RecordWell Data

Facility Improvements Program(PDF, 792KB)

Arlington County · Arlington County · Budget documents

Open the original document More from Arlington County

Text

Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.

Arlington County, Virginia CIP 2025 − 2034 INFORMATION TECHNOLOGY/EQUIPMENT: FACILITY IMPROVEMENTS PROGRAM 10 YEAR CATEGORY SUMMARY (in $1,000s) FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year Total 1. Fire Station Alerting System 0 0 0 0 0 0 0 0 2,020 0 2,020 Total Recommendation 0 0 0 0 0 0 0 0 2,020 0 2,020 CATEGORY FUNDING SOURCES (in $1,000s) FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year Total New Funding Federal Funding 0 0 0 0 0 0 0 0 0 0 0 State Funding 0 0 0 0 0 0 0 0 0 0 0 Developer Contributions 0 0 0 0 0 0 0 0 0 0 0 New Bond Issue 0 0 0 0 0 0 0 0 0 0 0 PAYG 0 0 0 0 0 0 0 0 0 0 0 Short Term Finance 0 0 0 0 0 0 0 0 2,020 0 2,020 Stormwater Utility Fee Revenue 0 0 0 0 0 0 0 0 0 0 0 Other Funding 0 0 0 0 0 0 0 0 0 0 0 Subtotal New Funding 0 0 0 0 0 0 0 0 2,020 0 2,020 Previously Approved Funding Authorized but Unissued Bonds 0 0 0 0 0 0 0 0 0 0 0 Issued but Unspent Bonds 0 0 0 0 0 0 0 0 0 0 0 Other Previously Approved Funds 0 0 0 0 0 0 0 0 0 0 0 Subtotal Previously Approved Funding 0 0 0 0 0 0 0 0 0 0 0 Total Funding Sources 0 0 0 0 0 0 0 0 2,020 0 2,020 D - 25 INFORMATION TECHNOLOGY/EQUIPMENT Capital Improvement Plan Facility Improvements FY 2025-2034 1. FIRE STATION ALERTING SYSTEM Project Highlights: • System used to alert and dispatch Fire personnel and apparatus. • Reliable systems lead to reductions in response time. • The cost to add this equipment to future fire stations will be built into the construction cost of those facilities. • The useful life of the system is ten years. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Short Term Finance 2,020 2,020 Previous Funding Total Funding 0 0 0 0 0 0 0 0 2,020 0 2,020 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • Evaluate current system and review requirements 4 months • Procurement and negotiation 9 months • Implementation 6 months Ch anges from Prior CIP: Funding changes reflect cost increases due to inflation and shifting replacement from FY 2031 to FY 2033 to align with the equipment's useful life of 10 years. D - 26

Source: Arlington County website. First collected Oct 18, 2026.