All Arlington Public Schools (APS) budget and operations decisions are based on the best information available at the time. Staff and community members are reminded that funding forecasts from Arlington County and the state may change, based
on many external factors. Similarly, student enrollment and projections are based on the best available information, but are also subject to change due to employment, housing and other economic factors. For these reasons, APS and the Arlington
School Board may adjust future budget allocations, staffing and other operations decisions to reflect the existing community and operating landscape.
Arlington Public
Schools/Arlington County
Proposed FY 2025-34 Capital
Improvement Plan (CIP)
Joint APS School Board and Arlington County Board
Work Session
June 4, 2024
2
• Welcome and Introductions
• County Manager's Proposed FY2025-34 CIP
• Superintendent's Proposed FY2025-34 CIP
• Questions and Discussion
All Arlington Public Schools (APS) budget and operations decisions are based on the best information available at the time. Staff and community members are reminded that funding forecasts from Arlington County and the state may change, based
on many external factors. Similarly, student enrollment and projections are based on the best available information, but are also subject to change due to employment, housing and other economic factors. For these reasons, APS and the Arlington
School Board may adjust future budget allocations, staffing and other operations decisions to reflect the existing community and operating landscape.
Agenda
Superintendent’s Proposed FY 2025-34 CIP
3
Superintendent’s CIP Goals
Align with APS’ Strategic Plan, Mission, Vision, and Core Values,
and the School Board CIP direction on December 14, 2023. *
Support
• Continued investment to improve and upgrade our major infrastructure,
• Continued investment in ongoing projects,
• Investment in new projects, and
• Investments with Arlington County on joint initiatives and projects.
* Per Arlington Public Schools Policy Implementation Procedure F-1 PIP-1 Capital Improvement Plan.
4
FY 2025-34 CIP Projects
CONTINUED INVESTMENTS IN PROJECTS FROM FY 2023-32 CIP
SB CIP
DIRECTION
SUPERINTENDENT’S
CIP GOALS
SUPERINTENDENT’S PROPOSED
FY 2025-34 CIP
CIP PROJECT TYPE
• Major Infrastructure Infrastructure
• Kitchen & Security Vestibule Renovations,
• Enterprise Resource Planning (ERP) System
Modernization,
• The Heights, Phase II, and
• The Career Center Campus Project
Ongoing
No • Public Address System Infrastructure
• Synthetic Turf Projects APS and County Joint
Initiatives
5
FY 2025-34 CIP Projects
PROPOSED NEW PROJECTS FOR FY 2025-34 CIP
SB CIP
DIRECTION
SUPERINTENDENT’S
CIP GOALS
SUPERINTENDENT’S PROPOSED
FY 2025-34 CIP
CIP PROJECT TYPE
• Major Infrastructure Infrastructure
• Feasibility studies for 3 – 5 facilities based on the
Long-Range Plan to Renovate Existing Facilities’
Methodology
New
• Relocate MPSA into the legacy Career Center building
with options for three different price points not to
exceed $45M
• Demolish current MPSA facility after relocation and
complete campus with green space
New
• Synthetic Turf Projects
• Trades Center Optimization
APS and County Joint
Initiatives
6
Project Funding and Timeline
5
Allocation of Funds
6
Debt Service Schedule for 10-Year CIP
Fiscal Total Difference Annual Debt Total Budget Debt Service as %
Year Debt from Prior Year Service Growth Expenditures of General Expenses
FY2025 $ 67,207,104 $ 2,557,665 3.96% $826,191,956 8.13%
FY2026 $ 68,822,618 $ 1,615,515 2.40% $846,846,755 8.13%
FY2027 $ 71,521,910 $ 2,699,292 3.92% $868,017,924 8.24%
FY2028 $ 74,595,134 $ 3,073,224 4.30% $889,718,372 8.38%
FY2029 $ 77,279,363 $ 2,684,230 3.60% $911,961,331 8.47%
FY2030 $ 79,824,075 $ 2,544,712 3.29% $934,760,364 8.54%
FY2031 $ 82,243,374 $ 2,419,299 3.03% $958,129,374 8.58%
FY2032 $ 83,702,073 $ 1,458,699 1.77% $982,082,608 8.52%
FY2033 $ 84,147,752 $ 445,679 0.53% $1,006,634,673 8.36%
FY2034 $ 81,637,083 $ (2,510,669) -2.98% $1,031,800,540 7.91%
FY2035 $ 80,687,073 $ (950,010) -1.16% $1,057,595,553 7.63%
FY2036 $ 76,664,718 $ (4,022,356) -4.99% $1,084,035,442 7.07%
FY2037 $ 72,584,333 $ (4,080,385) -5.32% $1,111,136,328 6.53%
FY2038 $ 66,483,065 $ (6,101,268) -8.41% $1,138,914,737 5.84%
FY 2023–32 CIP includes
funds for ACC Project with
capacity for 1,619 students
• Fall, 2026 – new GHC completed
• April 2027 – parking structure
and field completed
20
Available for
Redevelopmentas
Open Space
(Existing MPSA)
New Grace Hopper Center
Future
Use
MPSA
(Existing
ACC)
New
Field
Garage
S Highland St
S Walter Reed Dr
Long-Term Use of the Career Center Campus
7
Grace Hopper Center Project: Key Milestones and Timeline
Approvals Needed:
• Building permit
• Civil Engineering Plan (CEP)
• Land Disturbance Permit (LDA)
Schedule:
• June 2024: Contractor receives Administrative Notice to Proceed (NTP).
• Upon receipt of county approvals: Contractor mobilizes to the site and
begins construction.
• June 2026: Substantial Completion of Phase 1 (The new building).
• July 2026: Move equipment and staff boxes.
• August 2026: Staff setup.
• August 2026: Students arrive on campus.
• Spring 2027: Completion of Phase 2 (Parking structure).
• December 2027: Completion of Phase 3 (Fields and sitework).
8
11
Educational Specification: 625 students
• Proposes a “medium” level of renovation to accommodate the MPSA
program.
• Proposes removing the existing mezzanine structure that extends the length of
the building in the east-west direction, allowing adjacent classrooms access to
natural light.
• Includes a full-sized gymnasium addition and utilizes the old TV studio as a
stage adjacent to the gym.
• Utilizes some of the existing ACC classrooms, therefore the classroom sizes vary,
with five classrooms would not having access to natural light.
• Recently renovated spaces remain available forfuture use and can
accommodate an additional150 students.
MPSA Relocation to Legacy Career Center Building
Option # 2 Recommended
MPSA Relocation- Option #2: Recommended
12
N
County
Library
Community Partnership Opportunities
• Arlington County Library will remain on the campus for a minimum 5-6 years.
• This presence will provide additional access to library media resources and community
programs.
• Renovated spaces on the second floor will offer additional instructional space during
school hours.
• The County Library will have the flexibility to use these spaces during non-school hours.
Facility Conditions
• Summary of Findings
• The consulting team evaluated 41 buildings comprising over 5 million gross square feet. We found that
the overall facility condition index (FCI) of the overall portfolio was 0.129 (on a scale of 0.0 to 1.00, 0
being best), which is considered an indicator of “good” overall facility condition.
• In the overall portfolio of 41 buildings; 32 buildings were reported to be in “Good” condition; 8
buildings in “Fair” condition; 1 building in “Poor” condition mainly due to the condition of the roof
which is being addressed in the proposed CIP .
• “Good” reflects the best possible rating category for FCI and generally indicates that facilities across the
Arlington Public Schools system are in good condition.
• The FCI provides consistency for relative comparisons of condition and prioritizing capital expenditures
among facilities, as well as important considerations in developing a long-term maintenance, repair,
and renewal funding strategy for facilities.
• The near-term system replacements and project-based near-term needs (Local Projects) are often
referred to as deferred maintenance or DM.
PROJECT CATEGORIES AND CAPITAL INVESTMENT STRATEGIES
Local Projects
Major
Infrastructure
Deep Dive
• Capital Needs < $500,000
• Schedule – Over a fiscal year;
analogous to MC/MM
• Disruption –
Minimal/Localized
• Capital Needs < $500,000 -
$15,000,000
• Schedule – 1 to 3 years
• Disruption – Medium, major
disruptions planned over
summer/winter breaks
• Capital Needs > $15,000,000
• Schedule – 3 to 5 years
• Disruption – Major, possible
phasing required
Major Infrastructure Projects Site Determination
• Utilizing the Long-Range Plan
• Prioritize projects based on FCI score, systems’ remaining useful life (RUL), infrastructure
type. Facilities are not listed in any order of importance.
Facility Site/Project FCIAD FCIDM Facilities with greater number of RULs of 4 years or less and will have greater FCI
scores
Hoffman-Boston
HVAC Replacement*
0.164 0.200 Built-up Roof RUL=2; gas water heater RUL=3; heating system RUL=2; HVAC controls
RUL=2; comm, alarm, tele wiring RUL=2
Dorothy Hamm
Roof and HVAC
Joint Replacement
0.149 0.048 Built-up Roof: RUL = 2; Standard Wall Finishes: RUL=3; Emergency Generator: RUL=7;
Elevator: RUL=7; HVAC Controls RUL = 9;
Oakridge HVAC
Replacement
0.176 0.247 Wall, floor and ceiling finishes RUL=3; Central Plant RUL=3; HVAC controls RUL=2;
comm, alarm, tele wiring RUL=2
Williamsburg Roof
Replacement*
0.190 0.342 Built-up Roof RUL=2; wall, floor and ceiling finishes RUL=3; HVAC controls RUL=2;
Heating System RUL=2
Jamestown HVAC and
Roof Replacement*
0.279 0.198 Built-up Roof RUL=2; ceiling finishes RUL=2; gas water heater RUL=2; Chiller RUL=3;
HVAC controls RUL=2; comm, alarm, tele wiring RUL=2
*Possible adds from long range - roof, HVAC controls, waterheater, communications wiring, etc.
How School Sites were Determined for Proposed Feasibility Studies
• Highest priority based on classroom instructional spaces at sites:
• Identify schools with the greatest number of classrooms and the highest percentage of classrooms rated
"red" (does not meet standards).
• Review the identified schools to determine those with the fewest classrooms rated "green"
(meets standards).
• Evaluation of other educational space deficiencies
• Special education instructional spaces.
• Music and performing arts spaces.
• Operable windows.
• Review safety/security characteristics for the schools.
• Review common space deficiencies for schools identified with the highest educational space deficiencies.
• Characteristics not considered:
• Playgrounds are addressed under separate construction projects.
• Characteristics where all or the majority of facilities meet standards.
• For the schools identified:
• Review the FCIAD and FCIDM scores.
• Review capital investments in the past 20 years for the 3 – 5 schools.
18
• Schools Identified
− Thomas Jefferson Middle School
− Taylor Elementary School
− Barrett Elementary School
− Swanson Middle School
− Randolph Elementary School
Proposed Feasibility Studies Sites
Barrett Elementary
Thomas Jefferson MS
Taylor ES
How School Sites were Determined for Proposed Feasibility Studies
Facility
Site*
Educational
Spaces
< 5 Green
> 10 Red
Educational
Spaces
< 5 Green
> 15 Yellow
Educational
Spaces
> 15 Yellow
> 10 Red
Classrooms
Do Not Meet
Standards
FCIAD FCIDM
Common
Spaces
Review
> 2 Red
Capital Improvements in last 20 years
Thomas
Jefferson
28,25 25 0.153 0.158 3
Taylor 3,16 16 0.148 0.043 Roof & HVAC
Barrett 1,12 12 0.113 0.026 3 Roof & HVAC
Swanson 14 0.231 0.154
Randolph 4,7 4,7 7,7 7 0.146 0.06 Roof & HVAC
Based on ed space deficiencies overlayed with FCI assessment and Building Characteristics. Includes review of safety per SB CIP direction in December 2023
*Sites may be studied in any order.
Feasibility Studies Timeline
• Estimated feasibility study costs
− $2.5M for 3 schools / $3.2M for 4 schools / $4.M for 5 schools
• Time frame for studies will vary depending on complexity
− 10-12 months per facility / 2-3 months for estimate and reconciliation
• Feasibility study costs include
− Detailed site surveys.
− Three options and associated costs for required work and phasing to accomplish
the work.
1. Renovate
2. Addition and Renovation
3. Full building replacement with a new building.
− Two independent project cost estimates, including soft costs per building option.
Feasibility Studies Timeline - Breakdown
• Procure consultants to conduct the study
− Determine scope, solicit and accept proposals: 1-2 Months
• Study
− Evaluate existing conditions, review existing documents, undertake site
surveys, determine capacity & educational specifications with academics and
School Board: 2-3 months
− Develop and evaluate the options, with phasing plans (swing space): 5-7
months
• Cost estimating
• Two independent project cost estimates, including soft costs and phasing
costs per building option: 2-3 months for estimate and reconciliation
22
Joint Initiatives with Arlington County
Trade Center Optimization
• Plan for full electrification of APS
school buses, APS white fleet, and
County fleet.
• Improve efficiency of operations at
shared County and APS site that
supports 8 distinct trade center
programs and operations.
• Improve site safety.
• Provide adequate parking for staff.
13
23
Joint Initiatives with Arlington County
Trade Center Optimization Cost Matrix
Design
Options Square Footage
Bus
Parking
Spaces
Bus Spaces
with
Charging
White Fleet
Parking
Spaces
Staff
Parking
Spaces
Phasing
Concept
Total Project
Cost (In
Millions)
Option A
300,600 (New Garage)
67,200 (Renovate
Existing Building)
185 up to 126 85 101
Can phase building renovation and
new garage construction. Facility
staff can stay on site.
$289.5
Option B 264,000f (New Garage)
60,000 (New Building) 180 up to 180 112 131
Can phase new building
construction and new garage
construction. Facility staff can stay
on site.
$319.2
Option D
345,000 (New Garage) +
67,200 (Renovate
Existing Building)
174 up to 163 114 150
Garage can be built in 2 phases. Can
phase building renovation. Facility
staff can stay onsite.
$348.2
Option E 301,732 (Garage +New
Building) 159 up to 136 117 222
All facility staff would need to be located
offsite during construction. No Phasing:
Building and garage must be built
together. Possibility for shorter off-site
timeline vs the phased options.
$353.1
Option F 265,00 (Garage + New
Building) 171 up to 148 112 148
All facility staff would need to be
located offsite during phase 1
construction. Building and garage
can be phased separately.
$341.4
Target Level: Yellow =
75% - 99%
Desired Parking Count
Bus Fleet: *180 White
Fleet: 112
Staff Parking: 250
* Includes 60 Spare
spaces
Target Level: Green =
100%
Target Level: Orange =
Below 75%
Questions & Discussion
1
All Arlington Public Schools (APS) budget and operations decisions are based on the best information available at the time. Staff and community members are reminded that funding forecasts from Arlington County and the state may change, based
on many external factors. Similarly, student enrollment and projections are based on the best available information, but are also subject to change due to employment, housing and other economic factors. For these reasons, APS and the Arlington
School Board may adjust future budget allocations, staffing and other operations decisions to reflect the existing community and operating landscape.
Arlington Public
Schools/Arlington County
Proposed FY 2025-34 Capital
Improvement Plan (CIP)
Joint APS School Board and Arlington County Board
Work Session
June 4, 2024