FY 2025 - FY 2034 PROPOSED CIP
County Manager’sProposed Capital Improvement Plan (CIP)FY 2025 – FY 2034Presentation to County Board/School BoardJune 4, 2024
FY 2025 - FY 2034 PROPOSED CIP
2
FY 2025 - FY 2034 PROPOSED CIP
Transportation & Roads
Public Government Facilities
Parks and Recreation
Technology & Public Safety
Maintenance Capital
Arlington Neighborhoods Program
Stormwater Management
Metro
Capital Plan for FY 2025-FY 2034: $4.5B
3FY 2025 - FY 2034 PROPOSED CIP
Measured approachMindful of impacts of debt service on operating budget, uncertain external pressures (e.g. inflation / interest rates)Maintaining County’s Current Asset Inventorye.g., facilities, trails and bridges, technology systems, and roofs
Meet Regional, Legal, and Regulatory Obligationse.g., MetroResponding to Emerging Service Demands
Addressing Environment & ResiliencyPlanning for the Future
Guiding Principles
4FY 2025 - FY 2034 PROPOSED CIP
Economic trendsMajor Assumptions & Risks
Construction inflation –assuming 4%Interest rates on bonds –assuming 5.0%
Regulatory changesUnanticipated events that require capital investment
5FY 2025 - FY 2034 PROPOSED CIP
Focus on resiliency across many sectors•Situational Awareness Intelligence Unit•Water supply redundancy•Resilience hub at Lubber Run
Major Changes Since Last CIPBarcroft investment on County balance sheet: $120 million outstanding
Response to mental health & substance use•Potential partnership with VHC on S. Carlin Springs
6FY 2025 - FY 2034 PROPOSED CIP
Major Changes Since Last CIPResponse to remote workforce•Evaluation of Courthouse area buildings for further consolidation of spaceImplementation of recently adopted plans•Plan Langston Boulevard –Lee Center, transportation improvements•Transit Strategic Plan
Transportation program trade-offs•Commercial real estate tax outlook•Project complexity & inflation
Additional investments in water-sewer infrastructure and resiliency
Project Timeline Changes
7FY 2025 - FY 2034 PROPOSED CIP
TEN-YEAR GROWTHCounty: 4.5%APS: 2.4%County/APS: 3.6%FY 2034FY 2033FY 2032FY 2031FY 2030FY 2029FY 2028FY 2027FY 2026FY 2025(in thousands)COUNTY126,273127,459124,005117,631112,060105,09799,36794,76490,07085,323Debt Service(1,186)3,4546,3745,5716,9645,7294,6034,6944,889Annual Inc / (Dec) $-0.9%2.8%5.4%5.0%6.6%5.8%4.9%5.2%5.7%Annual Inc / (Dec) %SCHOOLS81,90784,54583,81282,15680,15977,53274,86572,12469,77267,292Debt Service(2,638)7331,6561,9972,6272,6672,7412,3522,565Annual Inc / (Dec) $-3.1%0.9%2.0%2.5%3.4%3.6%3.8%3.4%3.8%Annual Inc / (Dec) %AHIF – BARCROFT10,25910,29710,34410,37910,42410,45910,49510,7307,2007,200Debt Service(38)(47)(35)(45)(35)(36)(235)3,530-Annual Inc / (Dec) $-0.4%-0.5%-0.3%-0.4%-0.3%-0.3%-2.2%49.0%0.0%Annual Inc / (Dec) %
Growth in debt service should be sustainable and consistent with the projected growth of revenues. Debt service growth over the ten-year projection should not exceed the average ten-year historical revenue growth. Annual Debt Service IncreasesConsistent with Debt Policies but Still Significant
Ten Year Revenue Growth 2013-20234.4%
8FY 2025 - FY 2034 PROPOSED CIP
Existing Debt Service & Major Projects Financed
58,463 56,694 55,368 51,610 52,099 51,145 49,685 46,972 42,501 36,411 22,024 21,334 20,644 19,693 17,241 16,259 15,168 14,103 13,062 12,306 4,952 10,368 14,867 22,090 27,710 34,543 40,534 48,626 55,426 58,932 1,505 3,440 5,650 7,735 9,807 11,862 13,995 16,074 18,213 20,358
- 20,000 40,000 60,000 80,000 100,000 120,000 140,000
FY2025 FY2026 FY2027 FY2028 FY2029 FY2030 FY2031 FY2032 FY2033 FY2034THOUSANDS
EXISTING VS NEW GENERAL FUND DEBT SERVICE
Existing CountyExisting MetroNew CountyNew Metro
Major Projects in Existing DebtWMATA ($317MM)Fire Stations 3 & 8 ($25MM)Long Bridge Aquatics & Fitness Center ($42MM)Lubber Run Community Center ($47MM)Arlington Mill Community Center ($30MM)North Quincy Site Acquisition ($27MM)2020 14thStreet North Acquisition ($20MM)Head Start / 2920 S Glebe Road ($11MM)Trades Center ($17MM)TJ Parking Deck ($12MM)
9
FY 2025 - FY 2034 PROPOSED CIP
8.8%9.0%9.3%9.4%9.5%9.7%9.8%9.8%9.7%9.3%
0.0%1.0%2.0%3.0%4.0%5.0%6.0%7.0%8.0%9.0%10.0%11.0%
FY25 FY26 FY27 FY28 FY29 FY30 FY31 FY32 FY33 FY34
1. Debt Service as % of General Government ExpendituresNOT TO EXCEED 10%
*Includes APS debt per “MPSA Option 2” on page 34 of the Superintendent’s Proposed CIP presentation on May 16, 2024
Adhering to Debt Policies
10
FY 2025 - FY 2034 PROPOSED CIP
Asset Base and DebtTotal% ShareCounty% ShareAPSAPS Referenda Totals$1,601.2 53.3%$852.8 46.7%$748.4 2008-2022$1,481.0 56.2%$832.0 43.8%$649.0 2010-2022$1,404.8 55.1%$773.9 44.9%$630.9 2012-2022$1,251.3 53.0%$663.1 47.0%$588.3 2014-2022$1,032.3 53.3%$549.8 46.7%$482.5 2016-2022$716.6 52.0%$372.9 48.0%$343.7 2018-2022$472.7 49.1%$232.0 50.9%$240.7 2020-2022
35% 35%35%35%35%36%36%35%34%34%65% 65%65%65%65%64%64%65%66%66%0%20%40%60%80%100%120%
FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023
County / APS Asset Base
APS % of Asset BaseCounty % of Asset Base($’s in millions)Final Copy ACFR 12-15-2023 (arlingtonva.us)(Government, Fiscal Year 2023)
11FY 2025 - FY 2034 PROPOSED CIP
Total County ($174.4M)Community Infrastructure $76.2MLocal Parks & Recreation $25.8MMetro and Transportation $72.4M
UtilitiesUtilities $14.2 million
Proposed County Government 2024 Bond Referenda
2024 Referenda primarily funds projects in FY 2025 and FY 2026
12FY 2025 - FY 2034 PROPOSED CIP
Environmental Compliance & Innovation •Stormwater stream & water quality•Water Pollution Control Plant investmentsResiliency•Stormwater infrastructure capacity•Natural resiliency in our parks•Lubber Run Resiliency Hub
Vehicle Charging•Infrastructure for County and public useFacility Energy Updates•Energy Performance & renewable energy assessments•Solar on County facilitiesTransit Investments •Fleet replacement•ART operations and maintenance•Street lightingInvestments in FY 2025-2034 CIP
Advancing our Environmental & Resiliency Goals
13FY 2025 - FY 2034 PROPOSED CIP
Information Technology•Constituent Single Sign On•DHS Centralized Customer Service & Case Management•Police Computer Forensic Equipment•Specialized Fire Equipment•Police Traffic Equipment VehicleTransportation•ART Fleet Transition to Zero Emission Bus•MicroTransit Implementation Plan
Facilities•Crystal City Library•Lee Community Center•Situational Awareness Intelligence Unit•Carlin Springs Site•Lubber Run Resiliency HubParks & Recreation•Drew Park•New Park at 26thSt. N & Old Dominion Drive•Athletic Courts Program•Langston Boulevard Public Space Improvements
Major New Projects in the CIP
14FY 2025 - FY 2034 PROPOSED CIP
•UTILITIES FUND: $879.9 MILLION•Water-Sewer Maintenance ($388.0 million)•Water Distribution ($169.0 million)•Sanitary Sewer Improvements ($3.4 million)•Water Pollution Control Plant ($319.5 million)•STORMWATER FUND: $334.3 MILLION•Streams and Water Quality ($41.2 million)•Maintenance Capital ($50.9 million)•Capacity Improvements ($242.2 million)•ARLINGTON NEIGHBORHOODS PROGRAM: $97.9 MILLION•METRO: $398.5 MILLION
Program Summary
15
FY 2025 - FY 2034 PROPOSED CIP
1,058Lane-miles of County maintained and managed roads78ART buses990Bus stops>330 Bus shelters1Transitway1Bus station11Metrorail stationsCapital Bikeshare:110stations802bicyclesShared Micro-Mobility:1,800scooters355eBikes36County-maintained vehicular and pedestrian bridges729Multi-space parking meters679 Single space meters302 Signalized intersections300CCTV cameras24 Permanent traffic count stations1 Virginia Railway Express station190Uninterruptible power supply units31Speed indicator signs7Variable message signs87School zone flashers97Pedestrian flashing beacons8,614County-owned streetlights52,709Street signs
Transportation - $1.9 Billion
16
FY 2025 - FY 2034 PROPOSED CIP
147 Parks totaling 942 acres; 126 acres of Natural Resource Conservation areas
82 Playgrounds and 6 Spray Playgrounds
76 Basketball Courts and 12 Half Courts
90 Tennis Courts, 11 Pickleball Multi-Use Courts and 5 Practice Courts
54 Rectangular Athletic Fields -- 15 Lighted, 15 synthetic
43 Diamond Athletic Fields -- 19 Lighted, 2 synthetic
19 Combination Athletic Fields -- 3 Lighted
7 Community Gardens
48 Picnic Shelters
9 Dog Parks
55 Miles of Multi-use Trails (35 paved / 20 natural)
70 Bridges and Low-Water Fords
25 Restroom Structures
Picnic Tables, Benches, Grills, Kiosks, Drinking Fountains, Park Signs, Fences
250k+ trees in parks, 69% canopy cover (as of 2016 study)
Amphitheater, Skate Park, Other Amenities
Parks and Recreation - $308.8 million
17
FY 2025 - FY 2034 PROPOSED CIP
Arlington Economic DevelopmentAge: 17 - 114 years91,276 ft2
3 CSI NOC SitesAge: 14 - 36years18,290ft2
8 Fire DepartmentAge: 0 - 68 years219,155 ft2
15
Human ServicesAge: 0 - 67 years370,182 ft2
12LibrariesAge: 15 - 65years153,089ft2
6 Operations Age: 17 - 74 years621,110 ft2
15
Parks and Recreation Age: 4 - 239 years434,839 ft2
18Public SafetyAge: 17 - 72 years703,357 ft2
7 Transit Age: 7 - 65 yrs100,655 ft2
7
County-owned buildings in service (2.3 million ft2)2 vacancies (7,510 ft2)
Leased Offices(0.5 million ft2)
4
89Public/Government Facilities - $398.2 million
18
FY 2025 - FY 2034 PROPOSED CIPDesktop PCsDesktops: 9464 Year LifecycleRolling ReplacementLaptop PCsLaptops: 2,6953.5 Year LifecycleRolling ReplacementFiber Optic Cables70+ MilesRefresh/Replace As NeededServers: 40Hosts: 317 Year LifecycleRefresh = Rolling by End-of-Life
Core Network Equipment Core Switches: 25 Year LifecycleDistribution Network(Hub-Sites) Switches: 175 Year LifecycleAccess Network(In-Building) Switches: 1655 Year Lifecycle Wi-FiWAPs: 9833-5 Year LifecycleRefreshes 20% each yearUPS Power SystemsUPS: 1375 Year LifecycleData CenterInfrastructure Switches: 835 Year Lifecycle
ApplicationsEnterprise: 136Dept/Agency: 317Refresh = RollingBy End-of-Life
Technology - $212.6 million
19FY 2025 - FY 2034 PROPOSED CIP
•FY 2025 / FY 2026oFire Station 8, new ART O&M facility ($500k - $1.0 million)•FY 2026/2027oLong Bridge operating costs due to full utilization of Boeing donation ($2.5 million)•Out-yearsoNew library on Columbia Pike (incremental staffing or facility costs based on size and programming)oNew library in Crystal City ($750k+: new incremental staff and non-personnel resources required)oNew fire station on Columbia Pike ($4 million- $6 million)
Impact of Proposed CIP on Future Operating Budget
20
FY 2025 - FY 2034 PROPOSED CIP
Alignment in County and APS CIPs
SYNTHETIC TURF REPLACEMENTS
CONVERSION OF KENMORE MIDDLE SCHOOL FIELDS TO SYNTHETIC TURF AND REPLACEMENT OF LIGHTING
TRADES CENTER PLANNING STUDIES
21
FY 2025 - FY 2034 PROPOSED CIP
Proposed CIP presented to County Board
Board Work SessionsJune 4: Joint School Board County Board Work SessionJune 6: Transportation, Debt, MetroJune 11: Government Facilities, Parks and Recreation, Arlington Neighborhood ProgramJune 25: Public Safety, Technology, Stormwater, UtilitiesJuly 10: Public Hearing
Public Hearing
Final Board Mark-Up
Board AdoptionMay 28May-JulyJuly 10July 16July 20
FY 2025 - FY 2034 CIP Timeline
Aug. 16Nov. 5Election Day
Deadline for Filing with the Circuit Court
22
FY 2025 - FY 2034 PROPOSED CIP
County Manager’sProposed Capital Improvement Plan (CIP)FY 2025 – FY 2034Presentation to County Board/School BoardJune 4, 2024