Proposed Capital
Improvement Plan (CIP)
FY 2025 – FY 2034
Submission of a 10-Year
Plan for Transportation
2
Safety
Ensure goals of the Vision
Zero Action Plan are
incorporated in all
capital projects; identify
future projects based on
data collected and
analyzed through the
Vision Zero Program, with
focus on improvements
to the High Injury
Network
Equity
Review project locations
to ensure improved
access and mobility for
those reliant on transit,
walking, and biking;
advance studies in areas
lacking adequate
infrastructure and focus
capital improvements to
expand multimodal
access
Community
Energy Plan
Maximize sustainable
travel options for
residents, workers and
visitors with continued
investments in prioritizing
pedestrian, bicycle, and
shared mobility
infrastructure, and
enhanced transit service
Biophilia
Minimize
adding impervious
surface in new capital
projects and
incorporate more
biophilic elements,
including street trees,
natural plantings,
and bio-retention
infrastructure
where feasible
Transportation Advancing County Goals
Arlington County Master Transportation Plan
The Adopted Master Transportation Plan (MTP) provides policy guidance for Arlington’s
transportation system through 2030; it will undergo an update beginning later this year
3
Highlights and Key Takeaways
• On-going as well as major projects and initiatives in the 2025 – 2034 timeframe
• Complete Streets: Columbia Pike, Crystal City/Pentagon City transformation, Rosslyn is next,
Langston Boulevard to follow
• Transit: ART O&M, Crystal City 2nd Entrance, Transitway Extensions, Ballston West Entrance,
among other large projects
• Vision Zero goals embedded in Complete Street projects as well as the Street
Safety Improvement program
• Future bus purchases assume Battery Electric Buses (BEBs)
• Full Adopted TSP implementation starting FY 2026
• Funding for multimodal studies, but not for design or construction
• PAYG and Bond requests limited to State of Good Repair (SGR), bridges
4
Proposed 10-Year CIP: $1.5B
$000 FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10-Yr Total
Complete Streets Arlington 115,906 75,633 86,884 97,945 67,991 46,771 56,879 55,861 82,669 76,102 762,641
Arlington Transit Program 112,631 93,601 165,133 63,950 100,579 37,549 57,442 5,705 7,621 48,127 692,338
Maintenance Capital 17,062 16,628 17,282 17,618 18,298 18,640 19,364 19,725 20,478 20,848 185,943
Transportation Capital
Program Administration 4,873 5,019 5,169 5,324 5,483 5,648 5,817 5,991 6,170 6,356 55,850
Operating Costs 8,670 10,619 11,382 13,712 15,961 17,294 19,073 19,702 20,345 20,978 157,736
Total Submitted CIP 259,142 201,500 285,850 198,549 208,312 125,902 158,575 106,984 137,283 172,411 1,854,508
Implementation Adjustment (68,088) (48,268) (65,690) (55,192) (58,308) (8,360) (12,976) (7,417) (7,812) (12,066) (344,176)
Proposed CIP 191,054 153,232 220,160 143,357 150,004 117,542 145,599 99,567 129,471 160,345 1,510,332
Submitted CIP
5
Key Changes vs FY 2023 Adopted CIP
• Cost to transition ART Fleet to ZEB / BEB consolidated under a new program “ART
Fleet Transition to ZEB,” for a total cost of $134m across 10 years
• FY 2023 Adopted CIP included select elements scattered across multiple programs
• Cost escalation on transit projects
• Complete Streets portfolio: local placeholder funding removed from out-years
due to funding constraints
• Street Safety Improvement program funding increased 50% reflecting volume of
projects and faster pace of implementation to meet Board and community
expectations
• Reduced funding for paving and bridge maintenance due to improved condition
of assets
6
By Program and Funding Source
Almost 80% of funding is from new sources
Federal, 7%
State, 8%
Bonds, 9%
TCF - C&I,
19%
TCF - NVTA Local, 10%TIF, 5%
Regional,
15%
PAYG / Other, 6%
Existing
Funds, 21%
By
Funding
Source
Complete
Streets,
41%
Transit,
37%
Maintenance
Capex, 10%
Operating
Costs, 9%
Program
Admin, 3%
By
Program
7
Proposed 10-Year CIP: By Funding Source
Before implementation adjustment
10-Yr
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
New Funding:
Federal Funding 1,090 4,718 33,892 4,546 25,258 16,419 21,366 4,011 4,176 13,996 129,472
State Funding 15,140 11,587 48,107 16,481 17,710 7,364 15,122 3,320 4,560 17,261 156,652
Developer Contributions 885 902 2,315 12,595 4,428 3,880 3,612 35 0 0 28,652
New Bond Issue 13,540 14,540 16,015 16,365 17,070 17,625 18,425 17,030 17,725 18,060 166,395
PAYG 4,281 5,954 7,398 7,654 7,635 8,103 9,259 9,146 8,339 8,575 76,344
Other Funding 150 357 357 0 34 35 0 0 0 0 933
TCF - C&I 29,747 42,541 35,966 50,021 65,971 25,645 25,561 22,594 26,536 32,200 356,782
TCF - NVTA Local 11,618 17,717 19,270 17,965 18,425 15,203 22,175 14,781 15,873 24,913 177,940
Regional Funding 4,100 2,873 9,082 27,459 41,346 26,686 36,591 30,803 46,693 43,320 268,953
TIF 20,131 16,702 6,139 8,950 8,576 2,526 4,834 5,265 13,349 14,067 100,539
Subtotal New Funding 100,682 117,891 178,541 162,036 206,453 123,486 156,945 106,985 137,251 172,392 1,462,662
Previously Approved Funding
Authorized but Unissued Bonds 2,478 268 0 0 0 0 0 0 0 0 2,746
Issued but Unspent Bonds 1,945 617 713 0 0 0 0 0 0 0 3,275
TCF - C&I 58,095 13,494 6,750 4,287 0 29 89 0 31 19 82,794
TCF - NVTA Local 16,200 7,536 2,436 147 327 0 0 0 0 0 26,646
Regional Funding 22,972 24,738 75,227 23,388 0 0 0 0 0 0 146,325
TIF 4,207 3,331 5,143 862 23 2,387 1,541 0 0 0 17,494
Other Prev Approved Funds 52,563 33,624 17,041 7,829 1,509 0 0 0 0 0 112,566
Subtotal Previously Approved Funding 158,460 83,608 107,310 36,513 1,859 2,416 1,630 0 31 19 391,846
Total Funding Sources 259,142 201,499 285,851 198,549 208,312 125,902 158,575 106,985 137,282 172,411 1,854,508
8
Nov. ‘24 Proposed Bond Referendum: $29.8M
• 8% lower than FY 2023
Adopted CIP and
mostly limited to state
of good repair
• Reduced Paving ask
resulting from improved
pavement conditions
owing to mild winters
Total
CIP Program FY 2025 FY 2026 for Ref
Paving 11,201 12,590 23,791
Street Lighting 770 584 1,354
Sidewalks 721 743 1,464
Neighborhood Complete Streets 420 430 850
Signals & ITS Maintenance 355 397 752
WALKArlington 200 206 406
Street Safety Improvements 163 235 398
Curb & Gutter Missing Links 111 130 241
Bridge Maintenance 0 524 524
Total 13,941 15,839 29,780
Proposed CIP
9
6
Signals/ITS*
Program Investments
Multimodal program implements goals of the Master Transportation Plan (MTP)
73
Complete
Streets
Icons represent recent
and active complete
streets, transit, and signals
projects
11
Transit
Program
Investments
by the
Numbers
* In addition to signals / ITS
projects embedded in 73
Complete Street projects
eBuilder CIP Projects Dashboard (arcgis.com)
10
Achieving Racial Equity in the CIP
Capital Bikeshare System Surges with Record Ridership
• Ridership was up 23% across the system between April 2023
and April 2024
• Arlington trips in April: 33,756; tenth month in a row of record
ridership
Equity memberships increase
• ACCS Capital Bikeshare team has partnered with DHS, APAH,
AFAC, APS: REEP (Arlington Education and Employment
Program)
• 512 equity members in Arlington
• 2,655 total regional equity members
• Over 4,000 trips taken by equity members in April
Proposed CIP continues funding for Capital Bikeshare
• $17.3 million for system expansion and replacement
• $21 million for CaBi Operations and Maintenance
Capital Bikeshare engagement event at
Arlington Food Assistance Center
11
Recent Achievements
Projects that have started construction:
• Columbia Pike Multimodal Improvements Projects
Segments C & D
• Shirlington Road Pedestrian Bridge
• Army Navy Drive Complete Streets
• RB Corridor High Priority Phase 2
• Signals projects
Projects that have been recently bid for
contract:
• South Eads Street Phase 1 & 2 (awarded)
• N. Ohio Street, 12th Road N to 14th Street N
Projects going out to bid (finalizing ITB)
• East Falls Church Bus Bay Expansion
N. Ohio St. Safety Project
($1.3M)
S. Eads St. Complete
Streets ($2.9M)
Shirlington Road Pedestrian
Bridge ($3.3M)
Army Navy Drive
Complete Streets
($15.3M)
12
Project Accomplishments
Boundary Channel Drive Interchange
Improvements ($17.6M)
West Glebe Road Bridge
Reconstruction ($10.7M)
18th St. S (S. Eads St.-S. Fern St.) ($3.8M)Washington Boulevard and 13th
Street North Improvements ($4.0M)
Arlington Ridge Rd. & S. Lynn St.
($1.2M)
12th Street South Improvement
(S. Eads St. – S. Clark St.) ($4.2M)
Summer 2023 Fall 2023 Winter 2023-24 Spring/ Summer 2024
13
Transportation and Sustainability
• Arlington has invested in complete streets projects, transit
service, and Capital Bikeshare to provide options for
sustainable travel
14
Household Transportation Trends
2007/2008 Regional Travel Survey
2017/2018 Regional Travel Survey
Share of Daily Trips by Mode
34%
29%
42%
49%
39%
25%
19%
31%
24%
38%
23%
29%
13%
16%
13%
15%
21%
10%
9%
5%
3%
2%
4%
2%
5%
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Rosslyn-Ballston
Route 1
Columbia Pike
Shirlington
Other Arlington
Drive Alone Drive/ride with others Walk Transit Other
28%
25%
37%
44%
39%
13%
20%
29%
25%
32%
30%
32%
16%
18%
18%
22%
17%
11%
8%
6%
7%
6%
3%
5%
5%
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Rosslyn-Ballston
Route 1
Columbia Pike
Shirlington
Other Arlington
Auto trips down overall
• Trend more pronounced in Metro
corridors
Share of walking trips increased
• Over 30 percent of trips in Metro
corridors made by walking
Data from MWCOG/TPB Regional
Household Travel Survey
• Conducted every ten years
• Arlington pays for oversample
• Pre-pandemic travel data, how will
trends stabilize?
15
Household Transportation Trends
2007/2008 Regional Travel Survey
2017/2018 Regional Travel Survey
16%
20%
10%
3%
3%
16%
27%
14%
10%
9%
68%
53%
76%
87%
88%
0% 20% 40% 60% 80% 100%
Rosslyn-Ballston
Route 1
Columbia Pike
Shirlington
Other Arlington
0 vehicles 0 - 1 vehicle 1+ vehicles
27%
20%
9%
4%
1%
27%
25%
21%
9%
22%
46%
56%
70%
88%
77%
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Rosslyn-Ballston
Route 1
Columbia Pike
Shirlington
Other Arlington
Vehicles per Household
Vehicle ownership down
• Significant shift in Rosslyn-Ballston
corridor to car-free households
Reduction in vehicles per driver
• Notable shift outside major corridors
Data from MWCOG/TPB Regional
Household Travel Survey
• Number of vehicles per driver, per
household
16
Annual VMT, GHG Levels Declining Even With Ongoing Growth
Emissions Impacts on Arlington Roadways
Vehicle Miles Traveled (VMT), 2007 – 2022 Greenhouse Gas (GHG) Emissions from On-Road
Transportation, 2007 – 2022
17
GHG Impacts from Transportation Sources
• 36 percent of GHG emissions in Arlington are
generated by on-road transportation – travel
within the County and through the County
• The GHG emissions from these trips can be
minimized by conversion to electric vehicles,
and mode shift to non-auto travel
• Historic trends in VMT and GHG allow us to
infer the impact of multimodal transportation
on sustainability into the future
• The CIP delivers infrastructure and services to
support further shifting travel trends to transit
and active modes of transportation
2019 Community Energy Plan
GHG Emissions by Sector
18
Plans and Strategic Initiatives Guiding CIP
Plans and Strategic Initiatives Guiding CIP
19
FY 2025-2034 CIP Project Slides
Review of capital project highlights and state of good repair
initiatives for the ten-year program:
• Transit capital program
• Complete Streets capital program
• Capital maintenance program
Annual spend intensity
• Communicate magnitude of funding spent each fiscal year
• Range from $100,000 to $30 million per fiscal year
20
ART Operations and Maintenance Facility ART Fleet Transition to ZEB (Zero Emission Bus)
Proposed CIP: $27.4M (Fall 2024, Fall 2025 for BEB
infrastructure
Total Project Cost: $95.2M
Funding: State, TCF
Community benefits:
• Addresses need for an O&M facility for ART
• Includes charging for 12 Battery Electric Buses (BEBs),
one fast charger, and solar panels on roof of facility
and parking garage
Proposed CIP: $134.2M
Funding: Federal, State, Regional, TCF, TIF
Community benefits:
• Expands fleet and infrastructure to support BEBs
• Program includes incremental cost of BEBs (vs. RNG
buses), pavement reinforcement, charging
infrastructure at ART O&M Facility and ART Light
Maintenance Facility, and land purchase in FY 2027
and build-out
ART Operations and Maintenance Facility
NEW
21
ART Fleet Transition to Zero Emission Buses
Note: Costs shown are uninflated Assumption
Cost of Buses $1.2m
Ratio to RNG due to range limitations 1.3 : 1.0
Fleet size at end of CIP period 113 (includes 20 additional buses due to ratio)
Land purchase $25m in FY27 (54,000 square feet)
Construction (including A&E) $25.5m
Mid-life battery replacement $265K per bus after 7 years
• Assumptions will be refined following the pilot of BEBs on ART routes
• Costs may change significantly owing to multiple variables
• Assume conversion to RNG in FY 2025
22
ART Bus Replacement and Expansion
ART Fleet & Equipment Replacement ART Fleet Expansion
Proposed CIP: $67.7 million
Funding: State, TCF
Community Benefits:
• Replaces aging buses in ART fleet (78 buses) when
they reach end of useful life (12 years)
• Ensures reliability and accessibility of ART service
Proposed CIP: $13.5 million
Funding: State, Regional, TCF
Community Benefits:
• Purchase of 4 BEBs in FY 2025
• Purchases of additional buses in FY 2029 (7 buses) and
FY 2031 (4 buses) to support 10-year service plan for
ART as per Transit Strategic Plan
• Purchase cost reflects RNG buses; incremental cost of BEBs captured in ART Fleet Transition to ZEB program
23
Bus Operations Improvements
East Falls Church Station Bus Bays Transitway Extension to
Pentagon City
Shirlington Transit Station
Expansion
Proposed CIP: $8.6M (Spring 2026)
Total Project Cost: $12.7M
Funding: State, Regional, WMATA, TCF
Community Benefits:
• Enhances multimodal hub, relieves
operational congestion, and meets
accessibility needs
Proposed CIP: $23.8M (Spring 2026 for
Segment IIA)
Total Project Cost: $27.7M
Funding: State, Regional, Developer, TCF, TIF
Community benefits:
• Dedicated transit lanes, five new transit
stations, traffic signal modification, and
sidewalk / curb improvements
Proposed CIP: $11.9M (FY 2030)
Funding: Regional, TCF
Community Benefits:
• Add bus bays to Shirlington Station to
meet future demand
• Connect with future service changes
by City of Alexandria
24
Crystal City Metrorail Station East Entrance
• Proposed CIP: $127.1M
• Total Project Cost: $146.1M
• Funding: Federal, State, TCF, TIF
• Community Benefits:
• New second entrance at east end of metro station
to improve safety, accessibility, and connectivity to
VRE station
• Joint venture between JBG Smith, Clark
Construction, and county
• First county project awarded using the PPEA
process (Virginia Public-Private Education Facilities
and Infrastructure Act of 2002)
• Design underway; construction to start fall 2024
• Expected Completion: Spring 2027
25
Other Metrorail Station Expansion Projects
Transportation
Project Name Proposed CIP /
Expected Completion
Funding Project Description
Ballston-MU Metrorail Station
West Entrance
$177.0M
($181.0M total cost)
Summer 2029
State, Regional,
Developer, TCF
Construction of full second (west) entrance
to metro station, improving safety and
accessibility, as well as pedestrian
connection from points west. RFQ was
published in May. RFP to be issued this fall;
consideration of bids in 2025.
Court House Metrorail
Station New Elevators
$57.5M
Spring 2031
Federal, State, Regional,
Developer
Construct two high-speed elevators to
provide enhanced accessibility
East Falls Church Metrorail
Station Second Entrance
$0.8M
post-CIP
State, TCF Planning/scoping funding for full second
(west) entrance to metro station
26
Bus Stop Accessibility Improvements
“Level 1” Stops: 205 “Level 2” Stops: 304
• Retrofits existing bus stops to be ADA-compliant
• 990 bus stops: 63% are not compliant with current regulations, approximately 10% are not accessible
• All non-accessible stops are “Level 3” stops and will need the county to secure easements
• New federal guidance on accessibility (PROWAG) will also apply to bus stop improvements
Compliance = regrade sidewalk and install
pad to curbCompliance = relocation of newspaper boxes Compliance = widen sidewalk/pad, curb
ramps, crossings, regrading
“Level 3” Stops: 116
Bottom
line for
Level 3:
redesign
and
rebuild
roadway/
sidewalk
27
Bus Stop ADA: Implementation Strategy
Close to 70% compliance achieved over CIP period
• $10.2m funding in CIP *
• Propose advancing Level 1
stops immediately to bring into
compliance while concurrently
advancing design work on
Level 2 and Level 3 to ready for
construction
• 100% of Level 1 stops projected
to be in compliance by FY 2030
* Over and above $6m funding for Bus
Stop and Shelter Program which
replaces 5-10 bus shelters a year
28
BikeArlington/WalkArlington Programs
Transportation
Project Name Proposed CIP &
Expected Completion
Project Description
Arlington Memorial Trail $21.2 million
FY 2034
Design and construct new multi-use trail to connect
Memorial Avenue to Columbia Pike at Joyce Street
Arlington Boulevard
Trail, multiple phases
$22.4 million
FY 2028-2037
Segments at Fairfax Drive, Glebe Road to George Mason
Drive, and west to Granada Street
Capital Bikeshare $17.3 million Purchase of new and replacement bikes, e-bikes, stations
Countywide Pedestrian
Spot Improvements
$8.0 million
ongoing
Enhance safety and accessibility at locations within existing
street system, in partnership with Vision Zero Program
Lorcom Lane
Sidewalk
$1.2 million
FY 2026
Build out existing interim pedestrian path between North
Oakland Street and North Quebec Street
North Park Dr. and
George Mason Dr.
$1.3 million
FY 2025
Install traffic signal and expand curbs at the intersection
Studies – various
locations
$1.2 million
ongoing
Custis Trail Renovation and Expansion (FY 2025), W&OD /
Four Mile Run Connection to Carlin Springs Road (FY 2029)
NEW
Arlington Blvd. Trail Study
Capital Bikeshare
29
Columbia Pike Improvements
Columbia Pike Multimodal Improvements Columbia Pike Transit Stations
Proposed CIP: $44.5M (FY 2028)
Total Project Cost: $162.0M
Funding: TCF, Regional
Community benefits:
• Improved transportation accessibility for pedestrians,
cyclists, transit users, motorists
• Includes funding for Bike Boulevards
Proposed CIP: $8M (FY 2026)
Total Project Cost: $14.6M
Funding: Federal, State, TCF, GO Bonds
Community benefits:
• Real-time information, near-level boarding,
expanded seating, and improved lighting
30
Crystal City / Pentagon City Streets
Transportation
Project Name Proposed CIP &
Expected Completion
Project Description
15th Street South &
South Clark/Bell Street
$12.6 million
FY 2027
Construct multi-use trail between 12th and 18th Streets South,
improve pedestrian and bicycle facilities on 15th Street South
Army Navy Drive
Complete Street *
$9.1 million
FY 2026
Rebuilds Army Navy Drive with dedicated two-way bicycle
facility; enhanced transit, pedestrian facilities; street trees
Army Navy Drive
Protected Bike Lane
$3.8 million
FY 2026
Install two-way bicycle facility on Army Navy Drive between
South Joyce Street and Memorial Drive
CC2DCA Multimodal
Connection
$54.9 million
FY 2029
Construct a multimodal connection from the Crystal City VRE
Station to DCA, including connection at Mount Vernon Trail
Long Bridge Drive
Connection
$7.9 million
FY 2029
Construct trail along Long Bridge Drive, connecting future
Long Bridge Bike/Ped bridge to Clark/Bell multi-use trail
South Eads Street
Improvements, Phases
$19.1 million
FY 2034
Construct streetscape and bicycle ehancements on South
Eads Street between Army Navy Drive and 23
rd Street South
CC2DCA
Multimodal Connection
Army Navy Drive
Complete Streets
* Separate CIP Program
31
Improvements Outside Major Corridors (1)
* Separate CIP Program
Transportation
Project Name Proposed CIP &
Expected Completion
Project Description
Arlington Blvd/
Washington Blvd
$10.1 million
FY 2029
Improve safety for all modes at one of highest crash
locations in County; SS4A, Smart Scale applications
Arlington View
Connector Trail *
$10.4 million
FY 2028
New multi-use trail connecting Arlington View to Army
Navy Drive
(previously called the Army Navy Country Club Trail)
Four Mile Run Valley
Corridor Improvements
$8.8 million
FY 2028
Build out improvements in phases on FMR Drive, from
Shirlington Road to Barcroft Community Center
Military Road at Nelly
Custis Drive
$4.2 million
FY 2026
Install roundabout at intersection to improve safety;
underground utilities at intersection
North Sycamore Street
Improvements
$4 million
FY 2028
Enhance sidewalks, crossings, bicycle facilities, and
streetscape from Langston Boulevard to 19
th Street
Pershing Drive
Improvements
$2.8 million
FY 2027
Install permanent protected bicycle facilities from
Washington Boulevard to North Barton Street
Pershing Dr. & N. Cleveland St.
S. Four Mile Run Dr.
Complete Streets
32
Improvements Outside Major Corridors (2)
Transportation
Project Name Proposed CIP &
Expected Completion
Project Description
South Carlin Springs
Road
$2 million
FY 2026
Immediate sidewalk improvements in coordination with signal upgrade at 5
th
Street South; reviewing options to expand sidewalks north/south
South George Mason
Drive Improvements (1)
$13.5 million
FY 2028
Construct separated trail facility from Arlington Boulevard to Columbia Pike, signal
at 6
th Street, in partnership with National Foreign Affairs Training Center
South George Mason
Drive at Four Mile Run
$15.5 million
FY 2031
Scope, design, and construct intersection safety improvements. Received
Regional Roadway Safety Program award for scoping
South George Mason
Drive (2, 3)
$9.9 million +
FY 2034, FY 2037
Continue separated trail facility between Columbia Pike and County line.
Anticipated ATIIP grant, state funding
Walter Reed Drive – 6
th
Street to Columbia Pike
$8.4 million
FY 2028
Improve bicycle facilities, bus stops, and add traffic signal at 9
th Street following
Career Center project
Studies – various locations $3.4 million
ongoing
Four Mile Run Trail Crossing at Shirlington Road (FY 2025);
Carlin Springs Road Corridor Study (FY 2027);
Shirlington Road Multimodal Study (FY 2029);
Glebe Road Corridor Multimodal Study (FY 2029);
Wilson Boulevard Multimodal Study (FY 2030);
North George Mason Drive Study (FY 2030)
NEW
NEW
NEW
NEW
33
Langston Multimodal Improvements
Transportation
Project Name Proposed CIP &
Expected Completion
Project Description
Langston Boulevard
Multimodal
Improvements
$50.3 million
ongoing
Local and grant funding across the ten-year CIP
to advance recommendations identified in Plan
Langston Boulevard
Langston
Boulevard
Multimodal Study,
Areas 2 & 3
$600,000
FY 2026
Advance feasibility analysis for intersections and
segments between North Harrison Street and
Lorcom Lane in support of near-term private
development
Langston
Boulevard East
End Corridor
Improvements, Area 5
$800,000
FY 2028
Perform feasibility and transportation analyses on
recommended cross sections from Spout Run
Parkway to the Key Bridge
NEW
NEW
34
Neighborhood Complete Streets
Transportation
Project Name Proposed CIP &
Expected Completion
Project Description
8th Road South $348,000
FY 2025
Realign intersections at South Dinwiddie and South Frederick
to improve safety of pedestrian crossings and make ADA
accessible
14
th Street North $427,000
FY 2025
Construct sidewalk between North Ohio and North McKinley
Streets
South Irving Street,
two phases
$783,000
FY 2025
Install sidewalk between 6
th and 7th Street and make
sidewalks between 2nd and 6th Streets ADA accessible
Shared
Street
Pilot Projects
$100,000
FY 2025
Install signage and markings to designate three shared
streets: South Lynn Street (16
th to 20th), North Wakefield Street
(Carlin Springs to Wilson), and 12th Street South (Glebe to
Walter Reed); monitor travel patterns
Projects under
consideration
$2.4 million
FY 2026
Construct sidewalk on North Oakland Street (6
th to Pershing)
and 8th Road North (Kensington to Jefferson)
NEW
14th Street North
Shared Streets Pilot Projects
12th Street South
S. Lynn St.
35
Rosslyn-Ballston Arterial Improvements
Transportation
Project Name Proposed CIP &
Expected Completion
Project Description
Fairfax Drive at Kirkwood
Drive Intersection
$5.7 million
FY 2029
Improve intersection geometry, improve pedestrian
refuges, add bicycle lanes, upgrade traffic signals
Fort Myer Drive Tunnel
Removal
$42.4 million
FY 2031
Remove grade-separation, convert to two-way
operations, with wider streetscape and cycle track
North Meade Street
Improvements
$10.9 million
FY 2029
Reconstruct and realign North Meade Street at Arlington
Boulevard to improve safety for all modes
Rosslyn Multimodal
Street Improvements
$22.4 million
FY 2026-2030
Various streetscape, sidewalk, bicycle improvements to
support implementation of Fort Myer Drive project
Wilson Boulevard from
10
th to Kenmore Streets
$9.2 million
FY 2028
Install wider sidewalks, upgrade traffic signals and
streetlights, stormwater upgrades, and new street trees
Study: Fairfax Drive / 10
th
Street Corridor
$526,000
FY 2027
Establish a multimodal vision for the County-owned
section of VA Route 237
Wilson Blvd.
Core of Rosslyn
36
Street Safety Improvements – Vision Zero
System Studies / Improvements Arterial Studies / Improvements Capital Program Funding
Proposed CIP: $15.1 million
Community benefits:
• Systemwide and non-arterial safety
improvements and modifications
• May test temporary treatments; School
Slow Zones
• Quick build projects, additional PAYG
Proposed CIP: $4.7 million
Community benefits:
• Supports safety initiatives at intersections
and along arterials identified through
crash analysis
• Quick build projects
Proposed CIP: $5.7 million
Community benefits:
• Funding to seed future capital
projects identified by data-driven
safety studies
Wilson Blvd. & N. Rhodes St.
37
Additional Projects / Programs
Transportation
Project Name Proposed
CIP
Funding Project Description
Traffic Signals $36.2M State, Developer,
TCF, PAYG, GO
Bonds
• 302 signalized intersections; 25 to 35-year useful life but repairs can extend
life
• About 8 signal rebuilds undertaken each year under the Signals program
• Additional rebuilds done as part of Complete Streets or third-party projects
Intelligent
Transportation
Systems
$19.9M Regional, TCF • Leverages technology to improve efficiency of transportation operations
• Technology at signals, as well as standalone installations (beacons, sensors)
Streetlights $19.0M PAYG, GO Bonds,
TCF
• About 7,800 county-owned and 11,000 owned by Dominion Energy (DE)
• Replacements done when problems are identified with infrastructure
• Conversion to LED technology underway for DE-owned; older generation
LEDs being upgraded for further energy savings and to reduce glare
Parking Meters
Parking Technology
$12.4M State, Developer,
PAYG, GO Bonds
• 1,408 parking meters, including 729 multi-space and 679 single-space
meters
• 10-year useful life, component replacement used as cost-saving alternative
38
Proposed CIP: $11.2M
Funding: GO Bonds, PAYG
Community Benefits:
• 36 county-maintained bridges inspected biennially
• Average age of 48 years vs. life expectancy of 75 years
with proper maintenance
• Bridge elements rated on a scale of 0 to 9; County’s goal is
between 6 and 7 (“Satisfactory” to “Good”)
• Average rating currently 6.4; following replacement of
Arlington Ridge Road bridge, all bridges will be above 6
Proposed CIP: $30.2M
Funding: Federal, State, City of Alexandria, TCF, GO Bonds, PAYG
Community Benefits:
• Rehabilitates, upgrades, or replaces bridges
• Shirlington Road bridge recently upgraded with widened
sidewalks; construction underway for separate pedestrian
bridge
• Arlington Ridge Road bridge construction to start in FY 2025;
City of Alexandria paying 50% of cost not covered by grant
funding
Bridge Programs
Bridge Maintenance Bridge Renovation
39
Paving: Funding and Pavement Condition
• Proposed CIP funding $143.9m,
combination of GO Bonds and PAYG
• 1,058 lane-miles of County-maintained
streets
• PCI measured annually
• County’s goal is between 75 and 80
• 2023 PCI 83.3; however, Public Right-
of-Way Accessibility Guidelines
(PROWAG) and markings create
funding pressures
• Majority of bike lanes are in pavement
and evaluated as part of PCI
Pavement Condition Index (PCI)
40
Sidewalks Program
• Proposed CIP funding: $11.9m (GO Bonds, PAYG)
• 443 miles of County-maintained sidewalks
• FY 2024 1st year of concrete zone maintenance
• 2024 Condition Assessment
• 20% of sidewalks are rated fair or poor or very poor
• Goal is to achieve a rating of good or higher
57%
23%
16%
3% 1%
Excellent (100 to 91)
Good (90 to 81)
Fair (80 to 46)
Poor (45 to 31)
Very Poor (30 to 0)
Sidewalk Mileage By Condition
41
Key Assumptions and Risks
• ART Fleet Transition to BEB hinges on ambitious success with state
and federal grants
• Future cost of ART service operations outstanding
• Ballston West Entrance entering RFQ / RFP process
• Core of Rosslyn developer contributions rely on timing of
redevelopment
• CC2DCA reliant on current funding application to NVTA
• Recommendations from MTP Update and future studies unfunded
in this CIP
• Public Right-of-Way Accessibility Guidelines (PROWAG) Federal
guidance impacts all transportation programs – costs not factored
into this CIP
42
Summary and Conclusion
• CIP advances goals of current adopted policy
• Incorporates Vision Zero Action Plan, Community Energy Plan, biophilic goals, equity
• Policy guidance from the update to the MTP can be considered in the development
of the FY 2029 – FY 2038 CIP
• Project implementation challenges/risks
• Inflation, cost of materials and labor in contracts, impact of evolving federal guidance
• Easement negotiations will impact project timelines
• Long-term considerations
• How does the County anticipate evolving technology?
• Look to upcoming MTP update for guidance
• What is the future of telework and impact on travel trends?
• MWCOG/TPB conducts next Regional Travel Survey in 2027/2028
• How do we harness data to ensure that resources are directed to locations most in
need of redesign?
Proposed Capital
Improvement Plan (CIP)
FY 2025 – FY 2034
Submission of a 10-Year
Plan for Transportation