Proposed Capital
Improvement Plan (CIP)
FY 2025 – FY 2034
Submission of a 10-Year
Plan for Utilities
Utilities Overview
2
Guiding Principles
• System resiliency & redundancy
• Reinvestment in infrastructure
Guiding Plans and
Commitments
• Water Distribution System Master Plan (2014)
• Water Supply Resiliency Report (2023)
• Sanitary Sewer Collection System Plan (2024)
• Water Pollution Control Plant Solids Master Plan (2018)
• Investments at Washington Aqueduct & DC Water’s
Blue Plains Advanced Wastewater Treatment Plant
Asset Goals for System Renewal
3
525 mi
of water mains
Target:
• Annually replace 1.5-2.0% of
non-transmission distribution
system
Water Distribution
• 18% (94 miles) new
mains installed since
2000
• 13% (69 miles) cleaned
& lined
Water Assets by Age
4
*Targeted replacement schedule of 1.6% of the small diameter system
per year
Nearly half of the distribution system is 75+ years old
Concrete, 3.5% Unknown, 2%
Other & plastic, 0.50%
Cast Iron,
60%
Ductile Iron,
34%
Water Mains by Material
0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
Over 90 years old 75 to 89 years old 50 to 74 years old 25 to 49 years old Less than 25 years
old
% of System
Small Diameter (< 12") Water Main Age
Asset Goals for System Renewal
5
459 mi
of sanitary sewer
Target:
• All programs combined target
3% reline / rehab system
annually
Sanitary Sewer System
• 71% eligible small
diameter has been
relined
• 112 miles will be
relined during the
next 10 years.
Distribution of CIP Investments
6
Washington Aqueduct
Blue Plains
Advanced WWTP
Finished water
reliability &
interconnects
Visit the interactive CIP map on the County’s website
Projects are guided by
system plans:
• Maintaining and
upgrading system assets
across the County to
ensure operability and
resilience of the
water systems, sanitary
sewer collection and
treatment systems.
• Important for public
health for citizens and
businesses.
Completed Project Highlights
7
33" Spout Run Deep Sewer
Relining and Rehabilitation
12” water main under N.
Rhodes/ Queen St Bridge over
Route 50 in Fort Myer Heights
Preliminary Treatment Building
Bar Screens/Odor Control
Upgrades
Fund Balance
$27,980 3%
Utilities
PAYG
$164,050
19%
Bonds
$523,700
59%
Developer Fees
$104,095 12%
Other Funding
$60,060 7%
Utilities CIP Programs & Funding Sources ($000s)
$880M over 10 years
Program Totals Funding Sources
W-S
Maintenance
Capital
$388,020 44%
Water
Distribution
$168,980 19%
Sanitary Sewer
Improvements
$3,435 1%
Plant Capital
Sustainment
$319,450 36%
8
FY 2025-2034 CIP – W-S Maintenance Capital
Water Main Replacements Program Washington Aqueduct Capital Sewer Manhole Rehabilitation
Total budget: $78.8M
Comp Plan or Strategic initiative:
Water Distribution Master Plan
Community benefits:
• Service reliability
• Non-revenue water loss
reduction
• Improved water quality
Related Projects:
• Water Main Cleaning & Lining
Total budget: $145.8M
Comp Plan or Strategic initiative:
Water Resiliency and Redundancy
Community benefits:
• Public health necessity to provide
clean drinking water.
Related Projects:
• Finished Water Reliability &
Interconnections
• Regional Source Water Resiliency
Total budget: $11.2M
Comp Plan or Strategic initiative:
Sanitary Sewer Collection System Plan
Community benefits:
• Reduction of inflow & infiltration
• Restore structural integrity
• Extend service life by 50 years
Related Projects:
• Sewer - Infiltration/Inflow
• Large Diameter Sewer Rehabilitation
9
Sewer - Large Diameter Main Rehabilitation
Federal Grants
Projects for Large
Diameter Sewer
Comprehensive Plan
Goal: Maintenance
of sewage collection
system
10
Technology Enhancements: Advanced Metering
Infrastructure (AMI) Pilot
11
Total budget: $12.9M
FY24 – FY26 Pilot Program
• Initially pilot 100 commercial and residential accounts
• If successful, move to transitioning ~3,400 commercial and multi-
family accounts (comprises 75% of County’s water consumption)
Transition Residential over 4 years: FY28 – FY31
Multi-year program to transition the County from
Automated Meter Reading to AMI
• Real-time monitoring and reporting of water usage
• Ability to proactively detect leaks
• Water loss reduction
• Reduced carbon footprint by reducing vehicle miles
traveled (VMT)
Benefits
WATER & SEWER
Project Name Total 10-Year Budget
($000s)
Project Description
Water-Main Cleaning and Lining Program 17,850 Rehabilitates small diameter (8-inch and below) pre-1960s cast iron water mains
to restore flow capacity and improve water quality. In conjunction with the water
main replacement program, this project will improve the overall condition of the
County's water main assets.
Water-Large Diameter Main & Valve
Rehabilitation
11,155 Rehabilitates large diameter (20-36-inch) water mains that are over 50 years old,
as well as the rehabilitation or replacement of 16-inch or larger valves and
pressure regulating valves.
Water-Tank Rehabilitation 3,705 Water tanks are inspected every five years. Painting and other maintenance
work are programmed accordingly based on results.
Water-Small Diameter Valve
Rehabilitation & Replacements
3,335 Rehabilitates and/or replaces small diameter water valves throughout the
County, as identified through the Valve Inspection and Exercise Program.
Water-Large Meter Vault Rehabilitation &
Replacements
2,230 Ensures that large commercial meters, responsible for about 75% of the system’s
revenue, are kept in good working condition. Large meter vault inspections and
condition assessments are being conducted in conjunction with the large meter
replacements to identify vaults requiring rehabilitation or replacement.
Water-Pump Station Rehabilitation 565 Maintenance capital and rehabilitation of various water pump stations
throughout the County to keep the equipment and facilities properly functioning.
FY 2025-2034 CIP – W-S Maintenance Capital
12
WATER & SEWER
Project Name Total 10-Year Budget
($000s)
Project Description
Sewer-Main Replacement Program 31,950 Replaces smaller diameter sewer mains when lining sewer mains is
not viable or recommended.
Sewer-Infiltration & Inflow 27,500 Rehabilitates the small diameter (less than 15-inch) sanitary sewer
system to eliminate infiltration and inflow, the intrusion of rain, ground,
or surface water into the County's sanitary sewer system.
Sewer-Force Mains 3,615 Rehabilitates and/or replaces the County's force main systems, which
are necessary to convey sewage for much of the northern third of
the County, which are at a lower elevation than the rest of the
County.
Trades Center Equipment &
Improvements
1,035 Funding is related to relocating staff at the Trades Center from trailers
that are beyond their useful life to permanent facilities.
Water Sewer Frames & Covers 11,155 Involves adjusting the elevation of water valve or manhole frames,
either by raising or lowering, to align with the adjacent grade,
pavement, curb, etc. in conjunction with the annual street paving
program.
FY 2025-2034 CIP – W-S Maintenance Capital
13
FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 FY 32 FY 33 FY 34 10 Year Total
1. Sewer-Infiltration & Inflow $3,000 $3,105 $3,210 $3,315 $3,315 $3,420 $3,420 $3,525 $585 $605 $27,500
2. Sewer-Large Diameter Main
Rehabilitation 2,780 2,185 4,140 2,550 3,090 2,340 100 4,220 1,040 2,050 24,495
3. Water-Large Diameter Main & Valve
Rehabilitation 1,000 1,035 1,070 1,105 1,105 1,140 1,140 1,175 1,175 1,210 11,155
4. Water-Large Meter Vault
Rehabilitation & Replacements 200 205 215 220 220 230 230 235 235 240 2,230
5. Manhole Rehabilitation 1,000 1,035 1,070 1,105 1,105 1,140 1,140 1,175 1,175 1,210 11,155
6. Water-Pump Station Rehabilitation - 105 - 110 - 115 - 115 - 120 565
7. Sewer-Force Mains 2,100 155 160 165 165 170 170 175 175 180 3,615
8. Sewer-Main Replacement Program 2,000 2,590 3,210 3,315 3,315 3,420 3,420 3,525 3,525 3,630 31,950
9. Water-Small Diameter Valve
Rehabilitation & Replacements 300 310 320 330 330 340 340 350 350 365 3,335
10. Technology Enhancements 725 1,365 60 2,630 2,735 2,935 3,050 65 65 65 13,695
11. Trades Center Equipment &
Improvements - 1,035 - - - - - - - - 1,035
12. Washington Aqueduct Capital 7,800 8,075 8,345 8,620 8,620 8,890 8,890 67,915 9,165 9,440 145,760
13. Water-Main Cleaning and Lining
Program 1,600 1,655 1,710 1,770 1,770 1,825 1,825 1,880 1,880 1,935 17,850
14. Water-Main Replacement Program 7,000 6,725 6,955 7,180 7,735 7,980 8,550 8,810 8,810 9,075 78,820
15. Water/Sewer Frames/Covers 1,000 1,035 1,070 1,105 1,105 1,140 1,140 1,175 1,175 1,210 11,155
16. Water-Tank Rehabilitation 100 - 105 2,320 830 115 - 115 - 120 3,705
Total Proposed $30,605 $30,615 $31,640 $35,840 $35,440 $35,200 $33,415 $94,455 $29,355 $31,455 $388,020
W-S Maintenance Capital Summary: $388M
14
Water Pump Station Improvements Finished Water Reliability &
Interconnections
Regional Source Water Resiliency
Total budget: $3.8M
Comp Plan or Strategic initiative:
Water Resiliency and Redundancy
Community benefits:
• Redundancy
• Reliability during power outages
Related Projects:
• Lee PS MCC & Generator
• Ethan Allen Generator
• Minor Hill Generator
Total budget: $94.8M
Comp Plan or Strategic initiative:
Water Supply Resiliency Report
Community benefits:
• Resiliency and redundancy
• Ensures availability of drinking
water during emergencies
• FY23-FY27 Planning & Design
• FY28-FY31 Construction
• Formerly called “Source Water Reliability &
Interconnections”
Total budget: $60.5M
Comp Plan or Strategic initiative:
Potomac Secondary Source
Feasibility Study
Community benefits:
• Regional effort for off-river storage,
including federal funding
• Mitigates severe water shortages
due to environmental impacts
and/or source contamination
• Placeholder funding in FY34
• Formerly called “New River Crossing”
FY 2025-2034 CIP – Water Distribution
15
RENAMED RENAMED
WATER & SEWER
Project Name Total 10-Year
Budget
($000s)
Project Description
Water-Improvements for
Development
5,570 This program addresses opportunities to enhance the water
distribution system in conjunction with nearby developments, focusing
on improving water quality, redundancy, and transmission capacity.
Projects include water main looping, work to abandon existing mains
and the completion of loops in prior developments.
Transmission Mains Resiliency 4,205 This program provides redundant water mains to back up existing
transmission capacity.
FY 2025-2034 CIP – Water Distribution Projects
16
RENAMED
FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 FY 32 FY 33 FY 34 10 Year Total
1. Finished Water Reliability
& Interconnections
$500 $2,070 $2,140 $11,050 $22,100 $22,800 $34,200 - - - $94,860
2. Water-Improvements for
Development
500 520 535 550 550 570 570 585 585 605 5,570
3. Water-Pump Station
Improvements
2,250 110 265 830 - 125 - 130 - 135 3,845
4. Regional Source Water
Resiliency
- - - - - - - - - 60,500 60,500
5. Transmission Mains
Resiliency
150 310 3,745 - - - - - - - 4,205
Total Proposed $3,400 $3,010 $6,685 $12,430 $22,650 $23,495 $34,770 $715 $585 $61,240 $168,980
Water Distribution Summary: $169M
17
RENAMED
RENAMED
RENAMED
Sanitary Sewer Improvements Summary: $3.4M
Sewer - Improvements for Development Program
• Provides funding for small segments of new sewer main installation and other
work directly associated with development.
• Provides for extension of sewer improvements along the remainder of a block
where the developer is only responsible for work immediately on the frontage
of the site.
• FY 2025 includes funding for new sewer main on North Lexington Street from
9th Street North to Wilson Boulevard.
($000s) FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 FY 32 FY 33 FY 34 10 Year
Total
Improvements for
Development
$900 $260 $265 $275 $275 $285 $285 $295 $295 $300 $3,435
18
Activated Sludge Effluent Pump
Station #1 (ASE1)
Asset Management System
Replacement
Maintenance Capital – Fiberglass
Reinforced Plastic Tank Replacement
Total budget: $11.7M
Community benefits:
• More efficient pumping
infrastructure to handle a wide
range of flows at the WPCP
• FY25 Condition Assessment
• FY26 Design
• FY27-FY29 Construction
Total budget: $2.3M
Community benefits:
• Current software dates to 1990s
and does not have modern
functionality
• New software will help more
proactively maintain the WPCP’s
assets in a state of good repair
• FY24-FY26 Implementation
Total budget: $3.3M
Community benefits:
• Replaces five failing chemical
storage tanks
• Increased efficiency of chemical
usage for wastewater treatment
• Additional tank replacements are
planned for future years
FY 2025-2034 CIP – WPCP Capital Sustainment
19
NEW
Re-Gen: Phases 2 & 3
• Significant investment and long-term
sustainability in the Plant handling
processes
• Addresses potential future regulatory
changes while reducing community
impacts
• Contract with Design-Build team
executed in early 2024.
• Full design begins Summer 2024
• Guaranteed Maximum Price (GMP)
approval for construction expected
to be presented to the Board in late
2025
• External stakeholder engagement to
inform the community and gather
feedback
20
Total budget: $226.0M
Estimated Completion: End of CY 2029 Comp Plan or Strategic Initiative: Solids Master Plan
Sustainability & Community Benefits
Increase energy & operational efficiency of all buildings
Increase local energy supply and distribution efficiency in Arlington using District Energy
Increase locally generated energy supply through use of renewable energy options
Refine and expand transportation infrastructure and operations enhancements
Integrate CEP goals into all County activities
Advocate and support personal action through behavior change and effective education
Energy positive
Less truck traffic
Less chemical
usage
Lime deliveries
eliminated
Less fossil fuel
Offsets 81,000 MMBtu
per year
Fewer
greenhouse
gas emissions
4,290 metric tons per
year reduced
Re-Gen Supports 4 of the 6 Arlington Community Energy Plan Goals:
Stakeholder Tour 2022
Outreach at Rock-N-
Recycle 2023
21
More resilient
infrastructureBiosolids hauling
cut in half35% more energy
produced than
consumed
WATER & SEWER
Project Name Total 10-Year
Budget ($000s) Project Description
WPCP Maintenance Capital 22,310
Funding covers a wide variety of one-to-one capital replacements and capital
maintenance associated with the Water Pollution Control Plant's assets, including items
such as HVAC overhauls, major equipment rehabilitation or replacements, and capital
repairs to process structures such as tanks or pipes. Includes Improvements to Eads St
Property
Blue Plains Capital Improvements 19,155 DC Water's Blue Plains Advanced Wastewater Treatment Plant processes a portion of
Arlington County's sewage after transmission through Fairfax County mains.
Secondary Clarifiers 18,210 Rehabilitation and/or replacement of three secondary clarifiers will restore the tanks to full
working condition.
WPCP Technology Enhancements 10,120 This program includes a comprehensive suite of projects to address needed upgrades to
the WPCP's Process Control System (PCS) and associated technology infrastructure.
USACE Coastal Storm
Resiliency 5,900 The project will study a potential floodwall that would be constructed along the northern
bank of Four Mile Run between the Four Mile Run bike trail and the WPCP.
Grit System Upgrades 2,705
This project will evaluate and rehabilitate/ improve the grit collection and disposal system in
the Preliminary Treatment Building to improve removal of the abrasive material and protect
downstream equipment. Formerly called Primary Clarifier Upgrades
Odor Control 1,100 Due to the location of the WPCP, it is necessary to tightly control and limit odors by
collecting and treating odorous air.
FY 2025-2034 CIP WPCP Capital Sustainment
22
NEW
NEW
($000s) FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 FY 32 FY 33 FY 34 10 Year Total
1. Activated Sludge Effluent
Pump Station #1
$800 $1,550 $2,675 $4,970 $1,655 - - - - - $11,650
2. Asset Management System
Replacement
1,000 1,035 265 - - - - - - - 2,300
3. Blue Plains Capital
Improvements
1,210 1,705 1,825 2,775 3,010 2,605 2,130 1,455 885 1,555 19,155
4. Grit System Upgrades 300 595 1,175 635 - - - - - - 2,705
5. Improvements to Eads St
Property
- 10 - 10 - 10 - 10 - 10 50
6. Odor Control - - - 550 550 - - - - - 1,100
7. Re-Gen Phase II 10,600 4,865 - - - - - - - - 15,465
8. Re-Gen Phase III 17,200 58,030 62,925 50,575 21,755 - - -- - - 210,485
9. Secondary Clarifiers - - - - - - 1,140 5,170 7,755 4,145 18,210
10. USACE Coastal Storm
Resiliency
200 - - - - - 5,700 - - -
5,900
11. WPCP Maintenance Capital 2,000 2,070 2,140 2,210 2,210 2,280 2,280 2,350 2,350 2,420 22,310
12. WPCP Technology
Enhancements
3,500 2,070 535 550 550 570 570 585 585 605 10,120
Total Proposed $36,810 $71,930 $71,540 $62,275 $29,730 $5,465 $11,820 $9,570 $11,575 $8,735 $319,450
WPCP Capital Sustainment Summary: $319.5M
23
NEW
NEW
NEW
($000s) FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 FY 32 FY 33 FY 34 10 Year Total
Water-Sewer Maintenance 30,605 30,615 31,640 35,840 35,440 35,200 33,415 94,455 29,355 31,455 388,020
Sanitary Sewer Improvements 900 260 265 275 275 285 285 295 295 300 3,435
Water Distribution 3,400 3,010 6,685 12,430 22,650 23,495 34,770 715 585 61,240 168,980
Water Pollution Control Plant 36,810 71,930 71,540 62,275 29,730 5,465 11,820 9,570 11,575 8,735 319,450
Sub-Total 71,715 105,815 110,130 110,820 88,095 64,445 80,290 105,035 41,810 101,730 879,885
Implementation Adjustment
(20%) (14,340) (21,160) (22,030) (22,160) (17,620) (12,890) (16,060) (21,010) (8,360) (20,350) (175,980)
Total Recommendation 57,375 84,655 88,100 88,660 70,475 51,555 64,230 84,025 33,450 81,380 703,905
Utilities Program Summary: $703.9M
24
($000s) FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 FY 32 FY 33 FY 34 10 Year Total
New Funding
Developer Contributions 7,900 9,385 9,665 10,270 10,265 10,875 10,875 11,420 11,415 12,025 104,095
PAYG 7,993 13,202 19,470 18,050 22,355 19,790 19,930 16,365 12,830 14,065 164,050
New Bond Issue 3,400 10,820 17,665 33,795 50,545 32,890 48,535 74,355 15,550 73,785 361,340
Other Funding 9,040 13,050 13,495 10,940 4,930 890 2,050 1,795 2,225 1,645 60,060
Subtotal New Funding 28,333 46,457 60,295 73,055 88,095 64,445 81,390 103,935 42,020 101,520 689,545
Previously Approved Funding
Authorized but Unissued
Bonds
23,640 52,205 52,225 34,290 - - - - - - 162,360
Issued but Unspent Bonds - - - - - - - - - - -
Other Previously
Approved Funds 20,242 7,738 - - - - - - - - 27,980
Subtotal Previously Approved
Funding 43,882 59,943 52,225 34,290 - - - - - - 190,340
Total Funding Sources 72,215 106,400 112,520 107,345 88,095 64,445 81,390 103,935 42,020 101,520 879,885
Implementation Adjustment
(20%) (14,340) (21,160) (22,030) (22,160) (17,620) (12,890) (16,060) (21,010) (8,360) (20,350) (175,980)
Total Recommendation 57,875 85,240 90,490 85,185 70,475 51,555 65,330 82,925 33,660 81,170 $703,905
Program Summary
25
-
5,000
10,000
15,000
20,000
25,000
30,000
35,000
FY25 FY26 FY27 FY28 FY29 FY30 FY31 FY32 FY33 FY34
Debt Service ($000s)
Fiscal Year
Existing GO Debt
New Sewer
Debt
New Water
Debt
Existing VRA Debt
26
Projected Utilities Fund Annual Debt Service
Utilities Rate 6-Year Forecast
FY
2025
FY
2026
FY
2027
FY
2028
FY
2029
FY
2030
W-S Projected Rate Increase
from prior year* 4.8% ~5.5% 2-4% 2-4% 2-4% 2-4%
Annual increase to average
homeowner using 48
Thousand Gallons (TG)
$38 ~$45 $20-40 $20-40 $20-40 $20-40
27
* Rates are annually adopted by the County Board during the operating budget process. These are notional
projections based on current economic conditions. Rate drivers include water consumption/ sales, personnel
costs, chemicals, electricity, direct/ indirect/ overhead service charges, infrastructure investments, and alignment
with financial policies.
Bond Referenda ($000s)
Funding Source FY
2024
FY
2025
FY
2026
FY
2027
FY
2028
FY
2029
Total
Nov 2022 Approved Referendum* $13,850 24,788 50,439 48,812 37,989 1,482 177,360
Nov 2024 Referendum (Proposed)** --- 3,400 10,820 14,220
Total Planned Debt*** 13,850 28,188 61,259 48,812 37,898 1,482 $191,580
* Aligns uses according to November 2022 bond referenda ($149.5M Re-Gen, $17.9M water (including Aqueduct))
** Dependent upon Aqueduct federal borrowing authority implementation & timing. Unknown if will be available starting in FY 2025.
*** Excludes Implementation adjustment
28
2024 Utilities Bond Referendum ($000s)
Utilities CIP Category Projects/ Programs Amount
W-S Maintenance Capital Washington Aqueduct, Water Main
Replacements
$12,430
Water Distribution Finished Water Reliability & Improvements 505
WPCP Capital Sustainment Activated Sludge Effluent Pump Station #1
(ASE1)
1,285
29
Total 2024 Proposed Bond Referendum = $14,220
Summary & Conclusion
Utilities’ CIP requests align with Manager’s priorities:
• Environmental & Resiliency goals
• Maintaining State of Good Repair (SGR)
• Regional Commitments
• Sustainable funding aligned with financial policies
Challenges:
• Regulatory changes
• Pricing and supply chain volatility
• Extended delivery times
• Schedule impacts due to skilled labor shortages
• Resources to add new assets, as well as maintain aging assets
while operating current systems
30
Proposed Capital
Improvement Plan (CIP)
FY 2025 – FY 2034