PAY-AS-YOU-GO
CAPITAL
AND
SHORT-TERM
FINANCING
547
This page intentionally left blank
548
PAY-AS-YOU-GO CAPITAL
GENERAL CAPITAL PROJECTS FUND
The FY 2027 Adopted Capital Program budget is $ 65.1 million. The program areas shown
below include all capital fund sources. The chart below details the dollar amount allocated by
program.
Local Parks
and
Recreation
Programs,
$2.8 , 4 %
Information
Technology,
$7.4 ,11%
Public Safety,
$8.0 , 12%
Public and
Government
Facilities,
$3.4 , 5%
Energy
Management,
$0.7 , 1%
Regional
Partnerships
and
Contingencies,
$1.0 , 2%
Water and Sewer
Infrastructure
Capital, $34.7 ,
54%
Arlington
Neighborhood
s Program,
$0.8 , 1%
Stormwater
Capital,
$3.6 , 6%
Transportation ,
$2.5 , 4%
FY 2027 CAPITAL BUDGET ALLOCATION BY
PROGRAM
($'S IN MILLIONS)
549
PAY-AS-YOU-GO
GENERAL CAPITAL PROJECTS FUND
The Adopted FY 2027 capital program budget is broken out by funding source below. The
capital program is funded by Pay-As-You-Go (PAYG) and Short-term Financing. Detail about
the fund sources and associated projects can be found in the following pages.
Pay-as-you-go,
$6.4 , 10%
Reallocated
Balance,
$1.4 , 2%
Utilities Pay-as-
you-go, $34.7 ,
53%
Stormwater Pay-
as-you-go,
$3.6 , 6%
Short-term
Financing,
$17.9 , 28%
Other,
$1.14, 2%
FY 2027 CAPITAL BUDGET FUNDING SOURCE
($'S IN MILLIONS)
550
PAY-AS-YOU-GO
GENERAL CAPITAL PROJECTS FUND
FY 2025
ACTUAL
FY 2026
ADOPTED
FY 2026
RE-ESTIMATE
FY 2027
ADOPTED
Adjusted Balance, July 1 $94,756,045 $89,043,965 $95,380,144 $88,871, 144
REVENUES:
Commonwealth of Virginia 984,205 - - -
Federal Government 133,243 - - -
Charges for Services 13,974,540 - - -
Miscellaneous Revenue 4,894,869 - - -
Line of credit proceeds 14,548,656 9,141,000 9,141,000 11,000,000
Proceeds for bond premium - - - -
Proceeds from sale of bonds - - - -
GASB 75,564 - - -
Total Revenues 34,611,077 9,141,000 9,141,000 11 ,000,000
Transfer in 23,378,000 18,260,000 18,260,000 6, 837,000
Transfer out (5,000,000) - - -
Use of prior year revenue* - 6,509,000 6,509,000 2,520,000
Total Revenues and Transfers 52,989,077 33,910,000 33,910,000 20 ,357,000
Expenditures:
Capital projects current year 51,813,943 18,330,000 1 8 ,330,000 17,837,000
Capital projects carry over - 15,580,000 15,580,000 14,534,614
GASB 551,035 - - -
Total Expenditures 52,364,978 33,910,000 33,910,000 32 ,371,614
Balance, June 30 $95,380,144 $82,534,965 $88,871,144 $74,336, 530
GENERAL CAPITAL PROJECTS FUND
FUND STATEMENT
* The amount under Use of Prior year revenue is already in the beginning fund balance .
551
This page intentionally left blank
552
PAY-AS-YOU-GO CAPITAL
GENERAL CAPITAL PROJECTS FUND
WHAT IS A CAPITAL PROJECT?
Capital projects include the design, construction, renovation, or maintenance of capital assets.
Capital assets are County -owned infrastructure that are of significant value, such as bridges,
community centers, technology systems, roof systems, elevators, sewer and stormwater
infrastructure, public safety equipment and parks, to name a few. County projects are funded from
a variety of sources, including tax-supported Pay-As-You-Go (PAYG) funds, financed dollars such as
general obligation ( GO) bonds and short- term financed funds and, various other grants, fees, and
dedicated funding sources.
TYPES OF CAPITAL PROJECTS
Capital projects fall into one of two major categories: maintenance capital (MC) projects and general
capital projects . The m aintenance capital program serves to prolong the useful life of major
investments, while minimizing the need for repeated corrective maintenance. Although MC funds
are not contingency funds, they provide versatility in allowing the County to respond to unforeseen
emergencies. The County regularly conducts condition assessments of capital assets to establish an
inventory of capital needs and associated prioritization plans. Maintenance capital activities differ
from operating maintenance activities described elsewhere in this document in that maintenance
capital activities are normally larger scale in terms of cost, size, nature, and f requency of
maintenance activity.
General capital projects, on the other hand, are all other capital projects and include new projects or
renovations and expansions of projects, such as when the County constructs a new community center
or rebuilds and reconfigures a street intersection. This distinction between maintenance and general
capital projects is helpful because the two types have different goals. Maintenance capital projects
protect the County’s past investments in capital assets and ensure that Arlington residents get the
maximum use out of those assets. General capital projects aim to meet emerging community needs
by creating new capital assets or modifying existing assets to such a degree that the work cannot be
considered maintenance capital.
Beyond this distinction between maintenance and general, the County further categorizes capital
projects into Program Areas which correspond to the teams of County staff that execute the projects.
The capital projects discussed in the following pages are organized into the following Program Areas:
Regional Partnerships
Transportation
Facilities
Parks and Recreation
Technology
Public Safety
Arlington Neighborhoods Program
Arlington Economic Development/ Public Art
Capital Administration/Contingent
553
PAY-AS-YOU-GO
GENERAL CAPITAL PROJECTS FUND
HOW THE COUNTY PAYS FOR CAPITAL PROJECTS
Capital budget development is included in both the annual operating budget process and the biennial
capital improvement plan (CIP). The annual budget process approves and allocates funding for
capital projects using current year ongoing revenue, one-time funding, state and federal grant funds,
cost-share, short -term finance dollars, previously approved bond funding and various dedicated
funds. The CIP includes a projected ten year spend plan of all of the aforementioned sources, various
fees, and the approval of new GO bonds. Due to these multiple funding sources and the multi -year
nature of project execution, not all of the County’s planned spending on capital projects appears in
any one year of the operating budget. The CIP document shows the multiple year execution of
projects.
The County typically uses PAYG and short-term financing to fund assets with useful lives of 10 years
or less. Financed dollars, whether short- or long-term, are set on repayment schedules (debt service)
concurrent with the expected useful lives of the financed assets. For example, short-term financing
is often used for replacement of technology and equipment assets with expected useful lives from
three to eight years. Long-term financing (e.g., GO bonds) is used primarily for the County’s large
capital infrastructure investments, such as buildings or roads, with expected useful lives of 10 or
more years. Refer to the Debt Service section of this document and the A dopted Capital
Improvement Plan for more detailed information on the County’s long-term capital financing strategy.
OVERVIEW OF FY 2027 CAPITAL PROGRAM
The adopted FY 2027 General Capital Fund budget is supported by a variety of funding sources.
Funding recommendations include the General Fund transfer, short-term financing from the General
Fund and Auto Equipment Fund, utilization of project balances, fee revenue, and funds from
partnerships. Total project funding for FY 2027 is $26.7 million and is detailed on the table on the
following pages. These projects do not assume any new bond funding. The upcoming Capital
Improvement Plan (CIP), which will include new debt issuance will be proposed later this spring and
adopted in the summer.
This maintenance capital program serves to prolong the useful life of investments, while minimizing
the need for repeated asset repair emergencies in the operating budget. This adopted budget focuses
on replacing assets at the end of their useful lives, assets that are obsolete and assets presenting
potential safety concern. Because projects are often multi-year in nature, appropriations rather than
actual expenditures are presented.
In addition to the PAYG funding included in this section, there are PAYG investments in other funds
and operations including:
The Utilities Fund FY 2027 Adopted PAYG budget of $34.7 million includes funding for
Wastewater Treatment Plant capital maintenance and improvements to the Washington
Aqueduct, which supplies the County with 100 percent of its drinking water.
The Stormwater Utilities Fund FY 2027 Adopted PAYG budget of $3.6 million includes funding
for improvements to infrastructure and regulatory requirements in the stormwater system.
For additional information see the Capital Utilities and Stormwater Fund narratives.
554
PAY-AS-YOU-GO
GENERAL CAPITAL PROJECTS FUND
FY 2027 PAYG CAPITAL EXPENDITURES BY PROGRAM AREA
PROGRAM CATEGORY Transfer Funds Short-Term
Financing *
Reallocated
Balances Other
FY 2027
Adopted
Total
Regional Partnerships $768,000 - - - $768,000
Transportation Maintenance Capital 1,346,000 - - - 1,346,000
Transportation Com plete Streets 1,141,000 - - - 1,141,000
Facilities Maintenance Capital 1,216,000 $250,000 $934,000 - 2 ,400,000
Facilities Design and Construction 463,000 525,000 - - 988,000
Energy Management 265,000 340,000 135,000 - 740,000
Parks Maintenance Capital 150,000 1,702,000 - $920,000 2,772,000
Information Technology 200,000 7,208,000 - - 7,408,000
Public Safety * - 7,839,000 - 222,000 8,061,000
Arlington Neighborhoods Program 781,000 - - - 781,000
Public Art - - - - -
Joint Use Space Maintenance - - - - -
Capital Contingency/Admin - - 309,000 - $309,000
Total Projects $6,330,000 $17,864,000 $1,378,000 $1,142, 000 $26,714,000
* Short--term financing includes $6.8 million funded from the Auto Equipment fund which is charged back to Fire over the term of the financing period
PAYG and BOND BALANCE FUNDED PROJECTS
Regional Partnerships $768,000
Arlington County is a member of several regional organizations which provide services to Arling ton
residents and visitors. The Regional Partnerships program funds the County’s annual contributions
to support these organizations’ capital needs. This funding is separate from the County’s annual
operating contribution to these organizations, which is discussed in the Regionals narrative in this
document. The amount the County contributes every year for capital needs is determined by each
organization’s allocation formula.
Northern Virginia Regional Park Authority $768,000
The Northern Virginia Regional Park Authority (NVRPA) is a multi-jurisdictional agency comprised
of Arlington County, Fairfax County, Loudoun County, and the Cities of Alexandria, Falls Church,
and Fairfax which owns and operates over 10,000 acres of parkl ands with 21 major parks,
including Potomac Overlook, Upton Hill, and the W&OD Regional Parks in Arlington.
Transportation Program $2,487,000
Transportation – Maintenance Capital $1,346,000
The Transportation Maintenance Capital program in the Department of Environmental Services (DES)
maintains transportation infrastructure by repaving streets and bike lanes, maintaining pedestrian
and vehicular bridges, maintaining sidewalks, signals, signal infrastructure, and Intelligent
Transportation Systems (ITS), maintaining and replacing street and trail lights, maintaining and
replacing parking meters, and maintaining and replacing bus shelters.
555
PAY-AS-YOU-GO
GENERAL CAPITAL PROJECTS FUND
Bridge Maintenance $236,000
This is an ongoing program that provides funds to continue inspection, maintenance, and
rehabilitation of 38 vehicular and pedestrian bridges in Arlington County to assure an adequate
level of safety. Twenty -six bridges are included in the Federal Highway Administration (FHWA)
National Bridge Inventory (NBI), which establishes standards for inspection and maintenance of
public highway bridges. All NBI bridges are required to be inspected and reported on at least
biennially and the County has adopted this standard for all 38 bridges. The program goal is to
maintain the Bridge Condition Rating (BCR), a nationally used rating, in a range between 6 and
7, defined as satisfactory to good. In FY 2027, the program anticipates undertaking repairs and
maintenance of the bridges identified during regular biennial inspections. Additionally, funds will
be allocated to spring power washing and cleaning of the eleven largest vehicular bridges and for
emergency repairs after large storm events and traffic accidents.
Paving Program $500,000
The County currently maintains 1,058 lane miles of roadway by a combination of mill and overlay,
full depth rebuilding, micro -surfacing, and slurry sealing. The County utilizes a Pavement
Condition Index (PCI) to assess the road conditions. The County has established a desired
average PCI range of 75-80 (with 100 representing the best possible) and has raised overall PCI
to 83.2 in 2025 from an average PCI of 67 in 2014. The PAYG funds, along with anticipated GO
bond funds, will maintain the PCI level as long as changes in winter weather, contracting costs,
and oil prices do not negatively impact the anticipated paving program. The program operates
on a 15 -year paving cycle, on average, with about 60 lane miles of mill & overlay per year to
maintain the des ired average PCI. Arterials are repaved more often due to the traffic volumes
and types of vehicles using them. Crack sealant will be used on both arterials and neighborhood
streets to extend their life and reduce the frequency that they need to be milled & overlayed.
Sidewalk, Curb, Gutter Proactive Zone Maintenance $250,000
The program funds proactive and comprehensive inspection and maintenance of
County-maintained, curb, gutter , and sidewalks. The County is divided into 20 concrete zones,
and the program's goal is to address two zones a year, for a 10-year maintenance interval. Zone
maintenance is informed by a sidewalk survey, most recently completed in 2024 along with
project manager observations.
Signals and ITS Maintenance $360,000
This program is intended as a traffic signal capital maintenance program outside of planned
rebuild projects, ITS system deployments, and other capital activities. The program focuses on
three major areas to ensure a good state of repair: 1) ITS device replacement to replace
components and systems as they age out of service, including items such as beacons, detection
cameras, audible pushbuttons, etc.; 2) the structural inspection program, which inspects and
rates the existing traffic structures to ensure a state of good repair, and repair any critical or
emergency deficiencies; and 3) higher cost preventative signal maintenance activities such as
rewiring, cabinet replacements, pushbutton retrofits, and other items that extend the service life
of a signal. PAYG funds the structural inspections, repair work, replacement of components that
have a life of less than 10 years, and most preventative maintenance work.
Complete Streets Programs $1,141,000
The Complete Streets Program provides mobility and accessibility improvements throughout the
County and connections to the rest of the region. This is achieved by providing a high-quality transit
system, a robust bicycle and pedestrian network, provisions for Shared Mobility Devices (SMDs), and
additional transportation demand management approaches. The program also maintains and
develops systems to manage and analyze transportation assets, including physical assets (e.g.,
signs) and transportation data assets (for example, collected observed traffic data and crash data).
556
PAY-AS-YOU-GO
GENERAL CAPITAL PROJECTS FUND
BIKE Arlington $57,000
The BIKE Arlington program makes physical enhancements to Arlington's transportation
infrastructure, including trails and streets, to improve conditions for bicycling. The program's goal
is to increase the number of riders and bicycle trips by making bicycling a more attractive travel
choice through completing the bicycle network, tracking usage of bicycle facilities through the
counter program, and installing wayfinding. PAYG funds operational and maintenance costs for
the bike counter program, installation of and repairs to wayfinding signage and bike parking, as
well as spot safety upgrades to trails and on -street bicycle infrastructure that don’t quality for
other funds.
Parking Meters $465,000
The goal of parking meter and technology program is to enable efficient management of public
curb space. The scope of work includes: (1) modernization and maintenance of the County's
parking-meter equipment, including research into and deployment of new equipment types and
technologies, (2) maintenance of the occupancy-detection system that has been piloted and has
provided key insights into customer behavior and preferences and helped optimize pricing and
payment compliance, and (3) upgrades to the online application system for residential parking
permits (RPP) and a critical transition to electronic permits. The County currently has about 1,368
parking meters (717 multi-space meters and 651 single space meters) that require replacement,
or component repla cement, after ten years of useful life. As part of the programs, data are
collected and analyzed from parking- meter equipment and from non -metered curb space. This
analysis supports decision making about curbside management, such as the allocation of curb
space for various uses, and other regulations, such as time limits for parking.
Street Lighting Management $0
This program will rebuild and upgrade aging streetlights and resolve ownership issues between
the County and Dominion Energy that adversely affect performance and maintenance. County
streets are lit with 18,125 streetlights, of which 7,325 are owned by the County and 10,800 are
owned by Dominion Energy (DE, formerly Dominion Virginia Power). PAYG is used to proactively
replace conduits and conductors on aging lighting systems as outlined by the Streetlight
Management Plan (SMP). This effort updates the aging underground infrastructure and improves
service reliability as underground repair work typically creates the longest outages of streetlights.
PAYG is also used to upgrade some existing LED fixtures to newer models with improved
functionality as they fail and require replacement. An example of this is the change from a
radio-based communication node to a cellular-based control node. The control systems are used
to allow for remote monitoring of errors and for dimming. Other funding is available to continue
executing the program. This program may also receive GO bond funding determined during the
FY 2027 – FY 2036 CIP.
Street Safety Improvements $558,000
The Street Safety Improvement (SSI) program supports the Vision Zero goal the Arlington County
Board adopted in July 2019 (and the Vision Zero Action Plan adopted in May 2021) to eliminate
all transportation fatalities and severe injuries. The funds in thi s program are imperative to
implementing quick-action, multimodal safety improvements at locations with a crash history or
systemic safety risks. Locations demonstrating high crash rates or more severe crashes are
prioritized, as are improvements in equity emphasis areas or near schools. Initiatives being
advanced with PAYG funding include 1) school beacon modifications to support automated
enforcement of school zones, 2) pedestrian crossing enhancements, including the implementation
of yellow flashing beac ons, 3) speed reduction strategies, 4) pilot projects, which entail testing
innovative safety treatments, and 5) other quick build projects that address safety issues at
various locations. In addition to PAYG funding, this program may also receive GO bond funding
determined during the FY 2027 – FY 2036 CIP.
557
PAY-AS-YOU-GO
GENERAL CAPITAL PROJECTS FUND
Transportation Asset Management $61,000
Transportation assets include deployed assets such as signals and signs installed in the
right-of-way, inventory assets housed in warehouses, and traffic data assets. This program
develops and maintains a management system that not only keeps records but also makes data
more accessible and analytical. This includes the development and continuous update of a central
traffic database that houses both historic and recent transportation data, including but not limited
to characteristics of streets, traffic volume counts, speeds, crashes, and street classification. The
database is updated as new information becomes available and currently has the following
capabilities: open data accessibility to staff and public; integration with the County work order
and asset management system (Cartegraph); integration with the County’s Geographic
Information System (GIS); trend analysis; safety analysis; report and map generation; and
system performance monitoring. This program also helps track and manage assets by integrating
with the current inventory system associated with the County’s warehouse storage facility.
Additionally, it helps staff manage and track customer complaints about transportation -related
issues and tie the solutions into asset updates. As such, it plays a critical role towards supporting
the County’s Vision Zero goal.
WALKArlington $0
The WalkArlington program makes physical enhancements to Arlington's sidewalk and street
infrastructure in commercial as well as non -commercial districts. The objectives of the program
include: improving pedestrian safety, completing the planned pedestrian network , and making
the network accessible for all users. PAYG funds are used to implement tactical measures that
are not eligible for other funding sources. Other funding is available to continue executing the
program. This program may receive GO bond funding or Transportation Capital funding
determined during the FY 2027 – FY 2036 CIP.
Facilities Maintenance Capital Program $2,400,000
The Facilities maintenance program operates approximately 90 County -owned public facilities,
including office buildings, fire stations, support, maintenance and logistic facilities, recreation
centers, courts, and more. The Facilities Maintenance Capital program is a collection of major facility
maintenance projects designed to keep County facilities operating in a safe, efficient, and reliable
manner. This program and the Facilities Design and Construction program are integrated to maintain
and improve the portfolio of County facilities based on the life cycle of assets.
Central Library Plaza Renovation $1,500,000
The project will address water intrusion; the scope of work includes the installation of a perimeter
drainage system and regrading of the plaza surrounding the facility. This will also address
potential safety concerns from tripping and fall hazards. The space will also be re-evaluated with
Libraries and the Department of Parks and Recreation (DPR ) for other potential layouts and use
opportunities.
Residential Program Center (RPC) Elevator Modernization $650,000
The Residential Program Center (RPC) provides three crucial services – non-medical
detoxification, substance abuse recovery , and housing services for single adults experiencing
homelessness – all under one roof. Accessibility within the facility is critical to the operation of
the program and to facility code requirements. The elevator at the RPC has reached the end of
its useful life, and electronic control equipment has also become obsolete. The scope of this
project is to update the elevators within the building, including machinery, passenger cabs, and
electronic controls.
558
PAY-AS-YOU-GO
GENERAL CAPITAL PROJECTS FUND
Critical Site Uninterruptible Power Supply (UPS) Upgrade Program $250,000
This program is to replace the UPS units at critical public safety radio sites, ensuring continuity
of operations in the event of a power outage. Previous funding cycles have allowed for successful
upgrades to four (4) of the six (6) radio sites.
Energy Management $740,000
The Energy Management Program invests funds in various capital improvements that advance the
goals of the Community Energy Plan (CEP).
Electric Vehicle (EV) Chargers - Public Accessibility $190,000
This project includes two components that support key objectives of the adopted Community
Energy Plan (CEP), including policy 4.4 to promote and encourage electric vehicles in the private
and commercial sectors and support convenient charging stations throughout Arlington.
o Electric vehicle charging infrastructure for high -visibility and high -circulation public-use
County government sites through a match ($150,000) to the Federal funding through the
Clean Fuels Infrastructure (CFI) grant where the County is a sub awardee on the regional
project coordinated by the Metro Washington Council of Governments. The locations
identified for public EV charging installations through the CFI grant are Barcroft
Community Center, Barcroft Garage, Bluemont Park , and the Walter Reed Community
Center.
o Updating signage for all public and fleet charging locations for consistent messaging to
enhance clarity and user experience ($40,000).
County Facility Renewable Energy Assessment and Solar Installation $400,000
This program provides funding for on-site solar development at County facilities under a Power
Purchase Agreement (PPA) model rather than County-owned and maintained solar assets .
Shifting to a PPA model reduces the capital costs and ongoing maintenance costs for the County
because the PPA provider installs and maintains the solar arrays . The County purchas es the
electricity generated and saves money on electric bills and at the same time realizes the
greenhouse gas reduction and renewable energy benefits . Funding supports potential upfront
capital expenses for enhanced feasibility analysis, structural analysis, and electrical panel
upgrades that will be identified through the design process to ensure sites are solar ready for PPA
installations.
Energy Performance Measurement – County Buildings $150,000
This program, in partnership with the Facilities Management Bureau and Arlington Initiative to
Rethink Energy (AIRE), is to implement energy efficiency and decarbonization measures at
County facilities with a focus on energy and climate performance. In FY 2027, the funding will be
used for evaluation, measurement , and verification of recently installed HVAC electrification
projects. This effort will provide performance data on installed electrified HVAC systems that can
inform future facility electrification planning and analysis efforts through a data driven approach.
Facilities Design and Construction Program $988,000
The Facilities Design and Construction Program maintains and modernizes current County facilities
and plans for the County’s future facility needs. The program is integrated with the Facilities
Maintenance Capital program in planning periodic renovations and eventual replacement of obsolete
facilities at the appropriate points in the life cycle.
559
PAY-AS-YOU-GO
GENERAL CAPITAL PROJECTS FUND
Facility Condition Assessments & Planning Studies $463,000
Feasibility studies focus on near term and intermediate range planning to define options in
response to evolving facility needs, including opportunities for co-location, facilities consolidation,
and repurposing spaces to meet changing community needs . The planned feasibility studies
include Courts Square West, Bozman Government Center, 2020 N 14th Street, Quincy site
utilization study, and warehouse utilization study.
Facility Finishes and Furnishings $525,000
This program invests in the existing facilities interior/exterior finishes and furnishings, consisting
of interior maintenance capital and systems furniture replacement. This will address safety,
quality, and condition disparities between newer and existing buildings.
Parks Maintenance Capital Program $2,772,000 ($2,137,000 County/$635,000 APS)
The Parks Maintenance Capital Program provides for recurring, systematic reinvestment in existing
facilities by replacing inefficient and outdated infrastructure and preventing premature failure. The
program funds the replacement or major renovation of park and recreation facility assets, including
athletic fields and courts, field and court lighting, playgrounds, picnic shelters, restrooms, parking,
and other miscellaneous park and recreation facilities. The program also addresses accessibility,
safety, and storm water improvements that are complementary to renovating the facilities.
Capital Asset Manager
$150,000
This funding is for the staff position that manages the Parks Capital Asset Program.
Field Fund $285,000
The Parks Field Fund is supported by an annual fee assessed on official affiliated youth and adult
sports teams playing on Arlington County rectangular and diamond fields . Work to be identified
may include supporting the replacement and construction of synthetic turf fields and
enhancements to existing fields such as improved irrigation, site amenities or accelerated sod
replacement. The FY 202 7 PAYG budget reflects the projected annual revenue from FY 202 6
generated fees.
Long Bridge Synthetic Turf Replacement – Field #1 $1,270,000
These funds will be used for the design and construction for the replacement of synthetic turf
surfacing on Field #1 at Long Bridge Park. Costs include design development, replacement of
the synthetic turf and infill, repairs to the base layer and under -drain system, replacement of
field amenities, and construction administration Replacement of the synthetic turf on this field is
needed to maintain the high play quality offered through synthetic turf. The project cost share
between the County cost and Mary mount University is 50/50 ($635,000 Arlington County/
$635,000 Marymount University).
Long Bridge Synthetic Turf Replacement – Field #4 $1,067,000
These funds will be used for the design and construction for the replacement of the synthetic turf
surfacing on Field #4 at Long Bridge Park. Costs include design development, replacement of the
synthetic turf and infill, repairs to the base layer and unde r-drain system, replacement of field
amenities, and construction administration Replacement of the synthetic turf on this field is
needed to maintain the high play quality offered through synthetic turf. The County cost for this
project is $1,067,000. Unlike many of the County’s synthetic fields, there is no cost sharing
agreement in place for this field.
560
PAY-AS-YOU-GO
GENERAL CAPITAL PROJECTS FUND
Technology $7,408,000
The technology section includes both enterprise-wide and program specific projects. See the capital
project list section for additional technology funded projects in other capital funds.
Server & Storage Program $400,000
This program covers the general sustainment and replacement of physical County server
hardware and data storage. Continued investment in the maintenance of server and storage
hardware is crucial for ensuring the resilience and uninterrupted operation of technology
platforms that support critical business processes.
Workforce Device Modernization $3,206,000
This program provides funding for the cyclical replacement of workforce devices, including laptops
and desktops utilized by the County. The goal of the program is to maintain an 80 percent laptop
to 20 percent desktop device mix within the County. This program, formerly known as PC
Replacement, is responsible for managing the replacement of approximately 3,300 laptops and
730 desktop devices on a rolling replacement schedule.
Network $2,352,000
This annual program covers the replacement and refreshment of end-of-life equipment, hardware
systems, software, and cabling that provide network and wireless connectivity which support the
County’s data center infrastructure, network access and security, power protection, and worker
mobility and telework technology. For FY 2027, the budget primarily allocates funds for upgrading
the County's network infrastructure. The plan involves replacing network equipment at various
County site locations, which is cru cial to maintain and enhance connectivity. These network
improvements support the County's, Schools', and Public Safety's comprehensive requirements
for voice, data, and video communication.
Real Estate Assessment System $1,250,000
The Office of Real Estate Assessments is responsible for valuing approximately 66,000 parcels
annually, consisting of commercial, single -family and condominium properties. The current
system was initially implemented twenty years ago, and a custom in -house system was built
eight years ago to supplement missing functionality at the time. A new system will provide
significant functional enhancements with greater analytical and reporting capabilities as well as
integration with other systems. This is the second year of a two- year project with $1,250,000
required for the second year for a total project budget of $2,250,000.
HR/FIN System (PRISM+) Enhancements $200,000
Following the upgrade of the existing human resources and financial system to a cloud -based
solution (PRISM+) in FY 2026, funding for implementation services is needed to support the
implementation of new or modified functionality available as part of the future quarterly releases.
This continuous improvement will help the County improve the efficiency of business processes.
Services will include configuration, deployment & integration of modules, testing, training,
customer support and ensuring compliance with regulatory requirements.
Public Safety $8,061,000
The public safety section includes key system and asset replacements on a reasonable life cycle. The
projects are funded between both PAYG funds and short-term financed dollars.
561
PAY-AS-YOU-GO
GENERAL CAPITAL PROJECTS FUND
Police Electronic Summons System $222,000
In FY 2015, the County began assessing a $5.00 fee as part of the costs for each criminal or
traffic case in the district or circuit courts to purchase and implement an electronic summons
system. With an electronic summons system, citation data is automatically scanned and
electronically entered at the point of activity, improving efficiency and accuracy in the processing
of issued citations for Courts and Police personnel. Once the citation is complete, the transaction
data is sent electronically to the Court’s case management systems, allowing violators to prepay
their fines promptly and aid the Courts in managing their dockets while tracking their caseloads.
The cost of the system include s the software and hosting costs, peripheral equipment such as
handheld devices and portable printers, installation, training, and system maintenance.
Police Mobile Data Computers $400,000
The Mobile Data Computer (MDC) project includes refreshment of the hardware, software, servers
and vehicle docking stations required for police vehicles to utilize mobile computing technology
in the vehicle. These terminals or laptops permit data exchange via wireless technology to the
Police, Fire and Sheriff's Departments and are located in public safety vehicles.
Police Ballistic Shields $475,000
This project covers replacement of ballistic shields currently in place and have reached end of
useful life. Maintaining this equipment is critical to the life and safety of officers.
Police Computer Forensic Equipment $100,000
Digital evidence includes documents, pictures, text messages and other information that is stored
on cell phones, computers, and other devices which is captured during most law enforcement
investigations. Staff use forensic workstations and servers to store and analyze digital evidence.
For digital evidence to be admissible in court proceedings, it is critical to maintain the integrity of
the data and adhere to data capture and retention standards. Routine equipment replacement
keeps all servers operating w ith up -to-date technology and maintains data security. Modern
servers can reduce data space requirements, maintenance time and licensing costs.
Fire Apparatus $6,864,000
In FY 2027, the County anticipates receiving 6 pumpers that were ordered in FY 2023. This project
is funded from the Auto Equipment fund.
Arlington Neighborhoods Program - Program Management $781,000
These funds are for staff project management costs for the program. This ongoing program funds a
diverse set of infrastructure construction projects across the community. Since the 1960s, Arlington
residents and civic associations have collaborated with the County to identify and plan infrastructure
projects in their own neighborhoods. These projects have included everything from streetlight
installation to street intersection reconfiguration to tree and landscape restoration to new curb,
gutter, and sidewalk.
Capital Administration/Contingent $309,000
The FY 2027 adopted budget includes funding for administrative support of capital projects tracking,
reporting, and procurement in the Department of Management and Finance.
562
GENERAL OBLIGATION (GO) BONDS
GENERAL CAPITAL PROJECTS FUND
WHAT ARE BONDS?
Municipal bonds are debt securities the County sells to generate funding for capital investments that
will then be paid back overtime. When investors purchase County bonds, it is a debt that the County
will repay in one or more years with interest. The County’s regular payments to bond investors are
called “debt service.” The bond funding of capital investments operates under the principle of “inter-
generational equity.” Debt service is spread over multiple years in line with the useful life of an asset.
This allows those residents who may benefit from the project over time to pay for it. There are many
different types of bonds, which are primarily distinguished by the security backing them. The County
primarily issues General Obligation (GO) bonds and subje ct-to-appropriation bonds. GO bonds are
backed by the full faith and credit of the County, which is the strongest backing a municipal bond
can have. Subject -to-appropriation bonds are secured by an annual appropriation of revenues
sufficient to pay debt s ervice. Due to this lack of full faith and credit pledge, they typically carry a
lower credit rating.
HOW DOES THE COUNTY ISSUE BONDS?
In Arlington County, the primary type of bond s issued are General Obligation (GO) bonds. These
bonds carry the County’s full faith and credit pledge and require that residents must first approve
one or more bond referenda authorizing the issuance of GO bonds. These bonds are issued for capital
projects as identified in the County’s Capital Improvement Plan (CIP). The County seeks approval for
referenda as part of regular elections, generally in November of even numbered years. If residents
approve one or more bond referenda, then the County will include one or more projects approved
under each referendum in a future sale of GO bonds based on each project’s cashflow needs. The
specific amounts of the bonds to be sold for each capital project are determined as part of the
County’s CIP. Typically, the County’s CIP has a 10 -year “planning horizon,” which includes an
adopted capital budget for the first year and nine forecasted future planning years. In calendar year
2024, the County adopted a ten -year CIP cove ring fiscal years 2025- 2034, and six different bond
referenda were approved by voters in November 2024.
GO BONDS AND THE CAPITAL IMPROVEMENT PLAN
The CIP is a planning document that identifies the capital needs of the community over a
ten-year period. GO bond financing is one component of the overall funding plan in the CIP and is
generally used to finance capital projects with average useful lives of more than 10 years, matching
or exceeding the average maturity of the bonds issued . Full detail of the CIP can be found at
https://www.arlingtonva.us/Government/Programs/Budget-Finance/CIP.
Prior to FY 2020, GO bond funding was appropriated at the time of bond issuance, typically in the
spring of each fiscal year. Consistent with other capital funds, the appropriation of general obligation
(GO) bond funded projects is now included as part of the operating budget. As individual projects
approved in the CIP advance and become more defined, the timing of when the County sells its bonds
to investors may shift from the adopted CIP to align with changes to the timing or cashflow needs of
the project.
563
GENERAL OBLIGATION (GO) BONDS
GENERAL CAPITAL PROJECTS FUND
FY 2027 General Obligation Program Costs
Debt service on bonds to be issued in FY 202 6 will not begin until FY 2028 and will be included in
that year’s operating budget. The adopted FY 2027 debt service budget includes debt service on
bonds already issued through FY 2026. The bonds and associated debt service adhere to the County’s
financial and debt management policies.
564
GENERAL CAPITAL PROGRAM PROJECT LISTS
GENERAL CAPITAL PROJECTS FUND
Project Description FY 2027 PAYG Short-Term
Finance
Reallocated
Balances Other Total Budget
Northern Virginia Regional Parks Authority $768,000 - - - $768,000
Bridge Maintenance 236,000 - - - 236,000
Pavings, Marking, Slurry Seal 500,000 - - - 500,000
Signals and ITS Maintenance 360,000 - - - 360,000
Bike Arlington 57,000 - - - 57,000
Neighborhood Complete Streets - - - - -
Parking Meters 100,000 - - - 100,000
Parking Technology 365,000 - - - 365,000
Sidewalk, Curb, Gutter, Proactive Zone
Maintenance 250,000 - - - 250,000
Street Safety Improvements 558,000 - - - 558,000
Transportation Asset Management 61,000 - - - 61,000
Walk Arlington - - - - -
Central Library Plaza 1,216,000 - 284,000 - 1,500,000
CSI - Critical Site UPS Upgrade Program - 2 50,000 - - 250,000
Residential Program Center Elevator
Modernization - - 6 50,000 - 650,000
Facilities Conditions Assessments &
Planning Studies 463,000 - - - 463,000
Facility Finishes and Furnishings - 5 25,000 - - 525,000
Facilities Design & Construction
FY 2027 Capital Program Project List
Regional Partnership
Transportation Maintenance
Transportation Complete Streets
Facilities Maintenance
565
GENERAL CAPITAL PROGRAMS PROJECT LISTS
GENERAL CAPITAL PROJECTS FUND
Project Description FY 2027 PAYG Short-Term
Finance
Reallocated
Balances Other Total Budget
Electric Vehicle Chargers - Public Access - $ 190,000 - - $190,000
Energy Performance Management -
County Buildings - 15 0,000 - - 150,000
Facility Renewable Energy Assessment
and Solar Installation 265,000 - 1 35,000 - 400,000
Capital Asset Manager 150,000 - - - 150,000
Field Funds - - - 285,000 285,000
Long Bridge Synthetic Turf Field
Replacements (#1 & #4) - 1, 702,000 - 635,000 2,337,000
Human Resource and Financial System
Enhancements 200,000 - - - 200,000
Network - 2 ,352,000 - - 2,352,000
Real Estate Assessment System
Replacement - 1, 250,000 - - 1,250,000
Server Program - 4 00,000 - - 400,000
Workforce Modernization - 3 ,206,000 - - 3,206,000
Fire - Vehicle Apparatus - 6 ,864,000 - - 6,864,000
Police - Mobile Data Computers - 4 00,000 - - 400,000
Police - Ballistic Shields - 4 75,000 - - 475,000
Police - Computer Forensic Equipment - 1 00,000 - - 100,000
Police - E-summons Ticketing System - - - 222,000 222,000
Project Management 781,000 - - - 781,000
Capital Contingency /Admin - - 309,000 - 309,000
TOTAL $6,330,000 $17,864, 000 $1,378,000 $1,142,000 $26,714,000
FY 2027 Capital Program Project List
Capital Contingency / Administration
Public Safety
Arlington Neighborhoods Program
Parks Maintenance/Fields
Information Technology
Energy Management
566
GENERAL CAPITAL PROGRAMS PROJECT LISTS
GENERAL CAPITAL PROJECTS FUND
Project Description PAYG To tal Budget
Stormwater Infrastructure/Capacity Improvements
Capacity Project Planning Studies $50,000 $50,000
Stormwater Maintenance Capital
Four Mile Run Maintenance Capital 200,000 200,000
Manhole & Catch Basin Rehabilitation 370,000 370,000
Military Road Culvert at Gulf Branch 185,000 18 5,000
Stormwater Mains Rehabilitation/Replacement 1,000,000 1,000,000
Stormwater Frames and Covers 150,000 150,000
Terra Cotta/Corrugated Metal Pipe Upgrades 925,000 925,000
Streams and Water Quality
Outfall Rehabilitation Program 250,000 25 0,000
Stream Resiliency Program 150,000 15 0,000
Stream and Wetland Maintenance Capital 235,000 235,000
Water Quality Project Feasibility & Concept Design 150,000 150,000
Total Projects $3,665,000 $3,665, 000
Stormwater Capital Program
FY 2027 Capital Program Project List
567
GENERAL CAPITAL PROGRAMS PROJECT LISTS
GENERAL CAPITAL PROJECTS FUND
Project Description PAYG Total Budget
Sanitary Sewer System Improvements
Collection Improvements $250,000 $250,000
Water Distribution System Improvements
Distribution improvements 500,000 500,000
Finished water reliability & interconnections 100,000 100,000
Water Pollution Control Plant Capital Sustainment
Activated Sludge Effluent Pump Station #1 Upgrades 200,000 200,000
Asset Management and Work Order System Replacement 106,000 106,000
Blue Plains Plan Capital 1,705,000 1,705,000
Primary Clarifier Upgrades 575,000 575,000
Solids Master Plan (Re-Gen) Phase 2 765,000 765,000
Solids Master Plan (Re-Gen) Phase 3 7,166,000 7,166,000
Technology Enhancements 1,548,000 1,548,000
Water Pollution Control Plant Maintenance Capital Program 4,521,000 4,521,000
Water-Sewer Maintenance Capital
Large diameter sewer rehabilitiation and replacement 2,928,000 2,928,000
Large diameter water main rehabilitation and replacement 950,000 950,000
Large meter valve rehabilitation and replacement 200,000 200,000
Manhole rehabilitation 1,000,000 1,000,000
Non-expansion inflow and infiltration sanitary sewer
capital repairs and replacements
2,500,000 2,500,000
Sewer main and sewer force main replacement programs 3,430,000 3,430,000
Small diameter valve rehabilitation and replacement 300,000 300,000
Water main cleaning and re-lining projects 1,600,000 1,600,000
Water main replacement program 2,800,000 2,800,000
Water/sewer frames and covers 750,000 750,000
Water tank and pump station maintenance capital 850,000 850,000
Total Projects $34,744,000 $34,744,000
Utilities Capital Program
FY 2027 Capital Program Project List
568
PAY-AS-YOU-GO CAPITAL
UTILITY CAPITAL PROJECTS FUND
Our Mission: To provide and maintain a water distribution system, a sewage collection system, and
a wastewater treatment plant
The Department of Environmental Services is respon sible for managing the Utility Fund, which
includes providing and maintaining a water distribution system, a sewage collection system, and a
wastewater treatment plant.
Capital budget development is included in both the annual operating budget process and the biennial
capital improvement plan (CIP). The annual budget process approves and allocates funding for capital
projects using current year ongoing revenue, one- time f unding, state and federal grant funds,
cost-share, previously approved bond funding and various dedicated funds. The CIP includes a
projected ten year spend plan of all of the aforementioned sources, various fees, and the approval
of new G eneral Obligation (GO) bonds. Due to these multiple funding sources and the multi -year
nature of project execution, not all of the County’s planned spending on capital projects appears in
any one year of the operating budget. The CIP document shows the multiple year execution o f
projects.
The County typically uses Pay-As-You-Go (PAYG) to fund assets with useful lives of 10 years or less.
Financed dollars are set on repayment schedules (debt service) concurrent with the expected useful
lives of the financed assets. Long-term financing (e.g., GO bonds) is used primarily for the County’s
large capital infrastructure investments, such as buildings , equipment at the wastewater plant or
major water or wastewater mains, with expected useful lives of 10 or more years. Refer to the Debt
Service secti on of this document and the Adopted Capital Improvement Plan for more detailed
information on the County’s long-term capital financing strategy.
The Adopted FY 2027 Utility Fund PAYG Budget Summary, program budget appropriation distribution
graph, project descriptions, and fund statement are included on the following pages.
569
PAY-AS-YOU-GO
UTILITY CAPITAL PROJECTS FUND
Water-Sewer
Maintenance
Capital
50%
Water Distribution
System Improvements
2%
Sanitary Sewer System
Improvements
<1%
Wastewater
Treatment Plant
Capital
Sustainment
48%
Distribution of Fund Budget
FY 2027 ADOPTED PAYG BUDGET SUMMARY
PROGRAM CATEGORY AMO UNT
UTILITIES
Wastewater Treatment Plant Capital Sustainment $16,586,000
Water-Sewer Maintenance Capital 17,308,000
Water Distribution System Improvements 600,000
Sanitary Sewer System Improvements 250,000
Tot
al Project Cost 34,744,000
Less: Infrastructure Availability Fees & Other Revenue 6,300,000
Less: Inter-Jurisdictional Partner Contributions 10,854,082
Less: Interest Income & Miscellaneous Revenues 350,000
Less: Transfer in from General Fund 104,918
Net Utilities Funds Support $17,135,000
570
PAY-AS-YOU-GO
UTILITY CAPITAL PROJECTS FUND
FY 2027 ADOPTED UTILITIES BUDGET
Wastewater Treatment Plant Capital Sustainment $16,586,000
Water Pollution Control Plant Maintenance Capital Program. This program provides for
the annual repair, replacement , and upgrade of current equipment and infrastructure at the
plant and lift stations. Major program components include refurbishing or replacing equipment
to prevent premature failure, infrastructure improvements , and automating treatment
processes to increase operational efficiency, reliability, and redundancy. Additionally, studies
of alternative treatment processes to increase efficiency and reduce environmental impact are
funded through this program ($4,521,000).
Solids Master Plan (Re -Gen) Phase 2 – Intermediate Needs. Projects that need to be
completed in advance of Phase 3 which may involve additional equipment replacement or
demolition of underutilized facilities in preparation for the Phase 3 construction ($765,000).
Solids Master Plan (Re -Gen) Phase 3 – Class A Biosolids / Long Range Needs. The
Solids Master Plan will modernize solids treatment facilities and create opportunities for
resource recovery. The plant currently produces an alkaline stabilized Class B biosolids product
but is planning to produce Class A biosolids after the plan’s implementation. This phase
implements the long-term solution to producing a Class A biosolids product. More information
about this suite of projects can be found at www.arlingtonregen.com ($7,166,000).
Technology Enhancements. This program provides funding for the Plant’s Process Control
System (PCS) and other networked cybersecurity relat ed initiatives. Several discrete projects
have been identified as part of this program ($1,548,000).
Asset Management and Work Order System Replacement. The current asset
management and work order system is nearing end of life . This funding will be used to
implement a replacement system ($106,000).
Primary Clarifier Upgrades. This project will evaluate and rehabilitate / improve equipment
and facilities associated with the primary clarifiers to ensure alignment with industry best
practices. The last upgrade to the system was approximately 20 years ago. ($575,000).
USACE Coastal Storm Resiliency. The U.S. Army Corps of Engineers (USACE) is conducting
a study to reduce long- term coastal flood risk to vulnerable populations, properties,
infrastructure, and environmental and cultural resources in Northern Virginia within the Middle
Potomac River watershed. The project will study a potential floodwall that would be constructed
along the northern bank of Four Mile Run between the Four Mile Run bike trail and the Water
Pollution Control Plant ($200,000).
Blue Plains Plant Capital . The District of Columbia Water and Sewer Authority Blue Plains
Plant processes a portion of Arlington County’s sewage after transmission through Fairfax
County mains. The capital program funds Arlington’s annual payment through Fairfax County
to the Blue Plains Plant for capital improvements. It also funds improvements to the
transmission system. Payment is due under the terms of the October 3, 1994 , Sewage
Conveyance, Treatment, and Disposal Agreement with Fairfax County ($1,705,000).
Water-Sewer Maintenance Capital $17,308,000
The funding for these projects comes primarily from a transfer from the Utilities Operating Fund,
which is an enterprise fund. The revenues for this enterprise fund are derived primarily from water
and sewer utility billings. Infrastructure Availability F ees (IAF) charged to new users wh o increase
demands on the system are an additional funding source for these projects. The following projects
571
PAY-AS-YOU-GO
UTILITY CAPITAL PROJECTS FUND
and programs are planned to replace and rehabilitate the County’s water distribution and sewage
collection system.
Water main replacement program ($2,800,000)
Non-expansion inflow & infiltration sanitary sewer capital repairs & replacements ($2,500,000)
Large diameter sewer rehabilitation & replacement ($2,928,000)
Water main cleaning and re-lining projects ($1,600,000)
Water / sewer frames and covers ($750,000)
Sewer main & sewer force main replacement programs ($3,430,000)
Manhole rehabilitation ($1,000,000)
Large diameter water main rehabilitation & replacement ($950,000)
Small diameter valve rehabilitation & replacement ($300,000)
Large meter vault rehabilitation & replacement ($200,000)
Water tank and pump station maintenance capital ($850,000)
Water Distribution System Improvements $600,000
The water main projects in this program are designed to improve overall capacity or operation of the
water distribution system. These projects are part of the Water System Plan. Funding for these
projects is generated from fees charged to new users who increase demands on the water distribution
system.
Distribution improvements ($500,000)
Finished water reliability & interconnections ($100,000)
Sanitary Sewer System Improvements $250,000
The sanitary sewer collection improvements are intended to provide additional capacity to existing
sanitary sewer lines to accommodate new development in Arlington County. These projects are part
of the Sanitary Sewer System Plan. Funding for this program is generated from fees charged to new
users who increase demands on the sewer system.
TOTAL UTILITIES CAPITAL BUDGET $34,744,000
572
PAY-AS-YOU-GO
UTILITY CAPITAL PROJECTS FUND
Most capital projects span multiple years, from design to construction completion. Sewage
Treatment Service Charge s are the inter-jurisdictional partner contributions for eligible capital
projects and the FY 2026 re -estimate is based on projected capital execution . The FY 2025 Actual
and FY 2026 Re-Estimate columns reflect that funding for capital projects are carried forward each
fiscal year, and ending balances fluctuate, reflecting the carryover of these funds. The FY 20 27
Adopted Budget column is presented in a similar fashion to show planned execution of projects in
the fiscal year. These are staff ’s best estimates based on preliminary plans and design and
construction schedules.
FY 2025
ACTUAL
FY 2026
ADOPTED
FY 2026
RE-ESTIMATE
FY 2027
ADOPTED
ADJUSTED BALANCE, JULY 1 $38,085,920 $17,609,191 $23,024,741 $15,564,900
REVENUES:
Infrastructure Availability Fees 4,755,660 9,385,000 5,700,000 6,300,000
Sewage Treatment Service Charges 2,548,080 11,485,000 4,003,242 10,854,082
Interest 1,109,694 360,000 300,000 350,000
Miscellaneous Revenue - -
TOTAL REVENUE 8,413,434 21,230,000 10,003,242 17,504,082
Transfers In (Out):
Transfer in from General Fund 104,918 104,918 104,918 104,918
Transfer In from Utilities Operating Fund 7,993,000 10,204,000 10,204,000 17,135,000
TOTAL TRANSFERS IN 8,097,918 10,308,918 10,308,918 17,239,918
TOTAL BALANCE, REVENUES AND
TRANSFERS IN 54,597,272 49,148,109 43,336,901 50,308,900
EXPENDITURES:
Capital Projects - Current Year 16,511,353 31,538,918 20,312,160 34,744,000
Capital Projects - Carry-Over 15,061,178 10,000,000 7,459,841 11,120,000
TOTAL CAPITAL EXPENDITURES: 31,572,531 41,538,918 27,772,001 45,864,000
BALANCE, JUNE 30 $23,024,741 $7,609,191 $15,564,900 $4,444,900
UTILITIES CAPITAL PROJECTS FUND
FUND STATEMENT
573
This page intentionally left blank
574
PAY-AS-YOU-GO CAPITAL
STORMWATER CAPITAL PROJECTS FUND
Our Mission: To implement a comprehensive stormwater management program that balances the
following goals: 1) to reduce the potential for stormwater threats to public health, safety, and
property; 2) to reduce the impacts of new and existing urban development on Arlington streams, the
Potomac River, and the Chesapeake Bay; and, 3) to comply with State and federal stormwater, water
quality, and floodplain management regulations.
The Department of Environmental Services is responsible for managing the Stormwater Management
Fund. In prior years, the Stormwater Management Fund was a combined fund for operat ions,
maintenance, and capital projects funded through the Sanitary District Tax of $0.017 per $100 of
assessed real property value . Effective January 1, 2024, Arlington County has implemented a
Stormwater Utility, which has replaced the tax funding with utility fee funding based on a property’s
impervious area. More information can be found on the Stormwater Utility Fee website.
Starting in FY 2024, Stormwater Management F und is now an enterprise fund. With the change in
fund type, there is now a separate fund for operations and maintenance activities, and a capital
projects fund dedicated to the Pay -As-You Go capital program. The Stormwater Management
operating fund can be found in the “Enterprise, Special Revenue, and Internal Service Funds” section
of this budget book.
Capital budget development is included in the annual operating budget process and the biennial
capital improvement plan (CIP). The annual budget process approves and allocates funding for capital
projects using current year ongoing revenue, one- time funding, state and federal grant funds,
cost-share, previously approved bond funding and various dedicated funds. The CIP includes a
projected ten-year spending plan for all the sources, various fees, and the approval of new GO bonds.
Due to these multiple funding sources and the multi -year nature of project execution, not all the
County’s planned spending on capital projects appears in any one year of the operating budget. The
CIP document shows the multiple year execution of projects.
The County typically uses PAYG to fund assets with useful lives of 10 years or less. Financed dollars
are set on repayment schedules (debt service) concurrent with the expected useful lives of the
financed assets. Long-term financing (e.g., GO bonds) is used primarily for the County’s large capital
infrastructure investments, such as installation or replacement of long segments of stormwater pipe,
land acquisition, and replacement of large culverts under roads with expected useful lives of 10 or
more years. Refer to the Debt Service section of this document and the Adopted Capital Improvement
Plan for more detailed information on the County’s long-term capital financing strategy.
The Adopted FY 20 27 Stormwater Fund P ay-As-You-Go Budget Summary, program budget
appropriation distribution graph, project descriptions, and fund statement are included on the
following pages.
575
PAY-AS-YOU-GO
STORMWATER CAPITAL PROJECTS FUND
Stormwater
Maintenance
Capital
77%
Capacity
Infrastucture
1%
Streams &
Water
Quality
22%
Distribution of Fund Budget
FY 2027 ADOPTED PAYG BUDGET SUMMARY
PROGRAM CATEGORY AMOUNT
STORMWATER MANAGEMENT
Stormwater Maintenance Capital $2,830,000
Stormwater Infrastructure Capacity Improvements 50,000
Streams and Water Quality 785,000
Total Project Cost 3,665,000
Less: Interest Income & Miscellaneous Revenues 250,000
Net Stormwater Management Fund Support $3,415,000
576
PAY-AS-YOU-GO
STORMWATER CAPITAL PROJECTS FUND
FY 2027 ADOPTED STORMWATER CAPITAL BUDGET
Stormwater Maintenance Capital $2,830,000
Much of Arlington County's stormwater infrastructure was built during the 1940's and 1950's. It is
approaching the end of its useful life, and a regular repair and replacement program is necessary to
ensure the continued functioning of the storm drainage network during storm events to prevent
flooding and property damage.
This program provides for the regular replacement of storm sewer mains, catch basins, and end walls
(with their associated outfalls). Attention will be paid to the approximate 11 miles of corrugated
metal pipes and plate arch culverts that have deteriorated more quickly than other materials.
Associated master plans include the Watershed Management Plan and the Stormwater System Plan.
Stormwater Mains rehabilitation/ replacement program ($1,000,000)
Four Mile Run Maintenance Capital program ($200,000)
Stormwater Frames and Covers ($150,000)
Manhole & Catch Basin Rehabilitation ($370,000)
Terra Cotta/ Corrugated Metal Pipe Upgrades ($925,000)
Military Road Culvert ($185,000)
Stormwater Infrastructure/ Capacity Improvements $50,000
The Storm water Infrastructure Capacity Improvements program addresses infrastructure
improvements to the stormwater sewer system. The County’s stormwater capacity system was
predominantly planned and built prior to the adoption of stormwater regulation s and standards that
more consistently and appropriately addressed the effects of increased impervious areas and risks
associated with intense rainfall events and urban flooding. Improvements are designed and executed
on watershed, localized, and parcel -based scales to 1) mitigate flood risks; 2) maintain sys tem
infrastructure in a state of good repair; 3) install tertiary system elements; 4) construct drainage
projects where under capacity; 5) develop overland relief; 6) advance climate adaptation and
resiliency goals; and 7) otherwise implement the adopted Stormwater Master Plan and underlying
studies.
Capacity project planning studies ($50,000)
Streams and Water Quality $785,000
This program addresses regulatory requirements and policy objectives to reduce stormwater
pollution, rehabilitate and restore natural infrastructure, and promote environmental recovery and
restoration in the County’s stream valleys which have been impacted by stormwater runoff from the
County’s increases in impervious surfaces.
Arlington County exceeded the five percent Bay cleanup pollution reduction requirement for the
permit cycle that ended in June 2018. The current permit cycle (ending in CY 2026) requires a
cumulative 40 percent pollution reduction, with the subsequent permit requiring the full 100 percent
reduction. Progress to date has been made through public investments in green infrastructure and
stream restoration, water quality credit from redevelopment activity regulated under the Stormwater
Management Ordinance, and programmatic efforts such as street sweeping.
577
PAY-AS-YOU-GO
STORMWATER CAPITAL PROJECTS FUND
Increased program drivers to repair eroded streams and failed stormwater outfalls that emerged
from the July 8, 2019, extreme flooding event. Also, continued increases in impervious surfaces from
land development activity (both regulated and unregulated) add to the mitigation pressures on the
program. In FY 2022, DES enhanced Land Disturbance Activity (LDA) requirements with the LDA 2.0
initiative to require further mitigation of runoff impacts related to development.
Stream Resiliency Program ($150,000)
Stream & Wetland Maintenance Capital ($235,000)
Water Quality Project Feasibility & Concept Design ($150,000)
Outfall Rehabilitation Program ($250,000)
TOTAL STORMWATER BUDGET $3,665,000
578
PAY-AS-YOU-GO
STORMWATER CAPITAL PROJECTS FUND
FY 2025 FY 2026 FY 2026 FY 2027
ACTUAL ADOPTED RE-ESTIMATE ADOPTED
ADJUSTED BALANCE, JULY 1 $2,031,589 $2,031,589 $3,212,739 $3,089,239
REVENUES:
Grants 648,392 - 1,750,000 -
Interest 249,195 250,000 250,000 250,000
TOTAL REVENUE 897,587 250,000 2,000,000 250,000
Transfers In (Out): - - - -
Transfer In from Stormwater Management Fund 7,195,000 3,910,000 5,910,000 3,415,000
TOTAL TRANSFERS IN 7,195,000 3,910,000 5,910,000 3,415,000
TOTAL BALANCE, REVENUES AND TRANSFERS IN 10,124,176 6,191,589 11,122,739 6,754,239
EXPENDITURES:
Capital Projects - Current Year 6,911,437 4,160,000 7,910,000 3,665,000
Capital Projects - Carry-Over* - - 123,500 1,479,000
TOTAL CAPITAL EXPENDITURES: 6,911,437 4,160,000 8,033,500 5,144,000
BA
LANCE, JUNE 30 $3,212,739 $2,031,589 $3,089,239 $1,610,239
STORMWATER CAPITAL PROJECTS FUND
FUND STATEMENT
*Most capital projects span multiple years, from design to construction completion. The FY 20 25
Actual and FY 2026 Re-Estimate columns reflect that funding for capital projects are carried forward
each fiscal year, and ending balances fluctuate, reflecting the carryover of these funds. The FY 2027
Adopted Budget column is presented similarly to the planned execution of projects in the fiscal year.
These are the staff’s best estimates based on preliminary plans and design, and construction
schedules.