PUBLIC WORKS, SEWER & WATER COMMITTEE-
DATE: Monday October 26, 2026 TIME: 5:30 PM
LOCATION: VERONA CITY HALL
ROOM D122
111 LINCOLN STREET
VERONA, WI 53593
1. Call to Order:
2. Roll:
3. Public Comment:
4. Approval of the Minutes:
5. Discussion and Possible Action: Project 2022-107 Military Ridge State Trail Bridges-Paving. Pay
request #2. Janke General Contractors.
6. Discussion and Possible Action: Ordinance No. 26-1 - Amending Title 8, Chapters 3 and 4,
Recycling and Refuse Disposal and Collection.
7. Discussion and Possible Action: Request to reconsider recommendation to Council Action April
27, 2026, Related to South Main Street.
8. Staff Report:
9. Adjourn:
Beth Tucker Long - Chairperson
POSTED: October 22, 2026
POSTED: Verona City Hall
Verona Public Library
Miller’s Market
All agendas are posted on the City website at: veronawi.gov
WRITTEN COMMENTS: You can send comments to the Public Works, Sewer & Water Committee on any matter, either on or not on the
agenda, by emailing bmanning@veronawi.gov or in writing to Public Works, Sewer & Water Committee, 410 Investment Court, Verona, WI,
53593.
Notice: If you need an interpreter, materials in alternative formats, or other accommodation to access the meeting, please contact the City
Clerk at (608) 845-6495 at least 48-hours preceding the meeting. Every reasonable effort will be made to accommodate your request.
Notice is hereby given that a majority of the City Council may be present at the meeting of the Public Works, Sewer & Water Committee to
gather information about a subject over which they have decision-making responsibility. The City Council and any other standing
committees will not take formal action at this meeting.
City of Verona
111 Lincoln Street
Verona, WI 53593
(608) 845-6495
veronawi.gov
PUBLIC WORKS, SEWER & WATER COMMITTEE-
DATE: Monday October 12, 2026 TIME: 5:30 PM
LOCATION: VERONA CITY HALL
ROOM D122
111 LINCOLN STREET
VERONA, WI 53593
1. Call to Order: Meeting called to order at 5:30 pm by Alder Beth Tucker Long.
2. Roll: Beth Tucker Long, Alejandro Hernandez, Chris Weiss, also present, Rick Eilertson -AE COM,
Bryan Manning- Public Works Director, Jamie Aulik-City Administrator, Mike Trotter- Assistant Public
Work Director.
3. Public Comment: None.
4. Approval of the Minutes: Moved by Alder Weiss and seconded by Alder Hernandez to approve the
minutes of the September 28th meeting. Motion passed 3-0.
5. Discussion and Possible Action: Project 2024-105 Mark Drive Reconstruction Ph 2. Pay request
#4 Northwestern Stone LLC. Move by Alder Tucker Long and seconded by Alder Hernandez to
approve Project 2024-105 Mark Drive Reconstruction Phase 2, pay request #4 Northwestern Stone for
a sum not to exceed $394,048.68. Motion passed 3-0.
6. Discussion and Possible Action: Project 2022-107 Military Ridge State Trail Bridges-Paving. Pay
request #1. Janke General Contractors. Moved by Alder Weiss and seconded by Alder Hernandez to
approve Project 2022-107 Military Ridge State Trail Bridges-Paving, pay request #1 Janke General
Contractors for a sum not to exceed $161,463.47. Motion passed 3-0.
7. Discussion and Possible Action: Request to reconsider recommendation to Council Action April
27, 2026, Related to South Main Street. Move by Alder Tucker Long and seconded by Alder
Hernandez to recommend to Common Council that staff put together pros, cons, and consideration of
placing a southern sidewalk crossing on South Main Street, or a multi directional path on the east side
of south Main Street from 463 to Melondy Lane and have a Traffic Engineer present at the October 26
PWSW Committee meeting for discussion. Motion passed 3-0.
8. Staff Report:
9. Adjourn: Moved by Alder Tucker Long and seconded by Alder Weiss to Adjourn at 6:34 pm. Motion
Passed 3-0.
Beth Tucker Long - Chairperson
POSTED: October 8, 2026
POSTED: Verona City Hall
Verona Public Library
Miller’s Market
All agendas are posted on the City website at: veronawi.gov
WRITTEN COMMENTS: You can send comments to the Public Works, Sewer & Water Committee on any matter, either on or not on the
agenda, by emailing bmanning@veronawi.gov or in writing to Public Works, Sewer & Water Committee, 410 Investment Court, Verona, WI,
53593.
Notice: If you need an interpreter, materials in alternative formats, or other accommodation to access the meeting, please contact the City
Clerk at (608) 845-6495 at least 48-hours preceding the meeting. Every reasonable effort will be made to accommodate your request.
Notice is hereby given that a majority of the City Council may be present at the meeting of the Public Works, Sewer & Water Committee to
gather information about a subject over which they have decision-making responsibility. The City Council and any other standing
committees will not take formal action at this meeting.
Meeting Date: Monday October 26, 2026
PW/S&W Committee Memo
Page 1 / 2
Public Works/Sewer & Water Committee
Listed below is an explanation of the items on the Public Works/Sewer & Water Committee
agenda.
Item (5) Discussion and Possible Action: Project 2022-107 Military Ridge State Trail
Bridges-Paving. Pay request #2. Janke General Contractors.
Memo: This pay application covers completed work and purchased materials. Staff
inspected and verified the work and reviewed the application.
Recommended Motion: Move to approve Project 2022-107 Military Ridge State Trail
Bridges-Paving. Pay request #2. Janke General Contractors for a sum not to exceed
$184,910.08.
Item (6) Discussion and Possible Action: Ordinance No. 26-1 - Amending Title 8,
Chapters 3 and 4, Recycling and Refuse Disposal and Collection.
Memo: The proposed ordinance amends the City’s recycling and refuse regulations to incorporate the
City’s collection contract with Pellitteri and clarify collection requirements. The amendments establish
requirements for recycling cart placement and preparation, require the City to post its collection
contract on the City website, and clarify placement and timing requirements for oversize and bulky
waste. Specifically, oversize, and bulky waste must be placed immediately behind the curb or adjacent
to an alley, where applicable, and may not be placed on snowbanks or in the roadway during winter
months. The ordinance also clarifies that oversize and bulky waste is subject to the same collection
timing requirements as other refuse, including placement before 7:00 a.m. on collection day, but no
more than 24 hours in advance.
Recommended Motion: Move to recommend Ordinance No. 26-1 - Amending Title 8,
Chapters 3 and 4, Recycling and Refuse Disposal and Collection.
Item (7) Discussion and Possible Action: Request to reconsider recommendation to
Council Action April 27, 2026, Related to South Main Street.
Memo: At the October 12, 2026, Council meeting, staff to create a pros and cons list to
find the safest scenario on the east side of South Main St. and to have the traffic engineer
available at the next meeting this item is discussed. At the Council meeting, Traffic Safety
Engineering Staff will be on hand to give a presentation related to this item and answer
questions.
Meeting Date: Monday October 26, 2026
PW/S&W Committee Memo
Page 2 / 2
Recommended Motion: Recommend request to reconsider recommendation to
Council Action April 27, 2026, Related to South Main Street.
Staff Report
Streets Started speed hump install on Aspen,
Curb & gutter/inlet repair, Asphalt patching, Street Sweeping, Started Fall leaf collection, Manhole repair.
Utility Cleaning Sewers, Curb stop Repair, Water Samples, Working on Well 6 Heat Pump Well 5,
Generator Start Up at Locust Lift Station, Fog Program, Fire Flow Testing, Manhole repairs.
REQUEST AND CERTIFICATE FOR PAYMENT
PROJECT: Military Ridge State Trail - Pedestrian Structures REQUEST NO.: 2 REQUEST DATE: 10/19/2026
OWNER: City of Verona CONTRACTOR: Janke General Contractors ENGINEER: Joe Jirsa
City of Verona - Public Works 1224 Mount View Lane City of Verona - Public Works
410 Investment Court Verona, WI 53593 Athens, WI 54411 410 Investment Court Verona, WI 53593
CHANGE ORDER SUMMARY Request is made for payment, as shown below, in connection
Previously Approved Change Orders: Additions Deductions with the contract. Continuation Sheet is attached.
The present status of the contract is as follows:
ORIGINAL CONTRACT SUM:……………………………………………..….. $ 1,607,360.37
NET CHANGE BY CHANGE ORDERS:…………………………………………..$ -
CONTRACT SUM TO DATE:………………………………………………………$ 1,607,360.37
Current Change Order Additions Deductions
TOTAL COMPLETED TO DATE:…………………..……………………………..$ 364,603.74
RETAINAGE %:....... 5.00% RETAINAGE:….................................. $ 18,230.19
Net Change by Change Orders: $ - $ -
The undersigned CONTRACTOR certifies that (1) all previous progress payments received from OWNER on account of
work completed under the contract referred to above have been applied to discharge in full, all obligations of
CONTRACTOR incurred in connection with the work covered by prior applications for payment numbered _1_ through _1_
inclusive (none); and (2) title to all materials and equipment incorporated in said work or otherwise listed in or covered by
this application for payment will pass to OWNER at time of payment free and clear of all liens, claims, security interests, and
encumbrances (except such as covered by Bond acceptable to OWNER).
TOTAL EARNED LESS RETAINAGE:……………….………………………….. $ 346,373.55
LESS PREVIOUS CERTIFICATES FOR PAYMENT:……………................ $ 161,463.47
CURRENT PAYMENT DUE:………………………………………………………….$ 184,910.08
Submitted by Contractor: Date:
I herby certify that I have reviewed the work and that to the best of my knowledge and belief, the quantities shown in this estimate are correct. This application is in conformance with the Contract
Documents, therefore, I recommend payment of
Recommended by Engineer: Date:
Approved by Owner: Date:
Military Ridge State Trail - Pedestrian Structures - PAR 02 -10.19.26 REV.xlsx
10.19.2026
Mike Rausch
CONTINUATION SHEET REQUEST AND CERTIFICATE FOR PAYMENT -CONTRACTOR'S SIGNED CERTIFICATE IS ATTACHED
Item No.
(A)
Description of Work
(B)
Unit of
Measure
Scheduled
Quantity
(C)
Unit Price
(D)
Item Total
(C * D)
Work Completed
Total Completed To Date (E + F) Percent
Complete
Previous Requests (E) This Request (F)
Quantity Amount Quantity Amount Quantity Amount
1 Clearing STA 5 $ 2,525.00 $ 12,625.00 3.00 $ 7,575.00 $ - 3.00 $ 7,575.00 60.00%
2 Grubbing STA 5 $ 2,170.00 $ 10,850.00 2.00 $ 4,340.00 $ - 2.00 $ 4,340.00 40.00%
3 Removing Structure (structure) (01. NR-13-32) EACH 1 $ 42,956.00 $ 42,956.00 $ - $ - 0.00 $ - 0.00%
4 Removing Structure (structure) (02. NR-13-33) EACH 1 $ 34,000.00 $ 34,000.00 0.90 $ 30,600.00 $ - 0.90 $ 30,600.00 90.00%
5 Removing Structure (structure) (03. NR-13-34) EACH 1 $ 31,372.00 $ 31,372.00 $ - $ - 0.00 $ - 0.00%
6 Removing Concrete Pavement SY 462 $ 56.50 $ 26,103.00 $ - 112.00 $ 6,328.00 112.00 $ 6,328.00 24.24%
7 Removing Storm Sewer (size) (01. 8-INCH) LF 15 $ 38.20 $ 573.00 $ - 15.00 $ 573.00 15.00 $ 573.00 100.00%
8 Removing Storm Sewer (size) (02. 15-INCH) LF 16 $ 43.15 $ 690.40 $ - 16.00 $ 690.40 16.00 $ 690.40 100.00%
9 Removing Storm Sewer (size) (03. 36-INCH) LF 24 $ 65.45 $ 1,570.80 24.00 $ 1,570.80 $ - 24.00 $ 1,570.80 100.00%
10 Removing Storm Sewer (size) (04. 42-INCH) LF 22 $ 71.45 $ 1,571.90 $ - 22.00 $ 1,571.90 22.00 $ 1,571.90 100.00%
11 Excavation for Structures Bridges (structure) (01. NR-13-32) EACH 1 $ 11,985.00 $ 11,985.00 $ - $ - 0.00 $ - 0.00%
12 Excavation for Structures Bridges (structure) (02. NR-13-34) EACH 1 $ 11,200.00 $ 11,200.00 $ - $ - 0.00 $ - 0.00%
13 Excavation for Structures Culverts (structure) (01. NR-13-33) EACH 1 $ 51,255.00 $ 51,255.00 0.90 $ 46,129.50 0.05 $ 2,562.75 0.95 $ 48,692.25 95.00%
14 Backfill Structure Type A TON 322 $ 34.00 $ 10,948.00 $ - $ - 0.00 $ - 0.00%
15 Backfill Structure Type B TON 340 $ 34.00 $ 11,560.00 $ - 320.87 $ 10,909.58 320.87 $ 10,909.58 94.37%
16 Base Aggregate Dense 1 1/4-Inch TON 183 $ 31.35 $ 5,737.05 $ - $ - 0.00 $ - 0.00%
17 Base Aggregate Dense 3-Inch TON 207 $ 30.80 $ 6,375.60 $ - $ - 0.00 $ - 0.00%
18 Breaker Run TON 125 $ 37.00 $ 4,625.00 $ - 133.98 $ 4,957.26 133.98 $ 4,957.26 107.18%
19 Concrete Pavement 6-Inch SY 41 $ 159.00 $ 6,519.00 $ - $ - 0.00 $ - 0.00%
20 Concrete Pavement Approach Slab SY 64 $ 278.00 $ 17,792.00 $ - $ - 0.00 $ - 0.00%
21 Drilled Tie Bars EACH 2 $ 90.50 $ 181.00 $ - $ - 0.00 $ - 0.00%
22 Concrete Masonry Bridges CY 74 $ 1,647.00 $ 121,878.00 $ - $ - 0.00 $ - 0.00%
23 Protective Surface Treatment SY 309 $ 4.50 $ 1,390.50 $ - $ - 0.00 $ - 0.00%
24 Concrete Masonry Culverts CY 15 $ 1,585.00 $ 23,775.00 $ - 9.00 $ 14,265.00 9.00 $ 14,265.00 60.00%
25 Precast Concrete Box Culvert (ft X ft) (01. 8 FT x 4 FT) LF 128 $ 1,100.00 $ 140,800.00 32.00 $ 35,200.00 96.00 $ 105,600.00 128.00 $ 140,800.00 100.00%
26 Bar Steel Reinforcement HS Structures LB 5290 $ 2.00 $ 10,580.00 $ - 570.00 $ 1,140.00 570.00 $ 1,140.00 10.78%
27 Bar Steel Reinforcement HS Coated Structures LB 6870 $ 2.00 $ 13,740.00 $ - 100.00 $ 200.00 100.00 $ 200.00 1.46%
28 Prefabricated Steel Truss Pedestrian Bridge LRFD (structure) (01. NR-13-32) EACH 1 $ 127,700.00 $ 127,700.00 $ - $ - 0.00 $ - 0.00%
29 Prefabricated Steel Truss Pedestrian Bridge LRFD (structure) (02. NR-13-34) EACH 1 $ 97,545.00 $ 97,545.00 $ - $ - 0.00 $ - 0.00%
30 Rubberized Membrane Waterproofing SY 31 $ 34.00 $ 1,054.00 $ - $ - 0.00 $ - 0.00%
31 Concrete Collars for Pipe EACH 4 $ 1,310.00 $ 5,240.00 $ - $ - 0.00 $ - 0.00%
32 Piling Steel HP 10-Inch X 42 Lb LF 850 $ 82.25 $ 69,912.50 $ - $ - 0.00 $ - 0.00%
33 Riprap Medium CY 208 $ 106.00 $ 22,048.00 $ - 33.00 $ 3,498.00 33.00 $ 3,498.00 15.87%
34 Riprap Heavy CY 305 $ 106.00 $ 32,330.00 $ - $ - 0.00 $ - 0.00%
35 Relaid Storm Sewer 36-Inch LF 24 $ 84.00 $ 2,016.00 $ - $ - 0.00 $ - 0.00%
36 Pipe Underdrain Wrapped 6-Inch LF 184 $ 14.60 $ 2,686.40 $ - $ - 0.00 $ - 0.00%
37 Maintenance and Repair of Haul Roads (project) (01. 2022-107) EACH 1 $ 903.00 $ 903.00 $ - $ - 0.00 $ - 0.00%
38 Mobilization EACH 1 $ 165,000.00 $ 165,000.00 0.20 $ 33,000.00 0.05 $ 8,250.00 0.25 $ 41,250.00 25.00%
39 Water MGAL 6 $ 18.75 $ 112.50 $ - $ - 0.00 $ - 0.00%
40 Topsoil SY 3155 $ 11.25 $ 35,493.75 $ - $ - 0.00 $ - 0.00%
41 Mulching SY 631 $ 0.70 $ 441.70 $ - $ - 0.00 $ - 0.00%
42 Silt Fence LF 2102 $ 2.25 $ 4,729.50 100.00 $ 225.00 $ - 100.00 $ 225.00 4.76%
43 Silt Fence Maintenance LF 2102 $ 0.01 $ 21.02 $ - $ - 0.00 $ - 0.00%
44 Mobilizations Erosion Control EACH 12 $ 250.00 $ 3,000.00 1.00 $ 250.00 $ - 1.00 $ 250.00 8.33%
45 Mobilizations Emergency Erosion Control EACH 9 $ 250.00 $ 2,250.00 $ - $ - 0.00 $ - 0.00%
46 Erosion Mat Urban Class I Type B SY 2968 $ 1.85 $ 5,490.80 $ - $ - 0.00 $ - 0.00%
47 Erosion Mat Class II Type A SY 188 $ 2.45 $ 460.60 $ - $ - 0.00 $ - 0.00%
48 Turbidity Barriers SY 74 $ 40.00 $ 2,960.00 $ - $ - 0.00 $ - 0.00%
49 Inlet Protection Type C EACH 2 $ 75.00 $ 150.00 $ - 1.00 $ 75.00 1.00 $ 75.00 50.00%
50 Culvert Pipe Checks EACH 50 $ 20.00 $ 1,000.00 $ - $ - 0.00 $ - 0.00%
51 Tracking Pads EACH 5 $ 1,900.00 $ 9,500.00 $ - $ - 0.00 $ - 0.00%
52 Rock Bags EACH 75 $ 15.00 $ 1,125.00 16.00 $ 240.00 $ - 16.00 $ 240.00 21.33%
53 Fertilizer Type B CWT 1 $ 100.00 $ 100.00 $ - $ - 0.00 $ - 0.00%
54 Seeding Mixture No. 20 LB 128 $ 13.00 $ 1,664.00 $ - $ - 0.00 $ - 0.00%
55 Seeding Mixture No. 40 LB 18 $ 22.00 $ 396.00 $ - $ - 0.00 $ - 0.00%
56 Seeding Temporary LB 88 $ 3.00 $ 264.00 $ - $ - 0.00 $ - 0.00%
57 Seed Water MGAL 65 $ 30.00 $ 1,950.00 $ - $ - 0.00 $ - 0.00%
58 Signs Type II Reflective F SF 4 $ 25.00 $ 100.00 $ - $ - 0.00 $ - 0.00%
59 Moving Signs Type II EACH 7 $ 100.00 $ 700.00 $ - $ - 0.00 $ - 0.00%
60 Removing Signs Type II EACH 20 $ 35.00 $ 700.00 $ - $ - 0.00 $ - 0.00%
61 Moving Small Sign Supports EACH 7 $ 100.00 $ 700.00 $ - $ - 0.00 $ - 0.00%
62 Field Office Type B EACH 1 $ 5,390.00 $ 5,390.00 $ - $ - 0.00 $ - 0.00%
63 Traffic Control Drums DAY 5780 $ 0.28 $ 1,618.40 $ - $ - 0.00 $ - 0.00%
64 Traffic Control Barricades Type III DAY 4040 $ 0.40 $ 1,616.00 $ - $ - 0.00 $ - 0.00%
65 Traffic Control Warning Lights Type A DAY 5600 $ 0.15 $ 840.00 $ - $ - 0.00 $ - 0.00%
66 Traffic Control Signs DAY 18620 $ 0.35 $ 6,517.00 $ - $ - 0.00 $ - 0.00%
67 Traffic Control Covering Signs Type II EACH 4 $ 25.00 $ 100.00 $ - $ - 0.00 $ - 0.00%
Military Ridge State Trail - Pedestrian Structures - PAR 02 -10.19.26 REV.xlsx
68 Temporary Marking Crosswalk Removable Tape 6-Inch LF 102 $ 1.55 $ 158.10 $ - $ - 0.00 $ - 0.00%
69 Traffic Control EACH 1 $ 6,000.00 $ 6,000.00 0.25 $ 1,500.00 $ - 0.25 $ 1,500.00 25.00%
70 Temporary Pedestrian Curb Ramp DAY 120 $ 17.00 $ 2,040.00 $ - $ - 0.00 $ - 0.00%
71 Temporary Pedestrian Detectable Warning Field SF 128 $ 2.00 $ 256.00 $ - $ - 0.00 $ - 0.00%
72 Temporary Pedestrian Barricade LF 262 $ 5.05 $ 1,323.10 $ - $ - 0.00 $ - 0.00%
73 Temporary Audible Message Devices DAY 1840 $ 3.25 $ 5,980.00 $ - $ - 0.00 $ - 0.00%
74 Geotextile Type C SY 250 $ 3.30 $ 825.00 $ - 250.00 $ 825.00 250.00 $ 825.00 100.00%
75 Geotextile Type DF Schedule A SY 124 $ 2.65 $ 328.60 $ - 49.00 $ 129.85 49.00 $ 129.85 39.52%
76 Geotextile Type HR SY 1027 $ 3.45 $ 3,543.15 $ - 66.00 $ 227.70 66.00 $ 227.70 6.43%
77 Construction Staking Subgrade LF 540 $ 2.00 $ 1,080.00 $ - $ - 0.00 $ - 0.00%
78 Construction Staking Base LF 540 $ 3.50 $ 1,890.00 $ - $ - 0.00 $ - 0.00%
79 Construction Staking Structure Layout (structure) (01. NR-13-032) EACH 1 $ 4,500.00 $ 4,500.00 $ - $ - 0.00 $ - 0.00%
80 Construction Staking Structure Layout (structure) (02. NR-13-033) EACH 1 $ 5,500.00 $ 5,500.00 0.50 $ 2,750.00 0.50 $ 2,750.00 1.00 $ 5,500.00 100.00%
81 Construction Staking Structure Layout (structure) (03. NR-13-034) EACH 1 $ 4,000.00 $ 4,000.00 $ - $ - 0.00 $ - 0.00%
82 Construction Staking Supplemental Control (project) (01. 2022-107) EACH 1 $ 8,000.00 $ 8,000.00 $ - 0.50 $ 4,000.00 0.50 $ 4,000.00 50.00%
83 Construction Staking Slope Stakes LF 540 $ 4.00 $ 2,160.00 $ - $ - 0.00 $ - 0.00%
84 Crack and Damage Survey EACH 1 $ 10,000.00 $ 10,000.00 $ - $ - 0.00 $ - 0.00%
85 Special (01. Unstable Trench Bottom and Crushed Stone Stabilization (Sanitary
Sewer))
CY 14 $ 155.00 $ 2,170.00 $ - $ - 0.00 $ - 0.00%
86 Special (01. Trail Reconstruction for Site Access NR-13-032) EACH 1 $ 6,957.00 $ 6,957.00 $ - $ - 0.00 $ - 0.00%
87 Special (02. Trail Reconstruction for Site Access NR-13-033) EACH 1 $ 6,625.00 $ 6,625.00 $ - $ - 0.00 $ - 0.00%
88 Special (03. Trail Reconstruction for Site Access NR-13-034) EACH 1 $ 6,325.00 $ 6,325.00 $ - $ - 0.00 $ - 0.00%
89 Special (04. Salvage and Reinstall Rectangular Rapid Flashing Beacon Units) EACH 1 $ 2,890.00 $ 2,890.00 $ - $ - 0.00 $ - 0.00%
90 Special (05. Connection to Existing Manhole) EACH 2 $ 1,760.00 $ 3,520.00 $ - $ - 0.00 $ - 0.00%
91 Special (06. Relaid Apron Endwall) EACH 1 $ 1,415.00 $ 1,415.00 $ - $ - 0.00 $ - 0.00%
92 Special (07. Temporary Water Diversion (STA 163+97.15)) EACH 1 $ 26,325.00 $ 26,325.00 0.25 $ 6,581.25 0.50 $ 13,162.50 0.75 $ 19,743.75 75.00%
93 Special (08. Grading and Shaping Trail NR-13-032) EACH 1 $ 13,410.00 $ 13,410.00 $ - $ - 0.00 $ - 0.00%
94 Special (09. Grading and Shaping Trail NR-13-033) EACH 1 $ 51,705.00 $ 51,705.00 $ - 0.25 $ 12,926.25 0.25 $ 12,926.25 25.00%
95 Special (10. Grading and Shaping Trail NR-13-034) EACH 1 $ 2,055.00 $ 2,055.00 $ - $ - 0.00 $ - 0.00%
96 Special (11. Construction Staking Concrete Pad) EACH 1 $ 2,000.00 $ 2,000.00 $ - $ - 0.00 $ - 0.00%
97 Special (02. Fence Timber 4.5-FT) LF 288 $ 84.00 $ 24,192.00 $ - $ - 0.00 $ - 0.00%
98 Special (03. Decorative Fence 4.5-FT) LF 65 $ 568.00 $ 36,920.00 $ - $ - 0.00 $ - 0.00%
99 Special (04. Replacement Sanitary Sewer 12-Inch) LF 123 $ 130.00 $ 15,990.00 $ - $ - 0.00 $ - 0.00%
100 Special (01. Dewatering) LS 1 $ 7,236.00 $ 7,236.00 $ - $ - 0.00 $ - 0.00%
102 Special (01. Insulation) SF 431 $ 5.00 $ 2,155.00 $ - $ - 0.00 $ - 0.00%
103 Special (01. Trench Backfill (Sanitary Sewer)) TF 123 $ 32.00 $ 3,936.00 $ - $ - 0.00 $ - 0.00%
104 Special (01. Excavation, Hauling, and Disposal of Creosote Contaminated Soil TON 364 $ 148.00 $ 53,872.00 $ - $ - 0.00 $ - 0.00%
ALT 1 Bid Alternative 1 Piling Steel HP 10-Inch X 42 Lb LF 600 $ 86.00 $ 51,600.00 $ - $ - 0.00 $ - 0.00%
$ - $ - $ - 0.00 $ -
Original Contract Total: $ 1,607,360.37 $ 169,961.55 $ 194,642.19 $ 364,603.74
Change Orders REQUEST AND CERTIFICATE FOR PAYMENT -CONTRACTOR'S SIGNED CERTIFICATE IS ATTACHED
Item No.
(A)
Description of Work
(B)
Unit of
Measure
Scheduled
Quantity
(C)
Unit Price
(D)
Item Total
(C * D)
Work Completed
Total Completed To Date (E + F) Percent
Complete
Previous Requests (E) This Request (F)
Quantity Amount Quantity Amount Quantity Amount
$ - $ - $ - 0.00 $ -
$ - $ - $ - 0.00 $ -
$ - $ - $ - 0.00 $ -
$ - $ - $ - 0.00 $ -
$ - $ - $ - 0.00 $ -
$ - $ - $ - 0.00 $ -
$ - $ - $ - 0.00 $ -
$ - $ - $ - 0.00 $ -
$ - $ - $ - 0.00 $ -
Subtotal - Change Orders: $ - $ - $ - $ -
Project Total With Change Order: $ 1,607,360.37 $ 169,961.55 $ 194,642.19 $ 364,603.74
Military Ridge State Trail - Pedestrian Structures - PAR 02 -10.19.26 REV.xlsx
1
ORDINANCE NO. 26-XXX
AN ORDINANCE AMENDING TITLE 8, CHAPTERS 3 AND 4,
RECYCLING AND REFUSE DISPOSAL AND COLLECTION
The Common Council of the City of Verona, Dane County, Wisconsin, do ordain that Title
8, Chapters 3 and 4 of the Code of Ordinances, City of Verona, Wisconsin is hereby amended as
follows:
1. Section 8-3-17.5 is created to read as follows:
Sec. 8-3-17.5 – Collection of Recycling.
Residents shall properly prepare their recycling carts for curbside pickup. Collection shall
occur utilizing a cart owned by the collector/hauler with which the City is contracting. The
contractor shall empty the carts so long as the carts are placed curbside on their scheduled
days. Carts must be placed in an accessible curbside position (within two feet of street)
before 7:00 am on the scheduled days , but not more than twenty- four (24) hours prior to
such time . Proper preparation of cart includes the cart being placed in an accessible
location for the truck (e.g., not behind or within four (4) feet of parked cars, mailboxes, or
other obstructions). Proper preparation shall mean all recycling is contained within the
cart, cart lid closed, and the carts are placed curbside.
2. Section 8-3-21(d) is created to read as follows:
(d) The City shall post the contract between the City and the collector/hauler to the
City website, and any residents or properties receiving recycling services from the
City shall abide by the rules and regulations contained in the contract.
3. Section 8-4-12(a)(3) is created as follows:
(3) Oversize and Bulky Waste shall be placed immediately behind the curb of the
public street for collection or shall be placed immediately adjacent to the alley if
premises abut on an alley. During winter months, Oversize and Bulky Waste shall
not be placed on top of the snowbank, nor shall it be placed in the roadway.
4. Section 8-4-12(b)(1) is amended to read as follows:
(1) All garbage and refuse collected by the City under this Chapter shall be placed in
collection locations as designated in Subsection (a) above prior to 7:00 am. of the
scheduled collection day, but not more than twenty- four (24) hours prior to such
time. For avoidance of doubt, this includes Oversize and Bulky Waste.
2
5. Section 8-4-18(d) is created to read as follows:
(d) The City shall post the contract between the City and the collector/hauler to the
City website, and any residents or properties receiving refuse services from the City
shall abide by the rules and regulations contained in the contract.
6. This ordinance shall become effective upon passage and publication as required by law.
The foregoing ordinance was duly adopted by the Common Council of the City of Verona
at a meeting held on ______________, 2026.
CITY OF VERONA
_______________________
Luke Diaz, Mayor
(seal)
_______________________
Holly Licht, City Clerk
ADOPTED: _______________
PUBLISHED: _______________