10 YEAR CATEGORY SUMMARY (in $1,000s)
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year
Total
1. Fire Station Alerting System 0 0 0 0 0 0 0 0 2,020 0 2,020
Total Recommendation 0 0 0 0 0 0 0 0 2,020 0 2,020
CATEGORY FUNDING SOURCES (in $1,000s)
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year
Total
New Funding
Federal Funding 0 0 0 0 0 0 0 0 0 0 0
State Funding 0 0 0 0 0 0 0 0 0 0 0
Developer Contributions 0 0 0 0 0 0 0 0 0 0 0
New Bond Issue 0 0 0 0 0 0 0 0 0 0 0
PAYG 0 0 0 0 0 0 0 0 0 0 0
Short Term Finance 0 0 0 0 0 0 0 0 2,020 0 2,020
Stormwater Utility Fee Revenue 0 0 0 0 0 0 0 0 0 0 0
Other Funding 0 0 0 0 0 0 0 0 0 0 0
Subtotal New Funding 0 0 0 0 0 0 0 0 2,020 0 2,020
Previously Approved Funding
Authorized but Unissued
Bonds 0 0 0 0 0 0 0 0 0 0 0
Issued but Unspent Bonds 0 0 0 0 0 0 0 0 0 0 0
Other Previously Approved
Funds 0 0 0 0 0 0 0 0 0 0 0
Subtotal Previously Approved
Funding 0 0 0 0 0 0 0 0 0 0 0
Total Funding Sources 0 0 0 0 0 0 0 0 2,020 0 2,020
D - 25
INFORMATION TECHNOLOGY/EQUIPMENT Capital Improvement Plan
Facility Improvements FY 2025-2034
1. FIRE STATION ALERTING SYSTEM
Project Highlights:
• System used to alert and dispatch Fire personnel and
apparatus.
• Reliable systems lead to reductions in response time.
• The cost to add this equipment to future fire stations will be
built into the construction cost of those facilities.
• The useful life of the system is ten years.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Short Term Finance 2,020 2,020
Previous Funding
Total Funding 0 0 0 0 0 0 0 0 2,020 0 2,020
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Evaluate current system and review
requirements
4 months
• Procurement and negotiation 9 months
• Implementation 6 months
Ch
anges from Prior CIP:
Funding changes reflect cost increases due to inflation and
shifting replacement from FY 2031 to FY 2033 to align with the
equipment's useful life of 10 years.