E-3
Subject: DES: Complete Streets
Related Department(s): DES
FY 2025 Proposed Capital Budget
CIP Work Session
The following information is provided in response to a request made by Ms. Cunningham;
at the work session on 06/06/2024, regarding the following question:
Can you quantify the dollar amount of projects that were deferred or cancelled in the
Complete Streets Program to afford the cost escalation in the Transit program?
****************************************************************************************************
The Proposed CIP required trade-offs due to several issues, including the cost escalation
of capital projects and the reduced forecasted revenue from local dedicated transportation
sources (driven primarily by declining office values) in the Proposed CIP relative to the
last ten year Adopted CIP.
A number of projects have experienced significant cost escalation, with large transit
projects such as Crystal City East Entrance and Ballston West Entrance being the most
noteworthy examples due to construction inflation and WMATA soft cost escalation. Other
projects/programs – Pentagon City Second Elevator, Street Safety Improvements (Vision
Zero), and CC2DCA – also increased from the last CIP. Additionally, funding the T ransit
Strategic Plan (T SP) and transition of ART Fleet to zero emission buses (ZEB) was
prioritized in the proposed CIP.
Both factors combined to require significant trade- offs between the Transit program and
Complete Streets. Although transit projects benefit from various grants, almost $60m of
local funding (TCF and TIF) is proposed to be shifted towards Transit through FY 2032
(the last year of the prior Adopted CIP), with additional funds diverted in FY 2033 and FY
2034. In total, including all years and other programs like the Street Safety Improvement
program that increased significantly vs. the Adopted CIP (Street Safety Improvements
increased $9.5m, almost 60% vs. Adopted CIP), combined with lower revenues, over
$80m in local funding is proposed to be shifted from Complete Streets programs (table
below).
In addition to the shift between Transit and Complete Streets programs, the Proposed
CIP also left some projects and programs unfunded or deferred to the later years of the
CIP. The funding list below is the amount that was removed from the CIP and would need
to be reinstated to fund the project (with eligible funding type listed).
E-3
Staff has made some fairly aggressive assumptions regarding external funding for ART
Fleet Transition to ZEB in order to incorporate this program without further diversion of
funding in the Proposed CIP. In the event the funding is not secured at the levels
assumed, additional projects will have to be deferred or canceled in the next CIP . In
addition, staff is anticipating cost increases in our ART operations contract in FY 2025
and going forward from FY 2025 due to TransDev negotiations with ATU 689 related to
the first option year of that contract. This will likely put further pressure on TCF and require
further project deferrals to fund the expected increase.