Board of Public Works Regular Meeting Agenda
Monday, November 9, 2026 at 7:30 PM
Council Chambers and Virtual
In-Person Attendance:
City Hall Council Chambers
2nd Floor City Hall
335 S Broadway
Electronic Meeting Access:
https://www.gotomeet.me/DePere
Telephonic Meeting Access:
(866) 899-4679 -or- (312) 757-3117
Access Code: 154-883-28
1. Call to Order
2. Roll Call
3. Public Comments
Comments made during the public comment period shall pertain only to matters under the
jurisdiction of the Board of Public Works. §6-3(f) DPMC
4. New Business
A. Approval of the October 12, 2026 Board of Public Works Meeting Minutes
B. Consideration and possible action on Town of Rockland Annexation and Harter's Fox
Valley Disposal solid waste services*
C. Consideration and possible action on Change Order #1 for MSC Expansion Project*
D. Consideration and possible action on De Pere Easements for Project 4190-17-00*
E. Consideration and possible action on Resolution for Parking & Traffic Updates*
5. Future Agenda Items
6. Adjournment
Any person wishing to attend this meeting who, because of disability, requires special
accommodations should contact the Public Works Department at 920-339-4060 by
noon on the previous day so that arrangements can be made.
The Public or Members of the Board of Public Works, which may count toward an
official quorum, may attend the meeting either in person in the Council Chambers or
telephonically or electronically via video conferencing or other appropriate
technological means.
Page 1 of 39
This meeting may also be rebroadcast on TV throughout the week and available
on demand at https://deperewi.portal.civicclerk.com/.
Page 2 of 39
City of De Pere, Wisconsin
Request for Board of Public Works
Action
4.A
Meeting Date:
November 9, 2026
Department:
Public Works
From:
Natalie Markelz, Administrative Assistant
Subject:
Approval of the October 12, 2026 Board of Public Works
Meeting Minutes
Recommendation: Motion to approve.
Attachments:
2026 1012 Board of Public Works Meeting Minutes
Page 3 of 39
Board of Public Works
Regular Meeting
Minutes
335 South Broadway
De Pere, WI 54115
www.deperewi.gov
Monday, October 12, 2026 7:30 PM City Hall, Council Chambers 335 S.
Broadway
1. Call to Order
The meeting was called to order at 7:30 PM by Mayor James Boyd.
2. Roll Call
Present: James Boyd, Mike Eserkaln, Jonathon Hansen, Shana Ledvina, Dustin Thill
Absent:
Excused:
Others Present:
Scott Thoresen, Public Works Director
Eric Rakers, City Engineer
Tom Blohowiak, Maintenance Supervisor
Natalie Markelz, Administrative Assistant/Recording Secretary
3. Public Comments
Comments made during the public comment period shall pertain only to matters under the
jurisdiction of the Board of Public Works. §6-3(f) DPMC
None.
4. New Business
A. Approval of the September 9, 2026 Board of Public Works Meeting Minutes
RESULT: APPROVED [UNANIMOUS]
MOVER: James Boyd
SECONDER: Shana Ledvina
AYES: James Boyd, Mike Eserkaln, Jonathon Hansen, Shana Ledvina, Dustin Thill
B. Consideration and possible action on Design Options for the Main Avenue Slope*
Scott Thoresen, Public Works Director stated the Council and Board previously approved the
Resolution in regard to State/Municipal Financial Agreement (SMFA) costs with the Wisconsin
Department of Transportation (WisDOT) Main Avenue and Reid Street Project. He advised
costs are shared for redoing the Main Avenue slope by the railroad bridge. It was
recommended to remove vegetation and replace it with concrete. However, staff reached out
to neighboring owners at this location for their opinion on what should be in place. Mr.
Thoresen gave a little background stating City staff used to mow the slope, but due to hazards
we had stopped a couple years ago. He advised a letter was sent out to owners in this area
which included three options for the project; maintain slopes as they currently are, install
natural prairie planting, or install concrete. With numerous responses back, some were fine
Page 4 of 39
with concrete while others favored natural prairie plantings. One owner specifically stated he
was in favor of maintaining as is today and specifically does not want concrete.
Mr. Thoresen advised the purpose of this item is to present the summarized feedback from
residents and give direction to WisDOT. He asked what the Board would like to see at this
location, as staff does not have a preferred recommendation. Mr. Thoresen noted the concrete
would cost almost a half million dollars whereas natural prairie plantings or to leave how it
currently is would be significantly cheaper.
Mayor Boyd asked if anyone has desire to maintain slopes today or if that can be disregarded
as an option. Alderperson Thill stated residents were in favor of the natural plantings, and due
to the option being cost effective, he prefers that option. Alderperson Hansen said he is also
inclined to go with natural prairie plantings which was also the preferred option of the residents.
He asked if the area will be maintained for noxious weeds and how often staff would need to
maintain. Eric Rakers, City Engineer, explained staff would either pull or spot spray weeds,
maybe once a year.
Mayor Boyd wanted to point out that this is for the entire City, ones that drive by daily, it’s not
just for the owners nearby. He wanted the Board to keep an open mind on what makes most
sense for the City in general as it’s a heavily travelled location viewed by many individuals.
Alderperson Thill added that natural prairie plantings could include wildflowers which would
make it look aesthetically pleasing. Mayor Boyd stated he also wants it to look nice, but we had
a hard time taking care of this area already and wanted to make sure we know what this
entails. Alderperson Ledvina added that she would rather see plantings overgrown versus
concrete with cracks and weeds growing out of it. As such, she’s also in favor of natural prairie
plantings. Alderperson Eserkaln stated leaving as is wouldn't solve the problem, concrete is
more expensive and natural prairie plantings are a better look and aesthetic. He added if
weeding isn't as hazardous as mowing then we have made a step forward. Additionally, he
suggested if there would be a cement wall under the bridge, he believes we should have a
mural. Alderperson Ledvina questioned to the Mayor if he was implying we should send out a
survey. Mayor Boyd replied no, just wants to make Alderpersons aware of what they’re
selecting. He added residents thought it would be colored stamped concrete. Alderperson
Hansen pointed out in the letter from the packet it specifically states the concrete would not be
colored. Mayor Boyd agreed that natural prairie plantings is cost effective.
Mr. Thoresen stated this is our window to decide to let WisDOT know what we choose so they
can plan, we don’t have months to think about this. Mr. Rakers added that in the future if we do
not like natural prairie plantings, we can decide to change it.
Added discussion between Alderperson Thill, Mayor Boyd and Mr. Thoresen about the existing
sidewalk that will be removed in the future.
Mayor Boyd asked if the City does the design. Mr. Thoresen answered the item will go to
Council as a recommendation and once approved, will be relayed to WisDOT. Afterwards the
existing vegetation will be removed and prairie plantings will be installed. Alderperson Thill
asked if there will be wildflowers added. Mr. Rakers advised plantings do include flowers.
Alderperson Ledvina moved to approve Design Option #2, Natural Prairie Plantings, seconded
by Alderperson Thill. Upon vote, the motion passed unanimously.
Page 5 of 39
RESULT: APPROVED [UNANIMOUS]
MOVER: Shana Ledvina
SECONDER: Dustin Thill
AYES: James Boyd, Mike Eserkaln, Jonathon Hansen, Shana Ledvina, Dustin Thill
C. Discuss City Engineer Recommendations on No Action Parking and Traffic
Discussion Items
1. Request to paint stalls on Michigan Street, south of George Street.
Eric Rakers, City Engineer, advised the request came from a local business as people are
parking too close to the driveway and getting tickets. He explained that parking four feet from a
driveway is a State Statute. The City does not typically paint on the curb or street, however
downtown where parking stalls are marked is only as a convenience to maximize number of
stalls so people park efficiently. Due to this, staff is recommending no action.
2. Request for a stop sign on at the intersection of Flicker Trail and Red Wing Trail.
Mr. Rakers advised the constituent who brought this request forth was concerned as it’s close
to a park and they witness people not yielding. Mr. Rakers explained this location is an
uncontrolled intersection which the City has many where Stop Signs are not installed, rather a
Yield Sign might be. However, traffic count at this location is exceptionally low which does not
warrant any action.
Alderperson Ledvina said the SeeClickFix response from Mr. Rakers advised a Yield Sign
could be an option, but he did not list that here. Mr. Rakers answered that his recommendation
was based on the request for a stop sign. A Yield Sign would not be needed either because of
the low traffic volume. Alderperson Ledvina explained she has been to this location and
personally believes a Yield Sign should be here, especially to prevent a child from getting hit.
She further explained with the playground being new, it receives more visitors from outside the
neighborhood. Mr. Rakers advised having a Yield Sign does not guarantee someone yielding
to a pedestrian at a crosswalk. He further explained Yield Signs have not been installed
previously unless there is a specific site issue or an off-set intersection. As such, this location
is neither and his recommendation is staying consistent with how they’ve been approved to be
installed by the Board in the past. Alderperson Ledvina agrees with Mr. Rakers, however
states with the playground being nearby, believes this is a different circumstance than previous
requests and would like to see a Yield Sign installed.
Alderperson Eserkaln asked if there could be compromise and install a "Slow Children
Present" sign. Mr. Rakers advised we can take the item back and look at a Yield Sign and what
was done at other locations, specifically mentioning Irwin Avenue and Winnebago Street where
there was a request, also with a park nearby, and one was not installed.
Alderperson Ledvina added that she knows the resident who submitted the request. This
constituent was going to get signatures from the neighborhood as she believes many others
would like to have some kind of action taken.
Mr. Rakers explains there is a set policy on Stop Sign installation and if the Board wants to
change approach for the installation of Yield Signs, that can be done as well.
Page 6 of 39
Alderperson Ledvina asked if a crosswalk would be more appropriate. Mayor Boyd answered
that the item can be taken back to look at alternative solutions.
Alderperson Hansen added that Yield Signs have been installed at T intersections such as
Robin Street and Cook Street, however at other times there have not such as South Michigan
Street and Bomier Street. He stated the Board doesn't have a consistent policy for T
intersections as they have been taken case by case, so he’s in agreeance with taking another
look at this location.
3. Discuss a resident concern regarding vehicles not yielding to pedestrians in the crosswalks
at the intersection of Wisconsin and George Street.
Mr. Rakers advised the final request is more informational as he believes the resident spoke at
Common Council concerned about people not yielding at the intersection of Wisconsin Street
and George Street. He explained this is a Brown County signalized controlled intersection so
he has reached out to them. Brown County said they will look to place more signage. The
County did ask that the City trim trees at this location to make pedestrians more visible so Mr.
Rakers has reached out to the Forester.
Mayor Boyd said he was at this intersection recently to cross Wisconsin Street and George
Street and the signals for the pedestrians to cross did not work. Mr. Rakers will have staff
investigate and let the County know if they are not functioning properly.
Scott Thoresen, Public Works Director, added this has been an ongoing complaint for many
years as there is signage present, but not followed by vehicles. Mr. Rakers further added that
pedestrians have the right-of-way but also need to be vigilant.
Item #2 for a Stop Sign at Flicker Trail and Red Wing Trail will be taken back for future
discussion or possible recommendation. No action taken.
D. City Engineer Parking and Traffic Recommendations
Eric Rakers, City Engineer, explained the process is now different, if recommendations are
approved by the Board, they no longer go directly to Common Council, Resolutions will be
brought back to amend the ordinance.
1. Consider parking restrictions on Williams Street between Wisconsin Street and Michigan
Street.
Mr. Rakers stated due to the new extension of William Street, there are areas designated for
parking where staff is recommending three-hour parking on both sides of William Street as well
as No Parking in the other narrow areas.
2. Consider parking restrictions on Wisconsin Street between James Street and Williams.
Mr. Rakers advised the consideration is the west side being a loading zone as it’s adjacent to
the hotel and the east side, in the designated areas, three-hour parking and No Parking in the
narrow sections.
Page 7 of 39
3. Consider Everett Drive parking restrictions.
Mr. Rakers stated the next recommendation is for the new construction of the second phase of
The Bungalows of De Pere. Due to the narrow street, the recommendation is No Parking on
both the west and north side of the street.
4. Consider Preserve Court parking restrictions.
The next is on Preserve Court, which is the new cul de sac that extends off Employers
Boulevard, similar to the previous, staff is recommending No Parking on the west side of the
street.
5. Consider Stop Sign on Preserve at Employers Boulevard.
Finally, staff is recommending a Stop Sign due to the boulevard itself and Employers
Boulevard being a higher volume street along with new developments upcoming in the area.
RESULT: APPROVED [UNANIMOUS]
MOVER: Jonathon Hansen
SECONDER: Mike Eserkaln
AYES: James Boyd, Mike Eserkaln, Jonathon Hansen, Shana Ledvina, Dustin Thill
E. Consideration and possible action regarding SEH’s Fourth Amendment for
Consulting Services for MSC Expansion*
Scott Thoresen, Public Works Director, advised this is for additional services which is mainly
Engineering fees found after construction started that the State advised we required a special
engineering firm to do inspections, done by Brander Engineering. Other expenses are
miscellaneous for re-design or add-ons.
Alderperson Ledvina asked why this was not included in original bid. Mr. Thoresen advised
once the plans were complete, they went to the State for an approval process. The State had
then changed to have an independent firm complete the commercial inspections afterwards.
Alderperson Ledvina asked if this is the fourth change, what has been the total cost in
changes. Mr. Thoresen advised there will be a change order coming through within the next
month for miscellaneous changes to date. When Board and Council approved the project, it
included about $2.5 million for contingencies. We are still within the $19.5 million that the City
is bonded for. There will be more change orders for major changes after the fact.
Mayor Boyd asked the target completion date for the MSC Project. Mr. Thoresen answered
about this time next year.
Alderperson Hansen clarified that Council passed bonding resolution recently and the bonding
was under budget, but the additional costs are still covered. Mr. Thoresen confirmed.
Page 8 of 39
RESULT: APPROVED [UNANIMOUS]
MOVER: James Boyd
SECONDER: Jonathon Hansen
AYES: James Boyd, Mike Eserkaln, Jonathon Hansen, Shana Ledvina, Dustin Thill
F. Consideration and possible action to approve the bid from TweetGarot Mechanical
for the Preventative Maintenance Service*
Tom Blohowiak, Maintenance Supervisor, stated the City has been doing 3-year contracts for
preventative HVAC maintenance for all City buildings. The City has previously worked with
TweetGarot and Bassett Mechanical, currently under contract with Hurckman Mechanical.
Mr. Blohowiak stated he brought back as an RFP as Hurckman is not meeting our contract
standards. Mr. Blohowiak advised he let them bid on the RFP with the intent they would
provide information needed as they are not returning condition reports on equipment they
inspect as listed in the contract. He said they also use the City as filler work so they are not
consistent with timing on completion of work. He believes this correlates with their low pricing
as they are not dedicating their time to us. However, TweetGarot did a walkthrough with the
RFP process, and we've worked with them before, with quality results. Even though they are
more expensive, for these reasons Mr. Blohowiak recommends TweetGarot.
Mayor Boyd asked about the budget. Mr. Blohowiak responded if approved, it will be in the
2027 Budget.
Alderperson Hansen asked if Hurckman Mechanical responded to email that was included in
the packet. Mr. Blohowiak advised they had not.
RESULT: APPROVED [UNANIMOUS]
MOVER: Jonathon Hansen
SECONDER: Dustin Thill
AYES: James Boyd, Mike Eserkaln, Jonathon Hansen, Shana Ledvina, Dustin Thill
G. Consideration and possible action on 2026-2027 Sidewalk Snow & Ice Removal
Rates
Scott Thoresen, Public Works Director, stated this is an annual item prepping for winter. This is
computed with wage rates and recent compensation study. Due to retirements within the year,
the wages were brought down. Snow removal costs remain the same and minimum lot charge
has not increased.
RESULT: APPROVED [UNANIMOUS]
MOVER: James Boyd
SECONDER: Mike Eserkaln
AYES: James Boyd, Mike Eserkaln, Jonathon Hansen, Shana Ledvina, Dustin Thill
H. Consideration and possible action on update to the policy for Full Length Sanitary
Lateral Replacement Program
Page 9 of 39
Eric Rakers, City Engineer, informed the Board that this program started in 2024, where if the
City had project where they were replacing a person’s lateral under open cut construction, we
would offer to pay 100% of lateral rehabilitation through pipe bursting, if the resident chose, to
reduce inflow and infiltration (I&I) into the sanitary system. At the end of 2024, the policy was
updated to add an option for residents to repair laterals outside of a City project to receive up
to 50% reimbursement with a maximum amount. Mr. Rakers said we are looking to take a step
back from current process and offer up to a 50% reimbursement for pipe bursting or lining vs.
at 100%. He explained there have been some issues with the current process; homes without
a backflow preventer would have to install one, per Building Inspection, which means this is an
additional cost to the homeowner. Another issue is having a hard time coordinating plumbers
and inspections. On the construction standpoint, owners have backed out at last minute which
creates a domino effect and makes construction prices increase as it creates more work for
contractors. There also have been a few claims where homeowners state the contractor
damaged property and want reimbursement.
Finally the policy needs to be updated to address risers, Mr. Rakers advised there have been
instances where the owner chose to do pipelining who have risers, in these cases, the City
would cover the cost of the risers in the future as we are the ones who choose the depth of the
sewer.
Mr. Rakers added, going forward if staff find leaking laterals, we need to inform and require
residents repair within a timely manner as currently we are not making it mandatory. This will
be brought back to the Board for discussion.
Mayor Boyd stated he never thought the program would stay at 100% reimbursement
indefinite.
Alderperson Hansen asked if the homeowners are choosing to do this on their own, does the
City still get involved for inspection. Mr. Rakers answered yes as they need to provide post
televising and the connection in the basement is checked by Building Inspection. Alderperson
Hansen then asked when the City has projects in the future, will staff make residents aware of
the program at that time. Mr. Rakers answered that we can notify residents of the 50% match
program. Alderperson Hansen stated if owners don’t take advantage during construction, they
can still opt for it in the future. Mr. Rakers said that was correct, however they may potentially
damage their sidewalk, unless they choose cured in place pipe (CIPP), which most do.
Alderperson Hansen finally asked how much budgetary savings is anticipated with this change.
Mr. Rakers stated he did not know the numbers, however there is a budgeted amount each
year which has not been close to being maxed out yet. Mayor Boyd asked if we have ever
exhausted the funds. Mr. Rakers answered no. He said residents are aware and taking
advantage of the program. He added that we know it works as owner’s sump pump runs more
since the clear water that used to go into the sanitary is now being pumped out as it should.
Mayor Boyd added that the City should do a social media outreach or post on this and thought
a Mayors Corner would be beneficial to homeowners.
RESULT: APPROVED [UNANIMOUS]
MOVER: James Boyd
SECONDER: Jonathon Hansen
AYES: James Boyd, Mike Eserkaln, Jonathon Hansen, Shana Ledvina, Dustin Thill
Page 10 of 39
I. Consideration and possible action on applying for a Wisconsin Department of
Transportation SISP Grant*
Eric Rakers, City Engineer, did advise the deadline has come and passed, so he has already
submitted the grant, but if the Board does not want, he can ask to revoke the application.
Mr. Rakers explained this is a Signal Replacement Grant, a standalone project that WisDOT
has where they will reimburse eligible signals, paying 90% and the Municipality pays 10%. He
is recommending this for the Broadway Street and Cook Street intersection. WisDOT is
resurfacing Broadway Street next year and we have been asking them to modify the
intersection due to accidents. Staff initially requested to update the turn lane, which didn’t
happen so instead this is to add a leading left turn cycle at the signal. The signals need to be
modified to add this cycle, and the signals are old, so it makes sense to replace.
Alderperson Hansen believes this is a good short-term solution to improve safety and
potentially could be a first step to long term solutions down the road. He asked if we would be
completely replacing signals or retrofitting the existing. Mr. Rakers said we would replace.
Alderperson Hansen also noted that he spoke with the WisDOT Project Manager, Joshua
Lang, to either widen or elongate the left turn lane going southbound on Broadway Street in the
future.
RESULT: APPROVED [UNANIMOUS]
MOVER: James Boyd
SECONDER: Mike Eserkaln
AYES: James Boyd, Mike Eserkaln, Jonathon Hansen, Shana Ledvina, Dustin Thill
J. Consideration and possible action on the State/Municipal Maintenance Agreement for
the Construction of a Wet Detention Pond within Wisconsin Department of
Transportation Right-of-Way*
Eric Rakers, City Engineer, said this is in conjunction with the next item, proposing to build a
small stormwater management pond at Broadway Street and Cook Street by Honey Court
which will service area to the south. He stated this grant helps us treat the area that the State
is requesting us to do so.
RESULT: APPROVED [UNANIMOUS]
MOVER: Jonathon Hansen
SECONDER: Shana Ledvina
AYES: James Boyd, Mike Eserkaln, Jonathon Hansen, Shana Ledvina, Dustin Thill
K. Consideration and possible action on Award of Contract 26-09 Pond and Drainage
System Construction*
Eric Rakers, City Engineer, advised this is the pond construction project noted in the previous
item. Funding is a combination through the Department of Natural Resources grant at a 50/50
match for the pond and due to the water main relocation, water utility funding.
Page 11 of 39
Mayor Boyd moved to approve award of Contract 26-09 Pond and Drainage System
Construction to Kruczek Construction, Inc. in the amount of $171,171.00, seconded by
Alderperson Ledvina. Upon vote, the motion passed unanimously.
RESULT: APPROVED [UNANIMOUS]
MOVER: James Boyd
SECONDER: Shana Ledvina
AYES: James Boyd, Mike Eserkaln, Jonathon Hansen, Shana Ledvina, Dustin Thill
L. Consideration and possible action on Award of Contract 26-10 Phoenix of De Pere
Utility and Street Construction*
Eric Rakers, City Engineer, stated this is new construction going in the Humana complex which
is four 42-unit, multifamily buildings going north of Humana. Part of the contract is extending
utilities for the developer’s needs, building stormwater pond, gravelling and grading the road
with a separate contract for paving either late this year or early next year. The project is funded
by TID 15.
Mayor Boyd added that this is for the affordable housing units.
Mayor Boyd moved to approve award of Contract 26-10 Phoenix of De Pere Utility and Street
Construction to PTS Contractors, Inc. in the amount of $868,960.00, seconded by Alderperson
Thill. Upon vote, the motion passed unanimously.
RESULT: APPROVED [UNANIMOUS]
MOVER: James Boyd
SECONDER: Dustin Thill
AYES: James Boyd, Mike Eserkaln, Jonathon Hansen, Shana Ledvina, Dustin Thill
5. Future Agenda Items
Alderperson Hansen stated he knows that the Grant Street railroad crossing being is replaced
currently but still has concerns on Reid Street. He has noticed staff has put down mastic, which
has improved, but there are cracked timbers, so he’s asking if anything more staff can do to
improve.
Scott Thoresen, Public Works Director, advised timbers wouldn't be replaced. Staff has been
working with the railroad to fill with mastic which we can keep up with. However, they nor us
are going to put a lot of effort knowing it will be replaced in 2028.
Mayor Boyd said this will not be a future agenda item.
6. Adjournment
Mayor Boyd moved, seconded by Alderperson Eserkaln to adjourn the meeting at 8:31 PM. Upon
vote, motion carried unanimously.
Respectfully submitted,
Natalie Markelz
Page 12 of 39
City of De Pere, Wisconsin
Request for Board of Public Works
Action
4.B
Meeting Date:
November 9, 2026
Department:
Public Works
From:
Tony Fietzer, Street Superintendent
Subject:
Consideration and possible action on Town of Rockland
Annexation and Harter's Fox Valley Disposal solid waste
services*
Recommendation: Approve an annual contract with Harter's Fox Valley
Disposal to continue to collect solid waste at the newly
annexed parcels.
Attachments:
2026 1109 BOPW Memo_Annexation-Harter Solid Waste Services
Page 13 of 39
To: Honorable Mayor Boyd
Members of the Board of Public Works
From: Tony Fietzer, Street Superintendent
Date: November 9, 2026
RE: Town of Rockland Annexation and Harter’s Fox Valley Disposal solid waste services
The City of De Pere is anticipating annexation of four residential parcels in the Town of Rockland
beginning December 1, 2026. These parcels are currently receiving solid waste services through Harter’s
Fox Valley Disposal though the Town of Rockland. With the annexation, the city boundaries will increase
by several miles to the south.
I spoke with Harter’s Fox Valley Disposal, and they stated they would be willing to continue to collect
these four parcels and invoice the city annually for the collection. The quoted rate would be $25/month
per parcel. Due to the added distance, it would take to collect these parcels and the fuel costs/time,
staff is recommending approval of an annual contract with Harter’s Fox Valley Disposal to collect the
solid waste pending Legal review.
Page 14 of 39
City of De Pere, Wisconsin
Request for Board of Public Works
Action
4.C
Meeting Date:
November 9, 2026
Department:
Public Works
From:
Scott Thoresen, Public Works Director
Subject:
Consideration and possible action on Change Order #1 for
MSC Expansion Project*
Recommendation: Staff recommends approval of Change Order No. 1 with
SMA Construction Services, LLC, in the amount of
$573,034.90, resulting in a revised contract amount of
$14,406,034.90. Funding for this change order will be
provided through the project contingency budget
previously approved as part of the overall MSC Expansion
Project.
Attachments:
Consider MSC Expansion Change Order #1 11-04-2026, Consider MSC Expansion
Bids 3-4-2026, De Pere MSC Expansion Recommendation of Award Letter, MSC
Expansion 2-26-2026 Bid Results
Page 15 of 39
To: Honorable Mayor Boyd
Board of Public Works Members
From: Scott J. Thoresen, Director of Public Works
Date: November 4, 2026
RE: Consider and Possible Action on Change Order #1 for MSC Expansion Project*
Earlier this year the BOPW and Council approved the MSC expansion project for SMA
Construction Services, LLC in the amount of $13,833,000.00. The project budget included
$2,074,950.00 in contingency funding to address unforeseen conditions and owner-requested
modifications during construction. (See attached memo)
As the project has progressed, several changes have been identified and approved for pricing.
The total costs for the identified changs is $573,034.90.
These changes are summarized below:
CR #1 – Plumbing Revisions ($1,298.90)
Plumbing revisions were required due to the increased depth of the wash bay catch basin to
meet equipment supplier requirements.
CR #2 – Building #2 Revisions ($103,780.96)
The original storage building plans were rejected by the State because the storage of plastic
refuse containers classified the existing building as a moderate-hazard occupancy. To comply
with State requirements, a firewall separating the new and existing buildings was added. A
rolling fire shutter door was also installed to maintain internal access between the buildings.
CR #4 – Additional Tree Removal ($4,849.16)
Additional tree removal was requested by the City on adjacent properties.
CR #5 Electrical Revisions ($20,889.21)
The location of the new main electrical panel was revised due to concerns regarding sawdust
accumulation in the woodshop. In addition, staff requested modifications to better
accommodate future electrical needs. Select loads were redirected to the existing main
Page 16 of 39
2
electrical panel, requiring larger conductors and breakers to meet current electrical code
requirements.
CR #7 – Sewage Pump Relocation ($16,174.77)
The proposed sewage ejector pit was determined to be too close to new structural footing
pads. The pit was relocated into a dedicated room farther from the columns. Additional costs
include construction of the room, revised piping, and modifications to structural pier depths.
CR #8 – Site Revisions for New Retaining Wall ($394,440.98)
The City requested modifications to the public rubbish drop-off and fuel tank areas. The work
includes removal and storage of existing retaining wall blocks, construction of a new retaining
wall reaching approximately eight feet above grade at the rubbish drop-off area, and
installation of additional concrete pavement.
CR #9 – Temporary Electrical Service Installation ($30,375.00)
Temporary electrical service costs exceeded the contractor’s bid allowance due to delays in
relocating the existing WPS transformer. Temporary power was necessary because the new
foundation wall could not be constructed until the transformer relocation was completed.
CR #12 – Sewer and Inlet Revisions (-$1,547.00)
Credit associated with storm sewer and inlet revisions recommended by the City Engineer.
CR #13 – Salt Dome Concrete Paving (2,772.92)
The City requested replacement of the originally specified asphalt paving with concrete paving
at the new salt dome extension.
Staff recommends approval of Change Order No. 1 with SMA Construction Services, LLC, in the
amount of $573,034.90, resulting in a revised contract amount of $14,406,034.90. Funding for
this change order will be provided through the project contingency budget previously approved
as part of the overall MSC Expansion Project.
Page 17 of 39
To: Honorable Mayor Boyd
Board of Public Works Members
From: Scott J. Thoresen, Director of Public Works
Date: March 4, 2026
RE: Consider and Possible Action on Award of Contract for MSC Expansion*
The City’s consultant SEH received bids (See attached bid and recommendation letter) for the
contract for the Municipal Service Center (MSC) expansion.
The total estimated costs for the entire project is as follows:
• SMA Bid = $13,833,000.00
• Contingencies (15%) = $2,074,950
• Water & Sanitary Replacement = $200,000
• Storm Sewer Replacement = $400,000
• Temporary Office = $100,000
• Office Furniture/Cubicles = $350,000
• Miscellaneous Equipment/City Work = $400,000
• Utilities (WPS, Fiber, SCADA) = $100,000
• Consultant Fees = $831,444
Total Project Costs = $18,289,394
The budgeted amount from the 2025 & 2026 capital improvement program is $25,000,000.
Staff is recommending accepting the bid from SMA Constructions Services, LLC in the amount of
$13,833,000.00
Page 18 of 39
Engineers | Architects | Planners | Scientist s
Short Elliott Hendrickson Inc., 425 West Water Street, Suite 300, Appleton, WI 5491 1-6058
920.380.2800 | 888.413.4214 | 888.908.8166 fax | sehinc.com
SEH is 100% employee-owned | Affirmative Action–E qual Opportunity Employer
March 3, 2026 RE: De Pere, WI
Municipal Service Center Renovation
SEH No. DEPEW 161454
City of De Pere
925 S. Sixth Street
De Pere, WI 54115
On Thursday, February 26, 2026, eight (8) bids were received for the De Pere Municipal Service Center
renovation project. The low bid received including the alternate bids was submitted by SMA Constructio n
Services, LLC, of Green Bay in the amount of $13,833,000.00.
In reliance on the materials and information provided by the contractor, we have determined that 1) th ey
met the requirements for pre-qualification as established by the City of De Pere; 2) have a sufficient
understanding of the project and equipment to perform the construction for which it bid; and 3) accord ing
to their bonding agent they presently have the financial ability to complete the project as bid.
SEH makes no representation or warranty as to the actual financial viability of the contractor or its ability
to complete its work.
We recommend the project, including all of the alternate bids be awarded to SMA Construction Services,
LLC in the amount of $13,833,000.00. We also recomm end that the City carry a minimum 15%
contingency in addition to this contract amount.
Sincerely,
Trevor M. Frank, AIA
Architect in WI, AZ, FL, GA, IA, IL, IN, MI, MN, NC, ND, OH, RI, SD, VA
Project Manager
Page 19 of 39
De Pere, WI - Municipal Service Center (DEPEW 161454) (#10024552)
Owner: De Pere WI, City of
Solicitor: SEH - Appleton, WI
02/26/2026 01:00 PM CST
SMA Construction
Services, LLC IEI General Contractors Bayland Buildings Inc. Howard Immel Inc IC Construction
Company
Milbach Construction
Services, Co.
Frank O. Zeise
Construction Co., Inc. 8PINE. Inc.
Section Title UofM Unit Price Unit Price Unit Price Unit Price Unit Price Unit Price Unit Price Unit Price
Base Bid Lump Sum
LS $13,550,000.00 $13,883,000.00 $14,364,057.00 $14,461,220.00 $14,923,800.00 $15,612,011.00 $15,682,500.00 $19,915,000.00
Alternate 1
LS $190,000.00 $135,458.00 $96,836.00 $70,263.00 $303,000.00 $72,487.00 $81,750.00 $78,240.00
Alternate 2
LS $56,000.00 $96,058.00 $77,351.00 $61,745.00 $40,000.00 $74,899.00 $79,000.00 $172,785.00
Alternate 3
LS $37,000.00 $31,498.00 $32,848.00 $38,767.00 $38,000.00 $32,840.00 $36,300.00 $33,325.00
Base Bid Total:
$13,833,000.00 $14,146,014.00 $14,571,092.00 $14,631,995.00 $15,304,800.00 $15,792,237.00 $15,879,550.00 $20,199,350.00
Page 20 of 39
City of De Pere, Wisconsin
Request for Board of Public Works
Action
4.D
Meeting Date:
November 9, 2026
Department:
Public Works
From:
Eric Rakers, City Engineer
Subject:
Consideration and possible action on De Pere Easements
for Project 4190-17-00*
Recommendation: Staff recommends approval of the resolution.
Attachments:
2026 1109 CI_BOPW_De Pere TLE-4190-17-00, Reso26-XX DOT TLE Acquisition
Page 21 of 39
To: Honorable Mayor Boyd
Members of the Board of Public Works
From: Eric P. Rakers, P.E., City Engineer
Date: November 9, 2026
RE: Consideration and possible action on De Pere Easements for Project 4190-17-00*
The City has entered into a State/Municipal Financial Agreement (SMFA) with the Wisconsin
Department of Transportation (WisDOT) for pavement replacement on STH 32 (Main Avenue and Reid
Street) from Eighth Street to Third Street under Project ID 4190-17-00/21/54/71/72. Under the Terms
and Conditions of the agreement, the City is responsible for acquiring right-of-way required by the
project and eligible for 100% reimbursement. Specifically, Item 8.b. states:
“Project ID 4190-17-21, Real Estate: Acquisition of any necessary right-of-way within Connecting
Highway limits is the responsibility of the Municipality. Right-of-way required for the project should be
purchased by the municipality and may be eligible for up to 100% WisDOT participation and must be
acquired in the municipality’s name. Real estate required for parking lanes is not eligible.”
There are four De Pere properties that require temporary limited easements (TLE’s) for the project. The
properties are located at 615 Main Avenue, the parking lot between 436 and 444 Main Avenue, 360
Main Avenue, and the walkway between 331 and 337 Main Avenue. The TLE’s are for grading purposes
which allow a better match between the sidewalk and City property.
Because De Pere is reimbursed for real estate as noted above, there is no need to request
reimbursement for the TLE’s.
Recommendation:
Staff recommends approval of the attached resolution granting the TLE Acquisition to WisDOT.
Attachments:
Reso26-XX TLE Acquisition (PDF)
Page 22 of 39
RESOLUTION #26-XX
AUTHORIZING TEMPORARY LIMITED EASEMENTS TO THE
WISCONSIN DEPARTMENT OF TRANSPORTATION
(Parcel Nos. WD-387-1, WD-277, WD-376, WD-377, WD-926, WD-928 and WD-917-1)
WHEREAS, as part of Wisconsin Department of Transportation (WisDOT) improvements
to State Highway (STH) 32 from Eighth Street to Third Street, WisDOT is seeking Temporary
Limited Easements (TLEs) for a portions of City property that must be acquired through
resolution, as part of WisDOT Project Number 4190-17-21; and
WHEREAS, this matter has been reviewed by the Board of Public Works which consents
to the provision of the TLEs to advance this project and recommends approval thereof.
NOW, THEREFORE, BE IT HEREBY RESOLVED THAT:
The Common Council hereby authorizes and directs that the following portions of City-
owned parcels described below may be utilized for TLEs for STH 32 infrastructure
improvements and downtown corridor reconstruction (R/W Project Number 4190-17-
21), including the right to construct driveways, construct cut and/or fill slopes, including
for such purpose the right to operate the necessary equipment thereon and the right of
ingress and egress as long as required for such public purpose, including the right to
preserve, protect, remove or plant thereon any vegetation that the highway authorities
may deem necessary or desirable to prevent soil erosion, in and to the following lands in
the City of De Pere, Brown County, Wisconsin, described as follows:
Parcel 27 (as shown on Plat Sheet Number 10)
TLE BEING A PART OF LOTS 12, 13, 14 AND 15 OF BLOCK 6 OF DE PERE COMPANY’S ADDITION
TO THE VILLAGE OF WEST DE PERE LOCATED IN PRIVATE CLAIM NO. 28 WEST SIDE OF THE FOX
RIVER IN THE CITY OF DE PERE, BROWN COUNTY, WISCONSIN, FURTHER DESCRIBED AS
FOLLOWS;
COMMENCING AT THE SOUTHEASTERLY CORNER OF LOT 12 OF BLOCK 6 OF DE PERE
COMPANY’S ADDITION TO THE VILLAGE OF WEST DE PERE;
THENCE N82°37’26”W COINCIDENT WITH THE SOUTHERLY LINE OF SAID BLOCK 6 A DISTANCE
OF 84.20 FEET;
THENCE N07°22’34”E A DISTANCE OF 15.00 FEET;
THENCE S82°37’26”E A DISTANCE OF 7.10 FEET;
THENCE S07°22’34”W A DISTANCE OF 5.00 FEET;
Page 23 of 39
Resolution #26-XX
Page 2 of 4
THENCE S82°37’26”E A DISTANCE OF 77.09 FEET TO THE EASTERLY LINE OF LOT 12 OF DE PERE
COMPANY’S ADDITION TO THE VILLAGE OF WEST DE PERE;
THENCE S07°22’34”W COINCIDENT WITH SAID EASTERLY LINE A DISTANCE OF 10.00 FEET TO
THE POINT OF BEGINNING.
SAID PARCEL CONTAINS 877 SQ FT MORE OR LESS.
Parcel 38 (as shown on Plat Sheet Number 6)
TLE BEING A PART OF LOTS 1 AND 2 OF CARABIN’S ADDITION TO THE VILLAGE OF WEST DE PERE
LOCATED IN PRIVATE CLAIM NO. 29 WEST SIDE OF THE FOX RIVER IN THE CITY OF DE PERE,
BROWN COUNTY, WISCONSIN, FURTHER DESCRIBED AS FOLLOWS;
COMMENCING AT THE NORTHWESTERLY CORNER OF LOT 1 OF CARABIN’S ADDITION TO THE
VILLAGE OF WEST DE PERE;
THENCE S82°35’08”E COINCIDENT WITH THE NORTHERLY LINE OF SAID LOT 1 A DISTANCE OF
115.52 FEET TO THE BEGINNING OF A NON-TANGENT CURVE TO THE RIGHT;
THENCE COINCIDENT WITH SAID CURVE TO THE RIGHT A DISTANCE OF 170.45 FEET, HAVING A
RADIUS OF 155.00 FEET AND A CHORD THAT BEARS S59°03’16”E WITH A CHORD OF 54.65 FEET
IN LENGTH TO THE POINT OF BEGINNING;
THENCE CONTINUING COINCIDENT WITH SAID CURVE TO THE RIGHT A DISTANCE OF 64.56 FEET,
HAVING A RADIUS OF 155.00 FEET WITH A CHORD THAT BEARS S36°58’12”E AND IS 64.09 FEET
IN LENGTH TO THE WESTERLY RIGHT-OF-WAY LINE FOR REID STREET;
THENCE S07°28’22”W COINCIDENT WITH SAID WESTERLY RIGHT-OF-WAY LINE A DISTANCE OF
16.81 FEET;
THENCE N28°10’33”W A DISTANCE OF 77.00 FEET TO THE POINT OF BEGINNING.
SAID PARCEL CONTAINS 521 SQ FT MORE OR LESS.
Parcel 41 (as shown on Plat Sheet Number 12)
TLE BEING A PART OF LOTS 14, 15 AND 16 OF BLOCK 4 OF DE PERE COMPANY’S ADDITION TO
THE VILLAGE OF WEST DE PERE LOCATED IN PRIVATE CLAIM NO. 28 WEST SIDE OF THE FOX
RIVER IN THE CITY OF DE PERE, BROWN COUNTY, WISCONSIN, FURTHER DESCRIBED AS
FOLLOWS;
THE SOUTHERLY 4.00 FEET OF LOT 16 OF BLOCK 4 OF DE PERE COMPANY’S ADDITION TO THE
VILLAGE OF WEST DE PERE.
ALSO;
THE SOUTHERLY 2.00 FEET OF LOTS 14 AND 15 OF BLOCK 4 OF DE PERE COMPANY’S ADDITION
TO THE VILLAGE OF WEST DE PERE.
SAID PARCEL CONTAINS 192 SQ FT MORE OR LESS.
BUILDINGS WILL NOT BE AFFECTED BY TEMPORARY LIMITED EASEMENTS.
Page 24 of 39
Resolution #26-XX
Page 3 of 4
Parcel 73 (as shown on Plat Sheet Number 20)
TLE BEING A PART OF LOTS 48, 50 AND 51 OF THE PLAT OF WEST DE PERE LOCATED IN PRIVATE
CLAIM NO. 29 WEST SIDE OF THE FOX RIVER IN THE CITY OF DE PERE, BROWN COUNTY,
WISCONSIN, FURTHER DESCRIBED AS FOLLOWS;
THE SOUTHERLY 10.00 FEET OF THE WESTERLY 35.07 FEET OF LOT 48 OF THE PLAT OF WEST DE
PERE.
ALS0;
THE SOUTHERLY 10.00 FEET OF THE EASTERLY 7.73 FEET OF LOT 50 OF THE PLAT OF WEST DE
PERE.
ALSO;
THE SOUTHERLY 10.00 FEET OF THE WESTERLY 32.97 FEET OF LOT 51 OF THE PLAT OF WEST DE
PERE.
SAID PARCEL CONTAINS 758 SQ FT MORE OR LESS.
Parcel 84 (as shown on Plat Sheet Number 13)
TLE BEING A PART OF LOT 10, PLAT OF WEST DE PERE LOCATED IN PRIVATE CLAIM NO. 29 WEST
SIDE OF THE FOX RIVER IN THE CITY OF DE PERE, BROWN COUNTY, WISCONSIN, FURTHER
DESCRIBED AS FOLLOWS;
THE NORTHERLY 2.00 FEET OF THE EASTERLY 14.03 FEET OF THE WESTERLY 40.28 FEET OF LOT
10, PLAT OF WEST DE PERE.
SAID PARCEL CONTAINS 28 SQ FT MORE OR LESS.
BE IT FURTHER RESOLVED THAT:
Said temporary limited easements described above shall terminate on the date
construction for this project is completed.
BE IT FURTHER RESOLVED THAT:
A certified copy of this resolution shall be forwarded to the Wisconsin
Department of Transportation as part of the documentation related to the
aforementioned STH 32 (R/W Project Number 4190-17-21).
BE IT FURTHER RESOLVED THAT:
Page 25 of 39
Resolution #26-XX
Page 4 of 4
All City officials, officers and employees are further authorized and
directed to take such steps as are lawful and necessary in furtherance
thereof.
Adopted by the Common Council of the City of De Pere, Wisconsin, this _____ day of
________________, 2026.
APPROVED:
____________________________________
James G. Boyd, Mayor
ATTEST:
____________________________________
Carey E. Danen, City Clerk
Ayes: _______
Nays: _______
Board/Committee Approval: ______________
Page 26 of 39
Page 27 of 39
Page 28 of 39
51+0052+0053+00
33 37394141 4347
646668 72 7476 78
25.0019.4682.00
7.003.01 2.002.00
2.0024.0124.0124.0124.0124.0124.0124.0196.05
18.002.0016.0021.0523.05
2.00
22.5521.5275.1424.4743.1726.58
4
R/W PROJECT NUMBER: 4190-17-21SHEET NUMBER: 12STH 32 BROWN COUNTY
SIGNATURE:DATE:PRINT NAME:
PART OF LOTS 12-22, BLOCK 4 OF DE PERE COMPANY'S ADDITION TO THEVILLAGE OF WEST DE PERE LOCATED IN PRIVATE CLAIM NO. 28 W.S.F.R. ANDPART OF LOTS 11-14, PLAT OF WEST DE PERE LOCATED IN PRIVATE CLAIM NO. 29ALL IN THE CITY OF DE PERE, BROWN COUNTY, WISCONSIN.
TLE ACQUISITION MAP3RD STREET - 8TH STREETCITY OF DE PERE
NOTES:THIS EXHIBIT IS A GRAPHIC REPRESENTATIONAND IS FOR REFERENCE PURPOSES ONLY.REFER TO THE CONVEYANCE DOCUMENTFOR PARCEL RELATED DETAILS.PURPOSE OF ALL TLE'S ARE FOR SLOPING,UNLESS OTHERWISE NOTED.ALL FOUND IP'S ARE 1 INCH IRON PIPES,UNLESS OTHERWISE NOTED.
FEET0 3060
REFPVT. CLAIM LINE
PI: 53+00.91
P/L
P/L
P/L
P/L
P/LP/L
P/LP/LP/LP/L P/LP/LP/L
P/LP/LP/L P/LP/L P/LP/L
DE PERE COMPANY'S ADDITIONTO WEST DE PEREBLOCK 4LOT 22LOT 21LOT 20LOT 19LOT 18LOT 17LOT 16LOT 15LOT 14LOT 13LOT 12
LOT 14LOT 14LOT 14LOT 13LOT 12LOT 12LOT 11LOT 11LOT 11PLAT OF WEST DE PERE
(40')
(40')
WD-380WD-379WD-378WD-377WD-376WD-375WD-374
WD-923WD-922WD-921WD-920WD-918WD-917WD-915
104CITY OF DE PEREPARCEL 33 - NO EASEMENT OF RECORD
104
IPIP
IPIP IPIP
CUT "X"--CUT "X"
- CUT "X"
THIS MAP APPROVED FOR THE CITY OF DE PERE.THIS MAP PREPARED BY WESTWOOD PROFESSIONAL SERVICES, FOR THE CITY OFDE PERE
NO EASEMENT OF RECORD
Page 29 of 39
57+0058+0059+00
73 73 7735.0710.00
40.7010.0014.304
R/W PROJECT NUMBER: 4190-17-21SHEET NUMBER: 20STH 32 BROWN COUNTY
SIGNATURE:DATE:PRINT NAME:
PART OF LOTS 48, 50 AND 51 OF THE PLAT OF WEST DE PERE LOCATED INPRIVATE CLAIM NO. 29 W.S.F.R. IN THE CITY OF DE PERE, BROWN COUNTY,WISCONSIN.TLE ACQUISITION MAP3RD STREET - 8TH STREETCITY OF DE PERE
NOTES:THIS EXHIBIT IS A GRAPHIC REPRESENTATIONAND IS FOR REFERENCE PURPOSES ONLY.REFER TO THE CONVEYANCE DOCUMENTFOR PARCEL RELATED DETAILS.PURPOSE OF ALL TLE'S ARE FOR SLOPING,UNLESS OTHERWISE NOTED.
FEET0 3060
REF
PI: 56+45.92
P/L P/L P/LP/L
P/L
P/L
P/L (70')
8' PUBLIC PARKINGEASEMENTDOC. 25265046'
LOT 48PLAT OF WEST DE PERELOT 49LOT 50LOT 51
LOT 47 PLAT OF WEST DE PERE
LOT 90LOT 89LOT 91LOT 92PLAT OF WEST DE PEREPLAT OF WEST DE PERE
WD-926 WD-928WD-930
104CITY OF DE PEREPARCEL 77 - DOC. 2526504
104
IP
IPCUT "X"-
CUT "X"-
THIS MAP APPROVED FOR THE CITY OF DE PERE.THIS MAP PREPARED BY WESTWOOD PROFESSIONAL SERVICES, FOR THE CITY OFDE PERE
Page 30 of 39
407+48
BP: 407+47.60
407+48
BP: 407+47.60
48+0049+0050+00
4324.01 49 5153 57
828486 8892 929496
2.0036.0236.0224.0171.042.00
2.0054.0814.0426.0844.0922.0545.5720.5642.132.00
4
R/W PROJECT NUMBER: 4190-17-21SHEET NUMBER: 13STH 32 BROWN COUNTY
SIGNATURE:DATE:PRINT NAME:
PART OF LOTS 5-11, BLOCK 4 OF DE PERE COMPANY'S ADDITION TO THEVILLAGE OF WEST DE PERE LOCATED IN PRIVATE CLAIM NO. 28 W.S.F.R. ANDPART OF LOTS 7-11, PLAT OF WEST DE PERE LOCATED IN PRIVATE CLAIM NO. 29ALL IN THE CITY OF DE PERE, BROWN COUNTY, WISCONSIN.
TLE ACQUISITION MAP3RD STREET - 8TH STREETCITY OF DE PERE
NOTES:THIS EXHIBIT IS A GRAPHICREPRESENTATION AND IS FOR REFERENCEPURPOSES ONLY. REFER TO THECONVEYANCE DOCUMENT FOR PARCELRELATED DETAILS.PURPOSE OF ALL TLE'S ARE FOR SLOPING,UNLESS OTHERWISE NOTED.
FEET0 3060
PT: 48+24.91REFPVT. CLAIM LINE
P/L P/L P/LP/L P/L
P/L P/LP/LP/L P/LP/L P/LP/L P/L
P/L
P/L
P/L
P/L
DE PERE COMPANY'S ADDITIONTO WEST DE PEREBLOCK 4LOT 10LOT 11LOT 12LOT 9LOT 8LOT 7LOT 6LOT 5LOT 4
LOT 10LOT 11LOT 11 LOT 10LOT 9LOT 9LOT 8LOT 8LOT 7LOT 7
PLAT OF WEST DE PEREPLAT OF WEST DE PERE
(40')
(40')
WD-373WD-372WD-371WD-369
WD-913WD-917-1WD-912WD-911WD-910WD-909WD-908WD-907
12'12' UTILITY EASEMENTDOC. 2646944
102WE ENERGIES (ELECTRIC)PARCEL 96 - DOC. 2646944
102
IPCUT "X"-
THIS MAP APPROVED FOR THE CITY OF DE PERE.THIS MAP PREPARED BY WESTWOOD PROFESSIONAL SERVICES, FOR THE CITY OFDE PERE
LOT 10
Page 31 of 39
City of De Pere, Wisconsin
Request for Board of Public Works
Action
4.E
Meeting Date:
November 9, 2026
Department:
Public Works
From:
Eric Rakers, City Engineer
Subject:
Consideration and possible action on Resolution for
Parking & Traffic Updates*
Recommendation: Staff recommends approval of the resolution.
Attachments:
2026 1109 CI_BOPW_P&T Resolution, 2026 1012 CI-BOPW-PTTeam-
Recommendations, Ord26-XX Parking-Traffic
Page 32 of 39
To: Honorable Mayor Boyd
Members of the Board of Public Works
From: Eric P. Rakers, P.E., City Engineer
Date: November 9, 2026
RE: Consideration and possible action on Resolution for Parking & Traffic Updates*
Attached is the resolution for the Parking and Traffic action items approved at the October 12, 2026
Board Meeting.
Staff recommends approval of the resolution.
Attachments:
2026 1012 CI_BOPW-PTTeam-Recommendation
Ord26-XX Parking Traffic
Page 33 of 39
City Engineer Parking and Traffic Recommendations
October 7, 2026 Meeting
Parking and Parking Lot Items:
1. Consider parking restrictions on Williams Street between Wisconsin Street and Michigan
Street.
Discussion; Street was designed to accommodate parking in specific areas.
Recommendation; Allow three-hour parking in designated areas on both sides of the
road. Update the ordinance as follows:
Schedule G Parking
(section 150-22)
Three-Hour Parking 9:00 a.m.-6:00 p.m., Mon.-Sat.
Street Side of
Street
From Curb line or Feet/Dir. of Curb
line
To Curb line or Feet/Dir. of
Start
William Street N 40’ E/O Wisconsin Street 40’ W/O Michigan Street
William Street S 35’ E/O Wisconsin Street 40’ W/O Michigan Street
Schedule G Parking
(section 150-22)
No Parking
Street Side of
Street
From Curb line or Feet/Dir. of Curb
line
To Curb line or Feet/Dir. of
Start
William Street N Wisconsin Street 40’ E/O Wisconsin Street
William Street N 40’ W/O Michigan Street Michigan Street
William Street S Wisconsin Street 35’ W/O Wisconsin Street
William Street S 40’ W/O Michigan Street Michigan Street
2. Consider parking restrictions on Wisconsin Street between James Street and Williams.
Discussion; Street was designed to accommodate parking in specific areas.
Recommendation; Allow three-hour parking on the east side and a loading zone on the
west side in designated areas. Update the ordinance as follows:
Schedule G Parking
(section 150-22)
Three-Hour Parking 9:00 a.m.-6:00 p.m., Mon.-Sat.
Page 34 of 39
2
Street Side of
Street
From Curb line or Feet/Dir. of Curb
line
To Curb line or Feet/Dir. of
Start
Wisconsin Street E 50’ N/O James Street 210’ N/O James Street
Loading Zone
Street Side of
Street
From Curb line or Feet/Dir. of Curb
line
To Curb line or Feet/Dir. of
Start
Wisconsin Street W 60’ N/O James Street 180’ N/O James Street
No Parking
Street Side of
Street
From Curb line or Feet/Dir. of Curb
line
To Curb line or Feet/Dir. of
Start
Wisconsin Street E James Street 50’ N/O James Street
Wisconsin Street E 210’ N/O James Street William Street
Wisconsin Street W James Street 60’ N/O James Street
Wisconsin Street W 180’ N/O James Street William Street
3. Consider Everett Drive parking restrictions.
Discussion; This is part of the recently completed second phase of the Bungalows
development south of Employers Boulevard. Street was constructed for parking on one
side only.
Recommendation; Restrict parking on one side of the road. Update the ordinance as
follows:
Schedule G Parking
(section 150-22)
No Parking
Street Side of Street From Curb line or Feet/Dir. of
Curb line
To Curb line or Feet/Dir.
of Start
Everett Drive W&N North Honeysuckle Preserve Court
4. Consider Preserve Court parking restrictions.
Discussion; This is part of the recently completed second phase of the Bungalows
development south of Employers Boulevard. Street was constructed for parking on one
side only.
Recommendation; Restrict parking on one side of the road. Update the ordinance as
follows:
Schedule G Parking
(section 150-22)
No Parking
Street Side of
Street
From Curb line or Feet/Dir. of
Curb line
To Curb line or Feet/Dir.
of Start
Preserve Court W South End Employers Boulevard
Page 35 of 39
3
Signs – Other
5. Consider Stop Sign on Preserve at Employers Boulevard.
Discussion; This is a new intersection. Employers Boulevard is a higher volume street
with the Humana complex at the west end and proposed high density development
occurring in the area. The boulevard section creates additional challenges for the
intersection.
Recommendation; Update the ordinance as follows:
Schedule B Stop Intersections/Right Turn No Stop
(section 150-17)
Traffic On Stops At
Preserve Court Employers Boulevard
Page 36 of 39
ORDINANCE #26-XX
AMENDING CHAPTER 150 OF THE DE PERE MUNICIPAL CODE
REGARDING TRAFFIC REGULATIONS
THE COMMON COUNCIL OF THE CITY OF DE PERE, WISCONSIN DOES ORDAIN AS
FOLLOWS:
Section 1: Section 150-23, Schedule B (Stop Intersections/Right Turn No Stop), is hereby
amended as follows:
INSERTIONS:
Traffic On Stops At
Preserve Court Employers Boulevard
Section 2: Section 150-23, Schedule G (Parking), is hereby amended as follows:
INSERTIONS:
Three-Hour Parking 9:00 a.m.-6:00 p.m., Mon.-Sat.
Street Side of Street From Curb line or
Feet/Dir. of Curb line
To Curb line or Feet/Dir.
of Start
William Street N 40’ E/O Wisconsin Street 40’ W/O Michigan Street
William Street S 35’ E/O Wisconsin Street 40’ W/O Michigan Street
Wisconsin Street E 50’ N/O James Street 210’ N/O James Street
Page 37 of 39
Ordinance #26-XX
Page 2 of 3
No Parking
Street Side of Street From Curb line or
Feet/Dir. of Curb line
To Curb line or Feet/Dir. of
Start
William Street N Wisconsin Street 40’ E/O Wisconsin Street
William Street N 40’ W/O Michigan Street Michigan Street
William Street S Wisconsin Street 35’ W/O Wisconsin Street
William Street S 40’ W/O Michigan Street Michigan Street
Wisconsin Street E James Street 50’ N/O James Street
Wisconsin Street E 210’ N/O James Street William Street
Wisconsin Street W James Street 60’ N/O James Street
Wisconsin Street W 180’ N/O James Street William Street
Everett Drive W&N North Honeysuckle Preserve Court
Preserve Court W South End Employers Boulevard
Loading Zone
Street Side of Street From Curb line or
Feet/Dir. of Curb line
To Curb line or Feet/Dir. of
Start
Wisconsin Street W 60’ N/O James Street 180’ N/O James Street
Section 3: All ordinances or parts of ordinances in conflict herewith are hereby repealed.
Section 4: This ordinance shall take effect on and after its passage and publication.
Page 38 of 39
Ordinance #26-XX
Page 3 of 3
Adopted by the Common Council of the City of De Pere, Wisconsin, this day of
, 2026.
APPROVED:
__________________________________
James G. Boyd, Mayor
ATTEST:
__________________________________
Carey E. Danen, City Clerk
Ayes:
Nays:
Board/Committee Approval:
Publication Date:
Effective Date:
Page 39 of 39