Economic Development Authority — Agenda Minutes
Chesterfield County · Chesterfield County · Economic Development Authority · meeting of Mar 19, 2026 · Other
Open the original document More from Chesterfield County
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Economic Development Authority of Chesterfield County
Meeting Minutes
March19, 2026
P a g e 1 | 4
Members Attending:
Terri Cofer Beirne Danielle Fitz Hugh Faizan Habib
Robert Vaughn* John Hughes
John V. Cogbill, III Jesse Calloway
Members Absent:
None
*Attended via Teams
Others Attending:
John O'Neill, Hunton Andrews Kurth, LLP
Brendan Staley, Hunton Andrews Kurth, LLP
Mike Chernau, Senior County Attorney
Tim Davey, Timmons Group
Garrett Hart, Chesterfield Economic Development
Matt McLaren, Chesterfield Economic Development
Jake Elder, Chesterfield Economic Development
Samantha Furnish, Chesterfield Economic Development
Terri Cofer Beirne called the meeting to order at 3:03 pm and noted that a quorum was present for
the Economic Development Authority meeting on March 19, 2026.
Approval of the Minutes:
Terri Cofer Beirne requested that the Authority approve the minutes of the February 19, 2026,
meeting. John Hughes motioned to approve the meeting minutes as written. John Cogbill
seconded, and all members present voted in the affirmative.
Financial Statements Update:
Debbie Baicy provided the February financial report, highlighting cash reserves and project funding.
Springline at District 60 Update:
Jake Elder shared a plat showing the area where the future police station will be located in the
Springline development. He said the property is currently owned by the Economic Development
Authority (EDA). At this time, the EDA is prepared to initiate the transfer of approximately two acres
of the Springline site to the County for the police station.
Danielle Fitz Hugh motioned to authorize the Chair and Vice Chair, or either of them, to execute all
such agreements associated with the transfer of approximately a two-acre site at Springline to the
County for the Falling Creek Police Precinct. Faizan Habib seconded, and all members present
voted in the affirmative.
Jake explained as part of the County's site planning and layout process, an existing power line
easement impacts a portion of the property. While no building structures are permitted within this
easement, the County has secured a license agreement allowing the area to be used for parking.
This agreement was coordinated directly with Dominion Energy.
Economic Development Authority of Chesterfield County
Meeting Minutes
March19, 2026
P a g e 2 | 4
Jake also noted that a gas transmission line runs through the Stonebridge site, adjacent to the
power line corridor. The County has now successfully obtained all required easement and license
agreements and is fully authorized to proceed with construction.
Garrett Hart discussed the importance of establishing a cohesive theme for the Midlothian corridor
from both a marketing and pedestrian experience standpoint, consistent with the Springline
signage and branding. To ensure a unified identity, staff proposed re-engaging Cooper Carry to
develop a thematic approach that ties Springline into the broader corridor. This effort will be
funded using the remaining proceeds from the development.
He said a proposal has been received from Cooper Carry to complete this work. In addition, a
separate proposal has been developed to incorporate design elements for the planned pedestrian
bridge. While earlier concepts considered a more costly stone bridge, staff are pursuing a more
cost-effective steel bridge design, incorporating rail-inspired elements and branding features such
as Springline graphics to maintain visual consistency across the corridor.
Meadowville Technology Park Update:
Jake Elder reported visiting the LEGO manufacturing facility site earlier in the day alongside the
County's building inspections team. The project, being constructed by Gray Construction, remains
on schedule. The team anticipates beginning phased turnover of portions of the approximately 1.7
million-square-foot facility to LEGO and its vendors in late fall for equipment installation,
commissioning, and testing. Full operations are projected to begin in early 2027, with more than
1,000 employees expected on-site. He also noted ongoing solar infrastructure construction
associated with the project. A recent announcement indicated that the total investment has
increased to more than $1.5 billion, exceeding the originally announced $1 billion. Current
projections indicate the first brick will be produced in June 2027.
Jake provided additional updates on the following projects:
Chirisa continues construction on its third building within the campus.
Google's data center site off Bermuda Hundred Road is actively undergoing grading, with
the first building anticipated to be operational in the fourth quarter of 2027.
Chirisa is expanding operations at its Digital Drive campus (formerly the Cartograph site).
Civica's pharmaceutical manufacturing facility is now under roof, with interior construction
progressing.
Tim Davey reported that work continues on the two active roadway improvement projects,
including the perimeter road around the LEGO campus and a road-widening project. Progress has
been limited over the past two months due to unfavorable weather, and there have been no
significant updates since last month.
Upper Magnolia Green Update:
Tim Davey reported in 2023, the UMG project received a $25 million state grant, which has primarily
supported the design of critical infrastructure. A significant milestone was achieved in the past
month with the issuance of a permit to construct a 400-acre pad site.
In 2024, the project was awarded an additional $13 million to initiate construction activities. These
funds have supported the design and construction of the Duval Road realignment, which will
provide site access, as well as the development of an initial 10-acre pad for marketing purposes.
Economic Development Authority of Chesterfield County
Meeting Minutes
March19, 2026
P a g e 3 | 4
An additional $10.5 million in state funding has been allocated to advance other long-lead
infrastructure components. These funds are being used to begin clearing within the future
industrial footprint, including the western arterial collector corridor.
Tim also noted the award of $35 million through the Transportation Partnership Opportunity Fund
(TPOF). These funds will be combined with the $10.5 million allocation to support a coordinated
construction effort. The goal is to initiate a single mobilization in summer 2026 to advance both
clearing and roadway construction activities.
He said over the next 12 months, Duval Road access is expected to be completed, enabling
improved site visibility and access. Concurrently, substantial progress is anticipated on roadway
infrastructure extending from Hull Street Road into the site.
Other Updates:
Matt McLaren reported strong overall economic development activity, noting it as likely the most
robust in the past year. Several large-scale projects remain active across multiple sites, including
interest in the Upper Magnolia area; however, no final site selections have been made. He
highlighted the continued presence of multiple multi-billion-dollar projects in the market, reflecting
positively on the County's competitiveness and recent state investment.
Matt said Berry Hill in Danville is the only other site in Virginia comparable in size to Upper
Magnolia. It was reported that Berry Hill has informally indicated plans to sell the remaining
acreage to a data center developer, though details remain limited. While the project appears to be
primarily data center-focused, there may be some associated light manufacturing.
He also emphasized that developments of this scale typically require a significant workforce of
highly skilled engineering professionals, which may present challenges in other regions. The
situation at Berry Hill will continue to be monitored in coordination with state partners, with
additional information expected in the coming months.
Garrett Hart reported that significant progress has been made on addressing legislative concerns
related to data center policy and land-use and zoning issues affecting housing. Many of the
previously problematic provisions have either been removed or revised to a more acceptable level
through collaboration among regional and state partners. Staff noted ongoing differences between
the Governor and the General Assembly regarding data center policy, tax incentives, and related
economic development strategies. The Governor has expressed support for maintaining existing
incentive commitments, while legislative actions have moved in the opposite direction.
He said the main discussions have now shifted to the state budget, where key decisions remain
unresolved. The recent delay in the budget process provides the Governor with an opportunity to
propose a revised budget that aligns more closely with these priorities, including continued
support for economic development initiatives such as state marketing and site selection.
There being no further business, Danielle Fitz Hugh motioned to conclude the meeting at 3:46 pm.
John Hughes seconded, and all members present voted in the affirmative.
Economic Development Authority of Chesterfield County
Meeting Minutes
March19, 2026
P a g e 4 | 4
Respectfully submitted,
Samantha Furnish
Recording Secretary
Next Meeting: April 16, 2026, at 3 pm