ECONOMIC DEVELOPMENT: JOINT USE FACILITIES
MAINTENANCE PROGRAM
10 YEAR CATEGORY SUMMARY (in $1,000s)
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year
Total
Cultural Affairs - Joint-Use
Space Maintenance and Repairs
0 630 50 52 54 56 58 60 62 64 1,086
Total Recommendation 0 630 50 52 54 56 58 60 62 64 1,086
CATEGORY FUNDING SOURCES (in $1,000s)
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year
Total
New Funding
Federal Funding 0 0 0 0 0 0 0 0 0 0 0
State Funding 0 0 0 0 0 0 0 0 0 0 0
Developer Contributions 0 0 0 0 0 0 0 0 0 0 0
New Bond Issue 0 0 0 0 0 0 0 0 0 0 0
PAYG 0 630 50 52 54 56 58 60 62 64 1,086
Short Term Finance 0 0 0 0 0 0 0 0 0 0 0
Stormwater Utility Fee Revenue 0 0 0 0 0 0 0 0 0 0 0
Other Funding 0 0 0 0 0 0 0 0 0 0 0
Subtotal New Funding 0 630 50 52 54 56 58 60 62 64 1,086
Previously Approved Funding
Authorized but Unissued
Bonds 0 0 0 0 0 0 0 0 0 0 0
Issued but Unspent Bonds 0 0 0 0 0 0 0 0 0 0 0
Other Previously Approved
Funds 0 0 0 0 0 0 0 0 0 0 0
Subtotal Previously Approved
Funding 0 0 0 0 0 0 0 0 0 0 0
Total Funding Sources 0 630 50 52 54 56 58 60 62 64 1,086
C - 56
Arlington County, Virginia
ECONOMIC DEVELOPMENT Capital Improvement Plan
Joint Use Facilities Maintenance FY 2025-2034
CULTURAL AFFAIRS - JOINT-USE SPACE MAINTENANCE AND
REPAIRS
Project Highlights:
• This project collaboratively addresses the maintenance and
repairs of the joint -use spaces which will enable groups and
individuals to use the theaters and the scenic studio.
Neighborhood(s):
VARIOUS
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
PAYG 630 50 52 54 56 58 60 62 64 1,086
Previous Funding
Total Funding 0 630 50 52 54 56 58 60 62 64 1,086
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Planning, Assessment, & Procurement Spring 2026
• Order, Delivery & Installation Fall 2026
Changes from Prior CIP:
This project is new for the FY 2025-2034 CIP.