County Board Agenda Item
Meeting of November 15, 2025
County Manager: #### #
County Attorney: *****
Staff: Richard Stephenson, DMF
ARLINGTON COUNTY, VIRGINIA
DATE: November 12, 2025
SUBJECT: County Manager's Presentation of the Financial Results and Close-out for the Fiscal
Year (FY) Ending June 30, 2025. (The Public Hearing on this item will take place at the
November 18, 2025, County Board Recessed Meeting.)
C. M. RECOMMENDATION:
1. Adopt the FY 2025 County government appropriation resolution shown on
Attachment 1A.
2. Allocate remaining balances from FY 2025 to legally restricted and priority areas
identified by the County Board as shown on Attachment 1B.
3. Amend the FY 2026 County Operating Budget by approving the appropriations in
Attachment 2.
4. De-appropriate $500,000 from FY 2026 Washington Metropolitan Area Transit
Authority (WMATA) funding (101.9011006) to reflect final contribution to the
Stabilization Reserve in line with FY 2026 Budget Guidance from the County
Board.
5. Appropriate $350,000 from the Stabilization Reserve to the Department of Human
Services (101.5016002) for additional food aid during the federal government
shutdown.
ISSUES: The Board is being asked how should remaining one-time funds from FY 2025 be
allocated?
DISCUSSION: Financial information presented here reflects the preliminary work of the
County’s external auditors (Clifton Larsen Allen LLP). As in prior years, the County’s Annual
Comprehensive Financial Report (ACFR) will be available in December.
Consistent with the financial updates provided to the County Board in April and June 2025, the
County ended the fiscal year with very little discretionary savings or additional revenues. After
meeting legal restrictions, County Board financial reserve policies, and revenue-sharing with
Arlington Public Schools, the funding available for discretionary allocation totals $1.8 million,
2
or 0.2% of the revised FY 2025 County General Fund budget, excluding Arlington Public
Schools. This is a significant decrease from FY 2024 when available funds totaled $16.7
million, or 1.5% of the General Fund. The available funding results from a combination of tax
revenues very close to budget and certain expenses coming in above budget.
Best practices in financial management and retention of the County’s triple-AAA bond ratings
require that the County end each year with a surplus (revenues more than expenditures). The
County’s historically conservative budgeting practices, along with appropriately sized and
flexible contingents (such as the Stabilization Reserve which was increased in FY 2025 in
anticipation of current economic issues) have allowed us to accommodate unanticipated events –
such as cybersecurity, contractual cost increases, and state / federal budget cuts –to avoid mid-
year service reductions and budget cuts.
Total discretionary funding is $1.8 million at the conclusion of FY 2025. The main sources
contributing to the discretionary funds will be discussed later in this report. The County
Manager is recommending the following items be considered in the adoption of FY 2025 Close-
out:
•Healthcare ($1.5 million): costs of the County’s health insurance plans are trending
higher than employee and County-paid premiums; given the high-cost claims of
FY 2025, it is recommended to set aside additional funding to meet the expense trends of
FY 2026.
•Juvenile & Domestic Relations Court’s (JDR) Safe Havens Program ($276,070).
In addition to the numerous appropriation actions included in this report, two additional actions
are recommended by the County Manager:
1) De-appropriate $500,000 in accordance with County Board direction in April 2025 and
transfer the WMATA budgetary savings to the County’s Stabilization Reserve.
“The Board directs $11 million to be added to the County’ s Economic Stabilization
Reserve. In addition, if anticipated reimbursements from the Washington Metropolitan
Area Transit Authority are greater than $500,000, the additional amount should be added
to the Economic Stabilization Reserve, which was created in FY 2013 to address
unforeseen ‘economic displacement or potential federal/state budget cuts.’ Over the
years, the reserve has increased in funding and scope to address unexpected temporary
events such as major weather events, revenue declines, and local or regional economic
stress.”
2) Appropriate $350,000 from the Economic Stabilization Reserve to support needs in the
community for food aid during the federal government shutdown.
Financial information presented here will be finalized when the County’s external audit is
complete and the County’s Annual Comprehensive Financial Report will be available in
December. Expenditures, revenues, and recommended actions are discussed on the following
pages.
3
The County ended FY 2025 with a balanced budget. At the end of FY 2025, the County’s
General Fund balance is anticipated to be $360.7 million, a decrease of $11.6 million from the
end of FY 2024.
General Fund balance comes from three sources:
1) Amounts carried over from year-to-year for reserves and other County Board policy
designations (e.g., Schools revenue sharing and Affordable Housing Investment Fund
(AHIF) and subsequently reaffirmed by the County Board;
2) Revenues in excess of projections; and
3) Expenditures that are under budget.
Allocation of Fund Balance
The most significant portion of General Fund balance falls into the first category of funds carried
over year-to-year: approximately $359.0 million, or 99.5% of $360.7 million, is for required
reserves, restricted funding, allocations already approved by Board action, or for continuing
projects that happen to straddle fiscal years.
Carryover for Reserves & Restricted Funding ($359.0 million): Funding which remained from
FY 2025 which will carry over to their restricted and assigned areas includes:
•Reserves: $134.6 million
oOperating Reserve to maintain the required minimum of 5.5% of General Fund
operating budget per policy and needed to maintain the County’s triple-AAA
bond ratings: $92.8 million.
oSelf-Insurance Reserve: $8.9 million to remain in compliance with the County’s
financial policies. This reserve is primarily intended for one-time events in
workers’ compensation, employee health insurance, and the self-insured portion
of general, automobile, and public officials’ liability. For example, this reserve
was utilized for a judgement related to a large FLSA payment several years ago.
By policy, any utilization of the reserve requires repayment in the subsequent two
years.
oStabilization Reserve ($32.9 million): $21.9 million to maintain the required
minimum of 1.3% of General Fund operating budget per policy. An additional
$11.0 million was set-aside by the County Board at FY 2026 budget adoption
while another $0.5 million is recommended to be added in closeout
In most cases, utilization of reserves requires replenishment over a two-to-three-year period in
accordance with the County’s financial policies. However, as noted above, the $11.5 million
added in FY 2026 adoption does not have such a replenishment requirement.
•Restricted & Non-Spendable Funding: $29.5 million
oSeized Asset funds: $2.8 million
oGrants, Transit, & Restricted funds: $5.3 million
oFiduciary accounts (funds held in trust or for dedicated uses): $15.5 million
oLegally restricted and non-spendable: $5.9 million
4
▪$3.1 million to a non-spendable account for requirements under the
Governmental Accounting Standards Board (GASB) 87 and 96 for the
recognition of leases and subscription-based technology.
▪$2.7 million to restricted non-spendable items identified in the FY 2024
year-end audit process for prepaid expenditures. Prepaid expenditures
include annual operating licenses / subscriptions paid in advance such as
the County’s financial and human resources system contract that is paid in
the spring.
•Schools: $21.9 million – Schools’ carryover is a combination of School expenditure
savings ($20.0 million), and School’s portion of tax revenue per the Principles of
Revenue Sharing ($2.8 million), partially offset by School’s contribution to the General
Fund Operating Reserve ($1.0 million).
•Affordable Housing Investment Fund (AHIF): $110.7 million – A combination of
previously allocated project funds ($61.3 million) and unallocated funds for anticipated
projects ($49.3 million). Some examples of projects with previously allocated funding
include Barcroft debt service, Goodwill site redevelopment, and Crystal House #3 and
#6. Unallocated funds are envisioned to support existing projects in the CAF portfolio
with capital needs and/or projects at-risk due to expiring affordability. In addition to the
$110.7 million carried over in the General Fund, an additional $6.65 million in federal
HOME funds will be carried over in the Community Development Fund.
•Prior County Board Appropriations and Allocations: $62.3 million – The County Board
has taken a number of actions as a part of the adopted FY 2026 budget or where the funds
are already dedicated in use (e.g., short-term financing) or the project has been previously
funded by the County Board is a multi-year effort (e.g., planning projects). These items
include the following:
oDebt service for a number of technology and equipment purchases approved as
part of prior budgets and CIP ($15.8 million). Examples of items funded with
short-term financing include PC replacement, server and network replacement,
and public safety technology.
oFunding for items already appropriated as part of the FY 2026 Adopted Budget
($32.3 million) such as PAYGO funding for capital projects ($12.1 million),
compensation bonuses ($1.1 million), other post-employment benefit (OPEB)
trust fund ($3.0 million), a second recruit class for Fire ($2.2 million), upcoming
Climate Action Plan funding ($0.5 million), funding for buying down Barcroft
debt ($5.0 million), and a County Manager contingent ($2.0 million). See page
655 of the FY 2026 Adopted Budget for a full list.
oIncomplete & Multi-Year Projects ($14.2 million): This allocation funds specific
projects whose schedule covers multiple fiscal years – particularly community
planning or Notice of Funding Availability grant-making processes. In some
cases, these projects have already encumbered funds or the funding has been
spent since July 1. This allocation will ensure that these multi-year projects are
completed. Examples include the Historic Resources Inventory, Low Residential
5
study, and Comprehensive Plan update as well as funding for teen-based
programs initiated and continuing in FY 2026, environmental and childcare
initiatives, and completion of training for a Fire recruit class. See Attachment 2D
for additional details.
The County Manager also recommends setting aside discretionary funding for healthcare ($1.5
million) and JDR’s Safe Havens program ($276,070) as noted in the recommendations above,
which leaves no one-time funding unallocated.
Funding for healthcare is recommended to meet the expected expense trends of FY 2026.
Premiums for the County’s self-insured health insurance plans are set as part of the budget
process – well before the beginning of the fiscal year. The two-year trend has shown healthcare
costs outpacing contributions; in FY 2025, active employee costs exceeded budget by $7.7
million due to increasing costs and high-cost claims. Cost increases have been partially driven
by the increased use of a variety of weight loss drugs (e.g., GLP-1 type medication) and
utilization of in vitro fertilization (IVF) while the plans have also seen high-cost claims for
treatment of cancer. The County is considering plan design changes to address these costs
increases as well as monitoring market trends. Because the County cannot introduce plan design
changes off-cycle of the health care enrollment period, the proposed $1.5 million allocation will
help bridge health care costs for FY 2026. Current estimates are that the FY 2026 costs could be
over budget between $7 and $13 million.
The JDR Safe Havens Supervised Visitation and Exchange program helps children maintain
essential contact with the parent who used violence in the home, while keeping the victim parent
safe through sight and sound isolation. JDR applied for but was not awarded a federal grant to
fund the Safe Havens Program. Funding for the program was not included in the FY 2026
adopted budget as it was not known yet whether the grant would be received.
Expenditures
General Fund FY 2025 expenditures, including transfers to other funds and $636.5 million to
Schools, totaled $1,666.9 million. County Operating Department expenses totaled $784.9
million for FY 2025, an amount which includes $8.0 million in GASB (under GASB 72, 84, 87,
and 96) required adjustments. Excluding these reporting adjustments, there was $23.1 million
that was not spent by operating departments. This amount includes unspent grant funding which
must be carried over to the next fiscal year ($14.1 million) and monies provided by the County
Board for prior years’ one-time projects that are still underway or legally restricted ($8.3
million). Adjusting for grant funds and restricted/incomplete projects, the County departments
ended the fiscal year with $0.6 million in expenditure savings or approximately 0.1% of FY 2025
department operating budgets. For comparison, in FY 2024, the County ended the fiscal year
with $13.4 million in expenditure savings or approximately 1.8% of the FY 2024 department
operating budgets after adjusting for grant funds and restricted/incomplete projects.
After accounting for GASB adjustments related to leases, six departments exceeded their budget
appropriation:
6
•Fire (-$3,470,205): The over-expenditure was primarily due to overtime costs required to
meet minimum staffing requirements as well as for unused leave payouts.
•Police (-$1,262,403): The over-expenditure was primarily due to overtime costs required
to meet minimum staffing requirements as well as for unused leave payouts.
•Sheriff (-$506,288): The over-expenditure was primarily due to unused leave payouts,
additional costs for inmate medical care, and overtime costs required in the detention
facility for minimum staffing requirements, partially offset by savings from staff
vacancies.
•Emergency Management (-$321,693): The over-expenditure was primarily due to
overtime costs in the Emergency Communications Center.
•Libraries (-$30,661): The over-expenditure in personnel is due to the additional costs in
staffing the evening and weekend hours at the Courthouse library and several staff
unused leave payouts.
•Circuit Court (-$40,041): The over-expenditure was primarily due to unused leave
payouts and overtime costs.
Across County departments, a small level of savings is anticipated each year. There are always
unexpected vacancies or program delays. The difficulty is predicting where these vacancies and
delays will occur. As each fiscal year progresses, budgets are monitored, and adjustments are
made for the unpredictability of expenditures.
Other Fund Highlights
In Attachment 2 Supplemental Appropriations (recommendation F), a temporary year-end bridge
loan is recommended to the Development Fund (570) from the Stormwater and Utilities Funds.
At the end of FY 2025, the CPHD Development Fund experienced a deficit due to slowing
revenue activity and increased operational costs. This fiscal situation has been outlined to the
County Board through the budget process, and the Board has continued to raise fees over the last
two fiscal years to return this fund to positive cashflows.
As required by accounting for governmental funds, the cash balance is being shored up with this
temporary loan. The Utilities fund and the Stormwater are providing a temporary loan by
splitting the $11,290,430 equally. This temporary loan is for the end of FY 2025.
The Development Fund continues to be on a multi-year plan to reach fiscal sustainability
including the significant fee increases and expense reductions over the past two years and
anticipated fee increases again in FY 2027.
Revenues
In March 2025, the County Board was presented with updated revenue projections for the fiscal
year as a part of the Mid-Year/3rd Quarter Review. This update accounted for new economic
7
data and actual revenue collection trends. With the regional economic uncertainty at the time, the
Board directed the Manager to return in June with a revenue and economic update.
The second half of FY 2025 proved to be more volatile for the County’s tax revenue collection
primarily due to the changing federal administration and the impacts it had on the regional
economy. In the spring, with the various rounds of federal layoffs, federal retirement offers,
tariff uncertainty, and federal contracting uncertainties, the County began to experience declines
in a variety of consumption taxes. Meals, sales, and transient occupancy (hotel) taxes all began
to slow from prior growth trends.
In June 2025, revenue projections were updated to reflect the changing tax revenue patterns and
provided an update on revenues received from Business, Professional, and Occupational License
(BPOL) receipts (due to the timing of these revenues, this information was not available at the
time of the March 2025 revenue update). In June, the Manager reported that the decreases in
various tax sources would be offset by slightly higher BPOL and real estate tax receipts.
By fiscal year end, actual General Fund revenues, excluding fund balance, were $1.656 billion,
compared with a revised budget of $1.638 billion reported at the June 2025 revenue and
economic update.
Of this, final tax revenues were 0.4 percent, or $4.7 million, higher than the revised June
projections. The following tables show budgeted revenues, revised projections, and FY 2025
actual revenue receipts.
FY 2025 Revised Budget to Actual Tax Revenues
Budgeted
Revenue
(adopted in
April 2024)
Revised
Projection
(June 2025)
Actual
Revenue
$ Change
(June 2025
to Actual)
% Change
(June 2025
to Actual)
Real Estate $920,564,640 $923,564,640 $928,825,454 $5,260,814 0.6%
Personal
Property 146,802,147 145,302,147 144,885,030 (417,117) (0.3%)
BPOL 89,823,887 91,823,887 92,394,582 570,695 0.6%
Sales 57,700,000 55,000,000 54,795,088 (204,912) (0.4%)
Transient 26,000,000 25,400,000 25,517,705 117,705 0.5%
Meals Tax 50,500,000 50,500,000 50,560,320 60,320 0.1%
Other Taxes 43,637,000 44,737,000 44,073,331 (663,669) (1.5%)
Tax Totals $1,335,027,674 $1,336,327,674 $1,341,051,512 $4,723,838 0.4%
8
FY 2025 Revised Budget to Actual Non-Tax Revenues
Budgeted
Revenue
(adopted in
April 2024)
Revised
Projection
(June 2025)
Actual
Revenue
$ Change
(June 2025
to Actual)
% Change
(June 2025
to Actual)
License,
Permits, Fees $17,771,087 $17,371,087 $17,129,035 ($242,052) (1.4%)
Interest &
Rental Income 22,756,443 48,256,443 57,114,589 8,858,146 18.4%
Outside Charges
for Service 72,397,879 74,480,879 75,403,219 922,340 1.2%
Miscellaneous
Revenue 2,441,471 11,090,364 10,592,650 (497,714) (4.5%)
Affordable
Housing
Investment Fund
(AHIF)
- - 9,994,598 9,994,598 -
State Revenue 95,484,483 110,398,282 98,657,570 (11,740,712) (10.6%)
Federal Revenue 18,681,302 24,892,573 23,110,321 (1,782,252) (7.2%)
Transfers &
Other 10,236,950 15,095,111 12,112,996 (2,982,115) -19.8%
GASB - - 11,129,616 11,129,616 -
Non-Tax Totals $239,769,615 $301,584,739 $315,244,594 $13,659,855 4.5%
License, Permits, Fees – Came in slightly below the revised budget primarily due to lower than
anticipated site plan revenues and parking ticket revenues. This is partially offset by higher than
anticipated revenues for photo red light and photo speed fines.
Interest & Rental Income – Interest rates on investments remained elevated throughout
FY 2025 but with the Federal Reserve expected to begin reducing the federal funds target rate,
investment earnings are likely to moderate in future periods.
Outside Charges for Service – Exceeded budget primarily due to increased parking meter
revenue and Department of Human Services charges revenue, partially offset by ART bus fare
revenue and Department of Parks and Recreation fee reductions.
Miscellaneous Revenue – Exceeded budget primarily due to unbudgeted contributions for
Affordable Housing Investment Fund (AHIF), which consist of both developer contributions and
loan repayments. The County’s practice has been not to budget these funds given the uncertainty
9
of timing of receipt which is dependent on individual project financial closings. However,
anticipated receipts are factored into multi-year AHIF financial and project planning.
State Revenue – Came in under budget primarily due to unspent grant funds in the Department
of Human Services and the Department of Environmental Services that will be carried over into
FY 2026.
Federal Revenue – Came in under budget primarily due to a Department of Environmental
Service grant that was terminated during the fiscal year along with unspent grant carryover funds
in DES that will be carried over into FY 2026.
Transfers & Other Revenue – Actuals came in under budget due primarily to the budgeted
transfer from the IDA for the Ballston skating facility if revenues generated were not sufficient
to meet the debt service obligation. In FY 2025, revenues exceeded the debt service obligation,
so no transfer in from the IDA was required.
FY 2025 Revised Budget to Total Actual Revenues
Budgeted
Revenue
(adopted in
April 2024)
Revised
Projection
(June 2025)
Actual
Revenue
$ Change
(June 2025
to Actual)
% Change
(June 2025
to Actual)
Tax Revenues $1,335,027,674 $1,336,327,674 $1,341,051,512 $4,723,838 0.4%
Non-Tax
Revenues 239,769,615 301,584,739 315,244,594 13,659,855 4.5%
Total Revenues
(excluding fund
balance)
$1,574,797,289 $1,637,912,413 $1,656,296,107 $18,383,694 1.1%
PUBLIC ENGAGEMENT: The County Board will consider the County Manager’s
recommendations for adoption after a public hearing is held at the November County Board
meeting. Additionally, the public is invited to give feedback on staff’s recommendations by
emailing: DMF@arlingtonva.us.
FISCAL IMPACT: When the County Board makes final allocation and appropriation decisions
at the November 2025 board meeting on the FY 2025 Close-out package, the Board will ratify
final appropriations for FY 2025 fulfilling all County obligations and use of one-time funds to
meet critical priorities.
ATTACHMENT 1A
GENERAL FUND:
COUNTY BOARD......................................................…........................ 2,290,873
COUNTY MANAGER............................................................................ 7,154,325
MANAGEMENT AND FINANCE............................................................ 11,658,071
HUMAN RESOURCES………………............................................……….... 11,450,685
TECHNOLOGY SERVICES…………………………………………………………………………………38,513,704
COUNTY ATTORNEY.......................................................................... 4,420,501
CIRCUIT COURT - JUDICIARY.................................................................................1,294,205
CIRCUIT COURT................................................................................. 5,259,712
GENERAL DISTRICT COURT......................................................................... 385,051
JUVENILE AND DOMESTIC RELATIONS COURT...…......................... 8,556,889
COMMONWEALTH'S ATTORNEY........................…............................ 6,653,171
OFFICE OF THE MAGISTRATE………………………………………………………………………………….23,663
OFFICE OF THE PUBLIC DEFENDER..…………………………………………………………………488,437
SHERIFF........................…………………...……………................................................55,203,097
COMMISSIONER OF REVENUE.......................................................... 6,554,110
TREASURER....................................................................................... 8,083,160
ELECTORAL BOARD.......................................................................... 2,187,643
POLICE.................................................…............................................ 93,052,777
EMERGENCY MANAGEMENT……………………………………………………………………………………………….15,424,443
FIRE................................................................................................... 84,139,975
ENVIRONMENTAL SERVICES.........…................................................... 122,105,068
HUMAN SERVICES...........................................…................................... 197,968,202
LIBRARIES.....................................................…...................................... 19,381,173
ECONOMIC DEVELOPMENT.......................…........................................ 10,001,850
COMMUNITY PLANNING, HOUSING & DEVELOPMENT..........................................12,875,095
PARKS AND RECREATION.................................................................. 59,807,363
NON-DEPARTMENTAL.......................................................................... 74,408,444
DEBT SERVICE.................................................................................... 84,485,016
REGIONAL CONTRIBUTIONS............................................................... 9,866,754
METRO........................................….................................................... 49,837,756
TOTAL GENERAL GOVERNMENT APPROPRIATION.......................................... $1,003,531,211
OTHER OPERATING FUNDS:
BALLSTON QUARTER CDA…………………………………………………………………….3,703,092
TRAVEL AND TOURISM PROMOTION FUND……………………………………………1,538,301
BALLSTON BUSINESS IMPROVEMENT DISTRICT………………………………………………………1,302,817
ROSSLYN BUSINESS IMPROVEMENT DISTRICT…………………………………………………..4,367,307
NATIONAL LANDING BUSINESS IMPROVEMENT DISTRICT……………………..4,842,737
HOUSING AND COMMUNITY DEVELOPMENT ..........................................................2,991,904
HOUSING CHOICE VOUCHER FUND.........................................................................................28,361,081
COLUMBIA PIKE TIF......................................................................... 2,293,364
IDA - BALLSTON SKATING FACILITY (341)…………………………………………………………….2,379,666
IDA SIGNATURE (341)…………………………………………………………………………………………………..30,249
UTILITIES............................................................................................ 113,100,123
STORMWATER..................................................................................... 20,474,601
DEVELOPMENT FUND ………………………………………………………………………………….24,967,123
AUTOMOTIVE EQUIPMENT................................................................ 30,235,614
PRINTING............................................................................................. 2,010,904
BALLSTON GARAGE........................................................................... 2,747,361
BALLSTON GARAGE - 8TH LEVEL……………………………………………………………………….159,770
WTE MONITORING GROUP (743)…………………………………………………………………………107,945
OPEB BENEFITS (751)…………………………………………………………………………………………………….11,701,336
TOTAL OTHER OPERATING FUNDS................................................................... $257,315,295
BE IT RESOLVED BY THE COUNTY BOARD OF ARLINGTON COUNTY, VIRGINIA, THAT THE FOLLOWING
APPROPRIATIONS ARE HEREBY ADOPTED FOR THE FISCAL YEAR 2025 AND THAT ANY SURPLUS FOR GENERAL
COUNTY PURPOSES REMAINING AT THE END OF THE FISCAL YEAR SHALL RETURN TO THE GENERAL FUND OF
THE COUNTY.
FY 2025 APPROPRIATION RESOLUTION
11
ATTACHMENT 1A
GENERAL CAPITAL PROJECTS FUND:
DEPARTMENT OF MANAGEMENT AND FINANCE…………………………… 297,000
CABLE TV……………….………………….………...……………………………………………………………………………..1,752,668
TECHNOLOGY SERVICES............................................................................................24,261,408
ELECTORAL BOARD……………………………………………………………………………………………………..2,000,000
PUBLIC SAFETY……………………………………………………………………………………………………17,638,830
ENVIRONMENTAL SERVICES:
Government Facilities.................................................................................. 22,503,751
Facilities Maintenance................................................................................... 12,897,974
Transportation..................................................................................... 51,002,087
Ballston Public Parking Garage……………………………………………………………………………………………………………………1,932,679
HUMAN SERVICES…………………………………………………………………………………………………..2,493,434
ECONOMIC DEVELOPMENT / CULTURAL AFFAIRS………………………………………278,960
COLUMBIA PIKE REDEVELOPMENT……………………………………………………………………834,359
PARKS & RECREATION ……………………………………...…................................................27,536,234
COMMUNITY PLANNING, HSG & DEVELOPMENT.…….................... 867,220
REGIONALS & NON-DEPARTMENTAL.............................................................................10,379,815
TOTAL GENERAL CAPITAL PROJECTS FUND....................................................... $176,722,044
NON-GENERAL CAPITAL & BOND FUNDS:
STREET AND HIGHWAY BOND................................................................ 20,179,215
COMMUNITY CONSERVATION BOND.......……............................. 11,253,789
GOVERNMENT FACILITY BOND....................................................... 111,159,087
UTILITIES CONSTRUCTION.................................................................... 54,597,272
STORMWATER CAPITAL FUND……………………………………………. 15,994,625
STORMWATER MANAGEMENT BOND FUND…………………………………………….76,566,278
PARKS AND RECREATION BOND..……...................................... 48,807,545
TRANSPORTATION - HB2313 - LOCAL FUNDS (FUND 330)……………………………………………..67,259,302
TRANSPORTATION CAPITAL FUND (FUND 331)………………………………………………………………354,508,301
TRANSIT FACILITIES BOND (METRO).................................................... 44,070,803
TAX INCREMENT FUND (CC-PY-PENTAGON CITY)………………………. 49,717,579
IDA BONDS………………………………………………………………………………………………………………..13,217,790
WATER DISTRIBUTION BOND.......................................................... 33,372,474
WASTE WATER TREATMENT BOND……………………………………………………………………………18,761,600
TOTAL NON-GENERAL FUND CAPITAL.................................................................... $919,465,660
TOTAL CAPITAL FUNDS............................................................................................$1,096,187,704
12
Attachment 1B
FY 2025 into FY 2026 Carryover Appropriations and Allocations
1. Allocate $134,644,943 to County Reserves
a. $92,839,223 to the General Fund Operating Reserve, including $90,762,949 in
existing reserves and $2,076,274 in additional funding to maintain the County
Board’s policy of funding the General Fund Operating Reserve at a minimum of
five and one-half percent of the General Fund budget in FY 2026, which is
important to maintaining the County’s triple Aaa bond ratings;
b. $8,861,904 to the County’s Self-Insurance Reserve, including $7,139,000 in
existing reserves and $1,722,904 in additional funding to maintain the County
Board’s policy of funding the Self-Insurance reserve at a level equivalent to
approximately one to two months’ claim payments based on a five-year rolling
average;
c. $32,943,816 to the Stabilization Reserve, including $21,453,061 in existing
reserves, $490,755 in additional funding to maintain the County Board policy of
funding the Stabilization Reserve at a minimum of 1.3 percent a minimum of one
percent of the General Fund budget in FY 2026, and $11,000,000 the County
Board set-aside in the FY 2026 adopted budget.
2. Allocate $21,348,566 from the FY 2025 General Fund fund balance to legally restricted
and non-spendable accounts.
a. Allocate $15,479,088 to restricted accounts for funds required to be reported due
to GASB requirement 84 which specifies specific criteria for identifying activities
that should be reported as fiduciary activities. The adoption of GASB 84 caused
some funds, historically called Trust and Agency accounts, to be included in the
fund balance.
b. Allocate $3,146,711 to a non-spendable account for GASB 87 & 96 for the
recognition of certain lease assets and liabilities for leases, including those that
previously were classified as operating leases and recognized as income by
lessors and expenditures by lessees and for subscription-based software.
c. Allocate $2,722,767 to restricted non-spendable items identified in the FY 2025
year-end audit process.
3. Allocate and appropriate $8,154,007 from the FY 2025 General Fund fund balance to
legally restricted and required projects.
a. Allocate and appropriate $8,062,882 as detailed in attachment 2D, including
seized asset funds ($2,815,612); and grant and fee revenue ($2,450,589), and
other sources of restricted funding ($2,796,681).
b. Allocate and appropriate $91,125 to Pay-As-You-Go capital (313) as a transfer to
capital from the General Fund (101.9011007) for revenue received from easement
or property transfers and capital transfer reconciliation.
4. Appropriate $21,887,563 to Arlington Public Schools (APS), reflecting expenditure
savings generated by APS ($20,040,103) and higher taxes received for FY 2025
13
($1,847,460), which is partially offset by APS’s contribution to the General Fund
Operating Reserve ($971,696).
5. Allocate $110,669,251 and appropriate $108,669,251 to affordable housing programs
reflecting the unexpended Affordable Housing Investment Funds (AHIF) in FY 2025 and
the amount already appropriated by the County Board in April 2025 as part of the
FY 2026 Adopted Budget.
6. Allocate $62,259,311 and appropriate $29,930,221 from the FY 2025 General Fund fund
balance to items based on prior board actions and policies:
a. Allocate $32,329,090 already appropriated by the County Board as part of the
FY 2026 adopted budget. Funding includes one-time monies for FY 2026 capital
and facilities projects ($12.1 million), Barcroft debt ($5.0 million), Fire recruit
class & other staffing ($3.2 million), OPEB ($3.0 million), County Manager
contingent ($2.0 million), non-profit partners and contracts ($2.0 million),
economic incentives ($1.9 million), environmental initiatives ($1.3 million), and a
number of other miscellaneous projects ($1.8 million). See page 655 of the
FY 2026 Adopted Budget for a full list.
b. Allocate $15,763,590 in debt service balances that have been committed as part of
prior year CIPs but not yet spent, and appropriate to Non-Departmental
(101.9011003).
c. Allocate and appropriate $14,166,631 for carryover for incomplete projects that
span multiple fiscal years such as the climate action fund, childcare grant
initiative, youth well-being programming, ART electric bus pilot/study, and
several projects initiated and continuing in FY 2026 as detailed in attachment 2D.
7. Allocate and appropriate $1,784,988 to fund the County Manager’s recommendations as
outlined in the Board report and attachment 2D including:
a. $1,508,918 for a FY 2026 healthcare contingent;
b. $276,070 for the Safe Havens program where federal grant funding was not
awarded so the program can be continued in FY 2026.
14
Attachment 2
FY 2026 County Budget Appropriations
FY 2025 CLOSEOUT ADJUSTMENTS AFFECTING FY 2026
APPROPRIATION LEVELS
A. RECOMMENDATION: Re-appropriate in FY 2026, County purchase orders,
incomplete projects, carryover capital and operating projects, and revenues to be
received from federal, state, and other sources as summarized in Attachments 2A, 2B,
2C, and 2D.
EXPLANATION: Attachments 2A, 2B, 2C and 2D also summarize and detail
appropriations, expenditures, incomplete projects and other projects or programs
recommended for funding in FY 2026. This action also identifies those
appropriations of federal, state, and other revenues approved by the County Board in
FY 2025 that had not been received or expended as of the close of FY 2025.
Incomplete projects were, for the most part, funded in FY 2025 but unable to be
completed by the close of the fiscal year.
B. RE
COMMENDATION : Increase the FY 2026 General Capital Projects Fund (313)
appropriation by $15,983,346 to reflect non-grant revenues received during FY 2025
but not previously appropriated.
EXPLANATION: During FY 2025, revenues of $15,983,346 were received for
one-time uses as well as various on-going projects where the County was eligible for
reimbursement by developers and other public or private parties as listed below.
T
he developer contributions ($13,974,540) include site plan payments for:
• Rosslyn Gateway Park ($13,951,900)
• Ballston curb space management ($22,640)
Cable revenue supports the County’s cable access equipment and transmissions
($403,350).
The miscellaneous revenue ($1,534,923) is for several projects including:
• Funds received as part of DPR partnership and cost sharing agreements to
repair and replace synthetic turf fields:
o Kenmore Synthetic Turf Field ($1,200,000)
o Long Bridge Synthetic Turf Field ($105,000)
o Funds received for insurance claims and refunds ($229,923)
Other capital project areas include:
15
• Utility undergrounding contributions ($70,533) in the transportation program
for upcoming projects.
Developer Contributions
Cable TV Receipts
Miscellaneous
Utility Undergrounding
$13,974,540
403,350
1,534923
70,533
Total $15,983,346
C. RE COMMENDATION: Increase the FY 2026 Transportation Capital Fund (330)
appropriation by $1,435,371 to reflect higher than budgeted non-grant revenue
receipts during FY 2025.
EXPLANATION: A
ctual transportation non-grant revenue received is higher than
budgeted in FY 2025 by $1,435,371. NVTA local share revenues, sourced from a
sales tax add-on, came in higher than budgeted ($477,461); the balance is from user
fee revenues for Capital Bikeshare ($847,970) that are not budgeted and interest
income ($109,941).
D. RE COMMENDATION: Decrease the FY 2026 Transportation Capital Fund (331)
appropriation by $1,247,466 due primarily to lower than budgeted dedicated
commercial real estate revenue ($1,604,272) partially offset by an increases in other
non-tax revenue sources ($356,807).
EXPLANATION:
The decrease is due to lower than budgeted and dedicated
commercial real estate revenue ($1,604,272), partly offset by a refund received from
VDOT on a completed project ($351,668), and $5,139 in miscellaneous revenue.
E. RE
COMMENDATION: Decrease the FY 2026 Crystal City, Potomac Yard and
Pentagon City TIF (335) appropriation by $1,106,394 to reflect lower than budgeted
non-grant revenue receipts during FY 2025.
EXPLANATION: T
he decrease to the Crystal City TIF is due to lower than
budgeted (largely commercial) real estate revenue receipts ($856,394) and lower than
anticipated non-grant revenue ($250,000).
F. RECOMMENDATION: Allocate $5,645,215 from both the Stormwater and
Utilities funds for a total of $11,290,430 as a temporary year-end bridge loan to the
Development (570) fund.
EXPLANATION: A
t the end of FY 2025 the CPHD Development Fund experienced
a deficit due to slowing revenue activity and increased operational costs. This fiscal
situation has been outlined to the County Board through the budget process and the
Board has continued to raise fees over the last two fiscal years to return this fund to
positive cashflows. With the deficit, the CPHD Development fund is experiencing a
negative cash balance. As required by accounting for governmental funds, the cash
16
balance is being shored up with this temporary loan. The Utilities fund and the
Stormwater are providing a temporary loan by splitting the $11,290,430 equally. This
temporary loan is for the end of FY 2025.
G. RE
COMMENDATION: Decrease the FY 2026 County Utilities Construction Fund
(519) appropriation by $6,831,647 to reflect actual revenue received less than
budgeted during FY 2025.
EXPLANATION: D
uring FY 2025, the County Utility Pay-As-You-Go
Construction Fund (519) received $6,831,647 (29%) less revenue than the budget of
$23,343,000. Included is revenue from infrastructure availability fees (IAFs), interest
earnings and miscellaneous revenue, and Inter-Jurisdictional (IJ) partner revenue.
Infrastructure Availability Fees are charged for new water and sewer connections,
which have been lower than previously anticipated. Inter-jurisdictional partners pay a
pro-rata share of capital maintenance and capital projects at the Water Pollution
Control Plant, as well as their pro-rata share of sanitary sewer conveyance capital
maintenance. The budget for this revenue is based upon a planned amount of capital
projects being undertaken during the fiscal year. In FY 2025, executed capital
projects fell below the budgeted amounts. As projects continue into FY 2026 and
beyond, the IJ partners will continue to contribute their pro-rata share. Finally, one
federal grant U.S. Housing and Urban Development for a large diameter sewer
rehabilitation project was inadvertently double appropriated in FY 2025 ($750,000).
This de-appropriation has no impact on project construction.
The FY 2025 revenue related to Utility (PAYG) projects is broken out as follows:
Inter-Jurisdictional Contribution-Plant Capital ($3,701,919)
Infrastructure Availability Fees
Large Diameter Sewer – HUD Grant
(3,144,340)
(750,000)
Interest & Miscellaneous Revenue 764,612
Total ($6,831,647)
H. RE
COMMENDATION: Decrease the FY 2026 Water Bond Fund (525)
appropriation by $23,587,532, to reflect the double appropriation of these bonds.
EXPLANATION: D uring FY 2025, the Water Bond Fund (525) was inadvertently
appropriated to the incorrect Utilities bond fund resulting in a higher appropriation by
$23,587,532. This de-appropriation has no impact on project construction and does
not impact previously approved referendum balances.
I. RE
COM MENDATION: Decrease the FY 2026 Stormwater Pay -As- You-Go
(PAYG) Capital Fund (533) appropriation by $490,805 to reflect actual revenue
received less than budgeted during FY 2025 and correct double appropriation of grant
funds).
17
EXPLANATION: During FY 2025, grant funds in the Stormwater PAYG Fund
(533) were inadvertently double appropriated resulting in a higher appropriation by
$3,540,000. Interest revenues received were $250,805 less than budgeted. These
decreased appropriations are partially offset by an increased transfer from Stormwater
Management Fund (532) to the Stormwater PAYG fund (533) to mitigate the delay in
issuance of Stormwater bond ($3,300,000).
J. RE
COM MENDATION: Adjust the appropriations in attachment 2c for FY 2025 to
reflect corrections made to the closeout carryover of FY 2024.
EXPLANATION: Subsequent the close-out of FY 2024 it was discovered that
several appropriation actions were incorrectly displayed in a table for Board
appropriation. This is a technical correction to correctly align FY 2024 carryover
with the final audited financial results.
K. RE
COM MENDATION: Decrease the FY 2026 appropriation in fund 313
($4,650,000) and fund 317 ($350,000) for actions taken by the County Board in the
adoption of the FY 2026 capital budget.
EXPLANATION:
As part of the FY 2026 Adopted Budget, $4,650,000 in PAYG
funds were reallocated to fund projects in FY 2026 and $350,000 was reallocated in
facility bond funds (fund 317). Since the County Board has already taken action in
the adopted FY 2026 budget these funds need to be reduced from the FY 2025
carryover to avoid double appropriation.
18
MISCELLANEOUS FY 2026 SUPPLEMENTAL BUDGET
ADJUSTMENTS:
L. RE COMMENDATION: Appropriate $10,696 to the Rosslyn Business
Improvement District (204) from additional revenue received in FY 2025.
EXPLANATION: T he Rosslyn Business Improvement District fund has earned
interest eligible for drawdown from fund balance. The appropriated funds will be held
in a contingent account within the BID fund to address unanticipated program or
administrative expenses.
M. RE
COMMENDATION: Appropriate $12,121 from the Virginia Department of
Criminal Justice Services (DCJS) (101.461101) to the Commonwealth Attorney’s
Office (101.2501001) for the Victim Witness Grant Program.
EXPLANATION: D
CJS provides annual ongoing grant funds to local
victim/witness programs to provide direct services, information, and assistance
required by Virginia’s Crime Victim and Witness Rights Act. After the County’s
FY 2026 budget was adopted, DCJS published the final FY 2026 awards which
included $287,881 to the Commonwealth Attorney’s Office – an increase of $12,121
from the County’s FY 2026 adopted budget. This appropriation aligns the County’s
FY 2026 adopted grant budget with the grantor’s FY 2026 award.
N. RE
COMMENDATION: Appropriate an additional $27,328 in FY 2026 from the
Department of Justice (DOJ) BJA FY24 Second Chance Act Pay for Success Grant
(101.471101) to the Commonwealth Attorney’s Office (101.2501002).
EXPLANATION: T
he DOJ through the Office of Justice Programs awarded the
Commonwealth’s Attorney’s Office a grant in the amount of $1M for the Program
Year 2024 (Fiscal Year 2025). The year one grant funding amount is $27,328 above
the original amount appropriated for FY 2025. These grant funds support the
development and expansion of the Offender Aid and Restoration (OAR) Diversion
Program. This is a five-year grant award, October 1, 2024-March 31, 2029, with no
local match requirement. All costs will be covered by the grant and there is no impact
on net tax support. This appropriation aligns the County’s FY 2026 adopted grant
budget with the grantor’s year 1 and 2 project plan.
O. RE
COMMENDATION: Accept and appropriate $5,200 from the Virginia
Department of Motor Vehicles (VADMV) (101.364400) to the Sheriff’s Office
(101.280001) and authorize the County Manager, or his designee, to execute the
associated grant agreements.
EXPLANATION:
The Sheriff’s Office has been awarded $5,200 in Highway Safety
Grant funding by the VADMV to support the implementation of highway safety
projects. VADMV grant funds are made available for projects that have a goal of
improving highway safety through a reduction of speed-related fatalities and serious
19
speed related injuries. These funds will be used to cover overtime expenses associated
with selective speed enforcement in identified high crash areas within the County.
The grant does require matching funding of $2,600 for fuel and vehicle maintenance,
which are included as part of the FY 2026 operating budget.
P. RE
COM MENDATION: Appropriate $48,272 from the State Compensation Board
(101.463107) to the Clerk of the Circuit Court (101.2201001) and authorize 1.0 FTE
to provide for state mandated services related to the implementation of House Bill
2723 and Senate Bill 1466.
EXPLANATION:
The State is providing localities partial funding through the
Compensation Board to enact work required under HB2723 and SB1466 which
relates to the expungement and sealing of criminal records. It is anticipated that the
State will only be providing approximately 50% of the required funding for the
position. In FY 2026, the Clerk of the Court will hire a full-time position in January
2026, so no additional funding is needed in this fiscal year.
Q. RE
COMMENDATION: Authorize the addition of 17.0 FTEs to create the
permanent positions needed for the Sheriff’s transition to in-house medical team.
EXPLANATION: T his action increases the FTE count for the Sheriff in line with
the plan to transition from contractor provided medical care in the detention center to
a staff team. The Medical Director position was created in the FY 2026 adopted
budget; this action adds 1.0 FTE each for the Health Services Administrator,
Correctional Health Services Manager, Administrative Assistant, Psychiatric Nurse
Practitioner, Clinic Nurse Practitioner, Psychiatric RN, Registered Nurse – MAT,
Pharmacy Lead, and Licensed Practical Nurse – Chronic Care as well as 4.0 FTEs for
Registered Nurses – Intake and 4.0 FTEs for Licensed Practical Nurses. Funding for
the positions is being reallocated from contractual services.
R. RE
COMMENDATION: Appropriate $219,460 in Compensation Board revenue
(101.436100) to Clerk of Circuit Court ($16,457 in 101.2201001), Commissioner of
Revenue ($12,731 in 101.1601001), Commonwealth Attorney ($21,808 in
101.2501002), Sheriff ($150,452 in 101.2801001), and Treasurer ($18,012 in
101.1701001) for the 1.5% bonus for constitutional officers and employees approved
by the 2025 Session of the General Assembly.
EXPLANATION: T
he 2025 General Assembly approved funding and language to
provide for a 1.5% bonus for constitutional officers and their full-time employees on
July 1 to be reimbursable by the Compensation Board, provided that the locality uses
the funds for that purpose. The County paid these bonuses in July and has received
reimbursement from the Compensation Board.
S. RE
COMMENDATION: Transfer and appropriate $10,000 from the Department of
Parks and Recreation (DPR) Senior Adult Office Trust and Agency funds
(199.9013006) to the DPR Senior Adult Office (101.7045001) to fund the Creative
Movement classes offered at three DPR Congregate Meal Programs locations
20
(AMCC, LBCC, and WRCC), expansion of the Speakers’ Series, and other special
events offered to older adults as part of the senior adult programming.
EXPLANATION: T he Senior Adult Trust and Agency funds were established in
2002 through a longstanding partnership with the Arlington Community Foundation
(ACF). ACF established an endowment from the sale of property from the estate of
Alice E. Marsh, dedicated to supporting recreational programs and initiatives for
senior adults in Arlington County. The Creative Movement classes offered at all three
location sites are part of wellness programming for seniors as part of the state
guidelines for the meal program. The Speaker’s Series, monthly presentations with
professional speakers, will be expanded to include additional topics of interest
including dementia, technology, retirement, and health & wellness. Additional special
events that will be provided include fitness days, line dancing festival, and a
multicultural day.
T. RE
COMMENDATION: Appropriate $548,338 from Gasoline Tax revenues
received from the State (101.462103) to Non-Departmental (101.9011002) for the
annual debt service payment to the Northern Virginia Transportation District (NVTD)
to reflect a change in recording of these payments.
EXPLANATION: The annual NVTD debt service payment for the Route 50 bridge
was previously recorded as a reduction to a revenue account but will now be recorded
as an expense, requiring a corresponding budget adjustment.
U. RE
COM MENDATION: Appropriate $1.9 million from Non-departmental to
OPEB (101.9011002) as a technical correction to the FY 2026 appropriations
resolution.
EXPLANATION:
At FY 2026 budget adoption, $1.9 million in funding for OPEB
was inadvertently included in the line for Non-departmental. This technical
correction has no impact on the actual funding levels for OPEB or items funded in
Non-departmental.
V. RE
COMMENDATION: Appropriate $295,000 in ambulance revenues
(101.442104) to the Fire Department (101.3203001) as a technical adjustment to
reflect the portion of ambulance revenues remitted to Falls Church.
EXPLANATION: T
his technical budgetary adjustment follows an update in
accounting procedures where previously, the payment to Falls Church was recorded
as a reduction in revenue; moving forward, it will be recorded as an expenditure. This
net zero technical adjustment ensures accurate financial reporting by the Fire
Department.
W. RECOMMENDATION: Appropriate $261,187 in additional Virginia Aid to
Localities revenues (101.463401.SOF.F2FPR) to the Fire Department (101.3202001).
21
EXPLANATION: The Virginia Aid to Localities Program awarded Arlington a total
of $1,335,667. The final award is $261,187 above the budgeted amount in the FY
2026 Adopted Budget. Aid to Localities funding can be used for a variety of
department needs including personal protective equipment, training, fire prevention,
and supplies.
X. RECOMMENDATION: Accept and appropriate $4,000 in one-time grant funds
from the Virginia 9-1-1 Services Board (101.461101) to the Department of Public
Safety Communications and Emergency Management (101.3102010).
EXPLANATION: The Virginia 9-1-1 Services Board has awarded $4,000 in funds
under the FY 2026 Public Safety Answering Point (PSAP) Education Program. These
funds are to be appropriated to the Emergency Communications Division to assist
with individual training requirements from the Commonwealth of Virginia in FY
2026.
Y. RE
COMMENDATION: Decrease the FY 2026 Public Safety Communications and
Emergency Management budget by $300,000 (101.3101010) for the loss of grant
funds for an Urban Area Security Initiative (UASI) grant for a Critical Infrastructure
and Vulnerability Analysis (101.473249).
EXPLANATION:
The County was notified in October 2025 that it would no longer
be receiving the Urban Area Security Initiative (UASI) grant for a Critical
Infrastructure and Vulnerability Analysis grant which the County Board appropriated
in July 2025. No work had begun on this study.
Z. RE
COMMENDATION: Transfer a donation of $49,999 from a fiduciary account
(199.7091003) to the Parks capital program (313.7091003) to be used for the 23rd and
Eads Street Park.
EXPLANATION: I n FY 2026, the Crystal City Business Improvement District
donated $49,999 for the 23rd and Eads Street Park. As outlined in the memorandum of
understanding, these funds can be used to install electricity and lighting fixtures in the
park. These funds will be transferred to the Parks capital program to supplement the
existing project budget of $475,000 for a total project budget of $524,999.
AA. RE COM MENDATION: Decrease the appropriation in fund 313 for completed
projects in which short-term financing was budgeted and is no longer needed
($444,170).
EXPLANATION: Various public safety projects, a facilities project in Water-Sewer
Streets, the Greenbrier track project, and 1212 S. Irving Street group home are
complete and no longer require budgeted short-term financing funds. These funds
will be de-obligated and allow for this debt capacity to be reprogrammed in the
upcoming FY 2027 budget process.
22
BB. RECOMMENDATION: Appropriate $452,697 in cable franchise revenue to the
General Capital Projects Fund (313) from Verizon and Comcast supporting the
County’s cable access equipment and transmission (313.1404001.451201).
EXPLANATION: Cable franchise revenue is received by the County to support
related cable access equipment and transmission per the cable franchise agreements
(313.1404001.451201).
CC. RE
COMMENDATION: Decrease the FY 2026 General Capital Projects Fund
(313) appropriation by $785,317 to reflect de-appropriation of grant revenues.
EXPLANATION: The Shirlington Road bridge project was completed under the
planned project cost. Total assumed grant funding needed to fund a portion of the
project cost is not needed and therefore these funds are being de-appropriated from
the capital budget program as they cannot be transferred to other transportation
capital projects (313.4024002.ZBR02).
DD. RE
COM MENDATION: Decrease the FY 2026 Government Facilities Fund (317)
appropriation by $500,000 to reflect funds appropriated as part of the FY 2026 budget
which were already appropriated in FY 2025 for the Fire Logistics facility (ZQC22).
EXPLANATION: The Fire Logistics facility project had previous bond funding
appropriated as part of the FY 2025 budget. These funds were again appropriated as
part of the FY 2026 adopted budget in error. This action will reduce the project
budget back to its appropriate funding level.
EE. RE
COMMENDATION: Transfer and appropriate $2,694,504 from PAYG Capital
fund (313) to the Capital Transportation fund (331) to move received developer
contributions in PAYG Capital to the Transportation Capital fund where the projects
are being executed.
EXPLANATION:
Three transportation projects are underway in the Transportation
Capital fund (331) which are partly funded by developer contributions. These
projects include a bike sharing project, the Fort Myer Drive Two-Way Conversion
project, and the Transitway Extension to Pentagon City. This recommendation
includes transferring and appropriating $114,466 from project code 313.ZBS01,
$2,250,000 from project cost 313.ZRBFM, and $330,038 from 313.ZMA13. These
funds will be appropriated to similar account codes in fund 331.
FF. R
ECOMMENDATION: Decrease the FY 2026 Transportation Capital Fund (330)
appropriation by $510,247 to reflect de-appropriation of grant funding for a VDOT
decision to administer the capital project.
EXPLANATION:
Subsequent to project planning, VDOT has made a decision to
administer construction of the Arlington Boulevard – Washington Boulevard
interchange (330.4024002.ZDC21). Previously appropriated grant funding will not
23
be necessary to fund project administration now that the State is administering the
project construction.
GG. R ECOMMEN DATION: Transfer and appropriate $5,035,644 from the
Transportation Capital Fund (330) to the Transportation Capital Fund (331).
EXPLANATION: This transfer and appropriation is required to utilize a portion of
grant funding allocated to the Intelligent Transportation Systems program
($5,035,644 from 330.4024002.ZTR08) to the Columbia Pike Streets program
($2,415,969 to 331.4024002.ZDS39, $2,128,000 to 331.4024002.ZDS40, and
$491,675 to 331.4024002.ZDS41).
HH. R ECOMMEN DATION: Decrease the FY 2026 Transportation Capital Fund (331)
appropriation by $263,614 to reflect de-appropriation of grant funding.
EXPLANATION:
The decrease represents an aging grant on the Transitway
Extension to Pentagon City project; owing to project delays, the grantor is making
available newer grant funding to continue the planned project work
(331.4024003.ZMA13).
II. RE
COMMENDATION: Accept and appropriate $600,000 in one-time grant funds
from the Virginia 9-1-1 Services Board to the Department of Public Safety
Communications and Emergency Management Capital Funds (313.3102010.
461101).
EXPLANATION:
The Virginia 9-1-1 Services Board has awarded $600,000 in
funds under the FY 2026 Shared Call Handling Equipment (CHE) program for the
refreshment of technology in the 9-1-1 Center. These funds are to be appropriated to
DPSCEM Capital and used in conjunction with appropriated funds for the FY 2026 -
FY 2027 capital project of Call Premise Equipment replacement.
JJ. RE
COMMENDATION: Accept and appropriate $150,000 in one-time grant funds
from the Virginia 9-1-1 Services Board to the Department of Public Safety
Communications and Emergency Management Capital Funds (313.3102010.
461101).
EXPLANATION:
The Virginia 9-1-1 Services Board has awarded $150,000 in
funds to support the new FY 2026 Next Generation (NG) 911 additional funding
request. These funds are to be appropriated to DPSCEM Capital and used in
conjunction with appropriated funds for the FY 2026 - FY 2027 capital plan for the
implementation and training of the new system.
KK. RE
COM MENDATION: Accept and Appropriate $250,000 in remaining grant funds
from the Virginia Department of Emergency Management to the Department of
Public Safety Communications and Emergency Management Capital Funds
(313.3102010.461101).
24
EXPLANATION: The Virginia Department of Emergency Management (VDEM)
awarded Arlington County $1,000,000 in Emergency Operation Center technology
enhancement grant in FY 2025 to be used in conjunction with appropriated capital
funds for the buildout of the Arlington County Emergency Operations Center and
Situational Awareness and Intelligence Center. In FY 2025, $750,000 of these funds
were appropriated for use on the project, with the remaining $250,000 in grant funds
set for an FY 20026 appropriation to finish the project.
LL. RE
COM MENDATION: Appropriate $282,390 from the National Fish and Wildlife
Foundation (533.473101) to the Stormwater Capital PAYG Fund (533.4065003) for
the effort to restore water quality, habitat, and resilience.
EXPLANATION: Grant funds will be applied towards implementation of two
Green Streets and one Regenerative Stormwater Conveyance Capital Project to treat
upland runoff in the Grandma’s Creek Watershed. Matching funds in the amount of
$180,484 (inclusive of in-kind contributions) are required from the County as part of
the grant and are included in the Stormwater Capital PAYG Fund (533).
MM. RE
COMMENDATION : Decrease the FY 2026 Stormwater Bond Fund (534)
appropriation by $39,848,135 to reflect double appropriation of these bonds.
EXPLANATION: Based on previous, current and planned capital spending of all
available funds for Stormwater capital projects, a technical correction de-
appropriating $39,848,135 of bond funds is necessary to re-set the FY 2026 budget to
the appropriate level. This de-appropriation has no impact on capital project
construction and does not impact previously approved referendum balances.
NN. RE
COMMENDATION: Accept and appropriate $150,000 in one-time funding from
the Community Services Board Northern Virgina Regional Projects Office
(101.461101) to the Department of Human Services (101.5032002) for the RAFT
Program.
EXPLANATION:
The RAFT Program was awarded an additional $150,000 in one-
time funding in FY 2026 from the Community Services Board Northern Virgina
Regional Projects Office for long-term care community placements for RAFT
Program clients.
OO. RE
COMMENDATION: Accept and appropriate $50,000 in one-time funding from
the Department of Behavioral Health and Developmental Services (101.461101) to
the Department of Human Services (101.5033001) for the Developmental Services
Program.
EXPLANATION:
As part of the state performance contract, the Developmental
Services Program was awarded an additional $50,000 in one-time funding in
FY 2026 from the Department of Behavioral Health and Developmental Services for
workforce development, onboarding, and training for Developmental Disability
Specialist II’s.
25
PP. RE COMMENDATION: Appropriate $600,000 in STEP-VA Marcus Alert funds
(101.461101) from the Department of Behavioral Health and Developmental Services
(DBHDS) to the Department of Human Services (101.5023006).
EXPLANATION: T
he Department of Behavioral Health and Developmental
Services awarded Arlington an on-going state grant in the amount of $600,000 in FY
2025 for STEP-VA Marcus Alert. The funding is used for personnel expenses for 4.0
FTEs and grant administration costs.
QQ. RE
COMMENDATION: Accept and appropriate an additional $31,800 from the
Opioid Abatement Authority Individual Distribution Grant Award (101.461101) to
the Department of Human Services (101.5025006).
EXPLANATION: T he Opioid Abatement Authority awarded Arlington a grant
in the amount of $154,433 for Fiscal Year 2026. The final award is $31,800 above the
amount budgeted in the FY 2026 Adopted budget. Funding is designated for
1.0 Behavioral Health Therapist FTE supporting the Office-Based Opioid Treatment
Program.
RR. RE
COMMENDATION: Accept and appropriate an additional $26,602 from the
Workforce Innovation and Opportunity Act (WIOA) Program grant funds
(101.471201) from the Virginia Community College System (VCCS) to the
Department of Human Services (101.5013004).
EXPLANATION:
Workforce Innovation and Opportunity Act (WIOA) Program,
through the Virginia Community College System (VCCS) awarded Arlington a grant
in the amount of $814,891 for the Program Year 2025 (Fiscal Year 2026). The final
award is $26,602 above the amount budgeted in the FY 2026 Adopted budget. WIOA
funding is for the Arlington and Alexandria American Job Centers. Grants are
awarded every year for a two-year period and unspent funds carryover to the
following fiscal year. Funding is designated for programs’ activities including staff,
client training, supportive services, and administration.
SS. RE
COMMENDATION: Allocate $12,034,970 of IDA revenue bond proceeds in
Fund 340 to the General Capital Projects Fund (313).
EXPLANATION: The County previously issued IDA revenue bonds to fund its
Short-Term Finance program. These expenditures for County capital projects occur in
Fund 313 and the expenditures will be reimbursed from these proceeds. This action
re-aligns the proceeds received with where the expenses occurred.
26
GENERAL FUND OPERATING (101)
REVISED
APPROPRIATION EXPENDITURES
EXPENDITURES
(OVER)/UNDER
REVISED
APPROPRIATION
FINAL
APPROPRIATION
County Board 2,389,442 2,290,873 98,569 2,290,873
County Manager 8,015,880 7,154,325 861,555 7,154,325
Management and Finance 11,783,074 11,658,071 125,003 11,658,071
Human Resources 11,619,543 11,450,685 168,858 11,450,685
Technology Services 31,533,999 38,513,704 (6,979,705) 38,513,704
County Attorney 4,470,932 4,420,501 50,431 4,420,501
Circuit Court - Judiciary 1,416,629 1,294,205 122,424 1,294,205
Circuit Court 4,690,136 5,259,712 (569,576) 5,259,712
General District Court 414,198 385,051 29,147 385,051
Juvenile & Domestic Relations Court 8,762,650 8,556,889 205,761 8,556,889
Commonwealth Attorney 7,375,765 6,653,171 722,594 6,653,171
Office of the Magistrate 30,832 23,663 7,169 23,663
Office of the Public Defender 520,421 488,437 31,984 488,437
Sheriff 54,696,809 55,203,097 (506,288) 55,203,097
Commissioner of Revenue 6,614,865 6,554,110 60,755 6,554,110
Treasurer 8,413,441 8,083,160 330,281 8,083,160
Electoral Board 2,695,487 2,187,643 507,844 2,187,643
Police 91,698,803 93,052,777 (1,353,974) 93,052,777
Office of Emergency Management 15,102,750 15,424,443 (321,693) 15,424,443
Fire 80,546,760 84,139,975 (3,593,215) 84,139,975
Environmental Services 132,835,546 122,105,068 10,730,478 122,105,068
Human Services 206,967,422 197,968,202 8,999,220 197,968,202
Libraries 19,350,512 19,381,173 (30,661) 19,381,173
Economic Development 10,598,879 10,001,850 597,029 10,001,850
Community Planning, Housing & Development 13,249,599 12,875,095 374,504 12,875,095
Parks and Recreation 64,347,046 59,807,363 4,539,683 59,807,363
Subtotal, Operating Departments 800,141,420 784,933,242 15,208,178 784,933,242
Non-Departmental 192,958,076 74,408,444 118,549,632 74,408,444
Debt Service 84,647,699 84,485,016 162,683 84,485,016
Regionals 10,098,106 9,866,754 231,352 9,866,754
Metro 49,753,571 49,837,756 (84,185) 49,837,756
Total General Government 1,137,598,872 1,003,531,211 134,067,661 1,003,531,211
GENERAL FUND TRANSFERS:
Donations (199/799) 4,326,242 2,539,369 1,786,874 2,539,369
Travel and Tourism Promotion Fund (202) 246,700 217,473 29,227 217,473
General Capital Projects (313) 23,378,000 23,378,000 - 23,378,000
Utilities Fund (519) 100,000 104,918 (4,918) 104,918
Stormwater Fund (532) 290,000 296,011 (6,011) 296,011
Development Fund (570) - - - -
Printing (611) 297,312 297,312 - 297,312
Other Post Employment Benefits (751) - - -
Schools Operating (880) 656,526,236 556,434,434 100,091,802 556,434,434
Schools Community Activities (882) - 7,066,060 (7,066,060) 7,066,060
Schools Construction (886) - 3,988,901 (3,988,901) 3,988,901
Schools Debt Service Fund (888) - 65,267,575 (65,267,575) 65,267,575
Schools Comprehensive Services Act Fund (889) - 3,729,163 (3,729,163) 3,729,163
Total Interfund Transfers 685,164,490 663,319,215 21,845,275 663,319,215
Total General Fund Exp and Interfund Transfers 1,822,763,362 1,666,850,427 155,912,935 1,666,850,427
FY 2025 GENERAL FUND SUMMARY - EXPENDITURES, ENCUMBRANCES & REVISED APPROPRIATION
ATTACHMENT 2A
27
REVISED EXPENDITURES/ FINAL
APPROPRIATION TRANSFERS APPROPRIATION
BALLSTON QUARTER CDA (201) 3,644,698 3,703,092 3,703,092
TRAVEL AND TOURISM PROMOTION FUND (202) 1,591,700 1,538,301 1,538,301
BALLSTON BUSINESS IMPROVEMENT DISTRICT (203) 1,331,772 1,302,817 1,302,817
ROSSLYN BUSINESS IMPROVEMENT DISTRICT (204) 4,438,834 4,367,307 4,367,307
NATIONAL LANDING BUSINESS IMPROVEMENT DIST. (205) 5,047,694 4,842,737 4,842,737
HOUSING AND COMMUNITY DEVELOPMENT FUND (206) 12,686,457 2,991,904 2,991,904
HOUSING CHOICE VOUCHER (208) 30,671,700 28,361,081 28,361,081
COLUMBIA PIKE TIF (336) 2,344,230 2,293,364 2,293,364
IDA - BALLSTON SKATING FACILITY (341) - 2,379,666 2,379,666
IDA SIGNATURE (343) - 30,249 30,249
UTILITIES OPERATING FUND (503) 110,464,539 113,100,123 113,100,123
STORMWATER OPERATING FUND (532) 19,245,293 20,474,601 20,474,601
BALLSTON GARAGE (540) 3,419,121 2,747,361 2,747,361
BALLSTON GARAGE - 8th LEVEL (548) 136,151 159,770 159,770
CPHD DEVELOPMENT FUND (570) 29,078,292 24,967,123 24,967,123
AUTOMOTIVE EQUIPMENT FUND (609) 35,632,960 30,235,614 30,235,614
PRINTING (611) 2,006,626 2,010,904 2,010,904
WTE MONITORING GROUP (743) - 107,945 107,945
OPEB BENEFITS (751) - 11,701,336 11,701,336
TOTAL OTHER FUNDS 261,740,067 257,315,295 257,315,295
FY 2025 OTHER OPERATING FUNDS - EXPENDITURES/TRANSFERS, ENCUMBRANCES & REVISED APPROPRIATION
ATTACHMENT 2b
28
Attachment 2B
Other C ounty Funds Summary
The table on the prior page indicates the budget and actual expenditures in FY 2025 for each of
the non-General Fund, non-capital other operating funds.
Most of these funds are legally or
policy-restricted in use, or expenditures are limited to the amount of revenues received without
any General Fund tax support unless otherwise authorized. Several of these funds support
activities and projects that cross fiscal years and have balances that are carried over to fund these
multi-year efforts.
Most other County funds were within budget, with the following exceptions:
Ballston Quarter CDA –
FY 2025 expenses were $0.058 million more than budgeted due
to unbudgeted special assessment revenues that were disbursed to the bond trustee. In
addition, revenue was $0.5 million below budget due to lower than budgeted real estate
tax revenues, partially offset by higher meals tax and special assessment revenues. The
CDA bonds remain paid in full with the special assessment levy.
Utilities Fund –
The Utilities Fund is self-supported with dedicated fees. For the fiscal
year, the fund remained fiscally positive with revenues exceeding expenses in line with
financial policies. Total FY 2025 expenditures in the Utilities Fund were $2.6 million
more than budgeted. Overages were primarily in the following areas: $2.1 million at
Water Sewer Street Bureau largely due to higher water system maintenance costs
correlated with the large number of water main breaks ($1.8 million), $1.1 million for
purchased water at the Washington Aqueduct, and $0.3 million in debt service. Cost
savings were realized in other areas to offset the overages: $0.2 million at the Water
Pollution Control Bureau in vacancy savings, $0.2 million in savings for Water-Sewer
Engineering for utility markings, and $0.5 million in savings in overhead, indirect
charges, and inter-fund transfers.
U
tilities Fund revenues were $5.7 million (5%) higher than budgeted. Customer revenues
are the primary driver of higher than budgeted revenues ($5.3 million) due to a 5%
increase in water consumption over FY 2024. Additional revenues were due from Inter-
Jurisdictional (IJ) Partner revenues ($0.4 million). The IJ Partners pay a pro-rata share of
operating expenses for wastewater treatment based on their flow to the Plant. Both Plant
expenses and flows at the Plant varied from budgeted levels resulting in a budgetary
difference.
Stormwater Management Fund – The Stormwater Fund is self-supported with dedicated
fees. For the fiscal year, the fund remained fiscally positive with revenues exceeding
expenses in line with financial policies. FY 2025 operating and maintenance
expenditures in the Stormwater Management Fund were $1.2 million higher than
budgeted primarily due to the larger transfer to capital than budgeted ($3.3 million) to
offset the delay in bond issuance in Fund 534 in FY 2025. This overage was offset with
savings due to personnel vacancies ($0.9 million), debt service savings ($0.8 million),
and other non-personnel savings ($0.4 million).
29
Stormwater Management Fund operating revenues were $1.5 million (8%) higher than
budgeted. This was primarily due to higher than planned utility fee revenues ($1.1
million). This is the first fiscal year of the Stormwater Utility after the transition from the
Sanitary District Tax to the stormwater utility fee.
The Stormwater Management Fund ended FY 2025 with a balance of $6.7 million
including $3.0 million for the 90-day operating reserve. Excess fund balance above the
reserve may be used to mitigate future rate increases or other priority needs of the
Stormwater Management Program.
WTE Monitoring Group Fund, OPEB Benefits Fund, IDA – Ballston Skating Facility
Fund, and IDA Signature Fund – FY 2025 expenses were incurred in these funds but not
budgeted. WTE and OPEB are both trusts with expenses covered by the trusts. Both the
Ballston Skating Facility Fund and the IDA Signature Fund are trust accounts with
expenses fully funded by third parties per their loan agreements with the IDA.
A
ll other funds came in under budget.
Columbia Pike TIF – FY 2025 expenditure and revenue budgets were each $0.05 million
under budget. In line with the FY 2025 adopted budget, the entire balance of funding
available was utilized to offset the debt service costs of preserving affordable housing
units at Barcroft Apartments.
Housing and Community Development Fund – FY 2025 expenditures were $9.7
million
less than budgeted due to unspent entitlement funds, program income funds, and HOME-
ARP funds ($2.6M). The remaining funds will be carried over into FY 2025.
Housing Choice Voucher – FY 2025 expenditures were $2.3
million less than budgeted
due to unspent grant income and fund balance reserves for rental assistance and
administrative funding. These funds, which are provided by the U.S. Department of
Housing and Urban Development, will be carried forward into future years and applied to
the current year’s (FY 2026) housing subsidy and operational needs. Rental assistance
and administrative funding reserves are maintained to ensure the long-term financial
health of the program by providing staff the means to address unforeseen changes in the
County’s rental market or associated operational needs.
Ballston Garage (Levels 1-
8) – Ballston Garage funds ended FY 2025 with expenditures
$0.6 million less than budgeted. The lower expenditures were due to the reduction of
operating costs and capital maintenance. Revenue received exceeded the budget by $0.2
million due to higher than anticipated parking utilization on the eighth level for the
skating facility.
CPHD Development Fund – FY 2025 expenditures were $4.1
million less than budgeted
due to personnel savings attributed to vacancies, as well as savings in contracted services,
operating equipment, and lower than budgeted Indirect Costs. Revenues came in $6.5M
below budget due to lower than anticipated permit activity attributed to the current
economic environment. At the end of FY 2025, actual operating expenses exceeded
revenues by $6.2 million. This deficit, combined with the FY 2024 deficit, results in a
30
total fund balance deficit of $11.5 million. This deficit will be addressed through a multi-
year plan, initiated in FY 2025, that includes expense reductions and realignments, along
with fee increases.
Automotive Equipment Fund – F
Y 2025 expenditures in the Automotive Equipment Fund
were $5.4 million less than budgeted. This was primarily due to delays for replacement
vehicles, such as school buses and a fire apparatus, that were ordered in FY 2025 but were
not received and paid for during the fiscal year.
31
CAPITAL FUNDS
APPROPRIATIONS, EXPENDITURES AND CARRYOVER FOR FISCAL YEAR ENDING JUNE 30, 2025
GENERAL CAPITAL PROGRAM REVISED FINAL TOTAL GASB TOTAL
(FUND 313) APPROPRIATION (1) ADJUSTMENTS (2/4)APPROPRIATIONS EXPENDITURES ADJUSTMENTS (3) CARRYOVER
Department of Management & Finance & HR (1202001, 1205001) 297,000 297,000 295,447 - 1,553
CABLE TV & Telecommunications (1401001) 1,752,668 1,752,668 1,218,685 - 533,983
DTS (1401002,1404002,1405001) 24,261,408 24,261,408 17,256,510 551,035 7,555,933
Electoral Board (1801001) 2,000,000 2,000,000 - - 2,000,000
Sheriff (2804001) 908,663 908,663 359,838 - 548,825
Police (3011003) 1,055,022 1,055,022 263,467 - 791,555
DPSCEM (3101010,3102010) 10,472,876 10,472,876 6,699,717 - 3,773,159
Fire (3202001,3203001,3203002) 5,202,269 5,202,269 4,210,330 - 991,939
DES - Ballston Public Parking Garage (4023051) 1,932,679 1,932,679 - - 1,932,679
DES - Transportation (4021002 - 4022003 & 4024001 - 4024003) 50,811,388 45,625 50,857,013 7,740,033 - 43,116,980
DES - Other 45,625 45,625 4,359 - 41,266
DES - Government Facilities (4034001) 21,161,349 1,342,402 22,503,751 8,924,340 - 13,579,411
DES - Facilities Maintenance (4034002) 12,897,974 12,897,974 3,620,008 - 9,277,966
DHS - Residential Services and Information Services (5000000's) 2,493,434 2,493,434 429,695 - 2,063,739
AED - Public Art (8105003,8105004) 278,960 278,960 10,575 - 268,385
CPHD - Columbia Pike (8202005) 834,359 834,359 - - 834,359
CPHD - Neighborhood Conservation (8204001) 867,220 867,220 535,712 - 331,508
DPR (7091001 - 7091006) 27,415,308 120,926 27,536,234 4,916,397 - 22,619,837
Regionals / Non-Department (9011002,9011005,9011007) 9,459,452 920,363 10,379,815 879,865 - 9,499,950
TOTAL GENERAL CAPITAL PROGRAM 174,147,654 2,429,316 176,576,970 57,364,978 551,035 119,763,027
COUNTY BOND, IDA AND UTILITY FUND REVISED FINAL TOTAL GASB TOTAL
CAPITAL PROJECTS (FUND 314-340, 519-530) APPROPRIATION ADJUSTMENTS (2/4)APPROPRIATIONS EXPENDITURES ADJUSTMENTS CARRYOVER
STREET AND HIGHWAY (FUND 314) 18,810,006 1,369,209 20,179,215 9,536,433 - 10,642,782
COMMUNITY CONSERVATION (FUND 316) 10,205,288 1,048,501 11,253,789 1,757,308 - 9,496,481
GOVERNMENT FACILITY (FUND 317) -
DTS (1401001,1401002) 3,519,049 3,519,049 2,043,354 255,432 1,731,127
DPSCEM (3102010) - - - - 0
DES - Transportation (4024001, 4024002) 295,000 295,000 590,000 122,767 - 467,233
DES - Government Facilities (4034001) 76,811,549 (222,594) 76,588,955 10,060,557 - 66,528,398
DES - Government Facilities (4034002) 27,913,197 27,913,197 3,477,169 - 24,436,028
DES - Other 2,672 2,672 7,411 - (4,739)
DPR - Parks (7091001 - 7091006) - - - - -
Regionals / Non-Department (9011002,9011005,9011007) 422,406 2,122,808 2,545,214 4,432,808.00 - (1,887,594)
FUND 317 Total 108,963,873 2,195,214 111,159,087 20,144,066 255,432 91,270,453
PARKS AND RECREATION ( FUND 324) 45,918,039 2,889,506 48,807,545 3,237,274 - 45,570,271
TRANSPORTATION (FUND 330) 67,259,302 67,259,302 27,932,746 - 39,326,556
TRANSPORTATION CAPITAL FUND - C&I (FUND 331) 354,387,631 120,670 354,508,301 88,624,925 - 265,883,376
METRO (FUND 333) 21,477,724 22,593,079 44,070,803 14,491,445 - 29,579,358
CRYSTAL CITY/POTOMAC YARD/PENTAGON CITY TIF (FUND 335) 49,717,579 49,717,579 20,207,319 - 29,510,260
IDA BONDS (FUND 340) 16,558,168 (3,340,378) 13,217,790 1,543,918 - 11,673,872
UTILITIES - CONSTRUCTION (FUND 519) 54,597,272 54,597,272 31,572,531 - 23,024,741
WATER DISTRIBUTION (FUND 525) 33,372,474 33,372,474 3,365,685 - 30,006,789
SANITARY SEWER BOND (528) - - - - -
WASTE TREATMENT PLANT (FUND 530) 18,761,600 18,761,600 2,829,666 - 15,931,934
STORMWATER MANAGEMENT FUND (FUND 533) 15,994,625 15,994,625 6,911,437 - 9,083,188
STORMWATER MANAGEMENT BOND FUND (FUND 534) 76,566,278 76,566,278 1,969,574 - 74,596,704
TOTAL COUNTY BOND, IDA & UTILITIES CAPITAL 892,589,859 26,875,801 919,465,660 234,124,327 255,432 685,596,765
EXPLANATORY COMMENTS:
(1) Revised appropriation is current year budget (Paygo) + carryover from previous fiscal year+supplemental appropriations (such as bond sale, interest earned, etc) during the year
(3) Any net increases due to GASB rules 86 or 97 are reduced from the actual expenditures.
(2) Adjustments are funding changes within a fund. No changes can be made between funds without supplemental County Board action. Interest revenue earned in bond funds is added back in this
column.
(4) Included for FY 2025 are appropriation changes from FY 2024 close-out which were inaccuratly included in the November, 2024 board report and funding appriated by the Board in FY 2026 budget
adoption which was approved in April 2025..
ATTACHMENT 2C
32
Attachment 2C
Capital Pr ogram Area Funds Summary
The tables on the prior pages indicate the budget, expenditures, and balances as of the
end of Fiscal Year 2025 for each of the capital funds.
Public and Government Facilities Capital Program Area
Work completed in the Facilities Capital Program Area in FY 2025 include CourtSquare
West concrete repair, Detention Facility Medical Unit Ventilation, Equipment Bureau
and Fire Station 5 Roof replacements, Carlin Springs site demolition, Arlington
Economic Development (AED) office renovation (funded by landlord), Kelly Day Fire
Station renovations and North Side Salt Facility tarp replacement.
Sources of funding for Facilities capital projects include Government Facility Bond
(including voter-authorized but unissued bonds that have already been appropriated) and
Pay-As-You-Go (PAYG) funding. Combined balances from these funding sources that
are carried into FY 2026 total $112.8 million. The carryover funds will be used to
complete construction of the Situational Awareness Intelligence Unit; hoteling at select
floors at the Bozman Government Center; Oakland Street Warehouse renovations;
Courts-Police Building upgrades, Quincy #1 rehabilitation for Fire logistics and Quincy
#2 roof and HVAC projects; and the Madison Community Center roof, windows, HVAC
and fitness room project.
Funding will also be used to complete the Argus House window replacement; Equipment
Bureau and Fire Station 5 Door replacements; Central Library elevator, roof and plaza
repairs; along with other various ongoing maintenance capital projects.
Local Parks and Recreation Capital Program Area
Work completed in the Parks and Recreation Capital Program Area includes the track
replacement project at Greenbrier Park/ Yorktown High School. Additionally, the
program had a significant number of projects in design in FY 2025 some of which will
begin construction in FY 2026, including: Bailey’s Branch Park Playground, Bluemont
Tennis Courts, Jennie Dean Park, Lacey Woods Park, Monroe Park, Woodmont Park,
Rosslyn Gateway, as well as projects under construction at Arlington Junction and Walter
Reed for pickleball court renovations.
The planning process is currently underway for several DPR projects including
playgrounds and picnic shelters at Douglas Park and Gunston Park, Public Spaces Master
Plan refresh, and Master Plans for Three Urban Parks, and Arlington Boathouse. Various
Crystal City projects are in the planning stage via TIF funding for Center Park, 23
rd &
Eads Park, and Metro Market Square. Projects planned for kick off in FY26 include
playground replacement at Arlington Hall West Park and Doctor’s Run Park.
33
The replacement of the synthetic turf field at Greenbrier Park (Yorktown High School)
and the replacement of the lower field at Thomas Jefferson Community Center are
currently underway with design and will be replaced this fall/winter in order to deconflict
with APS scheduling constraints. Design for the conversion of the fields at Kenmore
Middle School is underway.
The Trail and Bridge Modernization Program continues to address a combination of full
replacement of trails and milling and repaving to extend the useful life of the County’s
existing multipurpose trails. For Fiscal Year 2025, the Program milled and repaved
approximately 11,300 linear feet of trail on 15 different segments within the County
including multiple segments of the Custis Trail, Four Mile Run Trail, Bluemont Junction
Trail, Lubber Run Trail and Washington Blvd. Trail.
During FY 2025, bridge replacement designs were advanced with four bridge
replacements being approved for construction. Construction plans for the replacement of
three bridges in Rock Spring Park were approved in May 2025. In addition, construction
plans for the replacement of the bridge in Alcova Heights Park were approved in June
2025. This latter bridge replacement will remove an existing aging bridge that has steps
at both ends of the bridge making it inaccessible per Americans with Disabilities Act
regulations. These two projects were bundled together and bid as one project in early
Fall 2025. The award of contract is anticipated to be approved at the November County
Board meeting. Construction is anticipated to be completed by Summer 2026.
Sources of funding for Park’s capital projects include Parks General Obligation Bonds,
PAYG, Short-Term Financing, developer or partnership funding, and Crystal City
TIF. Combined balances from these funding sources, excluding CC TIF, that are carried
into FY 2026 total approximately $83.32 million (including voter-authorized but
unissued bonds that have already been appropriated). Carryover balances are set aside
for Parks Land Acquisition and Public Space Program, Field Fund, Trail and Bridge
Modernization Program, and Parks Maintenance Capital and Parks Master Plan projects
in various stages of design or construction.
Arlington Neighborhoods Program and Economic Development Capital Program Areas
In FY 2025, Arlington Neighborhoods Program Area completed two street improvement
projects at a total cost of $71.9k. The Arlington Neighborhoods Program active projects
portfolio consists of 16 projects, most of which will be either in construction or preparing
for construction in FY 2026. Five of the current projects are expected to be completed by
the end of FY 2026.
Information Technology and Equipment Capital Program Area
This category includes enterprise-wide information technology, public safety, and other
department specific equipment and technologies. Specific projects that have had
significant FY 2025 expenditures include:
• Oracle System Upgrade ($5.3 million),
• Fire Defibrillator replacement ($3.5 million),
34
• Computer Aided Dispatch ($3.3 million),
• Customer Assessment and Payment Portal Refreshment ($3.2 million),
• Public Safety Radios ($2.85 million),
• Computer replacement ($2.02 million),
• Telephone System Replacement Project ($1.86 million)
• Network refreshment ($1.5 million),
• Server refreshment ($1.1 million),
• Data Center Consolidation ($727k),
• Public Safety Radio System Upgrade ($544k), and the
• Electronic Records Management System Modernization project ($443k),
• Day Care Center & In-home Child Care Licensing System ($419k),
• E-gov Cloud Migration (330k),
• Public Safety Data Warehouse ($285k),
• Conference Room Audio Visual Upgrades ($276k),
• Enterprise Payment Portal ($252k),
• Fire Bomb Squad Equipment replacement ($240k),
• Land Records System Replacement ($227k),
• Fire Command Vehicle technology upgrades ($200k),
• Justice Center Security Upgrades ($192k), and
• Heart Rate Monitors ($132k).
Sources of funding include cable television revenue, short-term financing, PAYG
funding, and Government Facility bonds. Combined balances to be carried into FY 2026
total $15.7 million.
Stormwater Management Capital Program Area
Sources of funding for Stormwater capital projects include Stormwater bond fund and the
Stormwater Capital Projects Fund balances. Combined balances from these funding
sources that are carried into FY 2026 total $83.7 million.
In FY 2025, major accomplishments were the acquisition of one property and the
demolition on two additional properties previously acquired for overland relief ($2.0
million), substantial completion of Gulf Branch Green Streets ($0.8 million), Sparrow
Pond supplemental storm sewer ($0.3 million), various outfall rehabilitations ($0.6
million), and Storm Drainage improvement at North Monroe Street ($0.8 million)
including terra cotta and corrugated metal pipe upgrades, stormwater frames and covers,
pipe relining and replacement and manhole rehabilitation.
The balances that are being carried forward into FY 2026 will be used on capital projects
in accordance with the County's adopted FY 2025 – FY 2034 CIP. The 2014 Stormwater
Master Plan provides a long-term framework for effective stormwater management.
• Funding for Stormwater Management Capital projects also includes federal and
state sources from which the program will seek reimbursement, which were
appropriated during FY 2024 and FY 2025 as they were approved and accepted
35
by the County Board. Total federal funding sources that are carried into FY 2026
total $5.3 million from:
o Virginia Department of Transportation (VDOT) for the Dumbarton
Culvert Replacement ($5.1 million)
o U.S. Department of Housing and Urban Development (HUD) for
utilization of Community Project Funding for Integrated Gray-Green
Infrastructure for Public Streets for Gulf Branch and South Walter Reed
Green Streets ($0.2m).
o State Funding sources total $0.08 million from the State and Local
Assistance Fund (SLAF) for Sparrow Pond wetland restoration.
Utilities Capital
Sources of funding for Utilities capital projects include Water, Sewer, and Wastewater
bond funds, and the Utilities Construction Fund. Combined balances from these funding
sources that are carried into FY 2026 total $38.9 million.
In FY 2025, major accomplishments include:
• Substantial completion of the North Glebe Road from Carlin Springs to North
Quebec Street watermain replacement ($2.4m), and
• the Interstate-66 Water Main Tunnel rehabilitation ($1.5m).
As a result of the Plant’s Solids Master Plan adopted by the County Board in July 2018,
the first phase of upgrading the solids handling processes began in FY 2019.
Re-Gen Phase 1 is complete with planning and design continuing for Re-Gen phases two
and three ($9.5m). Additionally,
• many segments of water mains were replaced or rehabilitated ($5.0m),
• other water mains were cleaned and lined ($1.7m),
• sewer mains were rehabilitated to reduce infiltration and inflow (I&I) ($2.1m),
and;
• other sewer mains were replaced and rehabilitated ($0.5m).
The balances that are being carried into FY 2026 will be used on:
• large diameter sewer rehabilitations ($4.7m)
• water reliability and redundancy ($2.5m),
• sewer main replacements and force main rehabilitation ($1.1m), pump station
improvements ($2.0m),
• sanitary sewer improvements ($1.5m).
• water main replacements ($1.2m), and
• at the Plant, balances will support the Re-Gen suite of projects ($15.9m). Capital
projects at the Washington Aqueduct ($6.3m) will also be partially funded in
FY 2026 from capital balances.
Funding for Utilities Capital projects also includes federal sources from which the
program will seek reimbursement, which were appropriated during FY 2024 as they were
approved and accepted by the County Board.
36
Total federal funding sources that are carried into FY 2026 total $1.5 million from the
U.S. Department of Housing and Urban Development (HUD) for utilization of
Community Project Funding on two projects to prevent sanitary sewer structural failures,
infiltration, and inflow.
These projects are the Sanitary Sewer Interceptor Pipe Rehabilitation at two locations:
1) Rosslyn Area of Potomac Interceptor ($0.75m grant) and
2) Columbia Pike/ Sparrow Pond section of the Four Mile Run Interceptor
($0.75m grant).
Transportation Capital
In FY 2025, major accomplishments included completion of a number of projects:
• ART Operations and Maintenance Facility
• Shirlington Road Bridge
• Columbia Pike – substantial completion of South Orme Street to South Oak Street
(Segment A)
• Columbia Pike – substantial completion of South Oakland Street to South
Wakefield Street (Segment F)
• North Ohio Street Safety Improvements
• North Park Drive and North George Mason Drive Intersection Improvements
• 28th Street South to South Meade Street Pedestrian Improvements
• Numerous quick build Street Safety Improvement projects throughout the County
• Various bus stop improvements throughout the County
• Traffic Signals
o Rebuild of 18 traffic signals 12 out of 18 rebuilds were through developers
and other projects. In total, 3 new signalized locations were built.
o 9 traffic signal battery backup systems installed.
o 8 intersections rewired.
o Signals cabinet upgrades at 14 locations.
In the Streetlights program, four capital streetlight projects were completed, including the
Dominion Electric Retrofit Project which achieved substantial completion ahead of
schedule.
Local funding sources for Transportation Capital projects include the:
• Commercial & Industrial Tax (TCF-C&I),
• TCF-NVTA Local funds,
• Metro & Transportation Bond funds,
• Crystal City/Potomac Yard/Pentagon City Tax Increment Funds (TIF),
• PAYG, and
• Developer contributions.
37
Combined balance from these funding sources that are carried into FY 2026 total $176
million and will be primarily used for the following categories:
• The Columbia Pike Multimodal Program balance of about $34.4 million will fund
completion of construction of remaining segments including South Garfield to
South Courthouse Street (Segment D) and South Courthouse Street to South Rolfe
Street (Segment C), as well as getting South Wakefield Street to South Oakland
Street and South Oak Street to South Orme Street to final completion.
Construction on all segments will be completed in FY 2026.
• Crystal City/Pentagon City/Potomac Yard Street Program’s balance of $21.9
million is programmed to fund various projects including the 15th Street
South/Clark-Bell Realignment, and along South Eads Street from Army-Navy
Drive to 15th Street South; addition to missing protected bike lanes along Army-
Navy Drive; pedestrian and bike connections along Long Bridge Drive; safety and
accessibility improvements along Crystal Drive; and the Crystal City to DCA
Multimodal Connection.
• Rosslyn-Ballston Arterial Street Improvement Program’s balance of $19.0 million
will be used for multimodal improvements along Wilson Boulevard, roadway
improvements around Meade Street Bridge, Fort Myer Drive sidewalk
improvements, Lynn Street cycle track, and to improve the intersection of Fairfax
Drive and North Kirkwood Road.
• Other Complete Streets Program balances of $23.2 million will be used for
Neighborhood Complete Streets Program projects ($3.2 million), Army Navy
Drive Complete Street ($0.5 million), Arlington View Trail Connector ($0.2m),
and for various improvements outside major corridors such as Walter Reed Drive
(6th Street South to Columbia Pike), Military Road/ Nelly Custis Drive
intersection, Four Mile Run Valley Area Plan Improvements, and various plans
and studies, including completion of the update to the Master Transportation Plan.
• The WalkArlington and BikeArlington program balances total $9.2 million. This
funding will be used to complete various small scale safety improvements at
intersections along the Rosslyn-Ballston corridor, Arlington Boulevard Trail
along Fairfax Drive in Rosslyn, and Arlington Boulevard Trail from Jackson
Street to George Mason Drive, as well as to advance the design on the Arlington
Memorial Trail project.
• The Transportation Engineering and Operations program balance of $10.0 million
will be used for traffic signal projects ($3.1 million) on various intersections and
streets including Route 1 and 27th Street South in Crystal City, Langston
Boulevard, and Washington Boulevard; $3.0 million for improvements in the
streetlight program for various locations in the County; $1.1 million for the Street
Safety Improvement program; $0.8 million for Intelligent Transportation System
program improvements; $0.9 million for ongoing traffic asset and data
management programs, including crash analysis and traffic counts needed to
complete other work throughout the County (including Vision Zero); and $0.8
million for Parking.
• Transit program’s balance of $45.5 million will continue funding major projects,
including Crystal City East Entrance, Ballston-MU Metro Station West Entrance,
38
Bus Bay Expansion East Falls Church Metro Station, Columbia Pike Transit
Stations, Transit ITS, ART Operations and Maintenance Facility (BEB
equipment), Court House Elevator, and ART Fleet Equipment and Replacement.
• Bridge Renovation and Maintenance funds of $10.4 million will be used to fund
the replacement of Arlington Ridge / Mount Vernon Road bridge as well as for
maintenance capital work on bridges throughout Arlington County.
• The capital reserve carryover is $4.2 million.
Funding for Transportation Capital projects also includes federal, state, and regional
sources from which the program seeks reimbursement. These include FY 2024 carryover
balances as well as various new federal, state, and regional funds that were appropriated
during FY 2025 as they were approved and accepted by the County Board. Combined
federal, state, and regional funding sources that are carried into FY 2026 total $208
million and will be used for the following categories.
• $126.4 million of federal, state, and regional funding will continue to advance
major Transit projects, including, the Transitway Extension to Pentagon City,
Ballston-MU Metrorail Station West Entrance, East Falls Church Bus Bay
Expansion, Columbia Pike Transit Stations, Transit ITS, and the ART Operations
& Maintenance Facility, ART Fleet Equipment and Replacement, and ART Fleet
Expansion.
• Federal and state funding of $17.9 million will be used to rebuild the Arlington
Ridge / Mount Vernon Road bridge.
• Federal, state, and regional funding of $9.5 million will fund various
Transportation Engineering and Operations projects including ITS corridor
enhancements along Washington Boulevard, Langston Boulevard, and Glebe
Road, as well as signal optimization, signal upgrades in East Falls Church, and
implementation of demand-based parking.
• State and regional Funding of $21.5 million for the Rosslyn-Ballston Arterial
Street Improvement Program will fund Core of Rosslyn projects, including the
North Lynn Street cycle track as well as design for the Fort Myer Drive Complete
Street project.
• Crystal City, Pentagon City, Potomac Yard Streets Program available federal and
regional funding of $27.3 million will fund the Crystal City to DCA Multimodal
Connection and the 15th Street South/Clark-Bell Realignment.
• Complete Streets federal, state, and regional funds of $3.7 million will fund
completion of the Army-Navy Drive project and various improvements outside
major corridors.
• Regional funding of $1.3 million for the Columbia Pike Streets Program will fund
final completion work within the Columbia Pike Multimodal Program from South
Oak Street to South Orme Street.
Several grants are being de-obligated unrelated to lack to project execution. Some of the
major projects for which grants are being de-appropriated include Shirlington Road
39
Bridge (project completed; remaining grant cannot be transferred to other projects) and
Route 50 and Washington Boulevard interchange (VDOT will administer the
construction).
40
ATTACHMENT 2D
FUND / DEPARTMENT / PROJECT EXPENDITURES REVENUES NET CARRY
General Fund:
Arlington Economic Development
Virginia Regional Innovation Fund (VIPC) Grant 100,000 100,000 -
BizLaunch Small Business Support 117,130 - 117,130
National Landing BID ReLaunch funding 7,758 - 7,758
subtotal 224,888 100,000 124,888
Commonwealth Attorney's Office
DOJ Smart Prosecution 112,439 112,439 -
DOJ 2nd Chance Act Pay Success Program 227,475 227,475 -
Seized Assets 40,873 - 40,873
subtotal 380,787 339,914 40,873
County Manager's Office
Green Valley Neighborhood Partnership Init. Pilot 80,000 - 80,000
Temp Staffing in HRO 63,217 - 63,217
EEO Refresher Training 6,794 - 6,794
subtotal 150,011 - 150,011
Treasurer's Office
Cashiering System 196,000 - 196,000
subtotal 196,000 - 196,000
Juvenile and Domestic Relations Court
Safe Havens 276,070 276,070
subtotal 276,070 - 276,070
Department of Environmental Services
Transit - NVTC Fundin
g for 16M Service Enhancement 5,000,000 5,000,000 -
ACC - Shared Mobility Devices 183,490 - 183,490
ACCS - TDM Revenue 711,547 - 711,547
ACCS - Commuter Store Fee Revenue 943,816 - 943,816
AIRE - ECBG Grant 263,390 263,390 -
ART BEB Electric Bus Pilot Analysis 327,691 - 327,691
subtotal 7,429,934 5,263,390 2,166,544
Department of Human Services
ACES Intervention & Prevention 440,000 - 440,000
BIS - Parenting Coaching 75,000 - 75,000
Behavioral Health Hiring Bonus 130,000 - 130,000
Grant: ADSD - Regional Older Adult Faculty MH Support Team
(RAFT) Dementia Services (SOFH9104) 16,633 16,633 -
Grant: ADSD - System Transformation Excellence and
Performance - STEP-VA Out
patient (SOFH9118) 155,294 - 155,294
Grant: ADSD - Regional Older Adult Faculty MH Support Team
(RAFT) Dementia Services (SOFH9104) 594,116 - 594,116
Grant: CFSD - Community Service Board Non-Mandated Mental
Health Services
(SOFH9123) 145,175 145,175 -
Grant: CFSD - Kinship Navigator (SOFH6KSH) 25,041 25,041 -
Grant: CFSD - Virginia Tobacco Settlement Funds H6TSF) 123,468 123,468 -
Grant: CFSD - Same Day Access (SOFH9114) 44,656 44,656 -
Grant: CFSD - Step VA Family Support (FSP) (SOFH9131) 103,256 80,923 22,333
Grant: CFSD - Substance Use Disorder Training and Services
(SOFH9520) 46,929 46,929 -
Grant: CFSD - Substance Abuse Prevention (SOFH9507) 3,429 3,429 -
Grant: CFSD - Substance Abuse Prevention Span Funding
(SOFH9157) 9,079 9,079 -
Grant: CFSD - State Opioid Response (SOFH9515) 10,030 10,030 -
Grant: CFSD - Community Service Board Regional Adult Mobile
Crisis Response (SOFH132) 471,512 471,512 -
Grant: DO - System Transformation Excellence and Performance -
STEP-VA Ancillar
y Services (SOFH9116) 233,619 233,619 -
Grant: DO - CCS Sunset (SOFH9149) 137,375 - 137,375
Grant: PHD - Public Health Infrastructure Grant (SOFH5ICA) 59,834 59,834 -
Grant: EID - CoC - Project Planning Grant (SOFH1COC) 149,330 149,330 -
Grant: EID - CSB Permanent Supportive Housing (SOFH9128) 2,475,504 2,475,504 -
FY 2025 CARRYOVER FUNDING ALLOCATIONS
41
ATTACHMENT 2D
FUND / DEPARTMENT / PROJECT EXPENDITURES REVENUES NET CARRY
Grant: EID - Workforce Innovation and Opportunity Act (WIOA)
(Program Year 2024) for FY 2025 and FY 2026 (SOFH1WIO) 704,189 704,189 -
Grant: EID - Community Solutions: Built for Zero Grant (CSG)
(SOFH1CSG) 168,929 168,929 -
Grant EID - Kaiser Permanente Continuum of Care Grant
(SOFH1KPG) 38,799 38,799 -
Grant BHD - State Restricted Mental Health Grant (SOFH9101) 160,075 160,075 -
Grant BHD - State DD Grant (SOFH95101) 34,362 34,362 -
Grant BHD - Not Guilty by Reason of Insanity Grant (SOFH9102) 2,407 2,407 -
Grant BHD - VA State Pharmacy Grant (SOFH9107) 357,312 357,312 -
Grant BHD - STEP-VA Ancillary Services (SOFH9116) 92,903 92,903 -
Grant BHD - STEP-VA Case Management (SOFH9119) 1,912 1,912 -
Grant BHD - Diversion First Project (SOFH9120) 88,628 88,628 -
Grant BHD - Permanent Supportive Housing (SOFH9128) 119,548 119,548 -
Grant BHD - MH Forensic Discharge Planning (SOFH9129) 210,054 210,054 -
Grant BHD - STEP-VA Veterans (SOFH9130) 128,288 128,288 -
Grant BHD - MH Forensic Discharge Planning (SOFH9144) 1,237 1,237 -
Grant BHD - PATH Program Grant (SOFH9153) 3,820 3,820 -
Grant BHD - STEP-VA Marcus Alert (SOFH9154) 250,080 250,080 -
Grant BHD - Supplemental Workforce Development (SOFH9155) 289,084 289,084 -
Grant BHD - Virginia CIT Funding (SOFH9156) 24,208 24,208
Grant BHD - Medication Assisted Treatment (MAT) (SOFH9504) 69,392 69,392
Grant BHD - Opioid Settlement Funds (SOFH9516) 8,169 8,169 -
Grant BHD - CSB Mental Health Coordinated Specialist Care
(SOFH9141) (114,028) - (114,028)
Grant DO - CSB IT Infrastructure Grant (SOFH9142) (61,868) - (61,868)
Grant DO - Kresge Foundation (SOFH4KR2) (121,486) - (121,486)
subtotal 7,905,294 6,648,558 1,256,736
Department of Community Planning, Housing & Development
Historic Resources Inventory 100,000 - 100,000
Historic Preservation Grant Fund 33,816 - 33,816
subtotal 133,816 - 133,816
Department of Management & Finance
Internal Audit Services Support 99,000 - 99,000
Oracle Project Management Services 62,700 - 62,700
subtotal 161,700 - 161,700
Department of Parks & Recreation
Youth Communit
y-based Pilot 351,747 - 351,747
Arlington Mill Computer Lounge Refresh 12,396 - 12,396
Park Project Equipment 199,727 - 199,727
subtotal 563,870 - 563,870
Fire Department
Return to Localities 95,004 95,004 -
Fire Programs 682,279 682,279 -
Lateral Bonuses 155,000 - 155,000
NVERS 32,518 - 32,518
Recruit Class Carryover 142,852 - 142,852
Protective Gear & Equipment 43,135 - 43,135
Operations Equipment 23,359 - 23,359
subtotal 1,174,147 777,283 396,864
Police Department
Seized Assets 2,774,739 - 2,774,739
VA DMV 2025 Alcohol 9,031 9,031 -
VA DMV 2025 Pedestrian/ Bicycle 1,816 1,816 -
Hiring Bonuses 467,183 - 467,183
Operations Equipment 51,509 - 51,509
subtotal 3,304,278 10,847 3,293,431
Sheriff's Office
DOJ Byrne Office Grant 16,771 16,771 -
FY 2025 DMV Grant 2,364 2,364 -
Falcon Group Consulting 460,601 - 460,601
subtotal 479,736 19,135 460,601
Non-Departmental
42
ATTACHMENT 2D
FUND / DEPARTMENT / PROJECT EXPENDITURES REVENUES NET CARRY
-
E-Summons - Fine Revenue to PAYG 1,283
-
1,283
F
ield Fund Reconciliation to PAYG 11,357 -
11,357
Clim
ate Action Fund 2,598,084 -
2,598,084
Clim
ate Action Fund (allocated to FY 2026 PAYG) 1,300,000 - 1,300,000
C
ollective Bargaining Support 175,000 - 175,000
Inter
-Departmental Planning 520,703 - 520,703
Public
Safety Data Review 200,000 - 200,000
RACE G
rants 75,000 - 75,000
CBO
/CMO Child Care Grant Initiative 3,960,551 - 3,960,551
Y
outh Well-being Plan 250,000 - 250,000
Y
outh Programming & Education 1,266,969 - 1,266,969
Neighborhood Equity Demonstration Project 141,191 - 141,191
Digital Equity Funding (unallocated) 2,296,681 - 2,296,681
Digital Equity FY26 NOFA Funding 500,000 - 500,000
Shor
t Term Financing Commitments 15,763,590 - 15,763,590
Healthc
are Contingent for FY 2026 1,508,918 - 1,508,918
-
-
-
s
ubtotal 30,569,327 - 30,569,327
G
ENERAL FUND TOTAL 52,949,858 13,159,127 39,790,731
HOUSING CHOICE VOUCHER FUND TOTAL 4,061,269 4,061,269 -
PAYG Fund:
E-Summons - Fine Revenue to PAYG 1,283 - 1,283
F
ield Fund Reconciliation (PAYG) 11,357 - 11,357
-
P
AYG FUND TOTAL 12,640
-
12,640
A
utomotive Equipment Fund:
Vehicle replacement: schools (carryover) 978,822 978,822 -
Vehicle replacement: county (carryover) 8,722,736 8,722,736 -
AUTOMOTIVE EQUIPMENT FUND TOTAL 9,701,558 9,701,558 -
TRAVEL & TOURISM FUND TOTAL 16,202
16,202 -
COLUMBIA PIKE TIF -
-
-
BALLSTON QUARTER TIF 1,020,647 1,020,647 -
T O T A L O T H E R F U N D S: 14,812,316 14,799,676 12,640
G R A
N D T O T A L A L L F U N D S: 67,762,174 27,958,803 39,803,371