Proposed Capital
Improvement Plan (CIP)
FY 2025 – FY 2034
Submission of a 10-Year Plan
for Stormwater & Utilities
Programs
Infrastructure Capacity vs. Planned Development
Water and Sanitary Sewer (Collection & Treatment) Systems have sufficient
capacity capable of handling growth.
• Master planning in 1970s thru 1990s resulted in capacity based on
forecasted demand which is more than sufficient for expected growth
thru 2040
• Increasing population offset by declining household consumption
due to conservation practices, decreasing household size, and
efficient fixtures
• Successful implementation of Infiltration & Inflow (I&I) program
mitigates need for treatment capacity expansion
Condition and function of County’s natural and engineered stormwater
systems is driven mostly by existing impervious surfaces and land use.
• Impervious surface growth very incremental in nature (<1% annually)
relative to existing high levels of impervious areas already in place (45%).
• County’s stormwater regulatory programs for land development focus on
mitigating some of these incremental impacts.
• Also impacts from unregulated activities which fall below regulatory and
zoning thresholds. Priority area for future study (e.g., low residential).
~20 MGD of
drinking
water
consumed
daily (54%)
~37 million
gallons
per day
(MGD)
available
drinking
water
Max Capacity:
40 Million Gallons
per day (MGD)
~22 MGD treated
(55%)
Drinking Water
Wastewater Treatment
Proposed Capital
Improvement Plan (CIP)
FY 2025 – FY 2034
Submission of a 10-Year
Plan for Stormwater
Stormwater Overview
4
Guiding Principles
• Systems adaptation & resiliency
• Environmental management & improvement
• Risk mitigation
Guiding Plans and
Commitments
• Stormwater Master Plan (2014)
• Storm Sewer Capacity Study
• County-wide stream assessment
• Watershed retrofit assessment
• Risk Assessment & Management Plan (2024)
• Chesapeake Bay Preservation Plan (2023)
• Virginia DEQ MS4 permitting/Chesapeake Bay TMDL
• National Flood Insurance Program (NFIP) (FEMA)
Stormwater Program Elements
Stormwater System
• Modeling, assessment, plan reviews
• Capacity projects
• Local drainage projects
• System repairs
• Channel maintenance
• Routine maintenance
Streams & Water Quality
• Stream resilience and repair, outfall repair, pond projects,
green streets
• MS4 permit (regulatory TMDLs), pollution prevention, training
and outreach, monitoring
• LDA and RPA program implementation
• Routine maintenance
5
System Snapshot
6
18,452
structures
Includes:
8940 catch basins
6780 manholes
1251 grate inlets
707 yard inlets
774 end sections
& end walls
45%
of County
covered by
impervious
area
270
miles
of pipes
32
miles
of streams
243
public
SWMFs
*included in
‘structures’ total
8,017
private
SWMFs
SWMF = Storm Water Management Facilities
CIP Impacts on the Programs
7
Stormwater Infrastructure
Resiliency across critical
government/civic assets
Increased system capacity
and reduced flood risk
Improved life-cycle repairs to
aged infrastructure
Insurability, market, and
property stability
Risk mitigation and
management
Cross-leveraging capacity/
capital maintenance
projects with water quality
benefits
Streams & Water Quality
Increased resiliency of stream
system and co-located
infrastructure
Local water quality
protection and improvement
Expansion of green
infrastructure in urban spaces
to mitigate stormwater and
heat impacts
Achievement of MS4 permit
and Chesapeake Bay
pollution reduction targets
Cross-leveraging water
quality projects with capacity
benefits
Flood Risk Reduction Priority Areas
8
The five Critical Watersheds
with the highest flood
damage calls since June
2006:
• Torreyson Run/Westover
• Crossman Run
• Little Pimmit East and
West
• Lubber Run
• Spout Run
Visit the interactive CIP map on the County’s website
Major Projects Completed
9
Ballston Wetland
Cardinal School Detention Vault – Construction
Four Mile Run Dredging
Headwaters of Donaldson Run Tributary B
Cardinal School Detention Vault – Complete
Capacity
Improvements,
$242,185 , 73%
Streams &
Water Quality,
$41,205 , 12%
Maintenance
Capital,
$50,865 , 15%
Stormwater Programs & Funding Sources ($000s)
$334,255 over 10 years
Program Totals
Stormwater
Utility Fee,
$42,410 , 13%
Interest Income,
$2,700 , 1%
Bonds,
$279,645 ,
83%
Grants,
$9,500 , 3%
*Notional grants of $5.75M included within Grants
10
Funding Sources
Spout Run Watershed Capacity Columbia Pike/ South Greenbrier St. Torreyson Run Watershed
Total budget: $70.0 M
Comp Plan or Strategic initiative:
Stormwater Master Plan
Community benefits:
• Establishment of overland relief
pathway to reduce risk of
repetitive flooding
Total budget: $17.2 M
Comp Plan or Strategic initiative:
Stormwater Master Plan
Community benefits:
• Floodwalls, additional inlets, pipe
upgrades, and detention to
mitigate repetitive flooding
• FY24 Design
• FY25 Construction
Total budget: $17.7 M
Comp Plan or Strategic initiative:
Stormwater Master Plan
Community benefits:
• Floodwalls, road realignment, pipe
upgrades, additional detention to
mitigate repetitive flooding
FY 2025-2034 CIP – Capacity Infrastructure
11
Voluntary Property Acquisition Program
• Some properties are at a higher risk of flooding
due to their location in former floodplains (low
topography areas)
• Program introduced in 2022, letters sent to some
property owners – Real Estate Bureau maintains
contact with owners
• Overall, six properties have been acquired (four
in Spout Run, one in Crossman Run and one in
Torreyson Run).
• Properties will be used for overland relief flow
paths, access to existing infrastructure, or space
for future infrastructure or stormwater facilities
Demolition of 4437 18th St. N
Rendering of Overland Relief
12
Land Acquisition Update
• 4423 18th St. N.
• 4433 18th St. N.
• 4437 18th St. N.
• 5840 18th St. N.
• 4434 19th St. N.
• 6415 24th St. N.
Six acquisitions to date:
13
Lubber Run Watershed Capacity Crossman Run Watershed Capacity Langston Blvd. Culvert @ N. Sycamore
Street
Total budget: $70.0 M
Comp Plan or Strategic initiative:
Stormwater Master Plan
Community benefits:
• Establishment of overland relief
pathway to reduce risk of
repetitive flooding
Total budget: $36.6 M
Comp Plan or Strategic initiative:
Stormwater Master Plan
Community benefits:
• Additional inlets, pipe upgrades,
and detention to mitigate
repetitive flooding
Total budget: $0.4 M
Comp Plan or Strategic initiative:
Stormwater Master Plan
Community benefits:
• Pipe upgrades to mitigate
repetitive flooding (requires
coordination with VDOT)
• FY25 Construction
FY 2025-2034 CIP – Capacity Infrastructure
14
STORMWATER
Project Name Total 10-Year Budget ($000s) Project Description
Flood Risk Reduction Program 14,250 Implements the capacity and flood risk reduction project priorities identified in the 2014
Stormwater Master Plan for areas which have experienced repeated flooding.
33rd Street North to
Williamsburg Capacity 4,720 Watershed-scale project in the Little Pimmit Run watershed to increase capacity by
connecting previously constructed storm drain improvements from the cul-de-sac at
33rd St N to Williamsburg Blvd.
Lower Long Branch Flood Risk
Reduction Project 3,470 Reduces risk of flooding along Lower Long Branch from South Glebe Road to 26th
Street South, including Troy Park.
Williamsburg at North
Underwood Capacity 3,105 Reduces the hydraulic grade line in Williamsburg Boulevard and increase capacity of
the storm drain system to address area flooding.
North Thomas Street 2,255 Increases capacity of the storm drain system along North Thomas Street to mitigate
flooding during severe storms.
Stohman's Run Watershed
Capacity Improvements 2,075 Increases capacity of the storm drainage system in Stohman's Run watershed along
39th Street North where there is no overland relief.
Miscellaneous Expansion/
Capacity Projects 1,670 Design and construction of pipe extensions needed to address localized drainage
problems.
Capacity Project Feasibility
Studies 1,660 Planning and feasibility studies provide an integrated approach to proper scoping of
potential projects.
Flood Resiliency Design &
Construction Guidelines 150 Addresses both residential and commercial design and construction measures,
techniques, policies and mechanisms. Includes active engagement with the public
and key stakeholders in real estate, architecture, construction, appraisals and
insurance.
FY 2025-2034 CIP Capacity Infrastructure
15
FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 FY 32 FY 33 FY 34 10 Year Total
1. 33rd Street North to Williamsburg
Capacity
- 160 1,115 1,175 1,010 1,260 - - - - 4,720
2. Capacity Project Feasibility Studies 150 155 160 165 165 170 170 175 175 175 1,660
3. Columbia Pike at South Greenbrier
Street
1,000 1,190 820 8,980 5,200 - - - - - 17,190
4. Crossman Run Watershed Capacity
Improvements
- 3,420 3,140 1,600 15,425 12,990 - - - - 36,575
5. Flood Resiliency Design & Construction
Guidelines
150 - - - - - - - - - 150
6. Flood Risk Reduction Program 1,500 1,590 1,995 2,205 1,070 1,100 1,130 1,190 1,220 1,250 14,250
7. Langston Boulevard Culvert at North
Sycamore
440 - - - - - - - - - 440
8. Lower Long Branch Flood Risk Reduction
Project
- - - - - 645 665 700 720 740 3,470
9. Lubber Run Watershed Capacity
Improvements
1,500 3,610 3,075 1,260 6,455 6,560 6,240 14,870 13,385 10,005 66,960
10. Miscellaneous Expansion/ Capacity
Projects
- 310 - 325 - 335 - 345 - 355 1,670
11. North Thomas Street 255 875 1,125 - - - - - - - 2,255
12. Spout Run Watershed Capacity
Improvements
7,900 8,130 8,630 8,340 7,630 7,805 6,920 5,815 4,490 4,305 69,965
13. Stohman's Run Watershed Capacity
Improvements
250 515 1,310 - - - - - - - 2,075
14. Torreyson Run Watershed Capacity
Improvements
1,725 4,140 4,860 5,340 1,635 - - - - - 17,700
15. Williamsburg at North Underwood
Capacity
- 155 865 960 1,125 - - - - - 3,105
Total Recommendation 14,870 24,250 27,095 30,350 39,715 30,865 15,125 23,095 19,990 16,830 242,185
Capacity Infrastructure Summary: $242M
16
Dumbarton Culvert - Upstream Dumbarton Culvert - Downstream Military Road Culvert
Total budget: $5.09 M
Comp Plan or Strategic initiative:
Stormwater Master Plan
Community benefits:
• Prevents road from being
flooded and damaged
Related Projects:
• Waterline upgrades in
Dumbarton St.
Total budget: $4 M
Comp Plan or Strategic initiative:
Stormwater Master Plan
Community benefits:
• Prevents road from being flooded
and damaged
Related Projects:
• Water main upgrades in
Dumbarton St.
Total budget: $3.12 M
Comp Plan or Strategic initiative:
Stormwater Master Plan
Community benefits:
• Prevents road from being flooded
and damaged
Related Projects:
• Gulf Branch stream resiliency
FY 2025-2034 CIP – Maintenance Capital
17
Storm Drainage Pipes and Structures
Condition of Assets
18
Inspected
on a 20-year cycle
(5% inspected/year)
Approx.
10%
of inspected assets
scheduled for
maintenance
3-5 years
of maintenance
work currently
scheduled
Future years
will increase rate of
scheduled
maintenance work
STORMWATER
Project Name Total 10-Year Budget ($000s) Project Description
Stormwater Mains Rehabilitation &
Replacement 26,965 Rehabilitation and replacement of existing storm drainage pipes within the
system.
Manhole & Catch Basin
Rehabilitation 2,760 Rehabilitation and replacement of manholes and catch basins that have
been damaged or are in need of maintenance. This is completed through
lining and/or structural rebuilds when necessary.
Stormwater Frames and Covers 2,760 Program funds the required adjustments to stormwater structure frames and
covers in conjunction with annual paving operations, raising or lowering a
casting or precast top from its existing elevation to align with the adjacent
grade, pavement, curb, etc.
Terra Cotta/ Corrugated Metal
Pipe Upgrades 2,410 Replacement of existing, poor condition terra cotta (TC) and corrugated
metal pipe (CMP) with reinforced concrete pipe or other modern pipe
materials, which have longer life spans.
Detention Vaults & Overland
Relief Maintenance 1,100 Underground detention facilities and overland relief paths require continued
capital maintenance efforts to ensure they remain effective.
Floodplain Channel & Split Stream
Maintenance 1,100 Floodplain channels must be maintained in order to ensure efficiency of the
existing conveyance system.
Four Mile Run Flood Control
Project Maintenance 1,005 Routine capital maintenance of the Four Mile Run Flood Control Project
area, as required by U.S. Army Corps of Engineers.
Sidewalk Underdrains 555 Installs underdrains on sidewalks, which are necessary in some locations to
prevent unsafe conditions on sidewalks and reduces hazards to pedestrians.
FY 2025-2034 CIP Maintenance Capital
19
FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 FY 32 FY 33 FY 34 10 Year Total
1. Detention Vaults & Overland
Relief Maintenance
100 105 105 110 110 110 110 115 115 120 1,100
2. Dumbarton Street Culvert-
Downstream
3,000 1,545 - - - - - - - - 4,545
3. Dumbarton Street Culvert-
Upstream
3,000 1,545 - - - - - - - - 4,545
4. Floodplain Channel & Split
Stream Maintenance
100 105 105 110 110 110 110 115 115 120 1,100
5. Four Mile Run Flood Control
Project Maintenance
500 50 55 55 55 55 55 60 60 60 1,005
6. Manhole & Catch Basin
Rehabilitation
250 260 265 275 275 280 280 290 290 295 2,760
7. Military Road Culvert at Gulf
Branch
2,090 1,030 - - - - - - - - 3,120
8. Sidewalk Underdrains 50 50 55 55 55 55 55 60 60 60 555
9. Stormwater Frames and
Covers
250 260 265 275 275 280 280 290 290 295 2,760
10. Stormwater Mains
Rehabilitation & Replacement
1,000 1,545 2,120 2,455 2,725 3,080 3,250 3,450 3,565 3,775 26,965
11. Terra Cotta/ Corrugated
Metal Pipe Upgrades
205 215 225 240 240 250 250 260 260 265 2,410
Total Recommendation 10,545 6,710 3,195 3,575 3,845 4,220 4,390 4,640 4,755 4,990 50,865
Maintenance Capital Summary: $51M
20
• Stormwater Master Plan: 2014 Baseline Stream
Condition Assessment
• > 6 miles of streams with severe erosion
• Approx. 40 stormwater outfalls in failing condition
• Erosion and damage continue and create new needs
• Since the 2014 Baseline Assessment:
• Approx. 1 mile of stream erosion fixed and 13 outfalls
• 1 stream project in design; 13 outfall projects in
planning/design
• Priority outfalls assessed/updated in 2020 to inform CIP
programming
• Priority stream reaches to be assessed/updated during
the next 5 years
Condition of Assets – Streams & Water Quality
21
2014 Stream Condition Assessment
Erosion severity map
Erosion is widely distributed overall, with intensity in
steeper terrain in Potomac gorge watersheds.
• Completed since 2014
• Completed before 2014
• Gulf Branch in design
• Emergency Four Mile Run repair
• Four Mile Run tidal restoration project (for reference)
Projects
•
•
•
•
Erosion Severity
Better
Worse
2014 Stream Condition Assessment
Outfall condition map
• Most damage also in
steeper terrain in Potomac
gorge watersheds
• 13 completed projects
concentrated in this area;
most co-located with
stream projects
• CIP projects will also target
other areas of damage
(blue arrows)
Good condition –
No action
needed
Fair condition –
Low priority for
repair
Poor condition –
High priority for
repair
Donaldson Run Tributary B
Sampling of benefits
• Repair failed streambanks and adjacent trails
• Protect 30” water main serving 20,000 residents
• Repair multiple failed outfalls
• Protect near stream trees
• Plant more native vegetation
• Contribute to MS4 permit compliance
Gulf Branch Stream Resiliency Concord Mews Watershed Retrofit Upper Long Branch Outfall
Total CIP budget: $3.1 M
Comp Plan or Strategic initiative:
Stormwater Master Plan
Community benefits:
• Sanitary and nature center
infrastructure protection,
environmental improvement
• FY25 Final Design
• FY26 Construction
Total CIP budget: $1.8 M
Comp Plan or Strategic initiative:
Stormwater Master Plan
Community benefits:
• Asset failure rehabilitation,
environmental improvement,
reduce street flooding
• FY24-FY25 Design
• FY26 Construction
Total CIP budget: $0.8 M
Comp Plan or Strategic initiative:
Stormwater Master Plan
Community benefits:
• Infrastructure rehabilitation,
erosion mitigation, environmental
improvement
• FY24-25 Design
• FY25-26 Construction
FY 2025-2034 CIP – Streams & Water Quality
25
NEW
MS4 permit compliance – 2nd permit
• On track for 40%
reductions required by
end of 2nd cycle (FY 2026)
• Additional compliance
helps mitigate fiscal
impact of reaching 100%
in 3rd cycle (FY 2028)
26
2nd Permit target
2006-2009 Historical BMPs
Septic Conversions
Watershed Retrofit
LDA Program
Stream Restoration
Ponds & Wetlands
Street Sweeping
MS4 permit TMDL (Total
Maximum Daily Load) reductions
required for:
• TSS (Total Suspended Solids)
• TP (Total Phosphorus)
• TN (Total Nitrogen)
MS4 permit compliance – projected 3rd permit
• Two CIP projects key to
achieving 100% targets for
TSS and TP
• Sparrow Pond (in
construction)
• Gulf Branch (90% design)
• Additional compliance
from outfall repair, pond
projects, and LDA
program
• Credits from Plant required
for 100% nitrogen goal
Projected new
deadline for
100%
27
1st permit target
2nd permit
target
3rd permit
target
ProjectedActual
STORMWATER
Project Name Total 10-Year Budget ($000s) Project Description
Outfall Rehabilitation Program 14,030 Outfall rehabilitation and repair projects are necessary to protect other
public and private infrastructure and increase the resiliency of the
integrated stream and stormwater network.
Stream Resiliency Program 13,810 Repair eroding and acutely degraded stream channels and protect critical
infrastructure such as sanitary sewer mains.
Green Streets & Infrastructure
Program 4,190 Re-construction and enhancement of existing stormwater ponds to improve
water quality performance and "green streets" streetscape bioretention. The
projects within this program help offset the continued increase in impervious
cover in our community.
Water Quality Project Feasibility &
Concept Design 1,660 Planning and feasibility studies provide an integrated approach to proper
scoping of potential projects.
Washington Boulevard Pond Retrofit 950 Improves Washington Boulevard Pond, an existing dry detention pond, to
enhance performance.
Gulf Branch and South Walter Reed
Green Streets 750 Four streetscape green infrastructure projects will be installed in the Gulf
Branch Watershed downstream of Military Road. Two additional projects will
be installed on S. Walter Reed Dr. in coordination with street improvements.
Quebec Street Outfall Rehabilitation 450 Rehabilitate the outfall and address slope erosion on Quebec Street
adjacent to the Dover Run Pumping Station.
Sparrow Pond Watershed Retrofit 450 Re-construction of an existing wet pond due to eroded sediment filling the
pond. Re-vegetation will help to restore the pond's function and address
concerns about public safety and flood storage.
FY 2025-2034 CIP Streams & Water Quality
28
FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 FY 32 FY 33 FY 34 10 Year Total
1. Concord Mews Pond Retrofit 250 1,545 - - - - - - - - 1,795
2. Green Streets & Infrastructure
Program
375 235 425 435 435 445 445 460 460 475 4,190
3. Gulf Branch and South
Walter Reed Green Streets
540 - 210 - - - - - - - 750
4 Gulf Branch Stream Resiliency 800 2,320 - - - - - - - - 3,120
5. Quebec Street Outfall
Rehabilitation
450 - - - - - - - - - 450
6. Outfall Rehabilitation
Program
925 1,725 1,305 875 1,475 1,510 1,510 1,555 1,555 1,595 14,030
7. Sparrow Pond Watershed
Retrofit
450 - - - - - - - - - 450
8. Stream Resiliency Program 250 260 2,915 275 3,000 280 3,080 290 3,165 295 13,810
9. Washington Boulevard Pond
Retrofit
- 155 795 - - - - - - - 950
10. Water Quality Project
Feasibility & Concept Design
150 155 160 165 165 170 170 175 175 175 1,660
Total Recommendation 4,190 6,395 5,810 1,750 5,075 2,405 5,205 2,480 5,355 2,540 41,205
Streams & Water Quality Summary: $41M
29
FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 FY 32 FY 33 FY 34 10 Year Total
Capacity Improvements 14,870 24,250 27,095 30,350 39,715 30,865 15,125 23,095 19,990 16,830 242,185
Streams & Water Quality 4,190 6,395 5,600 1,750 5,285 2,405 5,205 2,480 5,355 2,540 41,205
Maintenance Capital 10,545 6,710 3,195 3,575 3,845 4,220 4,390 4,640 4,755 4,990 50,865
Sub-Total 29,605 37,355 35,890 35,675 48,845 37,490 24,720 30,215 30,100 24,360 334,255
Implementation Adjustment
(20%)
(5,920) (7,470) (7,180) (7,135) (9,770) (7,495) (4,945) (6,045) (6,020) (4,875) (66,855)
Total Recommendation 23,685 29,885 28,710 28,540 39,075 29,995 19,775 24,170 24,080 19,485 267,400
Program Summary: $267M
30
FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 FY 32 FY 33 FY 34 10 Year Total
New Funding
Federal Funding 3,540 - - 4,000 210 - - - - - 7,750
State Funding - - 1,750 - - - - - - - 1,750
Stormwater Utility Fee
Revenue
3,835 3,910 3,435 3,945 3,840 4,500 4,295 4,865 4,615 5,170 42,410
New Bond Issue - 155 23,825 27,480 44,545 32,740 20,175 25,100 25,235 18,940 218,195
Other Funding 450 250 250 250 250 250 250 250 250 250 2,700
Subtotal New Funding 7,825 4,315 29,260 35,675 48,845 37,490 24,720 30,215 30,100 24,360 272,805
Previously Approved Funding
Authorized but Unissued
Bonds
21,780 33,040 6,630 61,450
Subtotal Previously Approved
Funding 21,780 33,040 6,630 61,450
Total Funding Sources 29,605 37,355 35,890 35,675 48,845 37,490 24,720 30,215 30,100 24,360 334,255
Implementation Adjustment
(20%)
(5,920) (7,470) (7,180) (7,135) (9,770) (7,495) (4,945) (6,045) (6,020) (4,875) (66,855)
Total Recommendation 23,685 29,885 28,710 28,540 39,075 29,995 19,775 24,170 24,080 19,485 267,400
Funding Summary
31
November 2024 Bond Referendum is not needed due to existing unissued balances on 2020 & 2022 Bond Referenda
32
Stormwater Utility Rate Regional Comparison
(Average Household)
In CY 2024, burden shifts from Real Estate Assessment-based stormwater tax to an Impervious Area-based Stormwater Utility Fee.
Fee will continue to increase to support the debt service/bonds issued in support of CIP.
$-
$50
$100
$150
$200
$250
$300
$350
FY2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 FY 2024 FY 2025
Adopted
Annual cost ($)
Fairfax County is the only jurisdiction still assessing a tax rate to fund stormwater.
Fairfax City transitioned to a utility in FY2023
Arlington$258
$287 District of Columbia
$324 Alexandria
$162
Fairfax County
Fairfax City
$242
$52 PW County
$291 Falls Church
Transitions from Tax to
Utility Fee for CY24
Projected Debt & Rate Impact
$-
$100
$200
$300
$400
$500
$600
$700
$-
$2,000
$4,000
$6,000
$8,000
$10,000
$12,000
$14,000
FY25 FY26 FY27 FY28 FY29 FY30 FY31 FY32 FY33 FY34
Stormwater Rate ($/ERU)
Annual Debt Service ($000s)
Fiscal Year
Projected Future Debt Existing 2021 GO Debt Projected Utility Rate ($/ERU)
FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 FY 32 FY 33 FY 34
Projected Annual
Rate per ERU
$258 $271 $311 $356 $389 $445 $494 $529 $556 $577
Projected Annual
Debt Service ($000s)
1,905 2,925 4,585 6,090 7,410 9,660 11,290 12,275 13,500 13,505
Debt Coverage Ratio
(req. 1.25)
2.41 1.65 1.42 1.44 1.38 1.36 1.38 1.40 1.34 1.38
33
Summary & Conclusion
Work in Progress:
o Flood Resilient Design and Construction Guidelines
o Investment in capital maintenance / systems maintenance (SGR)
o Long-term: Need to consider zoning overlays for climate-facing design and
construction
Challenges:
o Timing/ adjacency with voluntary property acquisition program
o Public expectations and urgency vs. public tolerance of significant disruption
o Space constraints
o Lack of easements to access conveyance system
o Policy decisions that are integral to design and execution
o Impacts of continuing climate change
34
Proposed Capital
Improvement Plan (CIP)
FY 2025 – FY 2034
Submission of a 10-Year
Plan for Stormwater