Board of Public Works Meeting — Agenda Packet
City of Menasha · Winnebago County · Board of Public Works · meeting of Nov 2, 2026 · Agenda packets
Open the original document More from City of Menasha
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
A Quorum of the Common Council, Administration Committee, Personnel Committee, Plan
Commission, Redevelopment Authority, and other City bodies may attend this meeting, though
no official action of these bodies will be taken.
BOARD OF PUBLIC WORKS MEETING AGENDA
Monday, November 2, 2026 at 6:30 PM
First Floor Conference Rooms
100 Main Street, Menasha, WI
A. Call to Order
B. Roll Call
C. Public Comments on Any Matter Listed on the Agenda
(5 minute time limit for each person)
D. Minutes to Approve
1. Board of Public Works, 10/19/26
E. Discussion / Action Items
1. Payment — Northeast Asphalt, Inc.; Contract No. 2026-03; Clovis Park Tennis
Courts Reconstruction; $203,143.68 (Payment No. 2)
2. R-49-26 - A Resolution Delaying Winter Parking Restrictions through
December 31, 2026, Pursuant to Sec. 10-1-21 of the Menasha Municipal Code
due to the Local State of Disaster (Emergency) (Introduced by Mayor
Hammond)
3. Public Works General Activity
F. Adjournment
"Menasha is committed to its diverse population. Our Non-English speaking population and
those with disabilities are invited to contact the Menasha City Clerk at 967-3603 24-hours in
advance of the meeting for the City to arrange special accommodations."
Page 1 of 9
BOARD OF PUBLIC WORKS MINUTES
Monday, October 19, 2026 at 6:45 PM
First Floor Conference Rooms
100 Main Street, Menasha, WI
A. CALL TO ORDER
Meeting called to order by Chair Marshall at 7:21pm.
B. ROLL CALL
Present: Alds. Rand, Eisenach, Hale, Perkins, Lewis, Marshall, Grade, School
Also Present: FD Sassman, DPW Merten, CDD Dane, PRD Sackett, PC Albrecht,
Interim CA Walsh, Mayor Hammond, Clerk Janet
C. PUBLIC COMMENTS ON ANY MATTER LISTED ON THE AGENDA
D. MINUTES TO APPROVE
1. Board of Public Works, 9/21/26
Motion by District 8 Alderperson School seconded by District 7 Alderperson
Grade to approve. Motion carried on voice vote.
2. Special Board of Public Works, 10/5/26
Motion by District 8 Alderperson School seconded by District 7 Alderperson
Grade to approve. Motion carried on voice vote.
E. DISCUSSION / ACTION ITEMS
1. Change Order — Contract No. 2026-04; Midway Place Resurfacing; Northeast
Asphalt Inc.; Add $4,070.15 (Change Order No. 1 & Final)
Motion by District 8 Alderperson School, seconded by District 7 Alderperson
Grade to approve.
Motion carried 8-0 on roll call.
2. Payment — Northeast Asphalt, Inc.; Contract No. 2026-04; Midway Place
Resurfacing; $4,070.15 (Payment No. 2 & Final)
Motion by District 8 Alderperson School, seconded by District 7 Alderperson
Grade to approve.
Motion carried 8-0 on roll call.
3. Payment — Donald Hietpas & Sons, Inc.; Contract No. M0002-09-00105; 2026
Utility Construction; $72,052.50 (Payment No. 5)
Motion by District 8 Alderperson School, seconded by District 7 Alderperson
Grade to approve.
Page 2 of 9
Motion carried 8-0 on roll call.
4. Payment — Northeast Asphalt, Inc.; Contract No. 2026-03; Clovis Park Tennis
Courts Reconstruction; $120,900.32 (Payment No. 1)
Motion by District 8 Alderperson School, seconded by District 7 Alderperson
Grade to approve.
Motion carried 8-0 on roll call.
Staff advised that the project is moving along nicely due to the favorable fall
weather. Staff also advised that tentative surface paving will happen in the
next two weeks. Staff additionally advised that the project will not be
completed until Spring 2027 and that the high school tennis season in Spring
2027 will not be able to use the tennis courts.
F. ADJOURNMENT
Motion by District 4 Alderperson Perkins seconded by District 7 Alderperson Grade
to adjourn the Board of Public Works meeting at 7:28pm. Motion carried on voice
vote.
Minutes submitted by City Clerk Evan Janet.
Page 3 of 9
Date:
Less Retainage: 5.0%
Payment 1
Payment 2
Payment 3
Payment 4
Payment 5
Payment 6
Payment 7
Date: BY:
Laura Jungwirth, Public Works Director:
Common Council Approval Date:
Recommended for Payment
Finance Department
Account Number Amount
Current Payment 203,143.68$
I certify that all bills for labor, equipment, materials and services are paid for which previous certificates for payment were issued.
(Lien Waivers from all subcontractors and suppliers shall accompany each Request for Payment.)
120,900.32$
Change Order 3: Total Earned to Date (Summary Attached): 341,098.95$
Change Order 4: 17,054.95$
Amount Due: 324,044.00$
Original Contract Amount: 745,217.74$
Change Order 1: Total Change Orders: -$
Change Order 2: Total Contract Amount (Including Change Orders): 745,217.74$
Address: W6380 Design Drive, Greenville, WI 54942
Contract Unit No.:2026-03
Project Description:Clovis Tennis Courts Reconstruction
Certificate of Payment
10/29/2026 Payment Request:2 (Two)
Contractor: Northeast Asphalt, Inc
Page 4 of 9
Item Quantity Description Unit Price Total Quantity Item Total
1. 1,275 Unclassified Excavation (C.Y.) 40.50$ 51,637.50$ 1275 51,637.50 $
2. 5,395 Fine Grading and Compaction (S.Y.) $ 3.80 20,501.00$ 5395 20,501.00$
3. 2,100 Placement of City Supplied Gravel Base (C.Y.) 12.50$ 26,250.00$ 2100 26,250.00$
4. 620 2" Asphalt Pavement 4 lt 58-28S Binder (Ton) 155.00$ 96,100.00$ 505.88 78,411.40 $
5. 550 1.75" Asphalt Pavement 5 LT 58-28S Surface (Ton) 165.00$ 90,750.00$ 587.57 96,949.05$
6. 1,800 Lawn Restoration (S.Y.) 13.18$ 23,724.00$ 0 -$
7. 1,032 10' High Black Chain Link Fence (L.F.) 57.00$ 58,824.00$ 0 -$
8. 3 4' Wide Black Chain Link Single Swing Gate (Each) 1,300.00$ 3,900.00$ 0 -$
9. 1 Site Electric (L.S.) 140,190.00$ 140,190.00$ 0 - $
10. 1,252 Tennis Court Control Joints with Joint Armor (L.F.) 19.79$ 24,777.08$ 0 - $
11. 1 Tennis Court Leveling (L.S.) 3,020.00$ 3,020.00$ 0 - $
12. 5,280 Tennis Court Surface (S.Y.) 11.79$ 62,251.20$ 0 - $
13. 4,728 Tennis Court Striping (L.F.) 1.22$ 5,768.16$ 0 - $
14. 8 Tennis Court Nets Complete (Each) 2,400.00$ 19,200.00$ 4 9,600.00 $
15. 1 Erosion Control (L.S.) 3,500.00$ 3,500.00$ 1 3,500.00 $
16. 1 54,250.00 $ 54,250.00$ 1 54,250.00 $
684,642.94$ 341,098.95 $
Alternate Bid B
Item Quantity Description Unit Price Total
1B. 5,280 Plexibond Fiberglass Membrane $ 9.11 48,100.80 0 -$
2B. 5,940 Type SR Geotextile Fabric 2.10$ 12,474.00 0 -$
60,574.80 -$
745,217.74$ 341,098.95 $ Total Base Bid + Alternate Bid B
CITY OF MENASHA
Contract Unit No. 2026-03
Clovis Park Tennis Courts Reconstruction
Base Bid Payment 2 (Two)
Construction Mobile/Demobile; Project Coordination; All Incidental
Utility and Misc. Roadway Work; and All Other Project Work Area
Restoration and Clean-Up to an Equal and/or Better Preconstruction
Condition as Required and Related to the Overall Project. (L.S.)
Total Base Bid (Items 1 - 16)
Total Alternate Bid B
Page 1 of 1
Page 5 of 9
RESOLUTION R-49-26
A RESOLUTION DELAYING WINTER PARKING RESTRICTIONS THROUGH DECEMBER 31,
2026 PURSUANT TO SEC. 10-1-21 OF THE MENASHA MUNICIPAL CODE DUE TO THE
LOCAL STATE OF DISASTER (EMERGENCY)
INTRODUCED BY: Mayor Hammond
WHEREAS, section 10-1-29 of the Menasha Municipal Code prohibits parking from
2:00am until 6:00am between November 1 and March 31, and
WHEREAS, section 10-1-29(a) of the Menasha Municipal Code allows overnight
parking between 2:00am and 6:00am between April 1 and October 31, and
WHEREAS, due to damage from the July tornado, residents may not be able to park
their vehicles in their driveway, and
WHEREAS, it is appropriate to allow vehicles to park on City streets consistent with
the April through October street parking regulations, and
WHEREAS, section 10-1-21 provides that the Board of Public Works may temporarily
impose or remove parking restrictions for a period of at least thirty (30) days but not to
exceed one (1) year. Any temporary signs posted by the Board of Public Works shall
supersede all existing posted rules for the days and times specified.
NOW, THEREFORE, BE IT RESOLVED, that the Board of Public Works extends the
overnight parking regulations in place from April 1 through October 31, shall continue
through December 31, 2026.
BE IT FURTHER RESOLVED, that the authority declaring snow emergencies shall
remain in full force and effect.
BE IT FURTHER RESOLVED, that the authority of the Mayor or Common Council
President to declare an emergency shall be extended to a general storm as provided in sec.
10-1-31(b)(1).
Page 6 of 9
Passed and approved this _____ day of _______, 2026.
Recommended by:
Motion/Second:
Austin R. Hammond, Mayor
Pass/Fail:
ATTEST:
Requires: ____Majority Vote
____2/3 Vote
Evan Janet, City Clerk
Page 7 of 9
100 Main Street, Suite 200 | Menasha, Wisconsin 54952-3151
Phone (920) 967-3610 | Fax (920) 967-5272 | menashawi.gov
City of Menasha | Department of Public Works
MEMORANDUM
DATE October 28, 2026
TO Board of Public Works
FROM James Merten, Director of Public Works
RE Public Works General Activity
1. WisDOT Project 4646-02-71 – CTH P (Valley Road) Reconstruction: Work is nearing
completion with restoration, pavement marking, and job site cleanup remaining.
Anticipated completion date is November 13th.
2. Contract M00002-09-00105 – Utility Reconstruction (Eighth Street/Third
Street/Clovis Park/Pleasants Park): Work on Eighth Street, Pleasants Park, Third
Street, and Clovis Park has been completed. Remaining work includes sewer
televising and Menasha Utilities items.
3. Contract 2026-01 – Street Construction (Eighth Street/Third Street): Work on
Eighth Street and Third Street has been completed. Remaining work pertains to
pending Menasha Utilities items.
4. Contract 2026-02 – Pavement Markings (Racine Street/Third Street): Due to the
combination of delay from the tornado, unreliable surface temperatures, and
contractor availability, this project has been pushed to spring of 2027.
5. Contract 2026-04 – Midway Place Resurfacing: Work has been completed.
6. Contract 2026-05 – Crack Sealing: Work will take place early/mid November.
7. Contract 2026-06 – Chip Sealing: Work has been completed.
8. Racine/First Traffic Signals: Work has been completed.
9. Racine/Broad Pedestrian Beacons: Work has been completed.
10. Nicolet Boulevard Intersection Control Evaluations: Phase 1 of the study has been
completed and has been accepted by Wisconsin Department of Transportation. Work
on Phase 2 is underway.
11. R-11-26 Rainfall Event Response: After thorough review, it was determined that an
ordinance is not necessary to carry out the objectives from the directive (to conduct
private sanitary lateral work as part of upcoming street/utility projects). That said, an
Page 8 of 9
2 of 2
ordinance will be prepared to modernize and strengthen the current code pertaining
to sanitary sewers later, after the recodification of the municipal code later this year.
12. R-28-26 Waterway Debris Cleanup: Per the authority granted by R-28-26, the City
has entered into a contract with Bill Neuens Enterprises of Iron Mountain, Michigan to
conduct debris removal operations from waterways affected by the tornado. This
work is anticipated to begin mid-November.
13. Deputy Director of Engineering Resignation: Deputy Director Corey Gordon has
submitted his resignation, with his last day of service set for November 13. A search
to fill the position is underway. We thank Corey for his contributions and wish him
well in his future endeavors.
Page 9 of 9