Arlington County, Virginia CIP
2025 − 2034
INFORMATION TECHNOLOGY/EQUIPMENT: DETENTION CENTER
SECURITY PROGRAM
10 YEAR CATEGORY SUMMARY (in $1,000s)
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year
Total
1. Body Scanner Replacement
in Detention Center
100 0 0 0 303 0 0 0 0 0 403
2. Courthouse Magnetometer /
X-Ray Machine
300 0 0 0 0 0 0 303 0 0 603
Total Recommendation 400 0 0 0 303 0 0 303 0 0 1,006
CATEGORY FUNDING SOURCES (in $1,000s)
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year
Total
New Funding
Federal Funding 0 0 0 0 0 0 0 0 0 0 0
State Funding 0 0 0 0 0 0 0 0 0 0 0
Developer Contributions 0 0 0 0 0 0 0 0 0 0 0
New Bond Issue 0 0 0 0 0 0 0 0 0 0 0
PAYG 400 0 0 0 303 0 0 303 0 0 1,006
Short Term Finance 0 0 0 0 0 0 0 0 0 0 0
Stormwater Utility Fee Revenue 0 0 0 0 0 0 0 0 0 0 0
Other Funding 0 0 0 0 0 0 0 0 0 0 0
Subtotal New Funding 400 0 0 0 303 0 0 303 0 0 1,006
Previously Approved Funding
Authorized but Unissued
Bonds 0 0 0 0 0 0 0 0 0 0 0
Issued but Unspent Bonds 0 0 0 0 0 0 0 0 0 0 0
Other Previously Approved
Funds 0 0 0 0 0 0 0 0 0 0 0
Subtotal Previously Approved
Funding 0 0 0 0 0 0 0 0 0 0 0
Total Funding Sources 400 0 0 0 303 0 0 303 0 0 1,006
D - 22
INFORMATION TECHNOLOGY/EQUIPMENT Capital Improvement Plan
Detention Center Security FY 2025-2034
1. BODY SCANNER REPLACEMENT IN DETENTION CENTER
Project Highlights:
• The Full Body Screening Security Station is a critical tool to
enhance the capabilities of Arlington County Sheriff's Office
(ACSO) personnel in the screening and detection of
contraband.
• Identifying contraband substances quickly increases inmate
and staff safety, potentially reducing or eliminating the need
for hospital transports.
• Use of the system provides a greater level of privacy to
inmates by eliminating the need for strip searches.
• The system also serves as a deterrent for those contemplating
smuggling contraband into the Arlington County Detention
Facility.
• The useful life of the equipment is ten years.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
PAYG 100 303 403
Previous Funding
Total Funding 100 0 0 0 303 0 0 0 0 0 403
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Planning, Assessment and Procurement 3 months
• Order, Delivery and Testing of Equipment 9 months
Changes from Prior CIP:
The previous CIP called for a system replacement in FY 2024 and
FY 2029. However, by extending the warranty in FY 2025 the
useful of the equipment is now 10 years. The current scanner is
due for full replacement in FY 2029.
D - 23
INFORMATION TECHNOLOGY/EQUIPMENT Capital Improvement Plan
Detention Center Security FY 2025-2034
2. COURTHOUSE MAGNETOMETER / X-RAY MACHINE
Project Highlights:
• The magnetometer and X -ray machines reside in the Courts
Building.
• This equipment is used to screen all visitors to the building
for potentially threatening items and assist in maintaining
security in the Courthouse.
• The useful life of the equipment is seven to ten years.
Funding Notes: Replacement is scheduled in FY 2025 and FY 2032 according to the equipment’s seven-year useful life.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
PAYG 300 303 603
Previous Funding
Total Funding 300 0 0 0 0 0 0 303 0 0 603
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Planning, Assessment and Procurement
Review
3 months
• Order, delivery and testing of equipment 9 months
Ch
anges from Prior CIP:
Funding amounts are updated to include replacement in FY 2025
and FY 2032 according to the useful life of the equipment.
D - 24