Finance Committee Meeting, April 19, 2018 Minutes 1
COMMITTEE MEMBERS PRESENT:
Paul Trampe, Board Member
Larry K. Pritchett, Treasurer
Debbie Williams, Commissioner of Revenue
Mark Cole, Deputy County Administrator
Mary Sorrell, Finance Director
OTHER STAFF MEMBERS PRESENT:
Annette D’Alessandro, Grants Manager
Jay Cullinan, FREMS Chief
Gail Crooks, Director Social Services
Bonnie Jewell, Budget Manager
Troy Tignor, Zoning Administrator
Ben Loveday, Deputy Director Utilities/Public Works
First Sergeant Greg Carter, Sheriff’s Office
Deputy Kate Matikonis, Sheriff’s Office
Deputy Kristel DiGravio, Sheriff’s Office
Karen Bailey, Records Manager Sheriff’s Office
Tracy Edwards, Program Assistant Sheriff’s Office
Budget Amendment & Appropriation to Reflect Increase in State/Federal Funding of
for Child Welfare Line Items Gail Crooks, Director Social Services, explained that
Social Services submitted a request in Mid -December to the Virginia Department of
Social Services (VDSS) for increases to several child welfare line items to reflect the
increased rate of expenditure as compared to the initial allocations approved by
VDSS for Spotsylvania County in FY 2018. The rates of expenditure are driven by
number of children in foster care, the number of children adopted for which subsidies
are provided (for children hard to place or with existing special needs), and the
number and intensity of the therapeutic supports that are being required in many of
the adoptive placements.
The state approved additional funding of $1,191,292 for Foster Care ($541,317),
Special Needs Adoptions ($25,700) and Adoption Subsidies ($624,275). She explained
that in order to accept this additional funding a FY 2018 budget amendment and
appropriation are necessary to reflect the increased state and federal funding.
On a motion by Mr. Pritchett, seconded by Dr. Trampe and passed unanimously, the
Finance Committee recommended approval of the proposed FY 2018 Budget
amendment and appropriation.
Grant Application Request for the 2018-19 School Resource Officer (SRO) and School
Security Officer Incentive Grant Program
First Sergeant, Greg Carter, explained that the Sheriff’s Office was requesting
approval to submit a grant application request for four additional SRO’s for four
County schools that do not currently have a dedicated SRO. The identification of
Finance Committee Meeting, April 19, 2018 Minutes 2
the selected schools most in need of a SRO was made in consultation with the School
Superintendent, the Director of School Safety, and the Sp otsylvania County Sheriff’s
Office.
The grant is offered by the Department of Criminal Justice Services (DCJS) through the
School Resource Officer and School Security Officer Incentive Grant Program to
establish new School Resource Officer (SRO) positions in local law enforcement
agencies and new School Security Officer (SSO) positions in local school divisions. The
grant program is focused on funding SRO/SSO positions where none currently exist
within a high, middle, or elementary school.
The grant does require a minimum local cash match as identified in the 2018 -2020
Composite Index of Local Ability -to-Pay. Spotsylvania County’s rate is 36.27%. Grant
funds can only be used to pay for salary and benefits for SRO/SSO positions. The total
amount requested for a new SRO position may not exceed $50,000 per SRO position
including the required local cash match. Any costs associated with the
implementation of the SRO/SSO program above the grant award must be borne by
the County, Sheriff’s Office, and/or the Schools. The recently adopted FY 2019
Budget included a portion of the local funding necessary, should the County get
approval for these four grant funded SRO’s and the Sheriff’s office is prepared to use
funding from their asset forfeiture or surplus funds to fund the balance of the local
funding necessary.
If approved, the Sheriff’s Office would request $127,460 in grant funds for the first year.
The required local funding needed for the remaining personnel costs would be
$134,023; however, it is estimated that an additional $57,234 of local funding will be
needed to cover the additional costs associated with mandatory DCJS SRO training,
and operating costs for the requested positions. Additionally, the Sheriff’s Office
requires one new vehicle for every three new SROs at an estimated cost of $35,000 ,
with the remaining SROs utilizing surplus vehicles.
Approved S RO positions must be assigned to one secondary or elementary school
and cannot rotate to other schools. Grants will be awarded o n a competitive basis
for one year beginning July 1, 2018 and ending June 30, 2019. Successful SRO/SSO
programs can request annual continuation funding in ensuing years for a maximum of
four years of grant funding. Approval of one grant does not guarante e funding
awards in subsequent years. Positions approved for continuation funding will be
based on the Composite Index of Local Ability-to-Pay. Grant funds cannot be used to
supplant local funds.
On a motion by Mr. Cole, seconded by Mr. Pritchett passed unanimously, the Finance
Committee recommended approval of the proposed grant application for four
School Resource Officers.
Finance Committee Meeting, April 19, 2018 Minutes 3
Budget Amendment & Appropriation for Sheriff’s Office Local Services Overtime
Bonnie Jewell, Budget Manager, explained that t he Sheriff’s Office provides traffic
control and other related services to local entities and is reimbursed for such services
which are generally provided through overtime hours. FY 2018 Overtime costs are
expected to be $75,000 greater than currently bud geted and those costs are
expected to be fully covered with increased reimbursement revenue for these local
services. As such, staff requests that the overtime budget be increased by $75,000
along with a corresponding increase in the reimbursement revenue line item for local
services provided.
On a motion by Ms. Williams, seconded by Mr. Pritchett and passed unanimously, the
Finance Committee recommended approval of the proposed budget amendment
and appropriation.
Byrne/JAG Law Enforcement Grant acceptance
Tracy Edwards, Sheriff’s Office, explained that the Sheriff’s Office had received
notification of a grant award in the amount of $46,226 from the Department of
Criminal Justice Services (DCJS). The Sheriff’s Office will utilize these funds to create a
Wellness and Maintenance Response team, which not only incorporates the peer
support component, but also includes multi -faceted support by providing information
on emotional, spiritual, physical, financial and family wellness resources.
Deputies Matikonis and DiGravio explained their previous experience with this type of
team in other localities and noted that the Sheriff’s Office is currently lacking a
Wellness and Maintenance Response Team (W&MRT) for their employees. Having
such a team would provi de useful in- house and outsourced services to agency staff
and their families.
They explained the unique culture within law enforcement wherein officers are more
willing and likely to discuss sensitive and personal topics with other officers, rather than
with individuals from outside groups. If a wellness team option is not available, the
officer could potentially internalize this stress and consequently suffer physical and
mental health issues. Studies show that this leads to multiple problems in and out of
the work environment to include high divorce rates, alcoholism and suicides.
This grant award will allow the Sheriff’s Office to utilize the curriculum from the
International Critical Incident Stress Foundation, Inc. (ICISF) to establish a certified
W&MRT. The W&MRT will consist of 13 members who will assist law enforcement staff
and their families to more effectively address crisis situations as well as the unique
stresses that impact the law enforcement profession. Three of the 13 members will be
sent to ICISF regional instructor trainings in support of becoming instructor certified.
One of the training s will be held in Chicago in July and the other is in Houston in
August. Upon completion of these regional trainings, the 3 staff members will take the
ICISF Instructor Certification exam and provide evidence of passing. The 3 instructors
will then be resp onsible for conducting in- house training for the remaining 10 W&MRT
Finance Committee Meeting, April 19, 2018 Minutes 4
members as well as all future members. Ultimately, the team of 13 will be recognized
as an official ICISF Critical Incident Stress Management Team.
Ms. Sorrell asked about the portion of grant funding awarded for Honor Guard
uniforms. They explained that the current Honor Guard is not at a level to meet the
needs of the Department and that $23,030 of the grant award will be used to
purchase 12 additional uniforms so that the Honor Guard can increase from 9 to 21
members.
On a motion by Dr. Trampe, seconded by Mr. Pritchett and passed unanimously, the
Finance Committee recommended approval of the acceptance of the grant award
and the associated budget amendment and appropriation.
Budget Amendment & Appropriation for Fire-Rescue Local Services Overtime
Bonnie Jewell, Budget Manager , explained that Fire/Rescue provides staffing for
various local events such as football games and the twice- a-year triathlon and is
reimbursed for such services which are generally provided through overtime hours.
The budget for overtime costs needs to be adjusted to match the amount of
reimbursement revenue expected for FY 2018 – an increase of $9,400. As such, staff
requests that the overtime budget b e increased by $9,400 along with a
corresponding increase in the reimbursement revenue line item for local services
provided.
On a motion by M r. Pritchett, seconded by Ms. Williams and passed unanimously, the
Finance Committee recommended approval of the proposed budget amendment
and appropriation.
Budget Amendment & Appropriation for Stormwater Management Compliance
Troy Tignor, Zoning Administrator explained that an increase in construction activity
and rainfall is driving an increase in the number o f stormwater management
inspections of construction sites. State Code requires us to inspect all open land
disturbing permits every two weeks during active construction periods and within 48
hours of each runoff -producing-event. We ensure compliance with these mandated
environmental inspection requirements through the use of third party engineering
personnel that are procured on a four -year contract. Fees paid by the landowners
are used to pay for the third party engineering services.
He explained tha t $90,000 in additional budget for engineering services is expected
to be needed to carry us through to the end of June 2018. These additional costs will
be paid for through an increase in revenue collections associated with the increased
volume of inspec tions. Staff is requesting approval of a budget amendment and
appropriation to reflect the increase in Zo ning’s consulting services expense budget
and the offsetting increase in revenues. There is no fee/rate increase being proposed
at this time to accom pany this budget adjustment. The revenue adjustment is simply
a revenue increase due to increased volume of inspections.
Finance Committee Meeting, April 19, 2018 Minutes 5
On a motion by Mr. Cole, seconded by Dr. Trampe and passed unanimously, the
Finance Committee recommended approval of the proposed bud get amendment
and appropriation.
Capital Projects Budget Adjustments
Bonnie Jewell, Budget Manager explained that staff is requesting approval of transfers
and appropriations for the following Capital Projects:
General Capital Projects
Adjustments to general capital projects are requested as follows:
• A transfer of completed project balances totaling $26,264 to the Capital Projects
Fund balance is necessary to close these projects:
o $17,726 from the FY 2017 Replacement Computers & Servers project;
o $145 from the FY 2017 Animal Control Replacement Vehicles project;
o $6,942 from the FY 2017 Fire/Rescue Replacement Vehicles project;
o $429 from the FY 2018 Parks & Rec Replacement Vehicles project;
o $268 from the FY 2018 County Admin Replacement Vehicle project; and
o $754 from the FY 2017 Refuse Disposal Equipment Replacement project.
• A transfer of $4,240 from the FY 2017 Fire/Rescue Replacement Vehicles project to
the FY 2018 Fire/Rescue Replacement Vehicles project to cover a shortfall on the
FY 2018 project.
• A transfer of $61,251 from the Patriot Park Field Lighting project to the Capital
Projects Fund balance is necessary to close the project. Additionally, staff requests
a corresponding shift of the $61,251 from the Capital Projects Fund balance to the
Marshall Park Replacement Lighting project to cover anticipated additional co sts
on that project.
Utilities Capital Projects
Adjustments to Utilities capital projects are requested as follows:
• A transfer of $21,000 from the Fawn Lake Pump Station 53 project to the Utilities
Capital Projects Fund balance is necessary to close the project.
• A transfer of $66,683 from the Utilities Lab/Office Expansion project to the Lick Run
Sewer line Extension project to fund the final change order on the latter project.
• A transfer of $90,000 from the Ni River Water Treatment Plant project to the Motts
Run Plant Expansion project to fund the undergrounding of electric utilities from the
Rt. 3 substation to the Motts facility. Due to age and tree cover, the overhead line
has caused three multi- day power outages and Dominion has recommended the
utilities be underground.
Finance Committee Meeting, April 19, 2018 Minutes 6
Additionally, Utilities staff has identified the need for two new projects, the funding for
which is to be transferred from existing projects as noted below:
• $1.5 million is requested for transfer from the existing Thornburg Distribution
Improvements project to a new Replace Mall Sewer Line project. The sanitary
sewer along Towne Center Blvd by the mall is in critical condition and should be
replaced immediately to avoid complete failure or collapse of the line and the
roadway above. Due to the depth, material, and condition of the existing sewer
line, the likelihood of complete structural failure or collapse is increased. In the
event of a sewer line failure, a substantial number of residences and businesses
along Rt. 3 would be affected as this line is a main sewer interceptor for the region.
• A total of $111,000 is transferred from various sources to fund a new Pump Station
52 Rehab project which will fund the design and installation of an emergency
backup pump to be installed at Pump Station 52. The pump station overflowed
and caused multiple backups in Fawn Lake in February 2018. Rehab is imperative.
Funding is requested for transfer to this new project from these sources:
o $50,000 from the Pump Station 36 Rehab project;
o $40,000 from the Piedmont Drive – Pump Station 16 & 43 Abandonment
project; and
o $21,000 from the Utilities Capital Projects Fund balance.
Mr. Pritchett asked if the Utility projects from which funding was being transferred
would ultimately need additional funding in a future year to replace the funding that
had been transferred out and if so, would we need to borrow that funding. Ms.
Jewell explained that the County has not borrowed funding for Utility projects since
2010 and that they did not anticipate the need to borrow funding for Utility projects
this year. Mr. Loveday said he did expect that this funding would need to be
replaced in a future year. Ms. Jewell explained that as part of the annual CIP process
staff reviews each active project to determine if available funding is still necessary.
Staff would initially make adjusts within current funding available for approved
projects based on the anticipated timing of expenditures, before any new debt
would be issued.
On a motion by Ms. Williams, seconded by Mr. Cole and passed unanimously, the
Finance Committee recommended approval of the proposed budget amendment
and appropriation.
Budget Adjustment and Appropriation for Two Months of Mall Satellite Library
Operations and Capital Costs in FY 2018
Ms. Jewell and Ms. Sorrell explained that the FY 2019 Adopted Budget includes
funding for operating and capital start -up costs for a satellite library location at the
Spotsylvania Towne Center. Library staff reports that it would be possible to
commence operations at the Towne Cent er as early as May 2018, but would need
Finance Committee Meeting, April 19, 2018 Minutes 7
two months of operations funding and full funding for capital start -up costs in FY 2018
to do so.
As such, County staff recommends use of $31,737 from the budgeted contingency to
fund two months of operations expenses for this satellite library branch in FY 2018; use
of $18,450 from the General Fund balance to fund full capital start-up costs in FY 2018;
and a reduction in the FY 2019 Budget to account for the $18,450 in capital start -up
costs happening in FY 2018 instead of in FY 2019.
On a motion by M r. Pritchett, seconded by M s. Williams and passed unanimously, the
Finance Committee recommended approval of the proposed budget amendment
and appropriation.
Other Business:
Adjournment:
Ms. Sorrell adjourned the meeting.
Source: Spotsylvania County website. First collected Oct 18, 2026.