Joint Board of Park Commissioners and Piers, Harbors, and Lakefront Committee Meeting — Other
City of Lake Geneva · Walworth County · Board of Park Commissioners · meeting of Sep 22, 2026 · Other
Open the original document More from City of Lake Geneva
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Lake Geneva’s Lakefront
5
West Dock Options
West Dock Concept A
x Replace all moorings with new docks
x Shift existing docks south by 25’, extend east and west to increase slip count to 78
x Add new dock near beach with 28 new docks and flex broadside shopper docks
x Extend existing fishing pier 50’
West Docks Option A Cost Estimate:
Main pier relocation: 1,000lf @ $400lf= $400k
New main pier: 950lf @ $800lf= $760k
Finger piers: 2,200lf @ $300lf= $660k
Total: $1.82m
West Dock Concept A
(Drawing not to scale)
LAND TO LAKE PLAN
6
West Dock Concept B
x Replace all moorings with new docks
x Shift existing docks south by 25’, extend east and west to increase slip count to 103
x Add new 200’ fishing pier / shopper docks to west
x Extend existing fishing pier 50’
x Total slip count 103 (101 existing)
West Docks Option B Cost Estimate:
Main pier relocation: 1,000lf @ $400lf= $400k
New main pier: 600lf @ $800lf= $480k
Finger piers: 2,400lf @ $300lf= $720k
Total: $1.6m
West Dock Concept B
(Drawing not to scale)
Lake Geneva’s Lakefront
7
East Dock Options:
East Dock Concept A
x No change to existing commercially leased docks
x Replace all moorings with new docks (24)
x Add up to 60 additional docks to replace West Moorings and/or former Lagoon Docks
x Total slip count 84 (24 existing east moorings, 51 existing west moorings)
East Docks Option A Cost Estimate:
New main pier: 1,380 @ $800lf= $1.1m
Finger piers: 1,950 @ $300lf= $585k
Total: $1.685m
East Dock Concept A
(Drawing not to scale)
LAND TO LAKE PLAN
8
East Dock Concept B
x No change to existing commercially leased docks
x Replace all moorings with new docks (24)
x Add 32 new docks to replace former Lagoon Docks
x Total slip count 58 (24 existing east moorings, 32 former Lagoon Docks)
x 150’ flex broadside shopper docks
x Close Wrigley to create dedicated boat ramp circulation and marina parking
East Docks Option B Cost Estimate:
New main pier: 860lf @ $800lf= $688k
Finger piers: 1,300 @ $300lf= $390k
Total: $1.08m
East Dock Concept B
(Drawing not to scale)
Lake Geneva’s Lakefront
9
East Dock Concept C
x No change to existing commercially leased docks
x Replace all moorings with new docks (24)
x Total slip count 24
x 530’ flex broadside shopper docks
x Close Wrigley to create dedicated boat ramp circulation and marina parking (with one way
northbound access)
East Docks Option C Cost Estimate:
New main pier: 780lf @ $800lf= $624k
Finger piers: 660 @ $300lf= $198k
Total: $822k
East Dock Concept C
(Drawing not to scale)
LAND TO LAKE PLAN
10
Beach Concept Options
Key Issues to Address
x Renovate/expand existing changing/restroom facilities
x Beach capacity
x ADA access
Beach Concept A
x Construct new restrooms/changing room at west end of beach
x Add ADA compliant access point at west end of beach
x Create raised 18’ wide boardwalk terrace with wood step seating along entire length of
beach (extend beach northward into slope to prevent any visual impacts from library or
path)
x Renovate existing changing rooms
x Add new entry portal structure at east end of beach, north of trash enclosure
x Add new ADA compliant ramp and path access to existing changing rooms
x Add beach access mats
x Consider floating play features?
Beach Concept A
(Drawing not to scale)
Lake Geneva’s Lakefront
11
Beach Concept B
x Construct new restrooms/changing room at west end of beach with upper level
observation deck
x Add ADA compliant access point at west end of beach
x Extend beach northward into slope to prevent any visual impacts for library or path
x Renovate existing changing rooms
x Add new entry portal structure at east end of beach, north of trash enclosure
x Add new ADA compliant ramp and path access to existing changing rooms
x Add beach access mat
x Consider floating play structures?
Beach Concept B
(Drawing not to scale)
Source: City of Lake Geneva website. First collected Oct 8, 2026.