Airport Commission — Minutes
City of Black River Falls · Jackson County · Airport Commission · meeting of Oct 15, 2026 · Minutes
Open the original document More from City of Black River Falls
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
The Airport Commission met at the Black River Area Airport on October 15, 2026
Commissioners Garth Rolbiecki, Dale Hoff, Kylee Wussow and Airport Mgr. Frank Voge,
Commissioner Ed Chamberlain and Desiree Gearing Lancaster were absent.
1. The meeting was called to order at 5:35 P.M. by Commissioner Wussow.
2. It was moved by Commissioner Rolbiecki ; seconded by Hoff to approve the July 2026
minutes. Motion carried.
3. It was moved by Commissioner Rolbiecki; seconded by Hoff to approve the financial
vouchers presented by Voge. Motion carried.
4. Master Plan Update - SEH Engineering Representative Melissa Underwood, presentation
of Airport Master Plan, schedule with updates (Inventory & Critical Aircraft
Determination Chapters). Presentation attached.
5. Airport Manager’s Report:
a. Hangers: hanger sales, future sales and possibility of new hangers being built.
b. Land Use Agreement provided to committee for review as a future possibility.
Next Meeting: January 21, 2027 at 5:30 PM.
6. Moved by Commissioner Rolbiecki to adjourn; seconded by Hoff. Motion
carried at 6:19 PM.
Respectfully submitted by,
Kylee Wussow
Airport Commission
MINUTES
Airport Master Plan Inventory & Critical Aircraft Meeting #2
October 15, 2026
5:30 p.m.
Airport Terminal
Meeting Chair: Melissa Underwood
Copies to: Attendees
I. Welcome & Introductions
A. The Master Plan process was shared with the grou p, the inventory chapter is out for stakeholder
review and the focus of the discussion this meeting was on activity forecasts and facility
recommendations.
B. The project schedule was reviewed. The Exhibit A property map work is in progress with the
boundary surveys completed last week. The mapping w ill be reviewed and shared at the next
meeting.
II. Inventory Chapter Review
A. AGIS update
1. Imagery has been obtained and the project is set up in the FAA’s review system. Field survey
services are 25% complete.
2. Once received from Martinez Geospatial, the data will be used for the basemap to develop
alternatives and complete the obstruction analysis.
B. RSA determination
1. The field survey was completed this summer to de termine if the RSA meets design standards.
2. Two areas were identified that need to be graded to meet design slope standards.
a. This work can be completed with the next pavemen t maintenance project.
3. All lights and navigational aids were identified as frangible.
C. Exhibit A/property research
1. Title research work was completed by ProSource. There were 46 title packets completed.
2. Boundary survey was completed by SEH last week.
3. The Exhibit A documentation will be reviewed at the next meeting. This data will provide the
City and Airport Commission with the necessary data to confirm airport boundary limits and
determine if future property is needed for any proposed development.
4. The previous land inventory map was completed in 2004.
D. SRE/maintenance equipment
1. The year of the SRE and maintenance equipment wa s the final item missing from the
inventory chapter.
2. The BOA was able to provide the missing informat ion at the end of the meeting. The data will
be included in the inventory chapter and submitted to the BOA for review.
E. Chapter review
1. The draft inventory chapter was presented to the committee members for review. Any
comments received will be addressed. The chapter wi ll be submitted to the BOA for review
and acceptance into the final Master Plan report.
Airport Master Plan Inventory & Critical Aircraft Meeting #2
October 15, 2026
Page 2
III. Critical Aircraft Determination
A. Runway Design Code (RDC)
1. The critical aircraft data was discussed with th e committee members. There are less than 500
annual operations reported for 2025 by existing data sources such as TFMSC and
FlightAware.
2. The group discussed the option to purchase a cou nter and camera system to document
operations at the airport.
3. Documentation of over 500 operations in a year i s required prior to the City receiving federal
funding for a future capital improvement project.
4. Due to the lack of 500 annual operations, the existing and future critical aircraft for BCK
has been identified as A-I, small aircraft . This category is represented by single-engine
aircraft.
a. The ultimate critical aircraft has been identified as a B-II, small aircraft . There is a
King Air 200 based on the airfield which is within this RDC and planning to continue to
accommodate this aircraft type will be important for the based airport community.
B. Existing operations
1. SEH will send the Airport Commission an email wi th the known counter services
available.
a. The Airport Commission will review these options and discuss them at the next
meeting.
2. The committee members discussed the opportunity to use fuel sale transactions to
document use at the airport. The Airport Manager wi ll review the fuel transaction data
over the year and send it to the group for review.
IV. Facility Recommendations
A. SASP Recommendations
1. The SASP classifies BCK as a Medium General Avia tion airport.
2. The committee members reviewed the facility reco mmendations from the SASP for a Medium
General Aviation airport compared to the inventory at BCK. The discrepancies were noted and
shared with the committee members.
B. Pavement maintenance
1. The existing pavement at the airport is in good condition.
2. The previous runway crack seal project was in 20 23.
3. The City could consider one more crack seal proj ect before a larger runway rehabilitation or
reconstruction project is pursued in eight to ten years.
a. Until that time, the Airport Commission will wor k on documenting existing operations to
reach the minimum threshold needed for federal funding.
C. Runway length & width
1. Based on the critical aircraft identification, t he runway length was developed from the federal
advisory circular data.
a. The FAA advisory circular recommends a runway le ngth of 3,300 feet.
b. The upcoming FAA advisory circular update uses t he SARLAT tool to identify the
recommended runway length for aircraft weighing 12,500 pounds or less. This tool
identified a recommended runway length of 4,205 fee t.
c. The goal is to document operations to justify ma intaining the existing 4,601-foot of
runway.
2. Similarly, the runway width justified for the ex isting critical aircraft is 60 feet wide.
a. The existing runway is 75 feet wide. The goal is to document operations to justify
maintaining the existing 75-foot-wide runway.
D. Airport Operations in Unpaved RSA
Airport Master Plan Inventory & Critical Aircraft Meeting #2
October 15, 2026
Page 3
1. Based on requests from the Kick-Off meeting. Air craft operations within the unpaved RSA
were discussed.
2. Federal guidance provides support for this type of operation.
3. The identified area will be documented on the Ai rport Layout Plan.
E. Direct access
1. There is direct access from the apron to the Run way 26 end.
2. The alternatives analysis will determine alterna tives to mitigate this design standard.
F. Wind coverage
1. The existing AWOS is located in an area that mee ts design standards.
2. Trees were identified within the 500-foot critic al area of the AWOS.
3. Alternatives will be reviewed to clear the tree obstructions or relocate the AWOS to increase
reliability in the reported weather data.
G. Apron & building area evaluation
1. Alternatives will be developed for the next meet ing to determine the ultimate layout of the
building area and account for hangar expansion and potential business growth.
V. Next Steps
A. Finalize facility recommendations chapter
B. Complete obstacle analysis
C. Develop preliminary alternatives
D. Next meeting: January 21, 5:30 p.m.
SEH believes that this document accurately reflects the business transacted during the meeting. If any attendee
believes that there are any inconsistencies, omissions or errors in the minutes, they should notify the writer at
once. Unless objections are raised within seven (7) days, we will consider this account accurate and acceptable
to all.
If there are errors contained in this document, or if relevant information has been omitted, please
contact Melissa Underwood at 763.442.2849.
mru
x:\uz\w\wiboa\192258\1-genl\16-meet\meeting #2_october 15 2026\bck_meeting #2_minutes_10162026.docx