County Board Agenda Item
Meeting of July 22, 2024
County Manager: #### #
County Attorney: *****
Staff: Karin Talley, Department of Management and Finance
ARLINGTON COUNTY, VIRGINIA
DATE: July 21, 2024
SUBJECT: Fiscal Year (FY) 2025 - FY 2034 Capital Improvement Plan Adoption
C. M. RECOMMENDATION:
1. Adopt the Fiscal Year 2025 – FY 2034 Capital Improvement Plan.
2. Adopt the attached FY 2025 County Bond Funds Appropriations Resolution
(Attachment A).
3. Adopt the revised language to the Stabilization Reserve section of the Financial &
Debt Management Policies.
4. Authorize the addition of one (1.0) full-time permanent FTE (full-time equivalent
employee) in the General Fund to support facilities planning efforts. The FTE will reside
in the General Fund and will charge their time to facilities planning studies as
appropriate.
5. Authorize the addition of one (1.0) full-time permanent FTE (full-time equivalent
employee) to support installation and maintenance of solar installations on County
facilities. The FTE will reside in the General Fund and will charge their time to solar
capital projects as appropriate.
ISSUES: This is a request for County Board consideration/adoption of the proposed FY 2025 –
FY 2034 Capital Improvement Plan and the appropriation of County bond funds.
SUMMARY: The adopted CIP provides a 10-year plan for investment in County and School
infrastructure and assets, totaling $5.2 billion. The funding sources for the CIP include federal
and state grants, bonds, pay-as-you-go (PAYG) funding, and dedicated and legally restricted
funding sources such as water-sewer revenues and transportation taxes.
BACKGROUND: The adopted CIP covers FY 2025 – FY 2034 and includes investments in
County government and Schools capital assets. The biennial 10-year CIP balances funding
availability with competing needs for investment. Given current economic and construction
market volatility, the CIP was prepared using conservative budget estimates with a primary goal
A - 21
of financial sustainability. Investments over the 10-year planning period focus on community
and County Board priorities, and County planning processes.
DISCUSSION: The table below summarizes the allocation of funds for the FY 2025 – FY 2034
Capital Improvement Plan by program area. The County and School CIPs total $5.2 billion.
Program summaries can be found on the following pages.
Capital Program Area FY 2025 – FY
2034 Proposed
FY 2025 – FY
2034 Adopted
$ Change
Arlington Neighborhoods $97,898 $97,898 -
Economic Development 2,174 2,174 -
Information Technology /
Equipment
212,616 212,616
Parks & Recreation 308,750 308,750 -
Metro 398,470 398,470 -
Government Facilities & Energy
Management
398,244 398,994 750
Regional Partnerships &
Contingencies
14,459 11,959 -2,500
Transportation 1,854,508 1,855,008 500
Subtotal County CIP $3,287,119 $3,285,869 -1,250
Water & Sewer Infrastructure 879,885 879,885 -
Stormwater Management 334,255 334,255 -
Total County CIP $4,501,259 $4,500,009 -1,250
School Capital Program* 691,060 691,060 -
Total County & School CIP $5,192,319 $5,191,069 -1,250
* Schools initial CIP included three options which ranged from $681.3 million to $696.5 million.
Changes made by the County Board between the proposed CIP and the adopted CIP include
several reallocations from the unallocated contingent of $3 million established by the Board at
the adoption of the FY 2025 operating budget. The reallocations include:
1) A replacement of Climate Action Fund (CAF) monies for the Lubber Run resiliency
project ($1.25 million) to fund the planned installation of a natural gas back-up generator.
The Proposed CIP assumed CAF funds would be allocated from the General Fund CAF
contingent to fund a portion of the Lubber Run resiliency project with the installation of a
gas generator as part of the total project cost. With the allocation of non-CAF funding to
this project, the CAF funding will remain in the General Fund (rather than the CIP) to
support other CAF qualifying projects and reduce the CIP by $1.25 million.
2) Addition of $500,000 to the Transportation Program to implement roadwork and
easements along S. Carlin Springs Road to facilitate safety improvements, with the
possibility of an additional $500,000, or in total, up to $1 million.
3) Addition of $250,000 toward the study of facility improvements to the Madison
Community Center.
4) Addition of $250,000 to study the potential for construction of adult changing facilities in
targeted public facilities.
A - 22
5) Addition of $250,000 to allow for additional resources (1.0 FTE) for the Department of
Environmental Services to manage and implement a variety of studies and work funded
in the CIP.
Arlington Neighborhoods and Economic Development investments total $100.1 million. The
Arlington Neighborhoods Program includes a total $97.9 million across the 10-year period for
investments in neighborhood beautification, street improvements, residential traffic management
park enhancements, street lighting and landscaping projects. Economic Development includes
investments of $2.2 million to perform tasks related to maintaining the County’s public art
program, public facilities maintenance, and County and School’s joint use facilities maintenance.
Information Technology and Public Safety investments cover a wide variety of technology
hardware, software, data management, and capital maintenance across all County departments
totaling $212.6 million in the adopted CIP. Funding for the County’s information technology
investments consist primarily of PAYG and Short-term financing. This funding allows for new
features such as Constituent Digital Services, Constituent Single Sign-On, and continued
upgrades and enhancements to applications including the Revenue Collection System and
Human Resource and Finance System. Funds are primarily used for the replacement and/or
refreshment of County assets including network equipment, servers, workforce devices such as
PCs and laptops, conference and courtroom equipment, Connect Arlington and funds for Data
Center Consolidation. The adopted CIP also reinvests in public safety technology and equipment
-- including equipment replacement in the County Courthouse and Detention Center as well as
investments in public safety radios, Emergency Call Center (ECC) equipment, mobile data
computers, and Fire/Police/Sheriff records management systems.
Local Parks and Recreation program investments include $308.8 million in funding for park
trail and bridge modernization, parks capital maintenance, synthetic turf replacements and parks
master plans. Projects included in the adopted CIP are in alignment with the adopted Public
Spaces Master Plan. The CIP continues the park trail and bridge modernization program,
including construction for replacement of pedestrian bridges at Alcova Heights Park, Bluemont
Park and Rock Springs Park, trail milling and paving, and a trail pavement condition assessment
study. Park capital maintenance projects include refreshment of the Public Spaces Master Plan,
design for replacement of the Arlington Hall West Playground, construction of the Doctor’s Run
Playground replacement and pooled park project improvements at several existing parks.
Funding is also included for the FY 2025 and FY 2026 replacement of the existing synthetic turf
at Greenbrier Park/Yorktown stadium field, Long Bridge Park Field #3, Thomas Jefferson
Middle School Lower Field, and the grass to synthetic turf field conversions at Kenmore Middle
School.
The CIP also includes master plan program funds for Arlington Boathouse, Rosslyn Gateway
Park, Drew Park, Jennie Dean Park Phase 2, Penrose Square Phase 2, Quincy Park, Shirlington
Park, Short Bridge Park, Three Urban Parks, New Park at 26th Street N. and Old Dominion Dr.,
Virginia Highlands Park and Nearby Public Spaces, Crystal City Parks and Public Space, Fairfax
Drive Public Spaces, the Emerging Uses Program (pickleball), and the Natural Resiliency
Program.
A - 23
Metro includes $398.5 million for our required Metro contribution which is in line with the
expenditures projected in the previous CIP.
Public and Government Facilities & Energy Management includes investments of $399
million. Highlights include capital maintenance of our 89 owned buildings to maintain them in a
state of good repair (roof replacements; heating, ventilation, air conditioning (HVAC) upgrades),
increasing our electrical energy commitments within County buildings to include solar ready,
electric vehicle (EV) charging, equipment replacements and energy resilience. The CIP also
includes renovations to the 29-year-old Courts/Police building to include upgrades to
courtrooms, addressing space inefficiencies, as well as technology backbone infrastructure
improvements. It provides for a comprehensive study of the nearly three-decade old Detention
Center and placeholder implementation of recommendations from that study. This CIP
continues critical Fire Department investments, including funding for a new fire station on the
west end of Columbia Pike. Other facility highlights include Crystal City and Columbia Pike
Libraries, Courthouse Complex Renovations and Infrastructure, the consolidation of the
Situational Awareness Intelligence Unit, EOC and Department of Public Safety Communications
and Emergency Management as well as planning studies for the Lee and Madison Community
Centers, and facility condition assessments to provide projected replacement timelines and
estimated replacement costs.
Transportation funding totals $1,855 million including a number of significant investments for
bridge renovation, the Columbia Pike Multi-Modal program, Crystal City, Pentagon City and
Potomac Yards Streets program, Metro station entrances, ART facilities, Columbia Pike transit
facilities, and numerous other safety and accessibility projects throughout the County. The CIP
continues the County’s commitment to developing and managing a multimodal transportation
system that expands travel choices, provides equal access to all users, and supports community
sustainability goals. This CIP also reflects ongoing support for the implementation of the Vision
Zero Action Plan with the goal of eliminating all critical injury crashes in the public right-of-way
by 2030. It further ensures maintenance of the County’s transportation infrastructure in a state of
good repair. To this end, it includes $143.9 million for paving to maintain the targeted paving
condition index (PCI) of 75 – 80, as well as $11.9 million to fund proactive maintenance of
sidewalks, curbs, and gutters. The goals of the Transportation Master Plan are considered in the
projects that are funded in this adopted CIP.
Water and Sewer Infrastructure includes $879.9 million with an emphasis on maintenance
capital, wastewater treatment improvements, and drinking water redundancy and resiliency
projects. The CIP includes $388.0 million for water-sewer maintenance capital, $169.0 million
for water distribution, $3.4 million in sanitary sewer improvements, and $319.5 million to Water
Pollution Control Plant improvements. This program maintains a state of good repair for close to
1,000 miles of water and sanitary sewer lines across the county. The Water Distribution Master
Plan, Sanitary Master Plan, and Water Pollution Control Plant Solids Master Plan guide and
prioritize the projects included in the adopted CIP.
Stormwater Management includes $334.4 million for capacity improvements, stream and water
quality projects and maintenance capital. The CIP includes $242.2 million for capacity
improvements, $41.2 million for water quality projects, and $50.9 million for a variety of
A - 24
maintenance capital projects. The program reflects the effort required to enhance and update the
County’s stormwater infrastructure to manage urgent needs and long-term resilience, driven
primarily by watershed scale projects to minimize the risk of flooding. Over $191 million is
being invested in four critical watersheds throughout the county which include Spout Run,
Crossman Run, Lubber Run, and Torreyson Run. The CIP also includes water quality projects to
reduce pollutants in adherence to the Virginia Department of Environmental Quality’s (DEQ)
Municipal Separate Storm Sewer System (MS4) Permit and the Chesapeake Bay Total
Maximum Daily Loads (TMDL).
Arlington Public Schools adopted its FY 2025 – FY 2034 CIP on June 20, 2024. The Schools’
CIP totals $691.06 million, including $84.0 million of general obligation bonds. The Schools’
10-year plan includes funding for kitchen improvements, entrance and vestibule renovations,
security improvements, moving the Montessori program to the Career Center and synthetic turf
field conversion at Kenmore Middle School.
County Bond Funds Appropriations: Since a portion of the FY 2025 appropriation is for bond
funded projects to be approved on the November 5, 2024 Referenda, appropriation of those
projects is requested now but is contingent upon and will not occur until the respective
referendum for each project is approved by voters, has been filed with the Circuit Court, and the
required 30-day contest period has expired. All project expenditures being appropriated as
FY 2025 bond funds are as planned in the FY 2025 – FY 2034 CIP and are consistent with the
debt projections included in the CIP.
Change to Financial Policy – Stabilization Reserve: The minimum amount for the Stabilization
Reserve has been increased from 1.0 percent to 1.3 percent of the General Fund Budget based on
action taken by the County Board at the adoption of the FY 2025 Operating Budget.
PUBLIC ENGAGEMENT: In the early phases of CIP engagement in March and early April,
almost 3,200 people participated, with 2,686 of those being online. Eleven pop-up engagements
were held around the County; this form of engagement helped reach a diverse population.
In addition to online responses and feedback received at pop-ups, program specific information
was discussed at Board work sessions on June 6, June 11 and June 25; a joint worksession with
the County/School Board on June 4; a Planning Commission meeting on June 3 as well as other
commissions (Park and Recreation Commission, Sports Commission, Forestry and Natural
Resources Commission, Fiscal Affairs Advisory Commission, Economic Development
Commission and the Transportation Commission); and finally, a CIP public hearing held on
July 10.
FISCAL IMPACT: Should the CIP be adopted, the annual debt service included in both the
Schools’ Adopted CIP and the County’s CIP remains in compliance with the County Board’s
limitations on debt issuance and debt service as outlined in the Financial and Debt Management
Policies. The planned issuance of new debt, combined with previously issued debt, maintains
debt and debt service levels necessary for the County’s triple-AAA bond ratings. Debt service in
FY 2025 is consistent with the amounts budgeted in the County and APS’ Adopted FY 2025
A - 25
operating budgets, with moderate growth in annual debt service projected in future fiscal years to
support the planned issuance of new bonds over the 10-year planning horizon.
A - 26
Attachment A
FISCAL YEAR 2025 COUNTY APPROPRIATIONS RESOLUTION
Be it resolved by the County Board of Arlington County, Virginia, that the following
appropriations of $129,795,000 are hereby made for the Fiscal Year 2025 for Authorized But
Unissued Bonds; Be it further resolved that the following appropriations of $129,795,000 will
be made only upon approval by voters at the November 5, 2024 ballot and after results have
been certified and filed with the Circuit Court and the required thirty day period for contesting
each bond referendum has expired:
COUNTY BOND FUNDS:
Authorized But
Unissued Bonds
2024
Referenda1 Total
Appropriation Appropriation Appropriation
Street and Highway Bond
Fund (314) - 13,540,000 13,540,000
Neighborhood Conservation
Bond Fund (316) - 0 0
Government Facility Bond
Fund (317) 10,300,000 27,855,000 38,155,000
Public Recreation Bond Fund
(324) - 7,480,000 7,480,000
Metro Bond Fund (333) - 21,800,000 21,800,000
TOTAL COUNTY BOND
FUNDS APPROPRIATIONS: $10,300,000 $70,675,000 $80,975,000
STORMWATER BOND
FUND APPROPRIATIONS: 21,780,000 - $21,780,000
UTILITY BOND FUNDS:
Water Bond Fund (525) 23,640,000 3,400,000 $27,040,000
Sanitary Sewer Bond (528) - - $0
AWT Plant Bond (530) - - $0
TOTAL UTILITY BOND
FUNDS APPROPRIATIONS: $23,640,000 $3,400,000 $27,040,000
TOTAL APPROPRIATIONS
FOR COUNTY $55,720,000 $74,075,000 $129,795,000
1 2024 Referenda will be appropriated upon approval by voters at the November 5, 2024 ballot and after results have
been certified and filed with the Circuit Court and the required thirty day period for contesting the bonds has expired.
A - 27