Proposed Capital
Improvement Plan (CIP)
FY 2025 – FY 2034
Submission of a 10-Year Plan
for the Department of
Technology Services
Department of Technology Services
• Continuation of existing
projects and commitments
• Keeping up with program
replacement cycles (State of
Good Repair)
• Adherence to Arlington
County Digital Strategy
• Major projects and
initiatives in DTS’s
proposed 2025 – 2034 CIP:
• Revenue & Collection System Upgrade
• Real Estate Assessment System
Modernization
• Undergrounding and strengthening fiber
connections at Schools
• Data Center Consolidation
• Constituent Single Sign-On
Department of Technology Services
(DTS) Overview
•
Continuation of existing projects
and commitments
•
Keeping up with program
replacement cycles (State of
Good Repair)
•
Alignment to the Digital Strategy
Major CIP Projects 2025
-
2034
•
Revenue & Collection
System Upgrade
•
Real Estate Assessment
System Modernization
•
Undergrounding &
strengthening fiber
connections at Schools
•
Data Center Consolidation
•
Constituent Single Sign
-
On
3
Program Accomplishments
Network PC Replacement ConnectArlington (CA)
Unified Communications Life Cycle Refresh Server & Storage
• Migrated six eGov applications to the
public cloud
• Enterprise Payment System (EPS)
• DES Outdoor Café Seating – Oct 2023
• Police False Alarm Invoice – Dec 2023
• Sheriff’s Office FOIA – Dec 2023
• DES Recycling Program Fee – Dec 2023
• ACFD Inspections & Permits – Feb 2024
• TRE CAPP online payments – Apr 2024
• Updated key systems including the
backups for enhanced data
protection
• Enhanced DES Traffic Engineering
servers for better camera
management
• Created a new video data storage
system for Environmental Services
• Completed the undergrounding
of aerial fiber at N Glebe
Rd/Chesterbrook intersection.
• Finished the core installation of
fiber in the Green Valley
neighborhood along Shirlington
Rd. (Art Bus Operations and
Maintenance Facility)
• Laptops: Total Units: 1,080
• Refreshed Units: 407 (38%)
• New Issuances: 538 (50%)
• Break-Fix: 135 (12%)
• Desktops: Total Units: 283
• Refreshed Units: 229 (81%)
• New Issuances: 32 (11%)
• Break-Fix: 22 (8%)
• Network Edge Refresh Project: Upgraded
165 network switches across the County.
• Wireless Access Point (WAP) Refresh
Project: Updated all ten Fire Stations, the
Fairlington Community Center and Bozman
with new WAPs.
• DNA Center Implementation Project:
Connected 336 devices, enhancing network
security and compliance.
• Telephone System Modernization
• Migrated nine depts & two
constitutional offices to the new
system
• 809 users transitioned to
the new phone system
• Migrated all seventeen call centers
to the new system within 120 days
• 414 agents transitioned to
the new call center system
4
Asset Inventory: Hardware & Software
Desktop PCs
Desktops: 946
4 Year Lifecycle
Rolling Replacement
Laptop PCs
Laptops: 2,695
3.5 Year Lifecycle
Rolling Replacement
Fiber Optic Cables
70+ Miles
Refresh/Replace
As Needed
Servers: 5
Hosts: 34
5 Year Lifecycle
Refresh = Rolling
by End-of-Life
Core Network
Equipment
Core Switches: 2
5 Year Lifecycle
Distribution Network
(Hub-Sites)
Switches: 17
5 Year Lifecycle
Access Network
(In-Building)
Switches: 165
5 Year Lifecycle
Wi-Fi
*WAPs: 983
3-5 Year Lifecycle
Refreshes 20% each year
Power Systems
*UPS: 137
*PDUs: 122
5 Year Lifecycle
Data Center
Infrastructure
Switches: 83
5 Year Lifecycle
Applications
Enterprise: 136
Dept/Agency: 317
Refresh = Rolling
By End-of-Life
Audio Visual Equipment
Conference Rooms: 112
Courtrooms: 10
Refresh = Rolling
By End-of-Life
WAPs: Wireless Access Points
UPS: Uninterruptible Power Supply
PDUs: Power Distribution Units
Proposed Programs/Projects
(In ‘000s) FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 FY 32 FY 33 FY 34 10 Year Total
Cloud Migration (eGov) 625 631 1,256
ConnectArlington 1,150 1,270 1,225 1,405 980 985 1,065 1,200 1,240 1,340 11,860
Constituent Digital Services 379 379 399 404 428 433 483 484 489 3,878
Constituent Single Sign-On 700 700
County Audio Visual Replacement 300 342 921 859 549 806 1,041 420 1,012 439 6,689
Data Center Consolidation 3,779 939 3,242 973 530 9,463
Enterprise Records Mgmt. System 1,343 1,343
Human Resource & Financial System 202 208 214 221 227 234 241 248 256 2,051
Land Records System 540 1,104 1,644
Network Equipment and Power Systems 1,732 1,544 2,121 2,096 3,889 3,182 1,919 2,449 2,550 4,495 25,977
Real Estate Assessment System 1,010 1,010
Revenue & Collection System 4,500 1,250 3,295 1,569 10,614
Server Hardware & Data Storage 780 586 603 621 640 659 679 699 720 742 6,729
Workforce Device Modernization 2,166 3,458 2,579 2,509 2,922 3,045 3,175 3,313 3,458 3,611 30,236
Total Recommendation 15,032 10,122 8,975 11,345 12,368 13,157 9,889 8,805 9,712 14,045 113,450
FY 2025 – 2034 Proposed CIP Summary
5
Funding Sources
(In ‘000s) FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 FY 32 FY 33 FY 34 10 Year Total
New Funding
Federal Funding
State Funding
Developer Contributions
PAYG 4,941 7,308 4,690 4,602 4,736 5,165 5,562 5,156 5,922 5,537 53,619
Short Term Finance 6,262 1,544 3,060 5,338 6,652 7,007 3,262 2,449 2,550 7,168 45,292
New Bond Issue 995 1,225 1,405 980 985 1,065 1,200 1,240 1,340 10,435
Other Funding
Subtotal New Funding 11,203 9,847 8,975 11,345 12,368 13,157 9,889 8,805 9,712 14,045 109,346
Previously Approved Funding
Authorized but Unissued
Bonds
Issued but Unspent Bonds 3,829 275 4,104
Other Previously
Approved Funds
Subtotal Previously Approved
Funding
3,829 275 4,104
Total Funding Sources 15,032 10,122 8,975 11,345 12,368 13,157 9,889 8,805 9,712 14,045 113,450
FY 2025 – 2034 Proposed CIP Funding Sources
6
FY 2025 - 2034 Proposed Funding Summary
61%19%
16%
4%
Proposed Programs
Hardware Refreshment Fiber & Data Center Projects
Application & Systems Refreshemnt Constituent Services
47%
40%
9%
4%
Proposed Funding Sources
Pay-As-You-Go Short Term Finance
New Bond Issue Issued but Unspent Bonds
7
Proposed Hardware Refreshment FY25-34
• Workforce Device Modernization: $30,236,000
• Refreshment of Laptops, Desktops, Peripherals Kits (Monitor, Mouse,
Keyboard).
• Supports automation, tracking, and reporting for County IT-related work.
• Network Equipment and Power Systems: $25,977,000
• Refreshment of cores (connectivity), distribution switches (routes
traffic), edge switches & wireless access points (access), & perimeter
(security) layers.
• Refreshment of security devices like firewalls as well as power systems
like uninterruptible power supplies & data center switches.
• Server Hardware & Data Systems: $6,729,000
• Refreshment of servers, hosts & backup storage units.
• County Audio Visual Replacement: $6,689,000
• 112 Conference Rooms
• 10 Courtrooms
Network Topology
(Dual Redundant)
Edge
Perimeter
Data Center
8
Proposed Fiber & Data Center Projects
• Connect Arlington (CA) ~ FY25-34 $11,860,000
• Replenish fiber inventory & underground aerial fiber to protect it from damage
• Finalize connections for missing links of the fiber ring to provide redundant paths
• Proposed projects include:
FY2025 Projects
Project Phase
Underground S Glebe & Richmond Hwy Construction
Alternative Path to Sequoia Plaza 1 Construction
Build to meet Alexandria E911 Construction
Connect Fiber Ring Little Falls Rd Planning & Engineer
FY2026 Projects
Project Phase
Connect Fiber Ring Little Falls Rd Construction
Underground Jamestown ES Engineering & Construction
Underground Taylor ES Engineering & Construction
Connect Fiber Ring Military Rd Planning & Engineer
FY2027 Projects
Project Phase
Underground Randolph ES Engineering & Construction
Underground Abingdon ES Engineering & Construction
Underground Columbia Pk & Four Mile Engineering & Construction
Connect Fiber Ring Military Rd Construction
• Data Center Consolidation ~ FY25, FY27-30 $9,463,000
• Phase I, which is set to begin in FY25, includes the reduction/relocation of Network Operation
Center (NOC) One
• Phase II, which is set to begin in FY27, includes the reduction/relocation of Network Operation
Center (NOC) Two
9
Proposed Application & Systems Refreshment
• Revenue & Collection System (ACE & CAPP): $10,614,000
• Revenue management & public payment portals for the
County
• 5-year maintenance cycle
• FY24-25, FY29-30, FY34
• Land Records System: $1,644,000
• Recording & maintaining of real property titles for the
County and City of Falls Church
• 5-year maintenance cycle
• FY29, FY34
• Enterprise Records Mgmt. System (ERMS): $1,343,000
• Records repository for the County
• 7-seven maintenance cycle
• FY31
• Human Resource & Financial System (PRISM+): $2,051,000
• Manages finance, HR, & business operations (accounting,
timekeeping, payroll, etc.)
• Implementation of select modules released quarterly
• FY26-34
• eGovernment Suite of Applications: $1,256,000
• Custom on-premise applications & systems (property
search, legislative tracking, housing permits, etc.)
• Migrate 15+ applications to the cloud
• FY25-26
• Real Estate Assessment System: $1,010,000
• Commercial & personal property value assessment
• Finalize the modernization of the new system
• FY26
10
Proposed Constituent Services Projects
• Constituent Single Sign-On ~ FY26 $700,000
• Solution to provide implementation and a core framework for constituents with
one password for all Arlington County accounts
• Priority for constitutional officers
• Enhanced Security
• Constituent Digital Services ~ FY26-34 $3,878,000
• Solution to streamline department operations and constituent digital services via:
• Business Process Automation (BPA)
• Leveraging technology to streamline and optimize constituent-facing processes.
• Artificial Intelligence (AI)
• Implementing AI-powered solutions to enhance the constituent experience.
• Machine Learning (ML)
• Utilizing ML algorithms to personalize and improve constituent services.
• Initial Departments to deliver benefits to constituents and visitors:
• Public Safety (all), DHS, CMO/CBO, AED
11
Summary & Conclusion
Summary – Keeping an eye on the future
• Infrastructure and Technology Modernization: Investment in network,
server, and AV improvements for long-term efficiency and reduced
downtime.
• System Upgrades and Cloud Migration: Investment in application
upgrades and cloud migration, aiming for improved resilience and
enhanced customer experience.
• Sustainable IT Development: Investment in data center consolidation and
fiber network balanced by long-term environmental and economies of
scale benefits.
Challenges
• CAPEX to OPEX
• Cost of doing business
• Pricing volatility
• Extended delivery times (supply chains)
• Keeping up with emerging technologies
12
Proposed Capital
Improvement Plan (CIP)
FY 2025 – FY 2034
Submission of a 10-Year Plan
for the Department of
Technology Services