CITY OF SOUTH MILWAUKEE
Plan Commission
Meeting Agenda
City Administration Building
2424 15th Avenue
South Milwaukee, WI 53172
Monday November 2, 2026 6:30 PM Committee Room
1. Call to Order.
2. Roll Call.
3. Approval of the September 22, 2026 meeting minutes.
4. Consideration of Bucyrus Façade Improvement Grant application for 1009 Milwaukee Ave for future
restaurant.
5. Schedule next meeting (November 24, 2026).
6. Adjournment.
PUBLIC NOTICE
NOTE: Upon reasonable notice, a good faith effort will be made to accommodate the needs of disabled individuals through appropriate aids and services. Requests should
be made as far in advance as possible, preferably a minimum of 48 hours. For additional information contact the City Clerk’s office at 414-762-2222.
CITY OF SOUTH MILWAUKEE
Plan Commission
Meeting Minutes
City Administration Building
2424 15th Avenue
South Milwaukee, WI 53172
Tuesday, September 22, 2026 6:30 PM Common Council Chambers
1. CALL TO ORDER
Mayor Briesemeister called the meeting to order at 6:30 PM.
2. ROLL CALL
Commissioners present: Bartoshevich, Brever, Haslam, Worm, Briesemeister, Olechowski
Commissioner excused: Gates
3. APPROVAL OF JULY 28, 2026 AND SEPTEMBER 15, 2026 MEETING MINUTES
MOVER: Haslam
SECONDER: Bartoshevich
VOTE RESULT: Motion Carried 6-0
4. PRESENTATION / DISCUSSION OF DEVELOPMENT PROPOSAL FROM SAWALL
DEVELOPMENT, REGARDING CITY-OWNED PROPERTY AT 2318 10TH AVE. SOUTH
MILWAUKEE, WI 53172.
Kevin Sawall from Sawall Development presented a concept site plan for the city-owned vacant property 2318
10th for a high-density multifamily development with below ground and rear onsite parking. All units are market
rate.
5. DISCUSSION/POSSIBLE MOTION TO CONVENE IN CLOSED SESSION PURSUANT TO WIS.
STAT. 19.85 (1)(E) TO DELIBERATE OR NEGOTIATE THE PURCHASE OF PUBLIC PROPERTIES,
INVESTING OF PUBLIC FUNDS, OR CONDUCTING OTHER BUSINESS WHEN COMPETITIVE OR
BARGAINING REASONS REQUIRE A CLOSED SESSION. SPECIFICALLY, TO DISCUSS THE
POTENTIAL ACQUISITION OF PROPERTIES WITHIN THE CITY FOR REDEVELOPMENT
PURPOSES.
RESULT: Motion to convene into closed session.
MOVER: Brever
SECONDER: Haslam
VOTE RESULT: Upon roll call motion carried 6-0
RESULT: Motion to reconvene into open session to consider the balance of the agenda.
MOVER: Haslam
SECONDER: Brever
VOTE RESULT: Upon roll call motion carried 6-0
RESULT: No action taken on item 5.
Plan Commission Meeting Minutes September 22, 2026
6. SCHEDULE NEXT MEETING (OCTOBER 27, 2026).
7. ADJOURNMENT
RESULT: Motion to adjourn at 7:40 PM.
MOVER: Brever
SECONDER: Bartoshevich
VOTE RESULT: Motion carried 6-0
Plan Commission Memo
Meeting November 2, 2026
Completed by: Economic Development Manager Ericka Lang
Date: October 19, 2026
Property Owner/Applicant Gary Karabelas
Future Business Gnome Restaurant, planned opening mid-2027
*winner of RenewTowns Business Pitch Contest
Project Description
Façade Total Project Cost $150,000 to $176,564
Requests $2,000 Design grant - 90% match, max $2,000
$80,000 Façade grant - 50% match, max $15,000
Staff Review
Quote 1 Fiedler Construction, Inc
Demo walls, windows doors, canopy, existing stucco
Fascia panels, doors, hardware, wood soffits
Install primed fiber cement siding and paneling details
New metal upper awnings
New aluminum storefront system and fenestration
If the grant exceeds the program $15,000 maximum amount, approval is also required by the
Common Council
Overall, the project meets the city's zoning architectural standards and commercial guidelines.
Demolition costs are not eligible expenses and project costs may vary depending on what is found
under the upper stucco. Permanent signage is an eligible grant expense and does not require
multiple estimates.
The owner may seek cost reductions, suggesting keeping the shed awning and replace the shingles
with a metal material to match upper metal awnings. However, this option does not restore a
traditional sign band typical of main street downtown buildings. The proposed fiber cement boards for
the upper facade will have seams and requires a seamless look - further information is needed.
RE: South Milwaukee Bucyrus Façade Grant Application Review, 1009 Milwaukee
Avenue
Suggested Motion: I motion to approve a Bucyrus Façade Improvement Grant request for 1009
Milwaukee Avenue , for up to $______, not to exceed 50% of eligible expenses, and $2,000 for
professional design costs, and to enter into an agreement with property owner Gary Karabelas.
Façade renovation of two-story mixed-use storefront. Remove lower brick façade, shed
awning and upper stucco and replace with fiber cement boards; add storefront window
system; raise storefront height and add a wood signage band, goose neck lighting, and
signs.
The building façade has been altered over five decades ago from it's original design, decreasing
storefront windows, decreasing two upper windows, adding a shingled shed awning, and stucco over
upper brick. The project keeps the upper windows the same size to reduce costs, adding metal
awnings and restores a large storefront window system.
Paint siding, doors, soffits, cornice
Electrical for lighting included
$140,000 - $160,000
SIGNAGE Sign Effectz
$8,550 non-illuminated fla g sign 57"x48"
$1,450 Pin-mounted nonlit aluminum FCO letters "GNOME" 12"H
$750 site survey & permits ($375 each)
$10,750
Total $150,750 - 170,750
Quote 2 Midwest MCG Construction Group
$9,200 demolition
$1,300 concrete work
$20,360 Masonry
$9,650 Metal sheet awning
$11,590 new window/doors framing
$32,360 insulation and fiber cement board installation/siding
$36,950 doors, windows, transom, sliding window
$8,060 Paint façade/trim
SIGNAGE $21,190 57"h x 48"wide routed blade sign w/ push thru acrylic
$8,400
Electrical exterior lighting (4) lights
$159,060
$7,954 5% contingency
$9,550
Project management
$176,564
Attached Materials:
Elevations Historic and current photos
Two quotes Sign renderings
Project Description
Concept Design Wall and Hanging Blade Sign at 1009 Milwaukee Ave 10/19/2026
South Milwaukee Façade Grant Photos 1009 Milwaukee Avenue | GNOME Restaurant
2 | P a g e
South Milwaukee Façade Grant Photos 1009 Milwaukee Avenue | GNOME Restaurant
3 | P a g e
A r c h i t e c t u r a l D e s i g n • I n t e r i o r D e s i g n • S i t e D e s i g n
3 1 1 2 W e s t H i g h l a n d B l v d • M i l w a u k e e , W i s c o n s i n 5 3 2 0 8 • p h . 4 1 4- 2 6 5- 9 2 6 5 • w w w . q u o r u m a r c h i t e c t s . c o m
2026-10-13
Attention: City of South Milwaukee Plan Commission
RE: Project Name: Gnome Restaurant – Façade Renovation
Quorum Architect’s Project Number: 26005-02
Project Scope at 1009 Milwaukee Ave, South Milwaukee, 53172
The scope for the façade renovation at 1009 Milwaukee Ave includes removal of the brick infill
and first floor framing at the commercial tenant street façade down to the concrete foundation
and building back a concrete curb to rest the new prefinished aluminum storefront on top of.
The demolition includes removing the residential door and infill framing which is in disrepair and
replacing with a hollow metal door and frame with transom light above to provide the residents
with some natural light in the internal stairwell.
The new storefront height will be raised to provide additional natural light into the commercial
tenant space and the heights of the wood signage band is pulling on the neighbors existing
elements for alignment. The existing masonry piers and steel columns of the opening provide
and excellent opportunity to showcase a wide prefinished fiber cement detailed column, framing
each side of the storefront glazing. The existing concrete ramp will remain and a new accessible
entry door will be provided that leads into a rebuilt interior vestibule.
The existing shed awning will be removed and replaced with the horizontal wood plank signage
band where pin mounted metal sign letters that read “GNOME”, the restaurants name, will be
placed. New gooseneck lighting above will highlight this lettering and beacons back to the
historic photos that were found at the Historical Society. A new wood blade sign will be mounted
directly above the door that is hung from decorative metal.
*Please note that the signage costs we received are not fully representative of the design intent
but are close and being refined to match the provided image.
The existing stucco system at the second floor residential level will be examined by a contractor
for removal and replacement, there are costs associated with repairing the substrate as needed
based upon findings. Based on the historic photos, it is assumed that not the entire substrate is
brick and that some studwall infill was done where the old bay windows were removed. Timing
of the bay window replacement is unknown and due to project costs, it is not feasible to try to
recreate.
The sliding residential egress windows will be replaced in kind with a prefinished aluminum
window and be provided with a prefinished metal awning above to give some dimension to the
façade. Finally, the existing metal cornice at the roof level will be repaired and painted.
Emily Neal
Quorum Architects, Inc.
PRELIMINARY BUDGETING SCOPE OF WORK
10/9/26
JOB NAME Gnome Façade Renovation
LOCATION 1009 Milwaukee Ave., South Milwaukee, WI
GENERAL
• Work involves demolition and construction related to the front façade only.
• Any hazardous materials will be removed by Owner prior to the start of
construction and is not included in this budget.
• Necessary GC general conditions and supervision are included.
• Temporary interior wall to close off the interior portion of the building during
construction and removal after new store front is installed is included.
• Temporary restroom and dumpsters as needed are included.
• Rental of a lift for work on the second-floor renovation is included.
• City of South Milwaukee plan review and permit fees are included.
• Architectural and engineering fees are excluded.
• Winter construction costs have not been included at this time
DEMOLITION
• Remove all walls, windows, doors, canopy, signage and other non-structural items
to make ready for new façade.
• Remove existing stucco veneer from brick at second floor.
MASONRY
• Match existing brick as close as possible and infill at new entrance.
CARPENTRY
• Build new non-bearing stud walls to form new fenestration for new storefront
system and entry doors.
• Install new signage fascia panels, doors and hardware, wood soffits.
STUCCO
• An allowance of $6,000.00 to apply a new stucco finish to the existing brick after
new window installation is included.
SIDING
• Furnish and install new pre-primed fiber cement siding and paneling details.
ROOFING
• Furnish and install new prefinished metal awnings.
HM FRAME, DOOR & HARDWARE
• Furnish new decorative HM frames and doors and associated hardware for the
two new entrances.
STOREFRONT
• New prefinished aluminum storefront system to be installed in newly framed
fenestration.
PAINTING
• Paint new siding, doors, frames and soffits.
• Bondo holes and repaint cornice.
EXTERIOR SIGNAGE
• Option #1, pin mounted letters, site survey and permit procurement costs from
SignEffectz are included in the budget.
PLUMBING
• None.
HVAC
• None.
ELECTRICAL
• Necessary demolition and removal of power and lighting prior to old storefront
removal is included.
• Rough in new four new decorative fixtures.
• Fixture allowance of $1,200.00 is included.
Gnome Restaurant - Façade Contractor: Midwest Construction Group, LLC
1009 Wisconsin Ave
South Milwaukee, WI 53172 LC: DC-032200318
10.9.2026 Designer: Quorom Architects
1 Sq. Ft.
Qty Inclusions Comments (Note any LF, SF or quantity to clarify)
Division #1 - General Requirements $0.00
Architectural Fees Provided directly by Quorum Architects
MEP Fees Included in numbers for each trade.
Permits and Fees Will be a pass-through cost, plus 5%
Division #2 - Existing Condition/Site Work $9,220.00
Demolition 1 Incl
*Demolition of existing wood structure in-fill of front wall windows.
*Remove existing canopy
*Remove existing windows
*Remove existing vinyl soffit underside of entry
*Salvage and return existing signage to owner.
*Other demo listed on the drawings dated 9/9/2026
Misc (Detailed Comment Required) 1 Incl Dumpster, Portable Toilet, Lift Rental
Division # 3 - Concrete $1,300.00
Misc Site Concrete (Detailed Comment Required) 1 Incl *Provide and install cast in place concrete curb, estimated 6-8" high, 4-6" wide.
Division # 4 - Masonry $20,360.00
Exterior Brick Cladding 1 Incl
*Removal of existing brick infill where new window will be.
*Remove existing brick window sill.
*Removal of stucco system finish, confirm substrate.
*Infill of new brick to match existing on façade and rear of building.
Sand Blasting 1 Incl
*Sandblast brick after stucco is removed to remove excess debris.
Division #5 - Metals $9,650.00
Decorative Metal 1 Incl
*Provide and install standing seam metal sheet awning mounted to face to
building. Allowed for each awning to be 65" wide x 2' deep, with a decorative
frame to support it.
*Restore and/or refinish existing metal cornice.
Division # 6 - Wood and Plastic $11,590.00
Wood Framing 1 Incl
*Provide and install framing for new windows and doors as required depending
on condition and useability of remaining framing following demo.
*Provide and install blocking as required for signs, awnings, planters on
exterior of building. Calculation of structural requirements will be by structural
engineer under architectural contract.
Finished Carpentry 2 Incl
*Provide and install (2) wall mounted planters
Division # 7 - Thermal & Moisture Protection $32,360.00
Exterior Insulation and Finish Systems 1 Incl *Provide and install painted fiber cement paneling and wood trim
Siding 1 Incl
*Provide and install fiber cement board panel system on air barrier with 3/4"
exterior sheathing on 2x6 wood stud with R-19 fiberglass batt insulation, vapor
barrier and 5/8" gypsum board.
*Provide and install wood decorative fascia board trim.
*Provide and install fiber cement paneling with decorative wood trim.
*Provide and install wood soffit
Bid Revision #:
ROUGH ORDER OF MAGNITUDE
Project #:
Address / Suite:
City / State:
Date:
Item
Midwest Construction Group Page 1 of 3 10/9/2026
Division # 8 - Openings $36,950.00
Doors and Frames 1 Incl
*Provide and Install Hollow Metal door and transom window, including door
hardware.
Windows 2 Incl
*Provide and install PreFinished Aluminum Window approximately 60"W x
48"H. Architectural-Grade 600 Series Brushed Aluminum left-sliding window.
Glazing 1 Incl
*Provide and Install Aluminum Storefront Window System approximately 64"W
x 108"H
*Provide and Install Aluminum Storefront Window System approximately 89"W
x 108"H
*Provide and Install (2) Aluminum Storefront Window Systems approximately
48"W x 108"H
*Provide and Install (1) Aluminum Storefront Window Systems with a 36" door
and 12" sidelite, including door hardware.
Division #9 - Finishes $8,060.00
Painting 1 Incl
*Provide and Install Paint on wood soffit - prime + 2 coats.
*Provide and Install Paint on wood decorative fascia board trim - prime + 2
coats where pin mounted signage will be.
*Provide and Install Paint on fiber cement paneling with decorative wood trim -
prime + 2 coats below storefront system
Division #10 - Specialties $21,190.00
Signage 1 Incl
*Provide and install (1) double faced illuminated illuminated flag sign with
Routed and Backed Graphics. Overall size approximately 57" tall and 48" wide.
Custom shaped sign with custom steel mouthing bracket to closely match and
provided concept. Routed aluminum face with push thru clear acrylic and first
surface translucent 3M vinyl graphics.
*Provide and install new pin-mounted metal signage (1) set 1/4" thick
aluminum FCO letters 12" tall "GNOME"
*Site Survey, Permit Procurement includes standard permit application
paperwork and submittal. If the municipality requires a board meeting for
review, attendance is billed separately. City permit fees billed at cost +5%on
final invoice.
Division #11 - Equipment $0.00
Division #12 - Furnishings $0.00
Division #13 -Special Construction $0.00
Division #14 -Conveying Equipment $0.00
Division #21 - Fire Suppression $0.00
Division #22 - Plumbing $0.00
Division #23 - HVAC $0.00
Division #26 - Electrical $8,400.00
Exterior Lighting 1 Incl
*Provide and install (4) decorative exterior lights, using power from previous
lighting in canopy, adding location, and making any updates to meet current
code.
*Provide and install time clock to control exterior lighting, and any required
conduit/wire to route it.
*Confirm electrical to existing blade sign meets current code and provide any
additional/updated electrical to power new blade sign.
*Provide and install documentation for permiting.
*South Milwaukee electrical permit
Division #27 - Communications $0.00
Construction Subtotal $159,080.00
Contingency Included 5% $7,954.00
General Conditions $9,550.00
General Conditions 1 Incl Project Management, Site Supervision, Site Protection, Cleaning
Per Diem / Travel N/A
Construction Total $176,584.00
Tax (if applicable) Incl -$
Grand Total $176,584.00
Midwest Construction Group Page 2 of 3 10/9/2026
Approval Qty Price Comments (Note any LF, SF or quantity to clarify)
2 $ 20,630.00
Allowed for Bay Window Assembly to be 5'W x 8'3"H x 18"D. Structural
reinforcement for the window opening not included.
Alternates Total $20,630.00
*The drawings and/or sketches provided, along with any associated budget figures, are preliminary and for informational purposes only. They do not
represent final design documents or guaranteed project costs.
*The Architect has provided a conceptual floor plan for the Client’s review and approval. This process may require a Disproportionality Survey and/or
compliance with other City regulations. Such requirements may result in design modifications and could impact the project scope, schedule, and cost.
*Upon completion of the Construction Documents (CDs), MCG will issue the finalized plans to subcontractors for updated pricing. The final contract value
will be based on bids and proposals received at that time.
*The Architect will submit the Construction Documents to E-Plan and/or the applicable City permitting authority for review and approval. MCG is not
responsible for any comments, corrections, requirements, delays, or changes resulting from the plan review or permitting process.
Building Occupancy Disclaimer
*Final inspection and issuance of a building occupancy permit by the applicable authority may identify additional deficiencies, code requirements, or
corrective work not included in the original scope of work. These requirements are determined solely by the governing jurisdiction and are beyond the control
of the Contractor.
*Any such required corrections or modifications shall be treated as additional work and may result in changes to the project scope, schedule, and cost. The
Contractor will notify the Client of any such requirements and provide pricing and timelines for approval prior to proceeding.
g
*If project scopes are developed based on verbal discussions without architectural drawings, MCG will prepare written scopes of work reflecting those
discussions. These documents must be reviewed and signed by the Client before work proceeds. Once approved, MCG will obtain pricing based on the
agreed scope.
*If any portion of the work requires permitting, the applicable subcontractor(s) will obtain permits for their respective scopes. If MCG becomes aware of City
comments or requirements that affect the project scope, cost, or schedule, MCG will promptly notify the Client and provide an updated assessment for
ALTERNATES
Add Alternate Description
BayWindow Framing and Painted Aluminum Window
with Wood Paneling and Metal Roof.
Midwest Construction Group Page 3 of 3 10/9/2026
Source: City of South Milwaukee website. First collected Nov 2, 2026.