Arlington County, Virginia
INFORMATION TECHNOLOGY/EQUIPMENT
Pr
ogram Description
The information technology (IT) and equipment maintenance capital program maintains the County's technology assets in order to 1)
sustain the County's existing business systems so they remain useful, operable and responsive to business needs, 2) best leverage the existing
infrastructure to support the business needs of the entire County as well as department specific applications, 3) reduce operating and support
costs associated with aging hardware, and 4) provide a reliable and secure environment for the operation of the County's syst ems while
furthering the County's goals for energy efficiency and worker productivity.
The IT systems, software, and hardware which serve departments typically reach the end of their useful life in three to ten years. At that
point, the systems become increasingly costly and more difficult to maintain, keep secure, and exchange information w ith other systems.
Priorities for determining which applications to replace first are driven by age, criticality of the system to operations, and availability of
ongoing support from the application's vendor. The IT systems and equipment are paid for through a combination of PAYG and short -
term financing, with operating impacts through principal and interest payments on the short -term finance as described in the Capital
Financing section of the CIP.
Pro
gram Summary
IT and equipment maintenance capital falls into four major program areas: Enterprise Information Technology (EIT), Lines of B usiness
Systems, Public Safety Technology, and General Equipment.
The Enterprise Information Technology capital improvement program funds four categories in accordance with the County's Digit al
Strategy:
• Maintenance Capital - Equipment includes the ongoing replacement of aging workforce devices (desktop computers, laptops
and tablets), servers, networks, audio visual, and other equipment, both employee and public facing. It also includes tools t o
support enhanced virtual government services and employee mobility.
• Hardware and Application Refreshment includes refreshment/replacement of software systems that provide key resources to
meet the County's internal and external demands. This includes upgrades to systems used County -wide such as the revenue and
collection system and the human resources and financial system.
• Data Migration & Consolidation addresses efforts to consolidate County Data Centers by migrating certain software applications
to cloud.
Line of Business Systems include special systems and equipment required for a department to maintain its specific operations and services.
This CIP funds replacement of existing line of business applications such as land records, and real estate assessment . It also includes
technology upgrades and new systems that the Department of Human Services requires for customer service and case management
replacement of electronic poll books.
The Public Safety Technology capital improvement program consists of key projects that will keep existing IT systems refreshed or replaced
on a reasonably expected life cycle (3 - 10 years) so that the systems remain useful, operable and responsive to public safety needs. Special
concerns for forecasting public safety technology requirements include: rapid technology advances that require upgrades and/o r
replacements; the need to maintain interoperability within the region; the need to maintain redundancies required for safety and to avoid
system failures; and responding to the changing needs of the workforce and the community. These issues may impact the needs of public
safety and the timing and scope of future projects. Four public safety agencies manage these projects: Police Department, Fire Department,
Department of Public Safety Communication and Emergency Management and the Office of the Sheriff. The public safety projects are
organized around lines of business rather than department. The key lines of business for public safety capital projects are Detention Center
Security, Facility Improvements, Public Safety, Communications, Public Safety IT Applications and Hardware, Response Equipment, Public
Safety Vehicle & Vehicle Technology.
Equipment includes machines used by individual departments for specific purpose s. This year’s CIP includes v oting machines and t ub
grinder for the Earth Products Yard.
Mas
ter Plan Impact
Advisory Commission: Information Technology (IT) Advisory Commission
D - 1
Arlington County, Virginia
INFORMATION TECHNOLOGY/EQUIPMENT
CIP
2025 − 2034
10 YE
AR CATEGORY SUMMARY (in $1,000s)
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year
Total
Enterprise Information
Technology
15,032 9,112 8,975 11,345 11,828 13,157 9,889 8,805 9,712 12,941 110,796
Lines of Business Systems 990 1,010 0 0 1,045 0 535 560 0 1,104 5,244
Detention Center Security 400 0 0 0 303 0 0 303 0 0 1,006
Facility Improvements 0 0 0 0 0 0 0 0 2,020 0 2,020
Public Safety Communications 2,850 4,899 2,020 0 0 2,121 2,121 0 4,828 5,404 24,243
Public Safety IT Applications
and Hardware
450 783 4,565 5,162 366 1,629 887 4,656 112 113 18,723
Response Equipment 700 278 0 0 0 4,080 404 0 539 4,858 10,859
Vehicles and Vehicle
Technology
0 1,126 6,985 61 9,594 4,545 8,476 5,726 0 0 36,513
Equipment 2,000 0 0 0 0 1,212 0 0 0 0 3,212
Total Recommendation 22,422 17,208 22,545 16,568 23,136 26,744 22,312 20,050 17,211 24,420 212,616
P
ROGRAM FUNDING SOURCES (in $1,000s)
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year
Total
New Funding
Federal Funding 0 0 0 0 0 0 0 0 0 0 0
State Funding 0 0 0 0 0 0 0 0 0 0 0
Developer Contributions 0 0 0 0 0 0 0 0 0 0 0
New Bond Issue 0 995 1,225 1,405 980 985 1,065 1,200 1,240 1,340 10,435
PAYG 9,043 7,838 5,104 9,764 5,910 5,279 6,630 6,130 6,034 5,650 67,382
Short Term Finance 9,550 8,100 16,216 5,399 16,246 20,480 14,617 12,720 9,937 17,430 130,695
Stormwater Utility Fee Revenue 0 0 0 0 0 0 0 0 0 0 0
Other Funding 0 0 0 0 0 0 0 0 0 0 0
Subtotal New Funding 18,593 16,933 22,545 16,568 23,136 26,744 22,312 20,050 17,211 24,420 208,512
Previously Approved Funding
Authorized but Unissued
Bonds 0 0 0 0 0 0 0 0 0 0 0
Issued but Unspent Bonds 3,829 275 0 0 0 0 0 0 0 0 4,104
Other Previously Approved
Funds 0 0 0 0 0 0 0 0 0 0 0
Subtotal Previously Approved
Funding 3,829 275 0 0 0 0 0 0 0 0 4,104
Total Funding Sources 22,422 17,208 22,545 16,568 23,136 26,744 22,312 20,050 17,211 24,420 212,616