RecordWell Data

Economic Development Authority — Agenda Minutes

Chesterfield County · Chesterfield County · Economic Development Authority · meeting of Nov 20, 2025 · Other

Open the original document More from Chesterfield County

Text

Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.

Economic Development Authority of Chesterfield County Minutes November 20, 2025 P a g e 1 | 4 Members Attending: Terri Cofer Beirne Faizan Habib Robert Vaughn John Hughes John V. Cogbill, III Jesse Calloway Members Absent: Danielle Fitz Hugh Others Attending: John O'Neill, Hunton Andrews Kurt, LLP* Mike Chernau, Senior County Attorney Mike Laing, ECI Tim Davey, Timmons Group Debbie Baicy, Chesterfield Accounting Garrett Hart, Chesterfield Economic Development Jake Elder, Chesterfield Economic Development Matt McLaren, Chesterfield Economic Development Samantha Furnish, Chesterfield Economic Development Aiden Thompson, Chesterfield Budget & Management* *Attended via Microsoft Teams Terri Cofer Beirne called the meeting to order at 3:04 pm and noted that a quorum was present for the November 20, 2025, Economic Development Authority meeting. Approval of the Minutes: Terri Cofer Beirne requested that the Authority approve the minutes from the October 16, 2025, meeting. Robert Vaughn motioned to approve the meeting minutes as written. John Hughes seconded, and all members present voted in the affirmative. Financial Statements Update: Debbie Baicy provided the October financial report, highlighting cash reserves and project funding. Springline at District 60 Update: Mike Laing reported that Phase 1 work is nearing completion. He presented to the Authority for approval a set of change orders related to the parking deck and infrastructure portion of the Whiting–Turner contract. The first item is a $16,500 adjustment for revised striping work on Midlothian Turnpike. After early utility work was completed, VDOT requested that the striping be redone in accordance with updated specifications. The second item is a $295,425 cost for relocating the existing storm line on Parcel 3. This work is part of the additional Phase 1D scope previously discussed in August. The storm line had initially been placed farther inside the parcel to accommodate an earlier plan. With the new mixed-use building now planned for Parcel 3, the storm line must be moved to clear the footprint of the future structure. Economic Development Authority of Chesterfield County Minutes November 20, 2025 P a g e 2 | 4 The third item is $314,991 for grading work on Parcels 2 and 3, also part of the Phase 1D preparations for the hotel on Parcel 2 and the residential/hotel and Collins mixed-use development on Parcel 3. Soil has been relocated across the site to create the required building pad elevations. Parcel 2 has been graded to the hotel developer's required starting elevation, while Parcel 3 has two soil stockpiles reserved for upcoming construction. Additional excess soil has been placed on Parcel 1/4 and remains available for sale. Robert Vaughn motioned for approval of change order #015 totaling $626,919 for the parking deck and infrastructure portion of the Whiting–Turner contract. Jesse Calloway seconded, and all members present voted in the affirmative. Mike reported that several allowances and the contingency line item within Whiting–Turner's contract were not fully utilized. Under the contract terms, the remaining balance returns to the project. As the infrastructure portion of the contract winds down, this amount will be credited. Robert Vaughn motioned for approval of change order IF-006, totaling $227,740, in the form of a credit from the infrastructure portion of the contract. John Cogbill seconded, and all members present voted in the affirmative. Jake Elder informed the Authority of the groundbreaking for the Hilton at Springline on December 10, 2025, at 4 pm. Garrett Hart reported that Shamin has closed on the land at Springline, and ownership of the property has transferred. As part of the transaction, Parcels 3, 3A, and 3D were exchanged for two parcels in Stonebridge. In total, the county traded 1.9 acres for 4 acres in Stonebridge. Shamin Hotel now owns all the property required for the development of both hotels in Springline. Meadowville Technology Park Update: Tim Davey reported that this month's update is similar to last month's, with the primary focus on infrastructure and road improvements in Meadowville Technology Park. Two major road projects are underway. The first is the road wrapping around the LEGO site toward Henricus, which has been under construction for several months. Much of the earthwork and drainage installation reported last month is complete, and the current effort is focused on bringing the roadway up to grade. The second project is the road widening effort associated with the LEGO development. This work is in its early stages and is expected to increase in activity in the coming months. Construction continues within the data center campus, and the nearby apartment projects around the traffic circles are actively underway. Upper Magnolia Green Update: Tim Davey presented an overview of the three major components of the project, noting that they are generally divided into engineering work and two construction initiatives. The engineering phase, funded through a $25 million VEDP grant, is nearing completion, with most work expected to conclude in the summer of 2026. The first construction project funded by this engineering effort is a $13 million grant to realign the roadway around the water line and create a marketing pad within the Upper Magnolia Green area. Economic Development Authority of Chesterfield County Minutes November 20, 2025 P a g e 3 | 4 The Authority has already awarded the associated construction contract, and the contractor is now mobilizing and beginning work. The second construction-related funding is a $10 million grant awarded for Phase 1 of the WACC, which will construct the initial portion of the road extending from Hull Street to serve the Upper Magnolia Green site. Tim reported that clearing activities funded by this grant are expected to begin during the first quarter. The project team is also pursuing additional funding to expand this initial phase and extend the proposed entrance road further. Tim reviewed the VDOT Woolridge Road expansion project, clarifying that while smaller in scope than some of the county's other projects, it remains significant at approximately $47 million and covers roughly 1.5 miles to Old Hundred Road. The purpose of the project is to relieve congestion and improve access to Route 288. The Authority discussed the planned 10-acre pad site that will allow VEDP to bring prospects on- site to visualize development opportunities at Upper Magnolia Green. The goal is to tour the pad site around this time next year. Other Updates: None Closed Session: Robert Vaughn move that the Authority meeting be closed (1) Pursuant to Section 2.2-3711(A)(3) Code of Virginia, for discussion or consideration of the acquisition of real property for a public purpose, or of the disposition of publicly held real property, where discussion in an open meeting would adversely affect the bargaining position or negotiating strategy of the public body, (2) Pursuant to Section 2.2-3711(A)(5) for discussion concerning a prospective business or industry or the expansion of an existing business or industry where no previous announcement has been made of the business' or industry's interest in locating or expanding its facilities in the county. John Hughes and all members present voted in the affirmative. EXIT: Robert Vaughn moved that the Authority leave the closed session held (1) Pursuant to Section 2.2- 3711(A)(3) for discussion or consideration of the acquisition of real property for a public purpose, or of the disposition of publicly held real property, where discussion in an open meeting would adversely affect the bargaining position or negotiating strategy of the public body, (2) Pursuant to Section 2.2-3711(A)(5) for discussion concerning a prospective business or industry or the expansion of an existing business or industry where no previous announcement has been made of the business' or industry's interest in locating or expanding its facilities in the community. Terri Cofer Beirne called for a vote certifying that to the best of each member's knowledge, (i) only public business matters lawfully exempted from open meeting requirements under Va. Code § 2.2- 3711 (A)(3) and (A)(5) and (ii) only such public business matters as were identified in the motion by which the closed meeting was convened were heard, discussed, or considered. All members present voted in the affirmative. Economic Development Authority of Chesterfield County Minutes November 20, 2025 P a g e 4 | 4 Director Attendance (Present/Absent) Vote (Aye/Nay/Abstain) Terri Cofer Beirne Present Aye Robert Vaughn Present Aye John Cogbill Present Aye Danielle Fitz Hugh Absent Faizan Habib Present Aye John Hughes Present Aye Jesse Calloway Present Aye John Cogbill motioned to authorize the Chair and Vice Chair, or either of them, to execute all such agreements, in form and substance acceptable to legal counsel, relating to Project Parsons. Robert Vaughn seconded, and all members present voted in the affirmative. There being no further business, Robert Vaughn motioned to conclude the meeting at 3:59 pm. Jesse Calloway seconded, and all members present voted in the affirmative. Respectfully submitted, Samantha Furnish Recording Secretary Next Meeting: December 18, 2025, at 3 pm

Source: Chesterfield County website. First collected Oct 17, 2026.