look at adjusting the required AMI for affordable units and base it off the Zoning district and not uniformly across the City.
(October 14, PC work session)
G.11 Reevaluate the “activities” sections (i.e. New Construction, Addition, Site Modification…) to allow small changes to a site
without going through full Development Review.
(October 14, PC work session)
Staff is already proposing a process that will allow small changes
(below the threshold of Minor Site Plans) to be exempt from
Development Review through a code amendment to 34-5.2.9
G.12 The Building Code needs to be changed. When you do over 2 units it is now commercial and not residential. The Zoning code
is no longer the issue, and it is the Building Code.
(October 14, PC work session)
G.13 We are a hilly City and that is not reflected in the code. 40’ requirement for entrances is an issue. Build-to requirement is for
partial blooks and not a development that is taking up the full block.
(October 14, PC work session)
G.14 Build-to width is creating a lot of issues. Utility requirements is a big issue as it takes away from what can be done with
sublots.
(October 14, PC work session)
2/10/26: This is creating a lot of issues, and we need to find a way to allow administrative relief. PC moved to Tier 3 (C.23).
G.15 1.1.6.C Effect
of Prior Code
1.1.7
Severability
In light of the issues with the ongoing lawsuit it seems like changing this section of the code to have a better fall back plan
would be prudent. I recognize that the ab initio judgement would not have been alleviated by an improved version of this
section, but it could help with issues in the future.
Allow the prior code to exist as a fall back and/or provide an expedited path to a special use permit for projects that are
under review and are impacted by judgements. If code readoption is required consider adopting on a district by district basis
rather than all at once
Dan Bracey – Two Street Studio October 2025
G.16 2.10.6 /
2.10.7
Build-to &
setbacks
Interactions with minimum primary street build-to widths and transition setbacks create undevelopable lots. For example in a
NX lot which has an 85% primary street minimum build to width that has a Type B 15' transition that overlaps with the build
to width, the minimum buildable site must have at least 100' of primary street frontage.
Provide build-to width alleviation for sites where transition setback zones overlap with build-to width zones
Dan Bracey – Two Street Studio October 2025
Page 19 of 22
Development Code Proposed Amendments Working and Tracking Document 2026 (UPDATE July 21, 2026)
Page 17 of 19
G.17 2.10.6.5.c.ii
Ped. outdoor
amenity
space
Meeting the 85% lot line or facade perimeter rule for pedestrian outdoor amenity space is very difficult on sites where the
sidewalk and streetscape zone are within the lot boundary.
Clarify or designate that the inner line of the required permanent public access easement for streetscape zones will be
treated as the street lot line for zoning calculations.
Dan Bracey – Two Street Studio October 2025
G.18 2.10.9.4.a.
Ground story
definition
The 6' Min/Max determination for ground story is too limiting for the topography in this area leading to a need to break
larger buildings into many modules which is very inefficient from a construction perspective
Revert to the previous ground story definition of 50% of the floor above/below grade to define ground story or provide
administrative alleviation for larger sites on hills
Dan Bracey – Two Street Studio October 2025
2/10/26: PC believes the terrain of the City needs to be taken into consideration. Not a priority now, but moved to Tier 3
(C.24).
G.19 2.10.10.A.3.b
Building
width
The intent of this section is to "promote fine-grained patterns of development and prevent long (should read "wide")
buildings that are out of context...by breaking wide buildings into multiple, clearly distinguished building widths. The
allowance for buildings to abut, but not share structure or components makes building cost and environmentally efficient
multifamily buildings on large sites very difficult.
175' (RX-3/NX) accommodates only 5-6 units per street facing facade, severely limiting multifamily buildings on some large
sites. 10-12 units per 275' street facing facade in RX-5 and CX is an improvement, but still very limiting on some lots.
Eliminate or increase the width restriction in higher density zonings, provide a path for administrative waiver, or provide a
path for longer buildings with mandated distinct facades
Dan Bracey – Two Street Studio October 2025
G.20 2.10.10.A.5
Open Space
Exception
Active depth requirements still apply to the facade that is pushed back to meet the open space requirement which creates an
issue in a multifamily building with a typical podium or deck wrap plan. Pushing the facade back ~30' would typically expose
either a corridor or a parking structure.
Do not apply the active depth requirements to the facade that is pushed back when using the open space exception.
Dan Bracey – Two Street Studio October 2025
G.21 2.10.10.B.2
Active depth
and parking
Residential corridors and parking spaces do not meet the requirements of active depth. This makes typical podium or deck
wrap residential layouts very difficult to achieve on most lots that are big enough to support that style of high density
multifamily development.
Provide guidelines for allowable screening systems for parking areas within active depth zones, do not apply active depth to
all stories of primary frontages, or only apply active depth on the primary street frontage.
Dan Bracey – Two Street Studio October 2025
G.22 2.10.11
Ground Story
Height
Required ground story heights in mixed use buildings should be determined based on the predominant use of the building,
e.g. a single commercial frontage in a predominantly residential building should not be required to have a taller ground floor
height.
Change 2.10.11.A.2(b) to define ground story height based on the predominant use of a building.
Dan Bracey – Two Street Studio October 2025
G.23 2.10.11.B
Finished floor
elevation
0' minimum finished floor elevations are extremely limiting on many sites that have significant grade changes or require
vehicular access to garages on the same grade as the residential floors.
Provide negative finish floor elevations for all districts
Dan Bracey – Two Street Studio October 2025
G.24 2.10.13
Entry
requirements
The issues relating to setbacks, streetscape requirements, build-to, and finished floor elevation make it difficult or impossible
to provide access to entries on sites with grade changes along primary facades since there is not enough space to provide the
stairs and/or ramps required to access those entries while meeting build-to width requirements.
Provide alleviation or alternate for additional entries on sites where this is an issue.
Dan Bracey – Two Street Studio October 2025
Page 20 of 22
Development Code Proposed Amendments Working and Tracking Document 2026 (UPDATE July 21, 2026)
Page 18 of 19
G.25 3.5.1.b.1
amenity
bldgs as
accessory us
Residential development amenity buildings currently meet the definitions for administrative determination of accessory use,
but are not defined as such
Include residential amenity buildings in the Permitted Use Table
Dan Bracey – Two Street Studio October 2025
G.26 4.2.2.C.1.b.iii
distribution
of affordable
units
In multi-building residential projects, the requirement to evenly distribute affordable dwelling units throughout a project, i.e.
throughout multiple buildings vs centralized in one building, eliminates the ability to utilize funding sources specific to low
income/affordable housing
Allow projects that fit this case to concentrate units in one building, perhaps with stricter equivalency requirements or with
administrative approval.
Dan Bracey – Two Street Studio October 2025
G.27 4.4.5-A (1) /
4.4.5-A (3)
Setbacks,
streetscape,
& build-to
Interactions with primary and side street setbacks and streetscape requirements create situations where build-to
requirements cannot be met. Required streetscape zones occur within the property lines making it impossible or difficult to
meet 15' (RX) and 10' (CX/NX) maximum primary street setbacks.
Clarify or designate that the inner line of the required permanent public access easement for streetscape zones will be
treated as the street lot line for zoning calculations.
Dan Bracey – Two Street Studio October 2025
G.28 4.5.5.B.2
parking
structure
requirements
This states that a parking structure must meet the standards of this Section, however the section includes requirements for
continuous curbs, interior islands every 10 spaces, perimeter landscaping, and landscaping on islands and medians which are
not generally feasible in parking structures.
This is presumably an error that requires a formatting change to this section as parking structures should not and can not be
built with these features.
Dan Bracey – Two Street Studio October 2025
G.29 4.8.2.C.1.c
0' max wall
heights
Retaining walls in yards may not exceed the maximum fence/wall height for the district. Many districts have a 0' maximum
wall height which would make it difficult or impossible to develop sites that are above the grade of the sidewalk.
Provide exception for this case, restrict retaining walls separately from fences and walls, or do not have 0' maximum wall
heights.
Dan Bracey – Two Street Studio October 2025
G.30 1. The less certainty, the less development. 2. Not all sites are equal. 3. We only know what we know until we know more. 4.
Time kill deals. 5. Lawsuits are terrible for business. 6. Incentives work. 7. Markets always win out.
Reference Jeff Levien Letter dated October 21, 2025
G.31 Would like to see the idea of expanding Sublots to all Zoning Districts not just R and RN districts.
Nicole Scro (in different meetings through 2025)
G.32
G.33
G.34
G.35
G.36
G.37
G.38
G.39
G.40
G.41
G.42
G.43
G.44
Page 21 of 22
Development Code Proposed Amendments Working and Tracking Document 2026 (UPDATE July 21, 2026)
Page 19 of 19
G.45
G.46
G.47
G.48
G.49
G.50
Page 22 of 22