October 19, 2026 Public Works Committee Agenda
OCTOBER 19, 2026 PUBLIC WORKS AGENDA.PDF
October 19, 2026 Public Works Committee Packet
OCTOBER 19, 2026 PUBLIC WORKS PACKET.PDF
1.
Documents:
2.
Documents:
County Board Public Works Committee
MEETING NOTICE
Monday, October 19, 2026
3:30 PM
County Board Room 114
Walworth County Government Center
100 W. Walworth St., Elkhorn, Wisconsin
Dennis Karbowski, Chair Ken Monroe, Vice-Chair
Supervisor Joe Schaefer Supervisor Rick Stacey Supervisor Bud Wojcik
(Posted in compliance with Sec. 19.84 Wis. Stats.)
It is possible that a quorum of the county board or any of its other committees could be in attendance at this
meeting.
Agenda enclosures are available upon request from the County Administrator’s Office or on the County’s
web page (www.co.walworth.wi.us).
A G E N D A
Note: all agenda items are subject to action.
1. Call to order
2. Roll call of committee members
3. Agenda withdrawals, if any
4. Agenda approval
5. Approval of Minutes
a) September 14, 2026, Public Works Committee Meeting (encl. pp. 1-4)
6. Public Comment Period
7. Consent Items
(One motion and second will approve all of the following items. Any item may be
pulled from the list and voted on separately)
a) Reports
1) Construction & Project Management Report – October 2026
(encl. pp. 5-9)
NOTICE: THIS MEETING IS PLANNED TO PROVIDE FOR REMOTE OR OFF -SITE ATTENDANCE
BY COMMITTEE MEMBERS.
THE PUBLIC CAN WATCH THE MEETING STREAMING LIVE: https://bit.ly/2026OctPW
Individuals wanting to provide a Public Comment can do so remotely by telephone but must contact
the County Administrator’s Office at 262-741-4357 on the day of the meeting and at least 15 minutes
prior to the start of the meeting to obtain instructions.
AGENDA – Walworth County Public Works Committee
Monday, October 19, 2026, at 3:30 PM Page 2 of 2
2) Report on the County Administrator's Approved Project Change Order
Internal Routing Approval Request for Lakeland Health Care Center (LHCC)
Building Renovations, Change Order #11, Project #W2306 (encl. pp. 10-11)
8. Unfinished Business
a) E-Bike Safety, Regulation, and Policy Recommendations – Law Enforcement
Perspectives (encl. pp. 12-26)
9. New Business
a) 2027 Preliminary Budget (An additional opportunity for discussion or to propose
amendments, if any)
b) Capital Improvement Project (CIP) Change in Scope for Dive Boat Replacement,
Project #C2408 (encl. pp. 27-28)
c) New 2026 Capital Project – Comprehensive Land Use Plan 2029 Update
(encl. p. 29)
d) Res. No. ** - 11/26 Authorizing Acceptance of Community Project
Funding/Congressionally Directed Spending (CPF/CDS) Grant (encl. pp. 30-32)
10. Reports/announcements by Chairperson
11. Set/confirm next meeting date and time – Monday, November 16, 2026, at 3:30 p.m.
12. Adjournment
Submitted by: Dennis Karbowski, Committee Chairperson
Richard Hough, Public Works Director
Posted: October 15, 2026
Public Works | W4097 County Road NN | Elkhorn, WI 53121
www.co.walworth.wi.us | (262) 741-3114 (o) | (262) 741-3117 (f)
Memorandum
To: Public Works Committee
Cc: Mark Luberda, County Administrator
From: Richard A. Hough, Public Works Director
Date: October 12, 2026
Re: October 19, 2026, Public Works Committee Meeting
The following is an overview from our Public Works management team concerning items
scheduled for the above -captioned Public Works Committee meeting. Should you have
any questions before this meeting, please do not hesitate to contact either the appropriate
manager or the Director of Public Works.
Consent Items
One motion and a second will approve all of the following items. Any item may be pulled
from the list and voted on separately.
Consent Items – Reports. The following reports are included on the Agenda. No action
is required unless you have questions that may be placed on file.
1) Construction & Project Management Report – October 2026 – Richard Hough
2) Report on the County Administrator’s Approved Project Change Order Internal
Routing Approval Request for Lakeland Health Care Center (LHCC) Building
Renovations, Change Order #11, Project #W2306 – Nicole Whitman
Unfinished Business
E-Bike Safety, Regulation, and Policy Recommendations – Richard Hough
Follow-up discussion seeking to provide law enforcement perspectives on enforcement
and public safety aspects of the growing use of electrified recreational devices.
Public Works Director’s Memorandum Page Two
New Business
2027 Preliminary Budget (An additional opportunity for discussion or to propose
amendments, if any) – Richard Hough
Opportunity to propose amendments to the preliminary budget.
Capital Improvement Project (CIP) Change in Scope for Dive Boat Replacement,
Project #C2408 – Undersheriff Hausner
The Sheriff’s Office requests to retain the existing dive team pontoon boat, Asset
#100114, and not declare it as surplus.
New 2026 Capital Project – Comprehensive Land Use Plan 2029 Update – Mandy
Bonneville
The Land Use and Resource Management (LURM) Department requests approval to
establish a new 2026 Capital Improvement Project (CIP) to fund professional services
for updating Walworth County’s Multi-Jurisdictional Comprehensive Plan.
Res. No. ** - 11/26 Authorizing Acceptance of Community Project
Funding/Congressionally Directed Spending (CPF/CDS) Grant – Richard Hough
Seeking board approval of a resolution authorizing County staff to accept and
administer the Community Project Funding/Congressionally Directed Spending
(CPF/CDS) Grant for the Lakeland Health Care Center Vacant Wing Modification
project.
/sa
DRAFT Walworth County Board of Supervisors
Public Works Committee Meeting Minutes
Monday, September 14, 2026
Walworth County Government Center, County Board Room 114
100 West Walworth Street, Elkhorn, Wisconsin
Chair Dennis Karbowski called the meeting to order at 3:30 p.m.
R
oll call was conducted and the following members were present: Chair Dennis Karbowski; Vice-
Chair Kenneth H. Monroe; Supervisors Joseph H. Schaefer, and Rick Stacey. Supervisor Bud
Wojcik was absent. A quorum was declared.
O
thers in Attendance
County Staff: Walworth County Administrator Mark W. Luberda; Director-Public Works Richard
Hough; Corporation Counsel/Director-Land Use and Resource Management Michael Cotter;
Director-Asset Management Vijay Narayanan; and Senior Project Manager Joseph Latocha.
On
motion by Supervisor Stacey, second by Supervisor Schaefer, the agenda was approved
with no withdrawals.
On
motion by Vice-Chair Monroe, second by Supervisor Stacey, the July 20, 2026 Public
Works Committee meeting minutes were approved.
P
ublic Comment
The following members of the public spoke regarding the ATV/UTV multimodal use on the White
River County Trail: Barb Nichols, Elkhorn, Wisconsin; Kole Nichols, Elkhorn, Wisconsin, and Alex
Rasch, Walworth, Wisconsin.
S
pecial Order of Business
7a. Appeals/adjustments to the proposed 2027-2031 Capital Improvement Plan (CIP)
Director of Public Works Richard Hough explained that the CIP was the result of a nine-month
team effort and credited Finance Manager Penny Bishop for her essential role. Before presenting
the Capital Projects Overview Brief (2027-2031), he asked for any amendments. Discussion
followed, including comments from Asset Management Director Vijay Narayanan and Senior
Project Manager Joseph Latocha about the planning process for the proposed disc golf course at
Price Park. No appeals or adjustments were made to the CIP.
7b
. Recommendation of the five-year CIP to the Finance Committee
Hough referenced the handout included on Pages 5-18 of the packet. Hough gave a summary of
the presentation entitled Capital Projects Overview Brief (2027-2031), highlighting:
• Roles of Planning/Plans &
Assessments
• Scheduled Assessments
• Parking Lots Plan
• 5-Year Highway Infrastructure Plan
• 10-Year Pavement Plan
• Government Center Projects
H
ough highlighted and discussed in detail the following Major Projects, included on Pages 12-13
of the packet, discussing the proposed years for the projects, the total budget and specific notes:
1 of 32
Walworth County Board of Supervisors
September 14, 2026 Public Works
Committee Meeting Minutes
Page 2 of 4
Hough discussed the Major Projects for the Mechanical, Electrical and Plumbing (MEP) Systems
Less Government Center (GC), included on Page 14 of the packet.
H
ough referenced and discussed the $240K+ Vehicle Updates, included on Page 15 of the
packet.
H
ough referred to and explained the appendix of projects to be evaluated for the 2028-2037 CIP,
included on Page 16 of the packet. Hough referred the 5-Year Comparison and Analysis, included
on Page 17 of the packet, discussing the difference in cost, the major changes, and the budget.
Hough concluded by discussing the inflation factors used for the various projects, included on
Page 18 of the packet.
W
alworth County Administrator Mark W. Luberda thanked Public Works for their efforts on the
CIP before and after the administrative review. He explained that the CIP presented is a solid plan
because of the extensive amount of time spent putting it together. Supervisor Stacey offered a
motion, second by Vice-Chair Monroe, to recommend to the Finance Committee the Five
year Capital Improvement Plan (CIP). Motion carried 4-0.
C
onsent Items
(One motion and second will approve all of the following items. Any item may be pulled from the
list and voted on separately)
8a. Reports
1) Director’s Bi-Monthly Report – September 202
6
H
ough summarized his Memorandum included on Pages 19-26 of the packet, regarding the
Department of Public Works Bi-Monthly Report – September 2026. The discussion focused on
vacancies, new hires, limited term employees, use of material and equipment, maintenance, asset
management/ inventories, updates to policies, plans, training and leadership development,
organization/department key activities, Spring/Summer Maintenance Season,
complaint/notification log, and the new category of Available Budget-Operating Budget Only.
Discussion ensued.
2) C
onstruction & Project Management Report – September 2026
Hough summarized his Memorandum included on Pages 27-31of the packet, Construction &
Project Management Report – September 2026, highlighting the Director’s Top Five Projects.
Discussion ensued.
3) Report on Highway Commissioner’s Approved Project Change Order Internal Routing
A
pproval Request for CTH-H (Williams to STH-120) Change Order #03, Project #240H1
H
ough referenced and summarized the Report on Highway Commissioner’s Approved Project
Change Order Internal Routing Approval Request for CTH-H (Williams to STH-120) Change Order
#03, Project #240H1, included on Pages 32-33 of the packet.
4) R
eport on the County Administrator's Approved Waiver of Competition for purchase of
Burke Plow Blades
2 of 32
Walworth County Board of Supervisors
September 14, 2026 Public Works
Committee Meeting Minutes
Page 3 of 4
Hough referenced and discussed the Report on the County Administrator's Approved Waiver of
Competition for purchase of Burke Plow Blades, included on Pages 34-36 of the packet.
Discussion ensued. Vice-Chair Monroe offered a motion, second by Supervisor Stacey, to
approve Item 8a.3. and 8a.4. Motion carried 4-0.
U
nfinished Business
9a. E-Bike Safety, Regulation, and Policy Recommendations
Hough reviewed his Memorandum and supporting documents, included on Pages 37-46 of the
packet, and explained that today’s discussion aims to guide internal E-bike regulation strategies
and draft a resolution for the Wisconsin Counties Association (WCA). He summarized County
Ordinance recommendations, outlined on Page 38 of the packet. Chair Karbowski voiced safety
and enforcement concerns about E-bike use. Hough noted ongoing initiatives, including
Pedestrian Safety for 2026, and recent discussions with municipalities, with another meeting
planned for the fall. E-bike regulations have also been addressed by the Traffic Safety
Commission, WCA, and at the State level. Vice-Chair Monroe offered a motion, second by
Supervisor Schaefer, to table Item 9a. for more information. Discussion ensued regarding
safety regulations and enforcement. Motion carried 4-0.
N
ew Business
10a. ATV Discussion (Multimodal Use) on White River County Trail
Hough discussed his Memorandum, included on Pages 47 and 48 of the packet, about creating a
multimodal trail on state trails, noting it was reviewed by the Parks Committee earlier today. He
highlighted the requirements and planning involved, as well as the pros and cons of multimodal
use on the White River County Trail. Public safety was the Public Works Department’s top
concern, and he noted that neighboring counties likely would not allow ATVs either. Public Works
staff advised against allowing ATVs on the White River County Trail. Discussion ensued
addressing walker safety, speed limits, possible additional funding, trail maintenance, concern of
potholes and destruction of the trail, potential business benefit, and coordination with neighboring
counties. Luberda explained to the Public Works Committee that earlier today the Parks
Committee voted 4-0 to not pursue the ATV Multimodal Use on White River County Trail. He
stated that if the Public Works Committee votes to go forward with multimodal use, the issue
would go back to the Parks Committee to rediscuss with the Public Works Committee’s input.
A
lex Rasch explained, from a snowmobile alliance perspective, the pros and cons of the ATV
multimodal use on the White River County Trail. In addition, he explained the snowmobile
alliance’s maintenance and accommodation methods. Rasch explained the trail must be open
year-round to qualify for additional ATV/UTV funding. He explained the total amount of
reimbursement from the state would increase from $3,500 to $11,000 with year-round ATV/UTV
use. Supervisor Schaefer offered a motion, second by Chair Karbowski, to pursue the
multimodal use of the White River County Trail. Motion carried 3-1. Vice-Chair Monroe
voted “No.” Hough concluded by stating the issue will go back to the Parks Committee two
months from now, they will have to reconsider, and then the next month will bring the Resolution
to both committees.
3 of 32
Walworth County Board of Supervisors
September 14, 2026 Public Works
Committee Meeting Minutes
Page 4 of 4
10b. Public Works Committee Priorities for Government Center Study
Hough discussed his Memorandum on Page 49 of the packet, highlighting key interests and
seeking guidance for the study. He read the example priorities listed in the first paragraph of his
Memorandum on Page 49. Discussion ensued regarding example priorities—longevity, renovation
and demolition costs, and Elkhorn’s position. Hough noted that a consultant is onboarded and
today’s guidance will aid the study. He also outlined the consultant’s current tasks listed in his
Memorandum, included on Page 49 of the packet. Discussion ensued.
L
uberda presented the following questions for Hough’s feedback.
• Replacing the Government Center's exterior cladding and alternative, more cost-effective
op
tions should be considered, even if they depart from the building's original 1960s style.
• Luberda noted that long-term use of the current building without updates is unrealistic and
suggested adapting the facility to save costs. Hough confirmed that consolidating
d
epartments and reception areas is feasible and offered to provide a renovation cost
an
alysis.
Hough responded that the team has explored department relocations within the building to enable
a consolidated reception desk, which is feasible. He added that if the Committee wants a detailed
analysis with cost impacts for such a renovation, they should let him know.
• The necessity of installing fire suppression systems that are not required by code was
debated, with Luberda noting the shift to digital records
H
ough agreed this is an option and referred to the minor risks slide, which lists projects
recommended for completion in the next decade. If the decision is to remain in the current
building, Hough said installing fire sprinklers would be a difficult choice. Hough said he would like
it clarified in the study if the County renovates the GC to a certain point, code compliance kicks in
and a sprinkler system has to be put in.
10c
. Overview of Public Works 2027 Operating Budget
Hough referenced and summarized the Overview of Public Works 2027 Operating Budgets,
included on Pages 50-72 of the packet. He discussed the Operation Budget Highlights:
Organizational Structure & Payroll; Highway Operations; Asset Management Division; Solid Waste
Program; Highway Infrastructure; Facilities/Parks Infrastructure; and Levels of Service
Clarifications.
R
eports/Announcements by Chairperson – There were none.
C
onfirmation of next meeting date and time: The next meeting was confirmed for Monday,
October 19, 2026 at 3:30 p.m.
A
djournment
On motion and second by Supervisor Schaefer and Supervisor Stacey, Chair Karbowski
adjourned the meeting at 5:29 p.m.
_________________________________________________________________________________
Submitted by Kathleen Aukland, Administrative Assistant. Meeting minutes are not considered final until
approved by the Public Works Committee at the next regularly scheduled meeting.
4 of 32
To:
CC:
From:
Date:
RE:
Rank Status
1 Complete
2 Planning
3 Construction
Phase
4 Contracted
5 Closure
Date
7-Oct
Construction and Project Management Summary Report - October 2026
Director's Top Five Projects: (including $1M+ Projects)
Department was seeking an STP - Local grant with 90%
matching funds for this $4.3M project. The project was
not selected for the 2026 -2030 funding round. Will
resubmit in two years with lower overall PASER.
Concrete Bridge Repairs
Work on two bridges will begin in late-October or early
November. Repairs are beyond internal capabilities but
less than would be required for replacement.
Emergency Response
Contracts
After years of development and coordination, the
Department has established contracts with several
vendors for emergency response (clean-up/recovery)
operations.
Lakeland Health Care
Center
The project is substantially complete, with most punch-list
items closed out. Grant rebate is processing. Occupancy
of final wing is anticipated o/a 20 or 27 October.
Project Remarks
White River Trail Clean Up
The Department of Natural Resources identified some
funding for disaster recovery operations performed this
summer, covers our costs which were less than $5K.
CTH B (Linton Road to STH-
120) with 5.2 Center Line
Miles
Memorandum
October 13, 2026
Walworth County Public Works Committee
Walworth County Administrator - Mark Luberda
Richard Hough - Public Works Director
Highlights and Activities
WisDOT Design Highlights
Project
I-43 Project See Attached Flyer
5 of 32
Page 2
We received the Notice of Award for the $1mm Department of Health and Human Services
(DHHS), Health Resources And Services Administration (HRSA), Community Project
Funding/Congressionally Directed Spending Projects (CPF/CDS) grant.
County Engineer Major Project Summary (Since Last Report)
Project Highlights and Activities
W2621
Lakeland Health Care
Center
D Wing CBRF
Highlights and Activities
26-003 - CTH-H
George St. to Geneva
Square
26-009- CTH-H
USH-12 to Co. Line
Construction on the mainline is substantially complete. Contractor is working on the lane
widening between Center St. and Sage St. Highway remains open to through traffic with
reduced lanes.
Reviewing submittals and schedules for bridge repair work. The work is tentatively scheduled
to take place in late October or early November. Repair work will be done using shoulder
closures only. No traffic impacts are anticipated.
Construction work is on-schedule. The first lift of asphalt has been placed - the final lift of
asphalt is scheduled for the week of 10/5. Highway is closed to through traffic, but remains
open to local traffic. Detour is in place for non-local traffic and trucking.
Project
W2648
Government Center
Facility Needs
Assessment
Associate County Engineer Top 3 Project Summary (Since Last Report)
26-059 Concrete
Bridge Repairs
Needs assessment questionnaires were issued and most have been returned. We are
conducting interviews with departments housed in the Government Center the week of
October 12 to generate a summary of the overall needs.
24-056 / W2306,
W2307, W2414
Lakeland Health Care
Center Renovation
Punchlist work is progressing and nearing completion. The DHS inspector was onsite
September 25 and had a few comments. The comments are being addressed for residents to
return to A Wing (Honey Creek Haven) this month.
We are compiling the final paperwork for the Energy Efficiency and Conservation Block Grant
(EECBG).
6 of 32
Page 3
DD (Name) Highlights and Activities
Barry Pierce
Barry Pierce
Barry Pierce
Vijay
Narayanan
Vijay
Narayanan
Vijay
Narayanan
PM (Name) Highlights and Activities
Joe Latocha
Joe Latocha
Joe Latocha
CTH A & USH 12
Visibility Concern
Staff is addressing a significant visibility concern at this location. Work
includes removing topsoil, vegetation, and restoration.
Campus Parking Lot
Maintenance
Highway staff completed 2026 Parking Lot maintenance. All in, this
included Reclamite application, crackfill operations, and painting.
Crackfill Operations began and continue on this roadway from the Grand
Geneva East to the County line
Deputy Director(s) Top 3 Summary (Since Last Report)
Project
HWY 50 DMA
Project Manager(s) Top 3 Summary (Since Last Report)
2026/27 Winter Ops
Preparations
Service Contracts
Continuing workload for Service Contracts and/or Cooperative Purchase
Agreements.
1) Completed: N/A
2) In-Progress: SO Range - HVAC PMs & Services & Lead Filter Removal;
Elevator Maintenance & Repair Service; CRAC Unit PMs & Repairs; JC - X-
Ray PM & Services; Water Treatment Services
Document 'lessons learned' from the field testing of the robotic mower at
the SO and development of a larger-scale robotic mower fleet &
deployment.
Updates to Campus Snow Plan and Development of Training Needs within
Facilities and Parks-Grounds Division
Continued
Development of
Robotic Mowers
Project
W2610 DA Additional
Storage
Work is moving along as scheduled. Walls constructed, electrical / data
completed and finished work is ongoing. Construction is scheduled to be
completed by Oct 23rd, with furniture delivery Oct 27 - 28.
RFP reviewed by purchasing, DPW is working through recommended
changes.
New Heating System has been commissioned and is running. Punchlist
items are expected to be completed by mid-late October. Lead times on
specialized materials has extended the project completion date slightly.
W2003 Phase II
Security RFP
W2402/W2404 Boiler
& Cabinet Unit Heater
7 of 32
PM (Name) Highlights and Activities
Elliott Blaszczyk
Elliott Blaszczyk
Elliott Blaszczyk
Project
Page 4
Southport has mobilized with replacing the (7) hydronic garage heaters at
the Sheriff's Office. Low voltage controls will replace the existing
pneumatics, bringing the building closer to eliminating pneumatic controls.
W2605 Sheriff's Office
Garage Heater
Replacements
The playground base, structure, and border are installed. Expecting
delivery of the climbing net, rope, and clambering loops in early
November. Installation and playground commissioning to follow.
W2538 Price Park
Natural Playground
W2627 LHCC Rear
Employee Entrance
Replacement
Replacement of the double-door employee entrance at Lakeland
Healthcare Center. Door has been delivered. Anticipated install date of
October 20th or 27th. Currently coordinating with the electrician and door
installer for a firm install date.
8 of 32
I-43 ROCK FREEWAY PROJECT OVERVIEW
Bowers Road to WIS 83 October 2026
The Wisconsin Department of Transportation (WisDOT) is scheduled to begin a pavement replacement and
improvement project along approximately 9.8 miles of the I-43 Rock Freeway, between Bowers Road and WIS 83
in Waukesha and Walworth Counties, with completion scheduled for summer 2029.
WORK TO BE COMPLETED:
• Concrete pavement replacements and resurfacing
throughout the project limits
• Structure improvements to multiple bridges along the
corridor
• Culvert pipe repair and replacement, and drainage
improvements
• New guardrail, signing, and pavement markings
2026 TRAFFIC IMPACTS:
• Periodic overnight lane and ramp closures will be utilized
un
til early November to construct emergency pullouts,
t
emporary shoulders, and ramp widening improvements
• Long-term lane closures on I-43 will
begin in spring 2
027
43
43
20
2020
COUNTY
ES 83
COUNTY
I
COUNTY
J
COUNTY
E
COUNTY
J
120
43
H
olzPkwy
COUNTY
L
COUNTY
D
COUNTY
ES
Phantom Lake
Potter Lake
Booth
Lake
Lake Beulah
Army
Lake
Eagle Spring L ake
COUNTY
N
COUNTY
D
East Troy
Airport
East Troy
Airport
Carver School RdCarver School Rd
Hillburn Mill RdHillburn Mill Rd
Stone School RdStone School Rd
Stingers Bridge RdStingers Bridge Rd
Pickeral Lake RdPickeral Lake Rd
Hamms RdHamms Rd
Bowers RdBowers Rd
Oakwood LnOakwood Ln
Townline RdTownline Rd
Colbo RdColbo Rd
Miller RdMiller Rd
Saint Peters RdSaint Peters Rd
Main StMain St
Beulah RdBeulah Rd
Bells School RdBells School Rd
Canadian National RR
Canadian National RR
Project Contact:
Rachel Andreoli
Construction Public Involvement Lead
(414) 758-9386 | Randreoli@hntb.com
https://projects.hub.wisconsindot.gov/
pages/10900905
SCAN FOR MORE
INFORMATION
map not to scaleLEGEND
PROJECT LIMITS
N
BEGINNING THE WEEK OF OCTOBER 5:
• Overnight lane and ramp closures on I-43 northbound
within project limits
If you would like to receive future
project updates, please contact
Rachel Andreoli at randreoli@hntb.com
to be added to our distribution list.
9 of 32
Approved
Enacted 10/22/2021
Form 6-310-B
Revised 07/18/2025 Change Orders Page 1 of 2
Form 6-310-B: Project Change Order Internal Routing Approval Request
Contract Name: 24-056 Lakeland Health Care Center Building Renovations Contract Number: 2523
Vendor Name: Tri-North Builders Inc Department Purchasing Contact: Nicole Whitman
1. Change Order Details Change Order( s) #: 11
Type of Change Order (select all that apply):
☒ T he work outlined in the chan ge order has already been performed. Failure to proceed with the change order would have
resulted in cessation of work and financial loss.
☐ P roposed work is beyond the original scope of work.
☒ P roposed work could not have been reasonably foreseen by architect, contractor , vendor, or County.
☒ P roposed work due to error or omission (further explained in comments below).
☐ S avings as a result of reduced scope or value engineering.
Change Order(s) Description: PCO 65 - HVAC added boiler vent piping and fittings $9,564.97, PCO 94 – AHU-1 Mech
room relocates and temp feeds $40,809.09; PCO 101 – RFI 85 electrical for cove lighting in main core $7,615.51; PCO
102 – HVAC added mechanical insulation $25,688.65; PCO 106 – Low voltage work for door changes on PCO 06
$5,103.54; PCO 108 – T&M extra work for B and A Wings combined $64,642.56; PCO 114 – HVAC above ceiling
investigation work $6,486.49; PCO 116 – HVAC VIC fitting with insulation in lieu of welding $14,307.96; PCO 120 -
Plumbing for A Wing misc. items $7,372.34; PCO 123 - Electrical relocates in A Wing $27,586.10; PCO 128 - Flooring -
Final prep in A Wing and B Wing with core $11,259.95; PCO 131 - HVAC RFI 116 - By-Pass control valve $4,408.95.
☒ Special circumstances/emergency/timing concerns requiring immediate action
☐ Updated Contract Dates: N/A
☐ Additional scope of work (justification to amend contract vs. a separate procurement in comments below)
Additional Comments: PCO 65 – Vent changes for boiler changes, Errors and Omissions and boiler spacing for access,
Owner Request; PCO 94 – Coordination for construction / sequencing maintaining operable building, Discovered
Conditions; PCO 101 - Existing light switching and feeds were not compatible with lighting layout per the drawings,
Discovered Conditions; PCO 102 - Pipe insulation not shown on drawings – Errors and Omissions and ductwork changes,
Discovered Conditions; PCO 106 - Scope of work required not shown on the drawings, Errors and Omissions; PCO 108 -
Floor prep, drywall repairs, fire caulking, façade stonework salvage / reuse, moving into B Wing coordination and misc
carpentry, Discovered Conditions; PCO 114 -Coordination of drawings/submittals for fan coil unit, Discovered
Conditions; PCO 116 - Due to access above ceiling, Discovered Condition; PCO 120 - Moving bathers, waste line, toilet
repairs, Discovered Conditions and sink not on drawings, Errors and Omissions; PCO 123 - Transformer relocation, misc
lighting / switching and power for HVAC, Discovered Conditions; PCO 128 – Discovered Conditions; PCO 131 -
Existing was not functioning or compatible with the new controls system, Discovered Conditions.
2.
Change Order Amounts/Funding
Change Order Amount: ☒ Actual (firm fixed, not-to-exceed) ☐ Estimated (indefinite quantity, time and materials, etc.)
Original Contract Amount ................................................................................... $ 9,167,595.00
Prior Approved Change Order(s) ........................................................................... $ 783,200.79
Amount of this Change Order(s): ........................................................................... $ 224,846.11
Revised Contract Total with this Change Order(s): .......................................... $ 10,175,641.90
P ercentage of total change orders, including this change .................................................. 11.0%
Project Contingency Remaining: ............................................................................ $ 239,122.28
Account Number/Name: 512050-58130-W2306; 512050-58*-W2307; 512050-58130-W2414.
Budget Sufficient? ☒ Yes ☐ No
Budget/Funding Comments: Within budget
10 of 32
Approved
Enacted 10/22/2021
Form 6-310-B
Revised 07/18/2025 Change Orders Page 2 of 2
3. Review Process (DPC to check the box for each applicable approval required.)
Reviewer approval confirms the change is reasonable, in the County’s best interest, and funds are available.
A
ll approvals are obtained electronically through the Intake Request
(except for Committee Approval/Report)
☒ Department Head
☒ Purchasing Manager
☐ C
orporation Counsel (if non-standard/vendor change order)
☒
Finance Director/Highway Commissioner (if within authority or proceeding to Administrator or Committee)
☒ County Administrator ( if special circumstances, reissuance, or proceeding to Committee)
C
ommittee: Public Works Type: Report Only Meeting Date: 10/19/2026_________
Committee: N/A Type: N/A Meeting Date: ___________
11 of 32
Memorandum
To: Public Works Committee Members
Cc: Walworth County Administrator – Mark Luberda
Sheriff’s Office – Sheriff Gerber
From: Public Works Director – Richard Hough
Date: September 1, 2026
Re: E‑Bike Safety, Regulation, and Policy Recommendations
September Public Works Committee requested further information regarding law
enforcement perspectives on e-bikes safety and enforcement. I reached out to the City
of Elkhorn and Village of Walworth, and the Sheriffs Office seeking their availability at
the October Public Works Committee.
If they are unable to attend, below is a summary of our conversation and research
findings. Also, I’ve attached their ordinances, and, a draft ordinance and resolution for
discussion prior to introduction to other committees in November.
Gathered perspectives from Law Enforcement:
• Village of Walworth stated, “The adopted ordinance is now being reviewed by
our village attorney as the village was contacted by an outside watch group
claiming that ordinance violates rights. The ordinance was created after
researching departments in the county and state that have existing ordinances.
Some minor changes, redactions, and additions felt appropriate were made prior
to presenting it to the Board.
With the drastic increase this past summer with crashes involving these items,
the goal behind the ordinance was for public safety, first and foremost. We know
that even with this ordinance, there is still only so much that an officer can do
regarding enforcement. The ordinance, which is attached, describes for example,
the different classifications, miles per hour each are, where they can be ridden
and where they are prohibited, etc.
12 of 32
Re: E‑Bike Safety, Regulation, and Policy Recommendations
Overall, without specific training, in my opinion, it will be difficult to enforce some
of the ordinance for areas such as classification. This training is currently not high
on the priority list. Plus, many times when a complaint is received, the suspected
person is no longer in the area to speak with.
Major Enforcement Concerns and Observations
• Regulatory Ambiguity & "E-Motos": Officers struggle to distinguish legal e-
bikes from illegal high-speed e-motorcycles or throttle-heavy "e-motos" that
exceed wattage and speed limits (often traveling 35–40 mph).
• Reckless Riding & Sidewalk Conflicts: Riders frequently dart into traffic, ignore
red lights and stop signs, and speed past pedestrians on crowded sidewalks and
multi-use paths.
• Young Riders & Accountability: Many underage children operate high-
performance devices without proper training or helmets, prompting police and
municipalities to consider holding parents liable through citations and
impoundments.
• Anonymity & Lack of Identification: Because e-bikes and e-scooters do not
require license plates, registration, or driver's licenses, police face hurdles in
tracking or penalizing moving violations.
Major Safety Concerns
• Surging statistics: U.S. emergency room visits and injuries tied to electric
micromobility skyrocketed from about 10,500 in 2017 to nearly 80,000 by 2024,
prompting Consumer Reports to withhold recommendations for tested e-scooter
models due to speed and stability risks.
• Severe trauma: Studies show e-device riders suffer higher rates of intensive care
unit (ICU) admissions and traumatic brain injuries (TBIs) than traditional bicycle
riders, often involving skull fractures and facial trauma.
• Pediatric patients account for over 45% of e-scooter injuries, with emergency
visits among kids surging drastically as younger riders operate high-speed
devices.
• High speeds: E-bikes can reach 20 to 28 mph (Class 3), and e-scooters
frequently top out at 20 mph, speeds that standard bicycle helmets are not rated
to protect against.
• Lithium-ion thermal runaway: Damaged, defective, or cheap replacement
batteries can overheat and trigger aggressive, hard-to-extinguish fires or severe
chemical burns.
• Lithium-ion thermal runaway: Damaged, defective, or cheap replacement
batteries can overheat and trigger aggressive, hard-to-extinguish fires or severe
chemical burns.
13 of 32
Re: E‑Bike Safety, Regulation, and Policy Recommendations
Reference Data:
1 Village of Walworth Ordinance, Passed July 2026
2 City of Elkhorn Draft Ordinance, pending 2026 board review
3 Draft Resolution to Governor of Wisconsin (Not Provided)
4 Draft Ordinance change to Chapter 66 of WALCO Ordinances (Not Provided)
14 of 32
15 of 32
16 of 32
17 of 32
18 of 32
CI
TY OF ELKHORN
COMMITTEE OF THE WHOLE AGENDA
August 17, 2026 – 4:30 p.m.
Council Chambers, 311 Seymour Ct., Elkhorn, WI 53121
1. C
all to Order
2. Roll Call
3. Discussion and possible decision on draft of an ordinance to amend the Municipal Code
Section 12.07 Entitled “Bicycles” and to create Section 7.225 Entitled “Bicycles, Electric
B
icycles, Electric Scooters and Play Vehicles” Relating to the Regulation of Bicycles,
Electronic Bicycles, Electric Scooters, and Play Vehicles
4. Discussion regarding city code provisions contained in Chapter 9.07 Regulation of Animals
within City limits and specifically the regulation of backyard chickens and possible decision
drafting revisions to city code
5. Ad
journ
D
ATED at Elkhorn, Wisconsin, this 14th day of August 2026
R
ebeca Perez, City Clerk
Should you have any questions or comments regarding any items on this agenda, please contact the City
Clerk’s office at 723-2219. Upon reasonable notice to the City Clerk, efforts will be made to
accommodate the needs of disabled individuals through appropriate aids and services.
19 of 32
1 of 6
CITY OF ELKHORN
O
RDINANCE NO. 2026-______
AN
ORDINANCE TO AMEND MUNICIPAL CODE SECTION 12.07 ENTITLED
“BICYLCES” AND TO CREATE SECTION 7.225 ENTITLED “BICYCLES, ELECTRIC
BICYCLES, ELECTRIC SCOOTERS AND PLAY VECHICLES” RELATING TO THE
REGULATION OF BICYCLES, ELECTRONIC BICYCLES, ELECTRIC SCOOTERS, AND
PLAY VEHICLES.
W
HEREAS, the City of Elkhorn has previously adopted a Code of Ordinances which
includes regulations regarding bicycles; and
W
HEREAS, Sections 349.18 and 349.237 of the Wisconsin Statutes authorize
municipalities to regulate bicycles, motor bicycles, electric scooters; and
W
HEREAS, the Committee of the Whole discussed the regulation of electric bicycles,
electric scooters, and play vehicles at its meeting on May 18, 2026; and
W
HEREAS, the City, as evidenced by the discussion at the Committee of the Whole
meeting, wishes to regulate the use of such vehicles within the City of Elkhorn.
T
he Common Council of the City of Elkhorn do hereby ordain as follows:
S
ection 1: That Section 12.07 entitled “Bicycles” is hereby amended to read as follows:
“12.07
Bicycles, Electric Bicycles and Electric Scooters.
(1
) License Required. No person shall operate a bicycle , electric bicycle, or electric
scooter customarily kept within the City on any street within the City unless the
bicycle, electric bicycle, or electric scooter is registered and tagged as required
herein.
(2
) [Reserved] State Statutes Adopted. The provisions of Sections 346.77 through
346.82, Wis. Stats., pertaining to rules of the road and operation of bicycles are
adopted by reference as if fully set forth herein.
(3
) Registration. Every owner or operator of a bicycle , electric bicycle, or electric
scooter within the City shall file with the Police Department a complete description
of such bicycle, electric bicycle, or electric scooter, upon forms furnished by the
Police Department, which shall include the following information:
(
a) Applicant's name and address.
(b) Name of bicycle, electric bicycle, or electric scooter manufacturer.
(c) Bicycle s Serial number.
(d) Model number and color.
20 of 32
2 of 6
(e) Class designation if an electric bicycle.
S
uch registration shall be serially numbered and kept on file by the Chief of Police
in his office as a public record.
(4
) Identification Tag. Upon registration, the owner shall affix an identification tag to
such bike, electric bicycle, or electric scooter serially numbered to correspond with
the registration, which shall be furnished by the Police Department. Such tag shall
not be removed unless by the Police Department for cause or for replacement with
another tag upon re -registration. Bicycles, electric bicycles, and electric scooters
shall be registered biennially.
(5
) Registration Fee. A charge of $3.00 per registration shall be made for the
registration or tagging of any bicycle, electric bicycle, or electric scooter under this
section.
(6
) Inspection of Bicycles , Electric Bicycles, or Electric Scooters. The Police
Department shall cause to be inspected each bicycle, electric bicycle, or electric
scooter presented for registration and shall refuse to register any bicycle , electric
bicycle, or electric scooter found to be in unsafe mechanical condition or not
equipped as herein required by state statute, federal regulation, or any section of
this Code of Ordinances.
(7
) Change of Ownership. Within 10 days after any bicycle, electric bicycle, or electric
scooter registered hereunder shall have changed ownership or been dismantled and
taken out of operation, such information shall be reported to the Police Department
by the person in whose name the bicycle , electric bicycle, or electric scooter has
been registered.
(8
) [Reserved] Bicycle Riding Regulations.
(
a) No bicyclist shall proceed on any street in the City by inertia of momentum
with his feet removed from the pedals.
(b
) No bicyclist shall remove both hands from the handlebars or practice any
trick or fancy riding in any street in the City or carry or ride any other person
so that 2 persons are on the bicycle at one time.
(
c) No bicyclist shall operate during the time from one half hour after sunset
until one half hour before sunrise unless equipped with a white light on the
front of the bicycle and a red reflector or a red light in the rear.
(d
) No person shall ride a bicycle on the sidewalks in the business district of
the City. The business district of the City, for the purpose of this section, is
defined as Walworth Avenue, between Lincoln and Broad Streets and
Wisconsin Street between Court and Geneva streets.
21 of 32
3 of 6
(
e) No person shall leave or park a bicycle at such a place or in such a way as
to create a hazard to pedestrians, automobile operators or anyone else.
(f) Persons riding or using bicycles or other similar vehicles along or upon any
public street, avenue, lane, alley or other public road, ground or way within
the City shall not ride more than 2 abreast, excepting in general parade or
public demonstration.
(9
) Suspension of Registration. The Chief of Police may suspend the registration of
and remove the identification tag from any bicycle , electric bicycle, or electric
scooter being operated upon any street in the City within the City limits of the City
of Elkhorn in an unsafe manner or in violation of any State law or local ordinance;
and such suspension of registration and removal of tag shall be in addition to other
penalties.
(
10) Violations. Any person operating any bicycle , electric bicycle, or electric scooter
not properly registered or carrying a proper identification tag or not being the owner
of a registered bicycle, electric bicycle, or electric scooter without an operator's
license card, as required herein, or who operates a bicycle, electric bicycle, or
electric scooter in an unsafe manner in violation of Section 7.225 or State Statutes,
shall be deemed as having violated this section.”
S
ection 2: That Section 7.225 entitled “Bicycles, Electric Bicycles, Electric Scooters, and Play
Vehicles,” is hereby created to read as follows:
“
Sec. 7.225 Bicycles, Electric Bicycles, Electric Scooters, and Play Vehicles.
(1
) State Statutes Adopted. The provisions of § 340.01, Chapter 346, and Section 347.489
of the Wisconsin Statutes pertaining to definitions, rules of the road and the operation
of bicycles, and equipment required on bicycles are adopted by reference as if fully set
forth herein.
(2) Equipment on bicycles and devices. No person shall operate a bicycle, e- bike, or
electric scooter upon a highway, sidewalk, or bicycle lane unless equipped as required
in Wis. Stat. § 347.489.
(a) L
ights and Reflectors. Bicycles, e bikes, and electric scooters must be equipped
with lights and reflectors as required in Wis. Stat. § 347.489 when riding from
the hours of dusk to dawn.
(3) Bicycle, e-bike, and electric scooter operation regulations.
(a) No person shall park or leave a bicycle, e-bike, or electric scooter at such a
place or in such a way as to create a hazard to pedestrians, automobile operators,
or to anyone else.
22 of 32
4 of 6
(b) No person shall ride or park a bicycle, e -bike, electric scooter on the sidewalk
in the Downtown Business District of the City of Elkhorn. The Downtown
Business District of the City, for the purpose of this section, is defined as
Walworth Avenue, between Lincoln and Broad Streets and Wisconsin Street
between Court and Geneva streets.
(c) Bicycles may be ridden on sidewalks other than those in the Downtown
Business District and on any street/highway in the City limits of the City of
Elkhorn. Every person operating a bicycle upon a sidewalk must ride in single
file and at low rates of speed. E-bikes and electronic scooters may not be ridden
on sidewalks within the City.
(d) Whenever a usable bicycle path has been provided adjacent to a roadway,
operators of bicycles, e -bikes, electric scooters, shall use such path and shall
not use the roadway.
(e) No person riding upon a bicycle, e -bike, electric scooter, or play vehicle shall
cling or attach himself or his bicycle, e-bike, electric scooter, or play vehicle to
any other moving vehicle within the City limits of the City of Elkhorn, nor shall
the operator of any such device tow or draw any coaster wagon, sled, person on
roller skates, toy vehicles, or any other similar vehicle on such highway.
(f) Any operator of a bicycle, e -bike, or electric scooter involved in a collision
with a bicycle, e- bike, electric scooter, other vehicle, or object resulting in
damage to such other property in excess of $25 or in a collision with a
pedestrian resulting in bodily injury to such pedestrian shall, within 24 hours,
report such collision to the Police Department.
(g) The bicycle, e -bike, or electric scooter operated by any person under age 18
years in violation of this section shall be surrendered to the Elkhorn Police
Department. Upon request, the Department shall release the device to the parent
or guardian of said operator, provided the device is registered as required under
§ 12.07.
(h) No person shall operate a bicycle, e- bike, electric scooter, or play vehicle at a
speed greater than is reasonable and prudent under existing conditions.
(i) No person shall operate a bicycle, e -bike, or electric scooter in excess of any
posted speed limit if operating within the City limits of the City of Elkhorn.
(j) An operator of a Class 3 e-bike must be 16 years of age or older.
(k
) No bicyclist shall proceed by inertia of momentum with his feet removed from
the pedals within the City limits of the City of Elkhorn.
23 of 32
5 of 6
(l) N o bicyclist , electric bicyclist, or rider of an electric scooter shall remove both
hands from the handlebars or practice any trick or fancy riding within the City
limits of the City of Elkhorn or carry or ride any other person so that 2 persons
are on the bicycle, electric bicycle, or electric scooter at one time.
(m
) Persons riding or using bicycles , electric bicycle, or electric scooters or other
similar vehicles along or upon any public street, avenue, lane, alley or other
public road, ground or way within the City shall not ride more than 2 abreast,
excepting in general parade or public demonstration.
(n) Riding and e bike, electric scooter, or bicycle in parking lots is prohibited,
unless having written permission from the owner or lessee or the rider is using
the parking lots as ingress or egress from a destination. Parking lots are not to
be used for recreational use unless owner permission is obtained.
(4
) Play vehicles.
(a) Operation on sidewalks. The operator of a play vehicle, operating the same on
any sidewalk where such operation is not prohibited, shall yield the right -of-
way to any pedestrian on a sidewalk.
(b) Operating play vehicles prohibited. The operation or riding of play vehicles is
prohibited in the following instances:
1. On sidewalks in the Downtown Business District.
2. In o ther areas held out to the public, such as parking lots, that are
properly posted prohibiting operation of play vehicles, unless having
written permission from the owner or lessee or using the parking lots
as ingress or egress from a destination. Parking lots are not to be used
for recreational use unless owner permission is obtained.
(c) No person riding upon any play vehicle may attach the same or himself or
herself to any vehicle upon a roadway or go upon any roadway except while
crossing a roadway at a crosswalk.
(d) The play vehicle operated by any person under age 18 years in violation of this
section shall be surrendered to the Elkhorn Police Department, and upon
request, the Department shall release the same to the parent or guardian of said
operator.
(5
) Violations and penalties.
(a) Any person 12 years of age or older who violate s any provision of this section
shall be subject to the penalties as set forth in § 7.26.
24 of 32
6 of 6
(b) Any parent or guardian of any child who authorizes or knowingly permits such
child to violate any of the provisions of this section may be subject to the
penalties in Subsection (a) above.”
Sect
ion 3: THIS ORDINANCE shall be effective after adoption and publication as provided by
law
S
ection 4: THIS ORDINANCE shall be posted and published as provided by law.
A
PPROVED AND ADOPTED THIS _____ day of _____ 2026.
____________________________________
G. Timothy Shiroda, Mayor
A
TTEST:
_____________________________
R
ebeca Perez, City Clerk
1st Reading: ____________
2nd Reading: ____________
Adopted: _______________
Published: ______________
25 of 32
MAP OF STREETS INCLUDED IN DOWNTOWN BUSINESS DISTRICT FOR PURPOSES OF
PROPOSED ORDINANCE 2026-08
REGULATING E-BIKES AND E-SCOOTERS
S
TREETS INCLUDED
W. Court St. (from N. Church St. to N. Wisconsin St.)
E. Court St. (from N. Wisconsin St. to N. Lincoln St.)
N. Lincoln St. (from E. Court St. to E. Walworth St.)
S. Lincoln St. (from E. Walworth St. to E. Geneva St.)
E. Geneva St. (from S. Lincoln St. to S. Wisconsin St.)
W. Geneva St. (from S. Wisconsin St. to S. Church St.)
S. Church St. (from W. Geneva St. to W. Walworth St.)
N. Church St. (from W. Walworth St. to W. Court St.)
W. Walworth St. (from Church St. to Wisconsin St.)
E. Walworth St. (from N. Wisconsin St. to N. Lincoln St.)
S. Broad St. (from W. Walworth St. to W. Geneva St.)
N. Wisconsin St. (from Court St. to Walworth St.)
S. Wisconsin St. (from Walworth St. to Geneva St.)
N. Washington St. (from E. Court St. to E. Walworth St.)
S. Washington St. (from E. Walworth St. to E. Geneva St.)
26 of 32
Form 1-220-B: Capital Improvement Project Change in Scope
D Requesting change in scope within Administrator Authority, Report to Public Works Committee.
� Change in scope requires Public Works Committee approval.
Requesting department: Sheriffs Office Approving committee: Public Works Committee
Capital Project Name Project Identifier Project Budget
Dive Boat Replacement C2408 $361,358
Justification to Change Scope Cost (Savings): NIA
The Sheriffs Office requests to retain the existing dive team pontoon boat, Asset# I 00 I 14, and not declare it as
surplus for this project. Retaining the existing dive boat enhances the department's capacity for operations,
especially during emergencies when multiple teams might need to deploy. The pontoon boat will provide a stable
means of transporting dive team personnel, equipment, and support materials to and from areas of operation. Its
use will help the team respond efficiently to water-related incidents, stage resources near the scene, and support
search, recovery, and other emergency operations when conditions and vessel safety permit. The remaining utility
the existing pontoon boat is expected to exceed the value returned through the surplus process because the surplus
value is expected to be low. The value of the existing pontoon boat is not expected to significantly decrease with
further use. The maintenance cost on the existing pontoon boat has totaled $985.94 across the previous two years.
The Sheriffs Office currently has storage arranged for both boats.
�.:.ve r iewed and approve the request. Funds are available within the project.
--=-10=---=-0.,_7 --=2=02=6=---------
Department Head Signature Date
Managing Project Department Head/Elected Official:
"W" or Road Project - PW Director "I" Project - IT Director "C" Project - No further signature required
I have reviewed from an operational perspective with the following comments:
PW or IT Direc1or Signature
Finance Director:
I have reviewed from a financial perspective with the following comments:
Approved�
Enacted 11/19/2020
Revised I 0/22/2021
Finance Director Signature
Capital Improvement Budget
Date
Dale
Form 1-220-B
Page I of2
10/7/2026
27 of 32
County Administrator:
□ Committee approval required
Comments on �-�a!lge of Scope:
D Report to Committee, compelling need to move forward exists
County Administrator Signature Date
Public Works Committee Decision: D Approved □ Disapproved Signature: ______ Mtg Date:
Form to be maintained by Senior Accountant-Public Works.
Approved
Enacted
Title Form#
Page 2 of2
10-13-26
I support the boat to be retained for support and shuttling during dive operations,
but I do not support its use directly in dive team operations itself. In short,
it can continue to be used as a boat, but not as a "dive" boat.
x
28 of 32
100 W. Walworth St. | PO Box 1001 | Elkhorn, WI 53121
www.co.walworth.wi.us | (262) 741-4972 (o) | (262) 741-4973 (f)
Memorandum
To: Walworth County Land Conservation Committee, County Zoning Agency, Public
Works Committee, and Finance Committee
Cc: Mark Luberda, County Administrator
Jessica Conley, Finance Director
Michael Cotter, Corporation Counsel/LURM Director
Richard Hough, Public Works Director
From: Mandy Bonneville, LURM Deputy Director/County Conservationist
Date: September 29, 2026
RE: New 2026 Capital Project – Comprehensive Land Use Plan 2029 Update
The Land Use and Resource Management (LURM) Department requests approval to
establish a new 2026 Capital Improvement Project (CIP) to fund professional services for
updating Walworth County’s Multi -Jurisdictional Comprehensive Plan. Section 66.1001
of Wisconsin Statutes requires comprehensive land use plans to be updated no less than
once every 10 years. An update to the plan for Walworth County is due by June of 2029.
The County will enter into an agreement with the Southeastern Wisconsin Regional
Planning Commission (SEWRPC) to perform the plan update. SEWRPC has performed
updates to Walworth County’s comprehensive plan since 2009. SEWRPC’s extensive and
detailed inventory of land use, population information and projections, transportation,
housing, and other plan elements for the area are valuable in preparation of the County’s
plan. The plan update is expected to take approximately two years to complete. The
project will be managed by LURM.
LURM is seeking authorization to create a capital project for 2026 and initiate a $25,000
budget amendment to commission SEWRPC’s services for the plan update. The project
will be funded utilizing vacancy savings from an Administrative Clerk III position with in
LURM.
29 of 32
1
Resolution No. **-11/26
Authorizing Acceptance of Community Project Funding/Congressionally Directed
Spending (CPF/CDS) Grant
M
oved/Sponsored by: Lakeland Health Care Center Board of Trustees, Public Works 1
Committee, and Finance Committee 2
3
WHEREAS, Walworth County applied for funding from Congress and was awarded a grant 4
reimbursement of eligible costs up to $1,000,000 through the Congressional Directed Spending 5
program for the construction of the Lakeland Health Care Center (LHCC) vacant wing 6
modification; and, 7
8
WHEREAS, the Congressional Directed Spending outlines guidance to federal agencies for 9
recipients to accept an award; and, 10
11
WHEREAS, the Human Resources and Services Administration is the governing agency for the 12
type of grant most appropriate for the Lake Health Care Center wing renovation project; and, 13
14
WHEREAS, the County received the formal application in June with an early July deadline for 15
its submission; and, 16
17
WHEREAS, the Board has recently released the administrative hold on LHCC Vacant Wing 18
Modification project regarding the study and predesign with an existing 2026 budget of 19
$190,000; and, 20
21
WHEREAS, the 2027 budget includes $4 million for the LHCC vacant wing modification 22
funded with $1 million in grant funding and $3 million in use of LHCC net position building 23
reserves with an administrative hold pending County Board action. 24
25
NOW, THEREFORE, BE IT RESOLVED, that the Walworth County Board of Supervisors 26
directs the County Administrator and County staff to accept the $1,000,000 Community Project 27
Funding/Congressionally Directed Spending Grant, agree to the terms and conditions, now that 28
we have formal notification of award by the federal Human Resources and Services 29
Administration. 30
31
BE IT FURTHER RESOLVED that “one-time” grants continue to require authorization as 32
specified in Chapter 30, Article VIII of Walworth County Code of Ordinances. 33
34
35
36
Rick Stacey Susi Pike 37
County Board Chair County Clerk 38
39
County Board Meeting Date: November 10, 2026 40
41
42
30 of 32
2
Action Required: Majority Vote X Two-thirds Vote Other ______ 1
Policy and Fiscal Note is attached.
Reviewed and approved pursuant to Section 2-91 of the Walworth County Code of Ordinances:
____
_______________________________ ___________________________________
Michael P. Cotter Date Jessica Conley Date
Corporation Counsel Finance Director
____
_______________________________
Mark W. Luberda Date
County Administrator
I
f unsigned, exceptions shall be so noted by the County Administrator.
31 of 32
3
Policy and Fiscal Note
Resolution No. **-11/26
I. T
itle: Authorizing Acceptance of Community Project Funding/Congressionally Directed
Spending (CPF/CDS) Grant
II. P
urpose and Policy Impact Statement: This resolution authorizes the County staff to
accept and administer the Community Project Funding/Congressionally Directed
Spending (CPF/CDS) Grant for the Lakeland Health Care Center Vacant Wing
Modification project.
III. B
udget and Fiscal Impact: The reimbursement of eligible costs up to $1,000,000 grant
from the federal Human Resources and Services Administration was formally awarded in
September 2026. The total project budget is estimated at $3.5M-$4M, subject to
additional decisions regarding the project's scope. The federal funds are likely to be
reduced if eligible costs are under the established and federally approved budget. If some
costs incurred are deemed ineligible, our planned project funding mix and associated
budget may need to be adjusted. The 2027 budget includes $1 million of grant funding
and $3 million of County funding with Lakeland Health Care Center net position building
reserves. No budget amendment is necessary at this time.
I
V. Referred to the following standing committee(s) for consideration and date of
referral:
C
ommittee: Lakeland Health Care Board Date: October 19, 2026
of Trustees
V ote:
C
ommittee: Public Works Committee Date: October 19, 2026
Vote:
C
ommittee: Finance Committee Date: October 22, 2026
V ote:
C
ounty Board Meeting Date: November 10, 2026
Policy and fiscal note has been reviewed and approved as an accurate statement of the probable policy and fiscal
impacts associated with passage of the attached resolution.
____
_______________________________ ____________________________________
Michael P. Cotter Date Jessica Conley Date
Corporation Counsel Finance Director
Mark W. Luberda Date
County Administrator