TRANSPORTATION CAPITAL FUND Department of Environmental Services Our Mission: To provide critical transportation infrastructure to enhance the community’s long-term economic and environmental sustainability. Transportation Capital Fund The Transportation Capital Fund (TCF) is comprised of two sources described below: the Commercial and Industrial (C&I) Tax and Northern Virginia Transportation Authority (NVTA) 30 percent Local.  Commercial & Industrial Tax is a source of funding authorized by the General Assembly in 2007 enabling the County to levy an additional real estate tax on industrial and commercial properties for transportation initiatives. In April 2008, the County Board proposed a tax of $0.125 per $100 of assessed value for transportation projects. Proceeds of the tax are held in a separate fund and must be used in accordance with the provisions in the state code.  NVTA 30 percent Local Funds is comprised of a 0.7 percentage point increase in the local sales tax approved in 2013 by the General Assembly as part of HB 2313 and the Grantor’s Tax (regional congestion relief fee), which was reinstated by the General Assembly in 2020 as part of HB 1414/SB 890. The NVTA receives the proceeds of this tax and retains 70 percent for funding of projects that are regional in nature. The remaining 30 percent of this tax is deposited in the Transportation Capital Fund along with the Commercial & Industrial tax. The Transportation Capital Fund allows the County to make major ongoing investments in multimodal transportation infrastructure and transit service . Together, these funds support improvements to neighborhood streets, as well as ongoing development of Arlington’s commercial and mixed- use districts such as the Rosslyn-Ballston Corridor, Crystal City, Pentagon City, Columbia Pike, Langston Boulevard, and Shirlington. These commercial mixed -use districts make up over 45 percent of th e County’s tax base, and include most of the County’s office, hotel, retail, and multi -family housing stock. TCF also provides the opportunity to leverage outside sources of funding from federal, state, and regional transportation programs as well as private sector partners. SIGNIFICANT BUDGET CHANGES The FY 2027 adopted budget for the Transportation Capital Fund (TCF) is $32,430,482, based on projected current year revenues. The complete spend down plan reflects utilization of current year revenues and fund balance as capital projects are rarely completed in a single year and require carryover of funds to be fully executed. The complete FY 2027 implementation plan compared to the revised FY 2026 plan is shown in the fund statement. The FY 2027 budget reflects: Commercial real estate tax revenue decreases based on assessment projections ($3,207,223). Northern Virginia Transportation Authority (NVTA) revenues increase based on FY 2027 projections ($614,582). 469 TRANSPORTATION CAPITAL FUND FUND SUMMARY PROGRAM FINANCIAL SUMMARY FY 2025 FY 2026 FY 2027 % Change Actual Adopted Adopted '26 t o '27 Capital Projects $116,557,671 $35,023,123 $32,430,482 -7% 116,557,671 35,023,123 32,430,482 -7% Revenues 70,138,967 35,023,123 32,430,482 -7% GASB - - - 70,138,967 $35,023,123 $32,430,482 -7% ($46,418,704) - - 42.50 43.50 43.50 Total Expenditures Total Revenues Change in Fund Balance Total Authorized FTEs 1) A total of 50.0 FTEs support the transportation capital program. 43.5 FTEs are funded by the Transportation Capital Fund and 6.5 FTEs are funded by the Crystal City Tax Increment Fund (TIF). 2) This table reflects the FY 2027 spending plan of current year revenues and does not show the use of fund balance for the total projected FY 2027 expenditures. See the Fund Statement for the execution plan. FY 2027 MAJOR PROJECTS Complete Streets  Improvements Outside Major Corridors: o South Walter Reed Drive Complete Streets Improvements, 5th Street South to Columbia Pike: Project will improve safety and accessibility for all modes on a corridor included in Arlington’s Vision Zero High Injury Network (HIN). The work will provide enhanced bik e facilities, sidewalks, curb extensions, crosswalks, and bus stop improvements. The project will create a safer, more accessible corridor and a new signalized intersection at 9th Street S. This effort is being coordinated with the adjacent Arlington Public School (APS) Career Center project. Construction began in FY 2026, focusing first on the new signal at 9 th Street S. to coordinate its installation with the APS opening in FY 2027. Construction is expected to be completed in FY 2028. o Military Road Safety Improvements - Military Road at Nelly Custis Drive: Project will enhance multimodal accessibility and safety at a complex intersection with documented speeding problems near two schools. Planned improvements include a roundabout to continuously control speeds; stormwater and waterline upgrades; utility undergrounding; bioretention; streetlights at crosswalks ; new curbs, curb ramps, sidewalks, curb extensions, high -visibility crosswalks, signage , and street trees. Construction is underway and anticipated to be completed in FY 2028. o South Carlin Springs Road Pedestrian Improvements: Project will expand the sidewalks to 6 -foot width with a 2 -foot buffer along both sides of S. Carlin Springs ( SCSR) between 3rd St S. and 6th Rd S. Easement acquisition continues to be an essential element of project execution. Construction began in FY 2026 on Phase 1 (intersection of SCSR at S . 5 th Street and e ast side between 5th Road S. and S . 5th Street). Construction is expected to begin on Phase 2A (remaining east side improvements) in late FY 2026, and construction on Phase 2B (west side improvements) is anticipated to start in FY 2027. 470 TRANSPORTATION CAPITAL FUND FUND SUMMARY o North Sycamore Street – Langston Boulevard to 19th Street North: Project will enhance pedestrian and bike facilities, crossings, and streetscape to improve safety and accessibility for all modes, and to implement improvements identified in the East Falls Church Area Plan. Design is being coordinated with the adjacent bus bay expansion project at the East Falls Church Metrorail Station. Design is nearing completion and construction is expected to begin in FY 2027. o South George Mason Drive , Arlington Boulevard to Columbia Pike: Project will implement the first segment of improvements recommended in the S outh George Mason Drive Multimodal Transportation Study (completed in 2023) to improve multimodal safety and access along S George Mason Drive . Planned improvements include a separated multi-use trail to improve bike and pedestrian connections, a new signal at 6th Street S., and intersection improvements at 8 th Street S. Design phase began in FY 2026. o South Four Mile Run Drive: The project will implement improvements identified in the Proposed Four Mile Run Valley Area Plan, the Nauck Village Center Action Plan, and recommendations from Vision Zero’s safety audit of S. Four Mile Run Drive. Multimodal and safety improvements will be provided on this corridor in three phases, focusing primarily on installing new sidewalks, crosswalks, and curb extensions. The first phase was completed in FY 2026 and provided improvements to S. Four Mile Run Drive from Shirlington Road to Nelson Street. Phase 2 will improve S. Nelson Street to S. Walter Reed Drive, and Phase 3 will address S. Walter Reed Drive to the Barcroft Community Center. Following extensive public engagement, design work is underway for Phases 2 and 3, and construction is anticipated to begin FY 2029. o Pershing Drive Complete Street: The project will implement multimodal improvements at intersections on North Pershing Drive east of Washington Boulevard to North Barton Street. The project will improve pedestrian crossings, enhance the protected bike lanes, and install street tree plantings where feasible. Construction is anticipated to begin in FY 2027 and be completed in FY 2028.  Rosslyn-Ballston Corridor Improvements: multimodal street improvements throughout the corridor that meet the planning goals outlined in the Master Transportation Plan (MTP) and area sector plans. These projects will provide significant street and sidewalk safety and functionality improvements. Projects include: o Wilson Boulevard Streetscape Improvements – Wilson Boulevard from North Kenmore Street to 10th Street North, and 10th Street North from North Jackson Street to North Ivy Street: The p roject implements the final phase of streetscape improvements recommended in the Virginia Square Sector Plan, which will improve pedestrian safety and accessibility in a heavily used commercial corridor that is on Arlington’s High Injury Network. Planned i mprovements include travel lane adjustments, new curb and sidewalks, stor mwater upgrades, new crosswalks, signal upgrades, streetlights, signage, street trees and paving, and will bury the last remaining overhead utility lines on Wilson Boulevard between Clarendon and Ballston. Design is complete and construction is anticipated to begin in FY 2027. o Fort Myer Drive Sidewalk and Intersection Improvements: This project will improve safety at a Vision Zero -identified hot spot intersection and will enhance bike and pedestrian facilities between eastbound and westbound Langston Boulevard to enhance bike and pedestrian safety and connectivity from the Custis Tra il into Rosslyn. The project will reconfigure the intersection of Fort Myer Drive and eastbound Langston Boulevard installing ADA compliant curb ramps, curb extensions, utility adjustments, new crosswalks, and new signal equipment. The work is being coordinated with the DPR-led master plan and renovation of Gateway Park. Construction is expected to begin in FY 2026 and is anticipated to be completed in FY 2027. 471 TRANSPORTATION CAPITAL FUND FUND SUMMARY o North Rhodes Street & Wilson Boulevard Intersection Improvements: Project will deliver multimodal safety improvements to the Wilson Boulevard & N. Rhodes Street intersection, which is located on a major commercial corridor that is included in the Vision Zero High Injury Network. Work includes signal upgrades, utility work, bus stop improvements, and new crosswalks, as well as curb ramps and sidewalks to improve safety and accessibility for people walking, biking, taking transit , and driving. Design work be gan in FY 2023 and is being coordinated with adjacent development . Construction is expected to begin in FY 2027.  Columbia Pike Multimodal Street Improvements: Multimodal improvements along the entire corridor have increased pedestrian safety and access with consistent and wider sidewalks; provided improved bicycle facilities mostly on adjacent bicycle boulevards; improve d traffic flow through the introduction of turn lanes and a consistent cross section; and increase d pedestrian safety at intersections. These investments also greatly improve access to local and regional bus transit service along the corridor. This is particularly important given that Columbia Pike is the highest ridership bus corridor in Arlington and one of the highest in the Commonwealth. o Construction on the last segments of the multimodal streetscape project on Columbia Pike reached substantial completion in late 2025/mid FY 2026 , implementing improvements from S. Orme Street to S . Nash Street, S. Oakland Street to S. Wakefield Street, S. Courthouse Road to S. Garfield Street, and S. Quinn Street to S. Courthouse Road . C onstruction closeout and landscape establishment costs are expected to be completed in FY 2028. o S. Glebe Road and 9 th Street S . Intersection Improvements: This project will implement safety improvements for all modes and includes upgrading curb ramps, crossings, sidewalks and adding signal support at an intersection where the Columbia Pike 9 th Street bike boulevard crosses S. Glebe Road. Design is anticipated to be completed in FY 2026, and construction is anticipated to start in FY 2027.  Crystal City, Pentagon City, Potomac Yard Street Improvements: Multimodal Street improvements throughout the area that will improve connectivity, access, and enhance private redevelopment opportunities. o Crystal City to Ronald Reagan Washington National Airport (DCA) Multimodal Connection: This project will create a context-sensitive multimodal connection between Crystal City and National Airport designed to meet the needs of a broad range of pedestrians, bicyclists, and micro -mobility users of all ages and abilities. National Environment Policy Act (NEPA) approvals were secured, and preliminary engineering work is underway with major design elements to be determined in FY 2027. o Clark Bell Extension to 15 th Street will connect South Clark Street to South Bell Street at 15th Street South to form a standard 4- way intersection and complete the street grid in the northern area of Crystal City. The project will also create space for the 15th Street South Garden Park, to be located to the north of 15th St South. Construction is underway and expected to be completed in FY 2027.  Neighborhood Complete Streets (NCS): The NCS program enables County staff to implement projects on non-arterial streets that focus on safety and accessibility. The program gathers nominated locations from the community and prioritizes them based on where a critical need has been identified and justified through objective criteria, established by the Neighborhood Complete Streets Commission (NCSC). The goal of the NCS program is to develop streets that are safe and accessible for all modes through projects t hat improve walking/bicycling connectivity; upgrade street crossings, particularly within school walking zones; and modify incomplete streets with the aim of providing safer facilities and changing motorist behavior to manage vehicular speeds and minimize conflicts with vulnerable road users. Every year, the NCSC nominates projects to advance to the Arlington County Board for funding approval. Six 472 TRANSPORTATION CAPITAL FUND FUND SUMMARY projects are currently in design. Construction is anticipated to start on three projects in FY 2026, one project in FY 2027, and two projects in FY 2028.  Update of the Master Transportation Plan: The Master Transportation Plan is an element of the County’s Comprehensive Plan, which is referenced along with other County Proposed plans to develop the CIP. Arlington’s Transportation Future began in FY 2026. This is the name of the process to refresh the County’s aging Master Transportation Plan and bring it current with industry standards and with the community’s values. County Staff are working with consultants to conduct a thorough, inclusive process to update the County’s guiding document for transportation infrastructure. This effort features an extensive public engagement process. The process will continue through FY 2027.  Transportation Systems and Traffic Signals: This program includes the upgrade and reconstruction of existing aged traffic signals and allows for the implementation of transportation operations and management systems components such as school zone beacons and pedestrian-activated beacons. Typically, the County rebuilds around eight signals per year with varying degrees of intersection -related improvements such as ADA-accessible curb ramps.  Intelligent Transportation System (ITS): This program enables the County to expand ITS system capabilities and conduct critical system upgrades. These projects include upgrading the County’s traffic signal system to allow for integration of existing components such as video detection, uninterrupted power supply (UPS), and Polara pedestrian push buttons into the central Traffic Management Center (TMC). In FY 2027, this program will continue to work towards designing and installing new ITS strategies such as data sharing and collection, transit signal priority, and communications enhancements. Additionally, in FY 2027, design will commence on a consolidation and update of the County’s travel time system and Dynamic Message Boards (DMS).  Strategic Network Analysis and Planning: This program supports multimodal traffic data collection and analysis services used for traffic engineering and operations projects including: o Traffic volume/speed/classification data collection at intersections and along corridors for all modes of transportation (vehicle, heavy truck, pedestrian, bike) to inform various transportation analyses. o Crash data organization and record upkeep, which allows for transportation safety analyses throughout the County and subsequent implementation of safety measures in identified problem areas. This supports the Vision Zero safety initiative. o Travel demand model data program to collect/purchase data useful in understanding travel patterns and travel behavior. This data will be used in modeling the impacts of potential infrastructure improvement projects or policy changes on the transportation system.  Street Safety Improvements (SSI): This program supports the Vision Zero Action Plan the County Board adopted in spring 2021 to achieve the goal of eliminating fatal and severe injury crashes. This is a five-year plan that is currently being updated, and a new five-year plan is expected to be finalized in June 2026. The program supports projects at intersections and streets where safety improvements are needed for pedestrians, bicyclists, transit riders, or motorists as determined through a comprehensive inv estigation, including crash analysis. It focuses on safety improvements that can be deployed or implemented in a relatively short amount of time with lower capital cost, such as installing Pedestrian Flashing Beacons at certain crosswalks. The program also collects before and after data to establish effectiveness, and in turn allow the development of an up- to-date Transportation Safety Toolbox. The program is funded with a combination of PAYG, TCF, and general obligation bonds, depending on the nature of the work undertaken and location. 473 TRANSPORTATION CAPITAL FUND FUND SUMMARY Transit  Crystal City Metrorail Station East Entrance: This project will design and build a new entrance to the east end of the Crystal City Metro station to provide better access from Crystal Drive, the existing and future Crystal City VRE station, and the Transitway. The Cou nty executed a comprehensive design -build agreement with Clark Construction in 2023. Construction is underway and the project is expected to be completed in FY 2027.  East Falls Church Bus Bay Expansion: The East Falls Church Metrorail Station currently has four bus bays that are at maximum capacity. The project will increase bus bay capacity by adding three new bus bays and replacing the existing shelters in the off-street bus loop. The project also includes pedestrian access improvements to and from the station’s park-and-ride lot, improvements to accessible parking, and improvements to the crosswalks at the entrance to the existing bus loop on N. Sycamore Street. Construction is underway and the project is expected to be completed in FY 2027.  ART Fare Collection System: This program will replace existing fareboxes on ART buses to be compatible with WMATA’s Next Generation fareboxes which will allow for the use of a contactless credit or debit card (physical card or mobile wallet ) on ART. Work is currently ongoing to obtain updated pricing from WMATA. The new fareboxes are expected to be installed and operational on all ART buses by the end of FY 2027.  Transit ITS: The Transit ITS and Security Program uses technology to improve transit reliability and operations, provide better rider information, and address safety and security needs. Key projects include upgrading and consolidating bus dispatch and vehicle tracking systems, real time transit information infrastructure at bus stops, improving bus travel times through Transit Signal Priority (TSP) on busy corridors, and planning timely replacement of aging back-end technology to maintain reliable service. Operations and Program Administration • Consistent with previous years, TCF also funds various operational and administrative activities including: o ART operations such as new routes or added hours on existing routes. o Capital Bikeshare operations. o Staff charges for the authorized FTEs noted in the Program Financial Summary table above. 474 TRANSPORTATION CAPITAL FUND FUND SUMMARY FY 2025 FY 2026 FY 2026 FY 202 7 ACTUAL ADOPTED RE-ESTIMATE ADOPTED ADJUSTED BALANCE, JULY 1 Construction Reserve $131,390,948 $100,492,789 $85,072,246 $69,495,920 Reserve 3,600,000 3,500,000 3,500,000 3,300,000 TOTAL BALANCE 134,990,948 103,992,789 88,572,246 72,795,920 REVENUES Commercial Real Estate Revenues 22,781,556 23,0 06,191 21,161,143 19,798,968 Capital Bikeshare - User Revenue 847,970 799,000 1,100,000 1,122,000 Misc. Revenues 494,952 - - - Grant Revenues 33,775,037 37,379,000 52,132,800 51,770,400 NVTA Revenues - Local 12,239,452 12,016,932 12,016,932 12,631,514 TOTAL REVENUES 70,138,967 73,201,123 86,410,875 85,322,882 TOTAL REVENUE & BALANCE 205,129,915 177,193,912 174,983,121 158,118,802 EXPENSES Capital Projects - Current Year 111,714,189 73,201,123 80,202,928 85,322,882 Capital Projects - Carry-Over - 22,913,691 15,776,326 14,575,909 Transfers to the General Fund 4,843,482 6,294,586 6,207,946 6,238,809 TOTAL EXPENSE 116,557,671 102,409,400 102,187,200 106,137,600 BALANCE, JUNE 30 Construction Reserve 85,072,246 71,284,509 69,295,920 48,781,202 Reserve 3,500,000 3,500,000 3,500,000 3,200,000 TOTAL BALANCE $88,572,246 $74,784,509 $72,795,920 $51,981,202 TRANSPORTATION CAPITAL FUND FUND STATEMENT Notes: 1. Most capital projects span multiple years from design to construction completion, and actual project execution may differ from forecasted. Ending balances at the end of a given fiscal year are carried forward to the next year. 2. Transfers to the General Fund cover the operating costs of specific ART routes and ART facilities, such as the new ART Operations and Maintenance Facility completed in Fall 2024. 3. Balances equivalent to a minimum of ten percent of annual budgeted TCF revenues are held in a reserve in accordance with the County Board’s financial and debt policies. 4. Miscellaneous Revenues in FY 202 5 reflect a refund from VDOT on a project in Rosslyn completed a few years ago, as well as some interest and realized gains on fund balances. 5. The increase forecasted in Capital Bikeshare user fee revenue is related to the new fee structure adopted in fall 2026. 475 TRANSPORTATION CAPITAL FUND TEN-YEAR HISTORY EXPENDITURE, REVENUE, AND FULL-TIME EQUIVALENT TRENDS * Beginning in FY 2022, actual expenditures and revenues received reflect the first year of implementing new Governmental Accounting Standard Board (GASB) standards for Statement No. 87 on leases and Statement No. 96 for subscription-based software. See the County Government GASB Summary for department details in the front section of the budget book. $ in 000s FY 2018 Actual FY 2019 Actual FY 2020 Actual FY 2021 Actual FY 2022 Actual* FY 2023 Actual FY 2024 Actual FY 2025 Actual FY 2026 Adopted FY 2027 Adopted EXP $41,991 $52,936 $41,203 $38,756 $43,218 $93,993 $36,408 $116,557 $35,023 $32,430 REV $48,209 $49,783 $51,985 $42,633 $49,647 $81,947 $36,408 $70,139 $35,023 $32,430 FTEs 22.00 29.00 29.00 29.00 41.00 41.00 41.00 42.50 43.50 43.50 0 5 10 15 20 25 30 35 40 45 50 $0 $10,000 $20,000 $30,000 $40,000 $50,000 $60,000 $70,000 $80,000 $90,000 $100,000 $110,000 $120,000 $130,000 FTEs EXP REV 476 TRANSPORTATION CAPITAL FUND TEN-YEAR HISTORY Fiscal Year Description FTEs FY 2018  Revenues increased based on commercial real estate projections ($1,640,387), and Northern Virginia Transportation Authority (NVTA) revenue projections ($85,559).  Added 4.0 FTEs including a Neighborhood Complete Streets Traffic Engineer position ($133,000) in the Traffic Engineering & Operations Bureau, a Design Engineer position ($133,000) in the Engineering Bureau to support the Neighborhood Complete Streets program, a Management & Budget Specialist position ($113,050) to support the overall transportation capital program, and the transfer of an existing position in the Real Estate Bureau from the Crystal City, Potomac Yard, and Pentagon City Tax Increment Financing Area (TIF) fund. 4.00 FY 2019  Revenues decrease d based on a reduction in commercial real estate assessments ($1,246,745), and a reduction in Northern Virginia Transportation Authority (NVTA) revenues due to the 2018 General Assembly action to provide dedicated funding to Metro ($4,307,391).  Added two Engineering positions ($276,000) in the Traffic Engineering & Operations Bureau; The first FTE will support the Transportation Systems & Traffic Signals and Intelligent Transportation Systems CIP programs. The second FTE will support delivery of the Complete Streets CIP program. 2.00  Added one Community Relations Specialist position ($133,000) to support the overall transportation capital program. 1.00  Three positions were transferred from the DES General Fund. The positions include two Budget Analysts and a Transportation Capital Pro gram Manager ($427,000). A portion of the time for these positions had already been charged to capital projects and the Transportation Capital Fund (net impact $257,000). 3.00  Added a Grants Compliance Specialist position currently charged to the Transportation Capital Fund but previously authorized in the County Manager’s Office (1.0 FTE). 1.00  As part of the FY 2018 closeout appropriation, revenue and expenses were reduced based on Virginia General Assembly action to dedicate funds to WMATA ($4,455,768). FY 2020  Revenues increased based on commercial real estate assessment projections ($1,242,804) and Northern Virginia Transportation Authority (NVTA) revenue projections ($346,152). FY 2021  Revenues increase d based on commercial real estate assessment projections ($146,644).  Revenues decreased based on Northern Virginia Transportation Authority (NVTA) revenue projections ($68,362). 477 TRANSPORTATION CAPITAL FUND TEN-YEAR HISTORY Fiscal Year Description FTEs FY 2022  Five capital project coordinators (5.0 FTEs) were transferred in from the General Fund to Transportation Capital Fund ($295,015). 5.00  Revenues decreased based on commercial real estate assessment projections ($1,611,257), offset by increased revenue projections for the Northern Virginia Transportation Authority (NVTA) ($1,210,946).  As part of the Adopted CIP FY 2022 – 2024, an additional 7.0 FTEs were authorized to be funded from Transportation Capital Funds. 7.00 FY 2023  The County Board approved an additional one percent merit pay adjustment for a total increase of 5.25 percent, increased the pay-for-performance budget by an additional 0.5 percent, and increased the pay range movement to five percent. Additional compensation changes approved by the County Board include an optional one -time cash-out of 40 hours of compensation time for those with balances of 80 or more, a one-time increase in shift differential pay from $0.75 to $1.00 per hour for the B shift and from $1.0 0 to $1.30 per hour for the C shift, and a one-time increase in language premium from $0.69 to $0.92 per hour.  Revenues increase d based on commercial real estate assessment projections ($225,118).  Revenues increased based on Northern Virginia Transpor tation Authority (NVTA) revenue projections ($712,548).  The FY 2023 Adopted Budget included a total of 47.5 FTEs to support the transportation capital program. 41.0 FTEs are funded by Transportation Capital Fund and 6.5 FTEs are funded by the Crystal City Tax Increment Fund. FY 2024  Commercial (C&I) ($1,070,739) real estate and Northern Virginia Transportation Authority (NVTA) ($1,852,858) revenues increased based on FY 2024 projections.  Transfer in of a Project Management Coordinator (1.0 FTE) from DES General Fund to TCF and the elimination of a Senior Procurement Officer position (1.0 FTE). This results in no change to the TCF FTE count. FY 2025  Transfer in from the General Fund of a Project Management Coordinator and 50 percent of a Design Team Supervisor ($160,197). 1.50  Commercial real estate tax revenue decreased based on commercial real estate assessment projections ($1,342,285).  Northern Virginia Transportation Authority (NVTA) revenues increased based on FY 2025 projections ($113,085). FY 2026  Converted and condensed some contractor roles supporting the Capital Bikeshare program to a County FTE ($147,162, 1.0 FTE) to realize a net savings of $85,000 and ensure direct management of County interests in Capital Bikeshare. This recommendation was in cluded in the recently completed Arlington County Commuter Services Strategic Plan. 1.00 478 TRANSPORTATION CAPITAL FUND TEN-YEAR HISTORY Fiscal Year Description FTEs  Commercial real estate tax revenue decreased based on commercial real estate assessment projections ($1,379,637).  Northern Virginia Transportation Authority (NVTA) revenues increased based on FY 2026 projections ($257,096). FY 2027  Commercial real estate tax revenue decreased based on assessment projections ($3,207,223).  Northern Virginia Transportation Authority (NVTA) revenues increased based on FY 2027 projections ($614,582). 479

Source: Arlington County website. First collected Oct 18, 2026.