OFFICIAL MEETING PACKET OF THE
PARKS AND RECREATION COMMITTEE
CHAIRPERSON/TRUSTEE BARBARA ERMELING PRESIDING
DIRECTOR OF PARKS AND RECREATION SHAWN OSTERBRINK; STAFF
ADVISOR
A meeting of the Parks and Recreation Committee, composed of five (5) appointed
members, will convene at Weston Municipal Center , which is located at 4747
Camp Phillips Road, Weston, October 26, 2026, at 4:00 p.m.
Village of Weston, Wisconsin
ATTENTION – NOTICE OF PUBLIC MEETING
Meeting: PARK AND RECREATION COMMITTEE
Members: Ermeling (C), Lopes Serrao (VC), Esker, Sleeter, Tatro
Ex-Officio: Maloney
Staff: Osterbrink, Falkowski
Date/Time: Monday, October 26, 2026, at 4:00 p.m.
Location: Weston Municipal Center, 4747 Camp Phillips Road, Weston, WI
54476
Agenda: The Agenda Packet will be sent out at least three (3) days prior to the
meeting.
Attendance: Parks and Recreation Committee Members, please indicate if you will
or will not be attending so we may determine in advance if there will
be a quorum.
Questions: Shawn Osterbrink Jessica Falkowski
sosterbrink@westonwi.gov jfalkowski@westonwi.gov
(715) 359-6114 (715) 359-6114
PLEASE NOTE THE FOLLOWING INFORMATION:
This notice was posted at the Municipal Center, and on the Village’s website at www.westonwi.gov, and was emailed
to local media outlets (Print, TV, and Radio) on 10/ 19/2026 @ 9:00 a.m. Any posted agenda is subject to change up
until 24 hours prior to the date and time of the meeting.
A quorum of members from other Village governmental bodies (boards, commissions, and committees) may attend the
above-noticed meeting to gather information. Should a quorum be other government bodies are present, this would
constitute a meeting pursuant to State ex rel. Badke v. Greendale Village Bd., 173 Wis.2d 553,494 N.W.2d 408 (1993).
Wisconsin State Statutes require all agendas for Committee, Commission, or Board meetings be posted in final form,
24 hours prior to the meeting.
Any person who has a qualifying disability, as defined by the Americans with Disabilities Act, requiring that meeting or
material to be in an accessible location or format, must contact the Weston Municipal Center at 715-359-6114, so any
necessary arrangements can be made to accommodate each request.
VILLAGE OF WESTON, WISCONSIN
OFFICIAL MEETING AGENDA OF THE PARKS AND RECREATION COMMITTEE
Parks and Recreation Committee Meeting – Agenda 10/26/2026
TO THE HONORABLE TRUSTEE ERMELING AND FOUR (4) APPOINTED MEMBERS OF
THE COMMITTEE: The following items were listed on the agenda in the Village Clerk’ s
Office, in accordance with Chapter 2 of the Village’s Municipal Code and will be ready for
your consideration at the regular meeting of the Parks and Recreation Committee on
Monday, October 26, 2026 @ 4:00 p.m., in the Village Board Room at the Weston Municipal
Center, 4747 Camp Phillips Road, Weston, WI 54476.
A quorum of members from other Village governmental bodies (boards, commissions, and committees) may/might
attend the above-noticed meeting to gather information. Should a quorum of other government bodies be present,
this would constitute a meeting pursuant to State ex rel. Badke v. Greendale Village Bd., 173 Wis.2d 553,494 N.W.2d
408 (1993). No official actions other than those of the Parks and Recreation Committee shall take place. Wisconsin
State Statutes require all agendas for Committee, Commission, or Board meetings be posted in final form, 24 hours
prior to the meeting. Any posted agenda is subject to change up until 24 hours prior to the date and time of the
meeting. All items listed on this agenda may be acted upon by the Park Committee.
If you are not able to attend in person interested persons may also attend via the zoom
link or by phone.
Join Zoom Meeting by Computer:
https://zoom.us/j/5445915099
Join Zoom Meeting by Phone:
+1 312 626 6799 US (Chicago)
Meeting ID: 5445915099
AGENDA ITEMS
1. Meeting called to order by Chair Ermeling
2. Pledge of Allegiance to the Flag
3. Roll Call by Recording Secretary
Ermeling (C), Lopes Serrao (VC), Esker, Sleeter, Tatro
4. Approval of minutes from the previous meeting: September 28, 2026.
5. Public Comments
6. Written Comments
EDUCATIONAL PRESENTATIONS & REPORTS
7. Update on Aquatic Center Repairs.
8. Update on Aquatic Center Season Financials.
VILLAGE OF WESTON, WISCONSIN
OFFICIAL MEETING AGENDA OF THE PARKS AND RECREATION COMMITTEE
Parks and Recreation Committee Meeting – Agenda 10/26/2026
UNFINISHED BUSINESS
NEW BUSINESS
9. Discussion and/or action on Machmueller Park Master Plan and Cost Estimate.
10. Discussion and/or action on Kennedy Park Master Plan and Quarterly Update.
FUTURE ITEMS
11. Possible next meeting date: November 23, 2026
12. Topics for future meetings
13. Remarks from Staff
14. Remarks from Committee Members
15. Announcements
16. Adjourn
This Agenda was posted at the Village Municipal Center, on www.westonwi.gov and
transmitted to media partners on October 21, 2026.
Village of Weston Parks and Recreation Committee Meeting September 28, 2026
Village of Weston, Wisconsin
MEETING MINUTES OF THE PARK & RECREATION
COMMITTEE MEETING
Monday, September 28, 2026, 4:00 p.m.
1.) Meeting called to order by Chair Ermeling at 4:00 p.m.
2.) Pledge Allegiance to the Flag
3.) Roll Call by Recording Secretary: Jessica Falkowski
Member Present
Ermeling, Barb (C) YES
Esker, Roger YES
Lopes Serrao, Luis (VC) ABSENT, EXCUSED
Sleeter, Pam YES
Tatro, Scott YES
Village Staff and other officials in attendance: Falkowski (Clerk), Administrator
Gebert, Hodell, Director Osterbrink, Director Wodalski, and Trustee Beck (online).
4.) Approval of minutes from the previous meeting: August 24, 2026.
*M/S/P: Tatro/Esker: to approve August 24, 2026, minutes.
Yes Votes: 4 No Votes: 0 Abstain: 0 Not Voting: 1 Result:
Pass Member Vote
Ermeling, Barb YES
Esker, Roger YES
Lopes Serrao, Luis ------
Sleeter, Pam YES
Tatro, Scott YES
5.) Public Comments
Grace Klopotek, 6003 Jessica St Weston made the following comments:
• Thanked the Committee for asking questions on the ice rink proposal at
Kennedy presented last month
• Asked if the Friends of Kennedy Park could put together a presentation
showing:
o Where they are at
o Where they plan to go
o How they plan to get there
• Provide more details on Prohaska Park
6.) Written Comments.
None
Village of Weston Parks and Recreation Committee Meeting September 28, 2026
EDUCATIONAL PRESENTATIONS & REPORTS
7.) Update on the Kennedy Park Renovation
Director Osterbrink stated that the update is brief but, staff and Friends of Kennedy
Park does provide quarterly updates that are more detailed.
Director Osterbrink contacted the contractors to complete the following:
• the touch up paint on the poles – week of October 5
• concrete touch ups on the cracked block and missing mortar - week of October 5
• dugout door adjustments – no date set
• dirt/sod repair where irrigation leak was detected and fixed – no date set
• lights are scheduled to be delivered and installed the week of October 19
8.) Update on Machmueller Park Master Plan.
Director Osterbrink stated a public input meeting was held September 3 at
Machmueller Park. The consultant took the information that was collected from
residents and park users that attended the meeting and revised the concept plan.
The newly revised plan includes adding a tennis and basketball courts along with a
small shade structure at that location - #14 on the master plan.
Director Osterbrink did receive three emails about adding an additional all-access
playground to the park. The information was passed onto the consultant.
Tatro supports the suggestion to add an all-access playground. Director Osterbrink
stated that in 2008 the Village had a concept design completed for an all-access
playground but the funding fell through.
Trustee Ermeling asked if the current playground was replaced in 2024 when all
the other playgrounds were replaced. Director Osterbrink responded no, the
playground was installed in 2007 and is still in good shape. The current
playground is proposed to be updated in the future on the concept plan - #5.
Trustee Ermeling also stated that if the proposed tennis court is under-utilized it
can easily be transformed into pickleball courts.
Director Osterbrink included four different types of bandshells in the packet.
9.) Update on Aquatic Center Repairs
Director Osterbrink stated he was contacted by the contractor and they are due to
arrive the week of October 5 to start working on the plumbing, motor/pump
replacements and the leak detection. Once the work is completed, staff can
winterize the pool vessel and building.
Village of Weston Parks and Recreation Committee Meeting September 28, 2026
Director Osterbrink has been working on the electrical and commercial pool
permits for the project from the Village. The plan has been approved by the State.
UNFINISHED BUSINESS
10.) Discussion and/or action on completing an updated Farmers Market End of
Season survey.
Director Osterbrink stated we are almost at the end of the season for the Farmers
Market. Does the Committee want to recommend staff to send out an updated
survey for vendors and customers to collect feedback? The first survey was
conducted three to four weeks into the season which, everything was new to
everyone. At that time, many people still did not realize the location was moved to
Kennedy Park and everyone had to learn the layout and parking.
Staff stated that adjustments were made as issues/concerns arose. For example,
staff addressed the parking issues, traffic control, and fixed the pothole.
Administrator Gebert stated the survey would run for 30 days, October 1- October
30.
Committee members stated that the following should be included in the survey:
• What people liked or did not like
• Suggestions of what people would like to see
• What could we do better
• Survey the vendors
Hodell made the following comments:
• Vendors like the new location because the area is larger so they can have their
vehicle and/or trailer at their spot. This is an asset when the weather is not
cooperative and when they need to restock or load up at the end of the day
• Customers like array of vendors and things offered for purchase
• Once the roundabout opened the traffic flow improved and customers started
parking more in the parking lot
• Customers commented more positively as the season went on as issues were
addressed, they became more accustomed to the site, and as more vendors
came with product
• Ten more vendors participated in this season’s market due to the larger location
• Customers can drive up to certain vendors, for example – vendors that sell
pumpkins or mums. The customers don’t have to carry their purchase across
the market to their vehicle, making it more convenient
• Hodell takes left over produce that is still fresh from vendors to Neighbor’s Place
on Tuesdays. On Wednesdays, the Neighbor’s Place has a food pantry day
• Hsu’s Growing Supply provides compost bins that vendors can dispose of
produce that is no longer fresh.
Sleeter stated that the Farmers Market became more organized and easier to get
around as the weeks went on.
Village of Weston Parks and Recreation Committee Meeting September 28, 2026
Trustee Beck added that the survey should be available now because things are
fresh in people’s minds.
*M/S/P Tatro/Sleeter: motion to proceed with the updated Farmers Market
Survey for vendors and customers to complete this fall.
Yes Votes: 4 No Votes: 0 Abstain: 0 Not Voting: 1 Result: Pass
Member Vote
Ermeling, Barb YES
Esker, Roger YES
Lopes Serrao, Luis ------
Sleeter, Pam YES
Tatro, Scott YES
11.) Discussion and/or action on collecting feedback regarding Ice Skating
Rinks at Kennedy.
Director Osterbrink stated that a discussion was held in March and April about
the use and costs to maintain the outdoor ice rink at Kennedy Park. The
discussion also included whether a survey should be conducted this fall during
the election. The following would be stated on an easel in the hallway asking
voters to check yes or no to an outdoor skating rink at Kennedy Park as they
pass by.
Committee discussed that not enough information would be given to voters to
make an informative decision if the question was placed on the easel to check
yes or no. The Committee would like a tenth question added to the Famers
Market survey – How else do you utilize Kennedy Park.
12.) Discussion and/or action on completing an updated Aquatic Center
Evaluation.
Director Osterbrink stated that the past couple months, discussions have taken
place on the annual operating and capital costs at the Aquatic Center. The
Village spent $102,000 earlier this year in leak detection and repairs. This fall
the motors and valves will be replaced for $100,000 plus and an estimated
$12,000 is projected for leak detection.
Aquatic Center evaluation was completed in 2016 which provided the Village with
a list of recommended items to upgrade or fix. Over the years majority of the
items have been completed. Since the evaluation is 10 years old, a trustee
suggested that another evaluation should be done.
Trustee Ermeling commented that maybe we should see what the school district
decides and if there is a possible joint venture with them.
Village of Weston Parks and Recreation Committee Meeting September 28, 2026
Tatro suggested that if we have an evaluation completed on our pool that could
help us decide if a possible venture with the school district would be a better
investment.
Staff provided an estimated cost of $7,000 - $12,000 for the pool evaluation to be
completed. Water Technology completed the evaluation in 2016 and the
evaluation includes the pool vessel and the mechanicals.
Director Osterbrink stated the items that have not been upgraded or replaced
have been sidelined due to the leaks we have had to fix the past couple of years.
The leak detection this fall is to detect a leak that is in the supply line for the play
structure. The pool was opened in 1999 making the pool 27 years old.
*M/S/P Tatro/Esker: motion to recommend approval to complete a new
aquatic center evaluation due to the fact that the current evaluation is 10
years old and may help in a decision to partner with another entity.
Yes Votes: 4 No Votes: 0 Abstain: 0 Not Voting: 1 Result: Pass
Member Vote
Ermeling, Barb YES
Esker, Roger YES
Lopes Serrao, Luis ------
Sleeter, Pam YES
Tatro, Scott YES
13.) Possible next meeting date: October 26, 2026, at 4p.m.
14.) Topics for future meetings
a.) Update on Aquatic Center – final numbers for the season
15.) Remarks from Staff
Director Osterbrink stated he had a report in the packet. Staff should be
receiving the warranty items to replace the broken parts on the spinner at
Sandhill Park within the next couple of weeks. Work has been completed for the
original list of items to be completed at the playgrounds. The Village will be
issuing the final payment to the installation company.
Director Wodalski added that through the current discussions and decisions that
have occurred about keeping the Farmers Market at Kennedy Park and what
potentially could happen with the hockey group will change the outlook of the
master plan. The next step would be to look at the park layout with the Farmers
Market now included and see how to adjust the baseball field that was mapped to
go there. The goal is to make a park that fits all users and age groups.
16.) Remarks from Committee Members
Village of Weston Parks and Recreation Committee Meeting September 28, 2026
None
17.) Announcements
Community Engagement night at the municipal center from 4-6p.m.
18.) Adjourn
*M/S/P Tatro/Esker: motion to adjourn the meeting at 5:02 p.m.
Yes Votes: No Votes: 0 Abstain: 0 Not Voting: 0 Result: Pass
Member Vote
Ermeling, Barb YES
Esker, Roger YES
Lopes Serrao, Luis ------
Sleeter, Pam YES
Tatro, Scott YES
Jessica Falkowski, Recording Secretary
REQUEST FOR CONSIDERATION
REQUEST FOR CONSIDERATION
Public Mtg/Date:
Parks and Recreation Committee – October 26, 2026
Description:
Update on the Aquatic Center Repairs
From:
Shawn Osterbrink, Director of Parks, Recreation &
Forestry
Question:
Update on the work at the Aquatic Center.
Background
Neuman Pools has been on site since October 8th. They have been working on the removal
of the old equipment and installation of the pumps, motors and valves. They are currently
waiting for some risers that stalled work on this project, so they moved on to leak detection
of the play structure supply pipe. Fortunately, after some testing they were able to find the
leak on Monday, October 19th.
Attached Docs: None.
______________________________________________________________________
Committee Action: None.
Fiscal Impact: None.
Recommendation: None.
Recommended Language for Official Action
None, update item.
______________________________________________________________________
Additional action:
REQUEST FOR CONSIDERATION
REQUEST FOR CONSIDERATION
Public Mtg/Date:
Parks and Recreation Committee – October 26, 2026
Description:
Update on the Aquatic Center Financials for 2026
From:
Shawn Osterbrink, Director of Parks, Recreation &
Forestry
Question:
Update on the financial for the Aquatic Center 2026
season.
Background
Attached is the budget status report for the Aquatic Center through September 30th, 2026.
Just a reminder that expenses will still occur through the end of the year for utilities and
miscellaneous work that needs to be completed as we winterize the facility and make
repairs. There also may be some additional revenue added as we were waiting for
payment from some of the groups, we billed this season.
Based on the report we are showing revenues of $246,650.75 and we had budgeted
revenues of $226,870.00. We are showing expenditures of $230,587.41 and had budgeted
$256,060.00 for expenditures. Based on what was budgeted we expected to be up to
$29,190.00 in revenue below expenditures. Currently we are showing a positive of
$16,063.34 of revenue over expenditures.
Attached Docs: Budget Status Report through September 30th, 2026.
______________________________________________________________________
Committee Action: None.
Fiscal Impact: None.
Recommendation: None.
Recommended Language for Official Action
None, update item.
______________________________________________________________________
Additional action:
VILLAGE OF WESTON
REVENUES WITH COMPARISON TO BUDGET
FOR THE 9 MONTHS ENDING SEPTEMBER 30, 2026
AQUATIC CENTER FUND
ACCOUNT NO ACCOUNT TITLE PERIOD ACTUAL YTD ACTUAL BUDGET UNEARNED PCNT
FOR ADMINISTRATION USE ONLY 75 % OF THE FISCAL YEAR HAS ELAPSED 10/12/2026 03:25PM PAGE: 1
TAXES
22-00-41110-000-000 PROPERTY TAXES .00 40,000.00 40,000.00 .00 100.0
TOTAL TAXES .00 40,000.00 40,000.00 .00 100.0
PUBLIC CHARGES FOR SERVICE
22-00-46734-000-045 SWIM FEE-JOINT MEMBERSHIP .00 12,090.99 13,000.00 909.01 93.0
22-00-46734-000-051 SWIM FEES-DAILY .00 113,486.25 100,000.00 ( 13,486.25) 113.5
22-00-46734-000-061 SWIM FEES-LOCKER RENTALS 31.99 31.99 70.00 38.01 45.7
22-00-46734-000-062SWIM FEES-POOL RENTALS/EVENING .00 3,824.64 2,000.00 ( 1,824.64) 191.2
22-00-46734-000-063SWIM FEES-GROUP RATE DISCOUNT/ .00 4,366.83 2,500.00 ( 1,866.83) 174.7
22-00-46734-000-064 SWIM FEES-B/DAY PARTY/DAILY FE .00 1,327.94 1,200.00 ( 127.94) 110.7
22-00-46734-000-065 SWIM FEES-B/DAY PARTY/CONCESSI .00 2,655.91 .00 ( 2,655.91) .0
22-00-46734-000-066 SWIM FEES-CONCESS DIRECT FROM .00 6,699.69 7,000.00 300.31 95.7
22-00-46734-000-074 SWIM FEES-WAC ONLY MEMBERSHIP .00 17,409.43 17,000.00 ( 409.43) 102.4
22-00-46735-000-071 SWIM LESSONS .00 2,519.24 4,000.00 1,480.76 63.0
TOTAL PUBLIC CHARGES FOR SERVICE 31.99 164,412.91 146,770.00 ( 17,642.91) 112.0
MISCELLANEOUS REVENUE
22-00-48110-001-000 INTEREST-INVESTMENTS 116.32 1,737.84 100.00 ( 1,637.84) 1737.8
22-00-48502-000-067POOL DONATIONS-PEPSI/COKE DON .00 500.00 .00 ( 500.00) .0
TOTAL MISCELLANEOUS REVENUE 116.32 2,237.84 100.00 ( 2,137.84) 2237.8
TRANSFERS IN
22-00-49229-000-000TRANSFER FROM ROOM TAXES FUN .00 40,000.00 40,000.00 .00 100.0
TOTAL TRANSFERS IN .00 40,000.00 40,000.00 .00 100.0
TOTAL FUND REVENUE 148.31 246,650.75 226,870.00 ( 19,780.75) 108.7
VILLAGE OF WESTON
EXPENDITURES WITH COMPARISON TO BUDGET
FOR THE 9 MONTHS ENDING SEPTEMBER 30, 2026
AQUATIC CENTER FUND
PERIOD ACTUAL YTD ACTUAL BUDGET UNEXPENDED PCNT
FOR ADMINISTRATION USE ONLY 75 % OF THE FISCAL YEAR HAS ELAPSED 10/12/2026 03:25PM PAGE: 2
REC FACIL-AQUATIC CENTER
22-05-55420-221-000 WATER/SEWER/STORMWATER .00 6,904.38 12,000.00 5,095.62 57.5
22-05-55420-222-000 ELECTRICITY 4,029.38 12,907.84 14,500.00 1,592.16 89.0
22-05-55420-224-000 NATURAL GAS 6,271.40 12,628.27 15,000.00 2,371.73 84.2
22-05-55420-225-000 TELEPHONE .00 .00 1,100.00 1,100.00 .0
22-05-55420-247-000 REPAIRS/MAINT-BUILDINGS .00 23,223.42 30,000.00 6,776.58 77.4
22-05-55420-279-000 STATE INSPECTION FEES .00 2,487.00 2,200.00 ( 287.00) 113.1
22-05-55420-286-000 CREDIT CARD MAINTENANCE FEES .00 48.00 .00 ( 48.00) .0
22-05-55420-290-000OTHER OUTSIDE CONTRACTED SER 46,954.83 148,327.80 144,575.00 ( 3,752.80) 102.6
22-05-55420-310-000 OFFICE SUPPLIES .00 .00 75.00 75.00 .0
22-05-55420-312-000 OUTSIDE PRINTING/STATIONERY & 74.00 153.50 160.00 6.50 95.9
22-05-55420-314-000 SMALL EQUIPMENT 469.61 469.61 1,750.00 1,280.39 26.8
22-05-55420-326-000 ADVERTISING .00 .00 500.00 500.00 .0
22-05-55420-344-000 OPERATING SUPPLIES-JANITORIAL/ .00 1,031.44 1,800.00 768.56 57.3
22-05-55420-346-000 OPERATING SUPPLIES-CLOTHING/UN .00 1,127.07 1,800.00 672.93 62.6
22-05-55420-366-000 OTHER SUPPLIES-CHEMICALS .00 19,352.23 25,000.00 5,647.77 77.4
22-05-55420-390-000 OTHER SUPPLIES-ALL OTHER SUPPL .00 624.19 1,500.00 875.81 41.6
22-05-55420-398-000OTHER SUPPLIES-CASH OVER OR S .00 162.91 .00 ( 162.91) .0
22-05-55420-808-000 COMPUTER SOFTWARE .00 1,139.75 1,600.00 460.25 71.2
22-05-55420-812-000 CAPITAL EQUIP-FURNITURE & FURN .00 .00 2,500.00 2,500.00 .0
TOTAL REC FACIL-AQUATIC CENTER 57,799.22 230,587.41 256,060.00 25,472.59 90.1
TOTAL FUND EXPENDITURES 57,799.22 230,587.41 256,060.00 25,472.59 90.1
NET REVENUE OVER EXPENDITURES ( 57,650.91) 16,063.34 ( 29,190.00) ( 45,253.34) 55.0
REQUEST FOR CONSIDERATION
REQUEST FOR CONSIDERATION
Public Mtg/Date:
Parks and Recreation Committee – October 26, 2026
Description:
Machmueller Park Master Plan and Cost Estimate
From:
Shawn Osterbrink, Director of Parks, Recreation &
Forestry
Question:
Should the park committee recommend approval of
the Machmueller Park Master Plan and Cost Estimate.
Background
Attached is the most recent version of the Machmueller Park Master Plan and Cost
Estimate for the improvements at the park. All requested changes and input f rom the
committee and public was considered for the plan.
Attached Docs: Machmueller Concept Plan and Cost Estimate.
______________________________________________________________________
Committee Action: None.
Fiscal Impact: N/A
Recommendation: Approve the Master Plan and Cost Estimate.
Recommended Language for Official Action
I recommend approval/denial of the Machmueller Park Master Plan and Cost
Estimate,
Or something else.
______________________________________________________________________
Additional action:
PRELIMINARY COST ESTIMATE
MACHMUELLER PARK
Weston, Wisconsin
Park Redevelopment Project
Rettler Project No.: 26.027
Item Estimated Unit Category
No. Item Description Units Quantity Price Extension Sub T otal
$580,410.00
1. Mobilization L.S. 1 $260,000.00 $260,000.00
2. General Demolition L.S. 1 $15,000.00 $15,000.00
3. Common Excavation, 12-inch depth C.Y. 10,500 $12.00 $126,000.00
4. Stripping Topsoil, 6-inch depth C.Y. 10,500 $2.50 $26,250.00
5.
Excavation below Subgrade with 12" Breaker Run (25% of asphalt and
large concrete area surfaces) C.Y. 750 $45.00 $33,750.00
6. Place Screened Topsoil, 6-inch dpeth C.Y. 6,475 $2.25 $14,570.00
7. Seed/Fertilize/Mulch Common Green Space S.F. 174,67 5 $0.50 $87,340.00
8. Erosion Control L.S. 1 $15,000.00 $15,000.00
9. Tracking Pad EACH 1 $2,500.00 $2,500.00
WALKING PATHS $90,000.00
10. Kafka Wax Coated Aggregate L.S. 1 $90,000.00 $90,000.00
Note: Aggrate is only for new paths. Does not include reinstalling existing
paths.
RESTROOM FACIILTY AND GATHERING PLAZA $1,173,810.00
11. 5" Concrete S.F. 13,990 $9.00 $125,910.00
12. Dense Graded Base, 6-inch depth S.Y. 1,710 $7.00 $11,970.00
13. Precast Concrete Bag Toss Boards SET 2 $3,000.00 $6,000.00
14. Water Utility L.F. 360 $60.00 $21,600.00
15. Sanitary Sewer Utility L.F. 360 $65.00 $23,400.00
16. Electric Service (For Food Truck Hookup) L.S. 1 $20 ,000.00 $20,000.00
17. 20' x 30' Poligon Band Shell L.S. 1 $320,000.00 $320 ,000.00
18. 5" Concrete (Band Shell) S.F. 500 $9.00 $4,500.00
19. Dense Graded Base, 6-inch depth (Band Shell) S.Y. 61 $7.00 $430.00
20. Restroom/Storage/Rental Building S.F. 1,600 $400.00 $640,000.00
TEEN PLAYGROUND $379,920.00
21. 12" x 12" Reinforced Concrete Curb (with base) L.F. 380 $45.00 $17,100.00
22. Poured-in-Place Surfacing & Base Aggregate Dense S.F. 5,815 $28.00 $162,820.00
23. Playground Equipment Allowance L.S. 1 $200,000.00 $2 00,000.00
TODDLER PLAYGROUND $571,690.00
24. 12" x 12" Reinforced Concrete Curb (with base) L.F. 570 $45.00 $25,650.00
25. Poured-in-Place Surfacing & Base Aggregate Dense S.F. 9,200 $28.00 $257,600.00
26. Playground Equipment Allowance L.S. 1 $250,000.00 $2 50,000.00
27. 5" Concrete S.F. 4,340 $8.00 $34,720.00
28. Dense Graded Base, 6-inch depth S.Y. 530 $7.00 $3,720.00
October 1, 2026
EARTHWORK/DEMOLITION/CONTRACTOR MOBILIZATION
Page 1 of 3
PRELIMINARY COST ESTIMATE
MACHMUELLER PARK
Weston, Wisconsin
Park Redevelopment Project
Rettler Project No.: 26.027
Item Estimated Unit Category
No. Item Description Units Quantity Price Extension Sub T otal
October 1, 2026
OUTDOOR FITNESS SPACE $213,250.00
29. 12" x 12" Reinforced Concrete Curb (with base) L.F. 120 $45.00 $5,400.00
30. Synthetic Playground Turf S.F. 4,535 $25.00 $113,380 .00
31. Synthetic Turf - Base Drainage Stone, 6-inch dep th S.Y. 504 $8.00 $4,040.00
32. Flat Panel Underdrain 1"x12" L.F. 280 $6.00 $1,680.0 0
33. 6" Storm Sewer L.F. 75 $50.00 $3,750.00
34. Fitness Equipment Allowance L.S. 1 $85,000.00 $85,00 0.00
PLAYING COURTS (1 TENNIS, 4 PICKLEBALL, 1 BASKETBALL) $303,740.00
35. Hot Mixed Asphalt, 3.5-inch depth S.Y. 500 $28.00 $14,000.00
36. Dense Graded Base, 10-inch depth S.Y. 550 $12.00 $6,600.00
37. Sawcut Asphalt Joints L.F. 500 $5.00 $2,500.00
38. 5" Concrete S.F. 6,930 $9.00 $62,370.00
39. Dense Graded Base, 6-inch depth S.Y. 847 $7.00 $5,930.00
40. Court Surfacing and Striping (Pickleball, Tennis, and Basketball) S.Y. 2,215 $24.00 $53,160.00
41. Tennis Court Netting (Posts, Net, Center Anchor Strap) SET 1 $2,500.00 $2,500.00
42. Pickleball Court Netting (Posts, Net, Center Anc hor Strap) SET 4 $2,000.00 $8,000.00
43. Basketball Hoop EACH 2 $10,000.00 $20,000.00
44. 4' High Black Vinyl Chain Link Fencing L.F. 510 $40 .00 $20,400.00
45. 4'H x 4'W Black Vinyl Chain Link Gate EACH 5 $1,000 .00 $5,000.00
46. 10' High Black Vinyl Chain Link Fencing L.F. 340 $5 5.00 $18,700.00
47. 4" Underdrain L.F. 890 $22.00 $19,580.00
48. Shade Structure - 16'x16' L.S. 1 $55,000.00 $55,000.00
49. Benches and Spectator Seating Allowance L.S. 1 $10,000.00 $10,000.00
EXISTING PARKING LOT AND DRIVE $49,000.00
50. Crack Fill and Sealcoat S.Y. 7,655 $6.00 $46,000.00
51. Striping L.S. 1 $3,000.00 $3,000.00
Page 2 of 3
PRELIMINARY COST ESTIMATE
MACHMUELLER PARK
Weston, Wisconsin
Park Redevelopment Project
Rettler Project No.: 26.027
Item Estimated Unit Category
No. Item Description Units Quantity Price Extension Sub T otal
October 1, 2026
NEW PARKING LOT $59,730.00
52. Hot Mixed Asphalt, 3.5-inch depth S.Y. 1,230 $28.00 $34,440.00
53. Dense Graded Base, 10-inch depth S.Y. 1,353 $12.00 $16,240.00
54. Concrete Curb Ramp w/ Detectable Warning Field EACH 1 $1,800.00 $1,800.00
55. Striping & Signs L.S. 1 $2,000.00 $2,000.00
56. 24" Curb and Gutter L.F. 150 $35.00 $5,250.00
SITE AMENITIES $115,000.00
57. Site Landscaping Allowance L.S. 1 $50,000.00 $50,000.00
58. Signage Allowance L.S. 1 $10,000.00 $10,000.00
59. Site Amenities Allowance (benches, trash recepta cles, plaza seating, etc.) L.S. 1 $20,000.00 $20,000.00
60. Stormwater Management Allowance L.S. 1 $35,000.00 $3 5,000.00
SUMMARY
CONSTRUCTION ITEMS TOTAL: $3,536,550.00
CONTINGENCY at 10%: $353,655.00
CONSTRUCTION ESTIMATE SUBTOTAL: $3,890,205.00
SOFT COSTS $247,560.00
CONSTRUCTION ESTIMATE TOTAL $4,137,765.00
NOTES:
Geotechnical study not completed at time of study. Soil conditions may impact cost estimate.
Topographic Survey not completed at time of study. Final existing base map may impact cost estimate.
Page 3 of 3
REQUEST FOR CONSIDERATION
REQUEST FOR CONSIDERATION
Public Mtg/Date:
Park and Recreation Committee, October 26, 2026
Description:
Update on the Kennedy Park Renovation and Capital Campaign
From:
Jami Gebert, Village Administrator
Michael Wodalski, Director of Public Works
Shawn Osterbrink, Director of Parks, Recreation and Forestry
Question: Update on the implementation of the master plan for Kennedy
Park and capital fundraising campaign.
Background
Construction/Renovation:
There are still a few items that need to be completed. There is some touch up painting, concrete work
and a couple other items. The doors in the dugouts were recently adjusted, and an irrigation leak we
found has been repaired, all under warranty. A walk through will be completed with the contractor and
engineering firm.
The Village, on behalf of the Friends of Kennedy Park (FoKP), has been in contact with Musco Lighting
to complete the field lighting on Rajek Field. The lights have been delivered and installed as of October
20th. The Village’s role is to coordinate the construction effort as those items will become Village
Property, while the FoKP, through the Community Foundation, will then make the payments for the
lighting.
Capital Campaign:
Youth baseball board donated $17,500 to the Kennedy Park Project in September. Almost $4000 in
concession stand money coming from a joint effort in the softball tournament. Softball folks agreed to
use our inventory proceeds went to the project.
This would increase the balance of $103,439.55 from July at the Community Foundation to
approximately $124,939.55, which $98,000.00 will be spent on the lights on Rajek Field.
The second Glow games are set and open on our website for February 20th, 2027. We have just
started organizing again but already have verbal commitments from excited teams and invested
business alike. https://www.dceyouthbaseball.org/tournaments/glow-games/27118
We'll have a clean-up day this Sunday to work on collecting equipment, taking down banners, and
cleaning out the sheds.
Travel baseball numbers are in for 2027, and we have a 30% increase in kids this year. I'm positive
the improvements to the park and the excitement around the program has helped extend our reach.
Baseball is working on scheduling three tournaments for next summer along with softball having one.
Also, with the decision to keep the Farmer’s Market at Kennedy there is a need to revisit the master
plan and determine what the next goal will be.
Master Plan:
Since the Farmers Market is going to remain at Kennedy Park it was discussed that the master plan
needs to be reviewed as the master plan shows a baseball field in that location. The approved master
plan has been included for review and discussion.
REQUEST FOR CONSIDERATION
REQUEST FOR CONSIDERATION
Figure 1: Drone Image of Rajek Field and the Babe Ruth Field during the June Youth Baseball Tournament
Attached Docs: Kennedy Park Master Plan and Cost Estimate.
Committee Action: None.
Fiscal Impact: None.
Recommendation: None.
Recommended Language for Official Action
PRELIMINARY COST ESTIMATE
Kennedy Park Master Plan
Weston, Wisconsin
Park Facility Redevelopment
Rettler Project No.: 22.062
Item Estimated Category
No. Item Description Units Quantity Unit Price Extension Sub Total
$1,462,600.00
1. Mobilization L.S. 1 $725,000.00 $725,000.00
2. Clearing and Grubbing L.S. 1 $10,000.00 $10,000.00
3. General Demolition L.S. 1 $50,000.00 $50,000.00
4. Common Excavation, 12-inch depth C.Y. 35,400 $8.00 $283,200.00
5. Strip Topsoil, 6-inch depth S.Y. 91,425 $1.00 $91,425.00
6. Place Screened Topsoil, 6-inch depth S.Y. 37,309 $3.00 $111,926.67
7.
Excavation below Subgrade Allowance (25% of asphalt
surface) S.Y. 3,600 $15.00 $54,000.00
8. Seed/Fertilize/Mulch Common Green Space S.F. 335,780 $0.35 $117,523.00
9. Erosion Control L.S. 1 $15,000.00 $15,000.00
10. Tracking Pad EACH 3 $1,500.00 $4,500.00
$745,600.00
11. Stormwater Management Allowance L.S. 1 $150,000.00 $150,000.00
12. Storm Sewer L.F. 3,000 $55.00 $165,000.00
13. Storm Control Structure EACH 5 $4,500.00 $22,500.00
14. Storm Basin EACH 30 $3,000.00 $90,000.00
15. Storm Endwall EACH 5 $1,500.00 $7,500.00
16. Site Electrical & Service Allowance L.S. 1 $250,000.00 $250,000.00
17. Street Cut & Utility Connection L.S. 1 $20,000.00 $20,000.00
18. Sanitary Utility Allowance L.F. 312 $65.00 $20,280.00
19. Water Utility Allowance L.F. 312 $65.00 $20,280.00
BASEBALL FIELD 1 (315'/350'/315') (SYNTHETIC INFIELD) $1,406,800.00
20. Remove Topsoil from Infield Area (8" depth) S.Y. 3,882 $1.50 $5,822.78
21. Synthetic Turf w/ Field Markings (infield) S.F. 34,937 $6.00 $209,620.23
22. Synthetic Turf - Finish Drainage Stone, 2" depth S.Y. 3,882 $6.00 $23,291.14
23. Synthetic Turf - Base Drainage Stone, 6" depth S.Y. 3,882 $12.00 $46,582.27
24. Geotextile Fabric S.Y. 3,882 $2.50 $9,704.64
25. 12" x 12" Concrete Curb and Nailer (with base course) L.F. 715 $35.00 $25,025.00
26. Flat Panel Underdrain 1"x12" L.F. 1,500 $12.00 $18,000.00
27.
12" HDPE Perforated Socked Storm Pipe w/clear Stone
Trench and End Caps L.F. 600 $90.00 $54,000.00
28. 48" Concrete Manhole EACH 3 $4,500.00 $13,500.00
29. Turf Utility Boxes EACH 2 $2,000.00 $4,000.00
30.
Baseball Pitching Rubber & Home Plate W/ Concrete
Foundations, Synthetic Turf SET 1 $4,500.00 $4,500.00
31. Baseball Bases w/ Concrete Foundations, Synthetic Turf SET 1 $2,000.00 $2,000.00
32. Turf Maintenance Equipment LS 1 $30,000.00 $30,000.00
33. Warning Track Material (6" depth) S.Y. 1,056 $25.00 $26,400.00
34. Underdrain L.F. 1,800 $25.00 $45,000.00
35. Topsoil Amendment S.Y. 9,025 $10.00 $90,250.00
36. Athletic Field Seeding S.F. 81,225 $0.50 $40,612.50
37. Irrigation EACH 1 $18,000.00 $18,000.00
38. 24' Backstop, Black Vinyl Coated L.S. 1 $40,000.00 $40,000.00
39. Fence, Black Vinyl Coated Chain Link, 8-foot high L.F. 1,260 $65.00 $81,900.00
40. Fence Gate, Black Vinyl Coated Chain Link, 4' W 8' H EACH 7 $2,500.00 $17,500.00
41. Fence Gate, Black Vinyl Coated Chain Link, 12' W x 8' H EACH 2 $4,000.00 $8,000.00
November 7, 2023
EARTHWORK / DEMOLITION
UTILITIES
42. Foul Poles SET 1 $12,000.00 $12,000.00
43. Dugout - CMU Masonry L.S. 1 $75,000.00 $75,000.00
44. Dugout with 7'x8' Storage Area - CMU Masonry L.S. 1 $90,000.00 $90,000.00
45. Scoreboard EACH 1 $30,000.00 $30,000.00
46. Electrical Allowance L.S. 1 $30,000.00 $30,000.00
47. Lighting Allowance L.S. 1 $300,000.00 $300,000.00
48. 5-Row Bleachers (52 seats) SET 3 $10,000.00 $30,000.00
49. Batting Cage/Bull Pens EACH 2 $13,000.00 $26,000.00
$1,034,600.00
50. Infield Material (6" depth) S.Y. 1,887 $25.00 $47,175.00
51. Warning Track Material (6" depth) S.Y. 992 $25.00 $24,800.00
52. Underdrain L.F. 2,360 $25.00 $59,000.00
53. Topsoil Amendment S.Y. 9,768 $10.00 $97,683.96
54. Athletic Field Seeding S.F. 87,916 $0.50 $43,957.78
55. Irrigation EACH 1 $40,000.00 $40,000.00
56. Pitcher's Mound/Bases SET 1 $4,500.00 $4,500.00
57. 24' Backstop, Black Vinyl Coated L.S. 1 $40,000.00 $40,000.00
58. Fence, Black Vinyl Coated Chain Link, 8-foot high L.F. 1,215 $65.00 $78,975.00
59. Fence Gate, Black Vinyl Coated Chain Link, 4' W 8' H EACH 7 $2,500.00 $17,500.00
60. Fence Gate, Black Vinyl Coated Chain Link, 12' W x 8' H EACH 2 $4,000.00 $8,000.00
61. Foul Poles SET 1 $12,000.00 $12,000.00
62. Dugout - CMU Masonry L.S. 1 $75,000.00 $75,000.00
63. Dugout with 7'x8' Storage Area - CMU Masonry L.S. 1 $90,000.00 $90,000.00
64. Scoreboard EACH 1 $30,000.00 $30,000.00
65. Electrical Allowance L.S. 1 $10,000.00 $10,000.00
66. Lighting Allowance L.S. 1 $300,000.00 $300,000.00
67. 5-Row Bleachers (52 seats) SET 3 $10,000.00 $30,000.00
68. Batting Cage/Bull Pens EACH 2 $13,000.00 $26,000.00
$641,900.00
69. Infield Material (6" depth) S.Y. 1,613 $25.00 $40,325.00
70. Warning Track Material (6" depth) S.Y. 678 $25.00 $16,950.00
71. Underdrain L.S. 1 $25,000.00 $25,000.00
72. Topsoil Amendment S.Y. 3,157 $10.00 $31,572.22
73. Athletic Field Seeding S.F. 28,415 $0.50 $14,207.50
74. Irrigation EACH 1 $25,000.00 $25,000.00
75. Pitcher's Mound/Bases SET 1 $4,500.00 $4,500.00
76. 24' Backstop, Black Vinyl Coated L.S. 1 $30,000.00 $30,000.00
77. Fence, Black Vinyl Coated Chain Link, 8-foot high L.F. 735 $65.00 $47,775.00
78. Fence Gate, Black Vinyl Coated Chain Link, 4' W 8' H EACH 5 $2,500.00 $12,500.00
79. Fence Gate, Black Vinyl Coated Chain Link, 12' W x 8' H EACH 2 $4,000.00 $8,000.00
80. Foul Poles SET 1 $12,000.00 $12,000.00
81. Gameshade Dugout w/ 8' Vinyl Fencing EACH 2 $20,000.00 $40,000.00
82. Concrete Dugout Pads and Base Course EACH 2 $10,000.00 $20,000.00
83. Scoreboard EACH 1 $20,000.00 $20,000.00
84. Electrical Allowance L.S. 1 $10,000.00 $10,000.00
85. Lighting Allowance L.S. 1 $260,000.00 $260,000.00
86. 3-Row Bleachers (32 seats) SET 3 $8,000.00 $24,000.00
SOFTBALL FIELD 1 (220') (NATURAL TURF)
BASEBALL FIELD 2 (315'/315'/315') (NATURAL TURF)
$808,600.00
87. Remove Topsoil from Infield Area (8" depth) S.Y. 1,613 $1.50 $2,419.17
88. Synthetic Turf w/ Field Markings (infield) S.F. 14,515 $6.00 $87,090.00
89. Synthetic Turf - Finish Drainage Stone, 2" depth S.Y. 1,613 $6.00 $9,676.67
90. Synthetic Turf - Base Drainage Stone, 6" depth S.Y. 1,613 $12.00 $19,353.33
91. Geotextile Fabric S.Y. 1,613 $2.50 $4,031.94
92. 12" x 12" Concrete Curb and Nailer (with base course) L.F. 455 $35.00 $15,925.00
93. Flat Panel Underdrain 1"x12" L.F. 1,500 $12.00 $18,000.00
94.
12" HDPE Perforated Socked Storm Pipe w/clear Stone
Trench and End Caps L.F. 600 $90.00 $54,000.00
95. 48" Concrete Manhole EACH 3 $4,500.00 $13,500.00
96. Turf Utility Boxes EACH 2 $2,000.00 $4,000.00
97.
Softball Pitching Rubber & Home Plate W/ Concrete
Foundations, Synthetic Turf SET 1 $4,500.00 $4,500.00
98. Softball Bases w/ Concrete Foundations, Synthetic Turf SET 1 $2,000.00 $2,000.00
99. Warning Track Material (6" depth) S.Y. 678 $25.00 $16,950.00
100. Underdrain L.S. 1 $17,000.00 $17,000.00
101. Topsoil Amendment S.Y. 3,157 $10.00 $31,572.22
102. Athletic Field Seeding S.F. 28,415 $0.50 $14,207.50
103. Irrigation EACH 1 $10,000.00 $10,000.00
104. 24' Backstop, Black Vinyl Coated L.S. 1 $30,000.00 $30,000.00
105. Fence, Black Vinyl Coated Chain Link, 8-foot high L.F. 735 $65.00 $47,775.00
106. Fence Gate, Black Vinyl Coated Chain Link, 4' W 8' H EACH 5 $2,500.00 $12,500.00
107. Fence Gate, Black Vinyl Coated Chain Link, 12' W x 8' H EACH 2 $4,000.00 $8,000.00
108. Foul Poles SET 1 $12,000.00 $12,000.00
109. Gameshade Dugout w/ 8' Vinyl Fencing EACH 2 $20,000.00 $40,000.00
110. Concrete Dugout Pads and Base Course EACH 2 $10,000.00 $20,000.00
111. Scoreboard EACH 1 $20,000.00 $20,000.00
112. Electrical Allowance L.S. 1 $10,000.00 $10,000.00
113. Lighting Allowance L.S. 1 $260,000.00 $260,000.00
114. 3-Row Bleachers (32 seats) SET 3 $8,000.00 $24,000.00
$147,800.00
115. Concrete, 5-inch depth S.F. 18,810 $7.00 $131,670.00
116. Dense Graded Base Course, 6-inch depth (under concrete) S.Y. 2,299 $7.00 $16,093.00
$800,000.00
117. Concession/Restroom/Scorers Booth S.F. 1,600 $500.00 $800,000.00
WALK CONNECTIONS (BASEBALL/SOFTBALL COMPLEX) $113,700.00
118. Hot Mixed Asphalt, 3.5" depth S.Y. 2,976 $25.00 $74,400.00
119. Dense Graded Base, 12-inch depth S.Y. 3,274 $12.00 $39,283.20
$921,200.00
120. Remove Topsoil from Infield Area (8" depth) S.Y. 1,613 $1.50 $2,419.17
121. Synthetic Turf w/ Field Markings (infield) S.F. 14,515 $6.00 $87,090.00
122. Synthetic Turf - Finish Drainage Stone, 2" depth S.Y. 1,613 $6.00 $9,676.67
123. Synthetic Turf - Base Drainage Stone, 6" depth S.Y. 1,613 $12.00 $19,353.33
124. Geotextile Fabric S.Y. 1,613 $2.50 $4,031.94
125. 12" x 12" Concrete Curb and Nailer (with base course) L.F. 455 $35.00 $15,925.00
126. Flat Panel Underdrain 1"x12" L.F. 1,500 $12.00 $18,000.00
127.
12" HDPE Perforated Socked Storm Pipe w/clear Stone
Trench and End Caps L.F. 600 $90.00 $54,000.00
128. 48" Concrete Manhole EACH 3 $4,500.00 $13,500.00
129. Turf Utility Boxes EACH 2 $2,000.00 $4,000.00
130.
Softball Pitching Rubber & Home Plate W/ Concrete
Foundations, Synthetic Turf SET 1 $4,500.00 $4,500.00
131. Softball Bases w/ Concrete Foundations, Synthetic Turf SET 1 $2,000.00 $2,000.00
132. Warning Track Material (6" depth) S.Y. 761 $25.00 $19,025.00
SOFTBALL FIELD 3 (200') (SYNTHETIC TURF INFIELD)
BALLFIELD PLAZA
BALLFIELD PLAZA CONCESSION/RESTROOM BUILDING
SOFTBALL FIELD 2 (200') (SYNTHETIC TURF INFIELD)
133. Underdrain L.S. 1 $17,000.00 $17,000.00
134. Topsoil Amendment S.Y. 3,157 $10.00 $31,572.22
135. Athletic Field Seeding S.F. 28,415 $0.50 $14,207.50
136. Irrigation EACH 1 $10,000.00 $10,000.00
137. 24' Backstop, Black Vinyl Coated L.S. 1 $30,000.00 $30,000.00
138. Fence, Black Vinyl Coated Chain Link, 8-foot high L.F. 820 $65.00 $53,300.00
139. Fence Gate, Black Vinyl Coated Chain Link, 4' W 8' H EACH 5 $2,500.00 $12,500.00
140. Fence Gate, Black Vinyl Coated Chain Link, 12' W x 8' H EACH 2 $4,000.00 $8,000.00
141. Foul Poles SET 1 $12,000.00 $12,000.00
142. Gameshade Dugout w/ 8' Vinyl Fencing EACH 2 $20,000.00 $40,000.00
143. Concrete Dugout Pads and Base Course EACH 2 $10,000.00 $20,000.00
144. Scoreboard EACH 1 $20,000.00 $20,000.00
145. Electrical Allowance L.S. 1 $10,000.00 $10,000.00
146. Lighting Allowance L.S. 1 $260,000.00 $260,000.00
147. 3-Row Bleachers (32 seats) SET 3 $8,000.00 $24,000.00
148. Concrete, 5-inch depth (bleacher pad) S.F. 3,348 $7.00 $23,436.00
149. Dense Graded Base Course, 6-inch depth (bleacher pad) S.Y. 409 $7.00 $2,864.40
150. Retaining Wall Allowance F.F. 788 $100.00 $78,750.00
TEE BALL BACKSTOPS/FIELDS $40,000.00
151. Tee Ball Backstop EACH 4 $10,000.00 $40,000.00
ADDITIONAL BATTING CAGES $78,000.00
152. Batting Cages EACH 6 $13,000.00 $78,000.00
HARD SURFACE - WEST PARKING LOT EXPANSION (143 SPACES) $257,800.00
153. Hot Mixed Asphalt, 3.5" depth S.Y. 4,912 $25.00 $122,800.00
154. Dense Graded Base, 12-inch depth S.Y. 5,403 $12.00 $64,838.40
155. Concrete, 5-inch depth (associated walk) S.F. 4,598 $7.00 $32,186.00
156. Dense Graded Base, 6-inch depth S.Y. 562 $7.00 $3,933.84
157. Concrete Curb Ramp w/ Detectable Warning Field EACH 2 $1,800.00 $3,600.00
158. Striping L.S. 1 $1,500.00 $1,500.00
159. 24" Curb and Gutter L.F. 412 $30.00 $12,360.00
160. Parking Lot Lighting EACH 3 $5,500.00 $16,500.00
HARD SURFACE - NORTH PARKING AND DRIVE (4 SPACES) $53,600.00
161. Hot Mixed Asphalt, 3.5" depth S.Y. 860 $25.00 $21,500.00
162. Dense Graded Base, 12-inch depth S.Y. 946 $12.00 $11,352.00
163. Concrete, 5-inch depth (associated walk) S.F. 1,500 $7.00 $10,500.00
164. Dense Graded Base, 6-inch depth S.Y. 183 $7.00 $1,283.33
165. Concrete Curb Ramp w/ Detectable Warning Field EACH 3 $1,800.00 $5,400.00
166. Striping L.S. 1 $800.00 $800.00
167. 24" Curb and Gutter L.F. 92 $30.00 $2,760.00
HARD SURFACE - EAST PARKING (154 SPACES) $331,400.00
168. Hot Mixed Asphalt, 3.5" depth S.Y. 5,668 $25.00 $141,700.00
169. Dense Graded Base, 12-inch depth S.Y. 6,235 $12.00 $74,817.60
170. Concrete, 5-inch depth (associated walk) S.F. 6,895 $7.00 $48,265.00
171. Dense Graded Base, 6-inch depth S.Y. 843 $7.00 $5,899.06
172. Concrete Curb Ramp w/ Detectable Warning Field EACH 4 $1,800.00 $7,200.00
173. Striping L.S. 1 $2,500.00 $2,500.00
174. Drive Apron, 6-inch depth concrete S.F. 505 $8.00 $4,040.00
175. Concrete, 8-inch depth (drive apron) S.Y. 62 $10.00 $617.22
176. 24" Curb and Gutter L.F. 810 $30.00 $24,300.00
177. Parking Lot Lighting EACH 4 $5,500.00 $22,000.00
ACCESSIBLE PLAY AREA (NORTH) $233,500.00
178. Play Equipment Allowance L.S. 1 $120,000.00 $120,000.00
179. PIP Surface S.F. 4,500 $22.00 $99,000.00
180. Concrete Thickened Edge Walk, 5-inch depth S.F. 1,126 $12.00 $13,512.00
181. Dense Graded Base, 6-inch depth S.Y. 138 $7.00 $963.36
PLAY AREA (AQUATIC CENTER AREA) $108,700.00
182. Play Equipment Allowance L.S. 1 $75,000.00 $75,000.00
183. PIP Surface S.F. 1,270 $22.00 $27,940.00
184. Concrete Thickened Edge Walk, 5-inch depth S.F. 448 $12.00 $5,376.00
185. Dense Graded Base, 6-inch depth S.Y. 55 $7.00 $383.29
PLAY AREA (SOUTH) $161,300.00
186. Play Equipment Allowance L.S. 1 $140,000.00 $140,000.00
187. Playground Surfacing (wood fiber @ 14" depth) S.Y. 503 $25.00 $12,575.00
188. 5" depth Concrete S.F. 985 $8.00 $7,880.00
189. Dense Graded Base, 6-inch Depth S.Y. 120 $7.00 $842.72
COVERED HOCKEY RINK AREA $181,100.00
190. 5" depth Concrete S.F. 18,746 $8.00 $149,968.00
191. Dense Graded Base, 6-inch Depth S.Y. 2,291 $7.00 $16,038.24
192. Boards and Brackets Allowance L.S. 1 $15,000.00 $15,000.00
193. Shelter (200'x85') - Not included in Estimate S.F. 17,000 TBD TBD
AQUATIC CENTER AMENITIES $107,100.00
194. Relocated Fencing L.F. 470 $65.00 $30,550.00
195. Remove Existing Volleyball Allowance L.S. 1 $1,500.00 $1,500.00
196. Aquatic Area Shade Shelters Allowance L.S. 1 $75,000.00 $75,000.00
SEATING AREAS (ALONG PERIMETER SIDEWALK) $8,800.00
197. Benches EACH 8 $800.00 $6,400.00
198. 5" depth Concrete S.F. 264 $8.00 $2,112.00
199. Dense Graded Base, 6-inch Depth S.Y. 32 $7.00 $225.87
$21,100.00
200. 8" Reinforced Concrete S.F. 350 $10.50 $3,675.00
201. Dense Graded Base, 6-inch depth S.Y. 47 $6.00 $280.00
202. 8' H Vinyl Coated Chain Link Fence (with privacy slatting) L.F. 55 $75.00 $4,125.00
203. Bollards EACH 4 $750.00 $3,000.00
204. 20' wide Gate EACH 1 $10,000.00 $10,000.00
BUILDINGS AND MISCELLANEOUS AMENITIES $3,909,250.00
205. Multipurpose Park Building S.F. 4,800 $450.00 $2,160,000.00
206. Storage Building S.F. 625 $200.00 $125,000.00
207. Park Restroom/Shelter Building (enclosed area) S.F. 1,635 $450.00 $735,750.00
208. Park Restroom/Shelter Building (open-sided area) S.F. 1,798 $250.00 $449,500.00
209. Existing Restrooms Reconstruction Allowance (2) S.F. 920 $450.00 $414,000.00
210. Skate Park Expansion Allowance (with additional fencing) L.S. 1 TBD TBD
211. Landscaping Allowance L.S. 1 $25,000.00 $25,000.00
SUMMARY
CONSTRUCTION ITEMS TOTAL: $13,574,450.00
CONTINGENCY at 7%: $950,220.00
CONSTRUCTION ESTIMATE SUBTOTAL: $14,524,670.00
SURVEY & GEOTECHNICAL BORINGS $20,000.00
SUMMARY - PROJECT TOTAL $14,544,670.00
Notes:
Topographic Survey not completed at time of study. Existing conditions may impact cost estimate.
Geotechnical study not completed at time of study. Soil conditions may impact cost estimate.
DUMPSTER AREA IMPROVEMENTS
1. ITEMS OF SPECIAL NOTE
2. WORK PLAN PROJECTS
Strategic Plan Initiatives
Community Engagement
o Continue to update residents via website and social media.
3. KENNEDY PARK RENOVATION
10/19/26
Renovation:
Lights for Rajek Field are scheduled for delivery the week of October 19 with installation
taking place immediately.
Capital Campaign:
Total funds at the Community Foundation are $103,439.55 as of July 20th.
Grants:
No new information to share.
Construction:
There are still a couple of items that need to be completed . There is fencing work and
concrete repairs. The contractor has worked with the sub -contractors to get these items
scheduled. The dugout doors wer e adjusted and an irrigation leak that was found in
September has been repaired.
4. AQUATIC CENTER REPAIRS
• A contract with Neuman Pools was approved at the July Board Meeting to
complete leak testing on the play structure. They will complete leak detection
following the plumbing project.
• Neuman Pools have been on site since October 8th working on the pumps,
valves, and plumbing project.
VILLAGE OF WESTON, WISCONSIN
SHAWN OSTERBRINK, PARK DIRECTOR
MONTHLY DEPARTMENT REPORT TO THE BOARD OF TRUSTEES
#2026-10 FOR SEPTEMBER 2026
5. PLAYGROUND UPDATE
• 10/19/2026 The final walk through was completed on Thursday, August 20th. The
two main items that were found were a cracked panel on the challenge course and
three broken net fasteners at Sandhill. All items were covered under warranty, and
final payment has been issued.
6. DISC GOLF COURSE UPDATE
• 10/19/2026 No new work has been completed since the previous update.
7. MACHMUELLER PARK MASTER PLAN
• The consultant has completed the revisions to the plan based on the comments
and has also completed the cost estimate. The plan and estimate will be
presented to the Park Committee at their October 26 meeting.
8. IDENTIFIED NEEDS
9. MISCELLANOUS COMMENTS / ISSUES
• Park Work – Staff have been spraying, fertilizing, emptying garbage, cleaning and
stocking restrooms, mowing, trimming, disassembling items at the aquatic center,
equipment maintenance and various other projects.
• Aquatic Center – Received our final invoice from the YMCA and payment has
been made. We will continue to have utility bills through the end of the year.
• Park rentals for the season end on October 15th.
END OF
PACKET