Village of Whitefish Bay, Wisconsin
Public Works Committee Meeting Agenda
Monday, November 9, 2026 at 5:30 pm
In Person Meeting - Village Hall - 2nd Floor Board Room
As an alternative to attending in-person, the public may access this meeting of the Public Works
Committee by phone or by computer. Please note that those participating remotely will not have an
opportunity to provide public comment. The phone number is: +1 312 626 6799. The Zoom Meeting code
is: 832 7883 7748 and the Passcode is: 784164.
https://us06web.zoom.us/j/83278837748?pwd=ZFFCS1Mza2Qvd09VaHkzOFBpWVgwUT09
AGENDA
1. Call to Order
2. Review and Approve Minutes of October 12, 2026 Public Works Committee
Meeting
3. Discussion/Recommendations regarding the Lake Michigan Storm Sewer Outfall
Remediation Project Design
4. Discussion/Updates regarding the MMSD Private Property Inflow and Infiltration &
LSL Replacement Project
5. Discussion/Approval regarding the 2028 Watermain and Lead Service Line
Replacement Program
6. Department Status Report and Project Updates (See attached packet)
Cc: Village Board, Village Manager, Public Works Superintendent, Department Heads, Village Attorney
Posted: 11/6/2026
Note: It is possible that members and/or possibly a quorum of members of other governmental bodies of
the municipality may be in attendance at the above-stated meeting to gather information; action will not be
taken by any governmental body at the above-stated meeting other than the governmental body specifically
referred to above in the notice.
Public Works Committee Minutes
Monday, October 12, 2026, at 5:30 p.m.
1. Call to Order:
Chairperson Serebin called the meeting to order at 5:30 p.m.
Present: President Buckley, Trustee Haller, James Zess, Ben McGillicuddy,
Chairperson Serebin
Also Present: Matthew Collins – Public Works Director, Anna Christopherson –
Assistant Village Manager, Maxine Miller – Staff Engineer, Patrick McCarthy – Public
Works Superintendent, and Mustafa Emir, CJ Beyer and Andrew Ashley of Clark Dietz
2. Review and Approve Minutes of September 14, 2026 Public Works Committee
Meeting
PRESIDENT BUCKLEY MOVED TO APPROVE THE MINUTES, SECONDED BY
TRUSTEE HALLER. MOTION CARRIED 5-0.
3. Discussion/Recommendation Regarding the Storm and Sanitary Sewer
Improvement Study
Director Collins introduced the item, noting the study arose from the 2025 southeastern
Wisconsin storms, including the thousand-year storm, and follows the Village's practice
of developing infrastructure roadmaps integrated into the Capital Improvement Program.
Director Collins emphasized that the study was a collaborative effort across the
department — engineering, wet weather response and operations, and long-term
planning.
CJ Beyer of Clark Dietz presented the study highlights. The modeling drew on existing
XPSWMM models, Village and MMSD system data, and rainfall data, using a
conservative 6-hour, 10-year design storm in lieu of the ordinance standard of a 24-
hour, 10-year storm. Risk was assessed by basin using a 7-foot basement-backup
assumption rather than tied to any particular historical storm. Reviewing the MMSD
interceptor system, the consultants found no reason to believe the regional interceptor
was a primary contributor to localized basement backups, noting MMSD data showed
freeboard remaining during recent events, including the August 2025 storm of
approximately eight inches.
On the sanitary side, the risk map incorporates prior improvements — the Fairmont
Relief Sewer, Palisades lift station, and lining and I/I programs — and identifies the
center of the Village as a hot spot, consistent with 2015–2016 memos. Committee
members questioned this finding based on their experience of the 2010 and 2025
storms, when the most significant backups occurred south of Hampton Avenue. The
consultants explained that the assessment is uniform and math-based rather than
relative: prior southern improvements have reduced risk there, elevating the central
Village's relative risk, and a pipe can be hydraulically fragile even where damage has
not yet occurred. Staff added that reported-backup data was too scattered to serve as
an equitable basis for capital decisions, so recommendations are grounded in hydraulic
flow and elevation data. The study identifies three relief sewers in the central Village —
in south-to-north order, Henry Clay, Birch, and Lake View each conveying flow directly
to the MMSD line, with the Henry Clay project recommended first if a single project is
pursued. Similar relief sewers installed in Bayside and the City of Milwaukee have
produced favorable results.
Regarding interconnections and operations, of approximately 20 historically listed
sanitary/storm interconnections, field verification found 14 remain active, concentrated
on the north side. The study recommends installing or repairing backflow preventers
where freeboard between the two systems is shallow, establishing an annual inspection
and maintenance program, and addressing five or six of these as projects within the
next year. The Village currently has one level sensor and one flow monitor; the study
recommends an alarm at the priority risk area, flow monitoring at the second priority
area, and use of the wet weather response standard operating procedure included as a
report appendix, with an additional monitor to be considered in a future capital
improvement.
On the storm sewer side, the Village has seven basins — four draining to Lake
Michigan and three to the river. Key findings include inlet sizing and spacing (inlets
needed approximately every 300 feet on long blocks), non-standard gooseneck inlets to
be fixed when encountered on projects, and six local low points, including the Wilshire
and Beaumont areas. The Lancaster storm sewer, which was built but stopped short of
its outfall at a 42-inch sanitary sewer and was partly filled with concrete, is
recommended for completion with a siphon to leverage the pipe already in the ground.
For the Wilshire triangle in the southeast corner — where the storm sewer runs between
homes — the study presents options of an approximately $750,000 relief storm sewer
or approximately $1.2 million in storm water controls at the Bartlett green space, with
the relief sewer recommended first given resident attachment to the green space and
concerns about the historic railroad corridor there. Committee members identified the
Wilshire triangle as the Village's number one priority, citing August 2025 flooding of front
yards and basements, and concluded the Village has reached a tipping point where
storm drainage should be prioritized because resident impacts there now exceed those
of the priority sanitary areas. Staff agreed the Village need not shift entirely but can
stagger storm and sanitary projects holistically.
The report's recommendations section carries cost estimates for the items above — all
preliminary concepts with no design or engineering completed. Director of Public Works
Director Collins outlined next steps in two parts: operational items, including wet
weather SOPs ready by next season and bypass/backflow preventer work within the
next year funded within existing utility budgets; and capital items, with all
recommendations entering the CIP process — presentations beginning in 2027 for the
2028–29 borrowing, Village Board conversations beginning around June, design
engineering in fall/winter, and construction in 2028. The Committee also discussed the
report's value as a consolidated record of prior consultant work (approximately two
terabytes from nearly a dozen consultants), with staff identifying GIS as the long-term
repository for future boards.
MR. ZESS MOVED TO RECOMMEND TO THE VILLAGE BOARD TO ACCEPT THE
STORM AND SANITARY SEWER IMPROVEMENT STUDY, SECONDED BY
TRUSTEE HALLER. MOTION CARRIED 5-0.
4. Department Status Report and Project Updates
Director Collins reported that the contractor was rough grading Devon, with utility
adjustments occurring this week; the base course and binder coat are planned for
Thursday and the topcoat for Saturday, although he characterized that schedule as
optimistic based on-site conditions. Several areas with compromised, soft soil still
require excavation and remediation. If the contractor addresses those areas, the project
could be fully paved by Saturday; more realistically, completion is expected within
approximately the next eight days.
5. Adjournment
PRESIDENT BUCKLEY MOVED TO ADJOURN AT 7:18 P.M., SECONDED BY
TRSUTEE HALLER. MOTION PASSED 5-0.
Respectfully submitted,
Anna Christopherson
Assistant Village Manager
Village of Whitefish Bay Public Works Department
155 W. Fairmount Ave Whitefish Bay, Wisconsin 53217 (414) 962-6690 Fax (414) 967-1391
Mathew Collins, Director of Public Works
November 9, 2026
Memo to: Chairperson Serebin and Village of Whitefish Bay Public Works Committee
From: Matthew Collins, Director of Public Works
Re: Storm Sewer Outfall Rehabilitation Design Review
On February 17, 2025, the Village Board approved the contract for Mid City Corporation to inspect three of the Lake Michigan
outfalls and contiguous manholes, document existing conditions, and complete inspection reports including repair suggestions and
cost estimates. In April, 2025, Mid City performed the inspections of all accessible stormwater outfalls that discharge into Lake
Michigan with the exception of LM4 that has recently been rehabilitated. Mid City completed the analysis and presented their
findings within a report to the Public Works Committee on October 13th, 2025. The final report guided the Village with prioritizing
critical storm water utility maintenance and rehabilitation projects and capital budget planning.
The Village Board adopted a 6-year Capital Improvement Plan (CIP) that includes $200,000 in the 2026 budget for storm sewer
manhole lining and repairs. Some of the available CIP funds were leveraged to for the Village Board to approve engineering services
to allow for professional engineering services to complete design, field survey, utility easements, environmental impacts/permits,
and bid assistance for LM#1 rehabilitation as well as safety grate installations at LM#1 and LM#3.
Ruekert Mielke has completed their preliminary design scope of the LM#1 outfall and the LM#3 safety grates including evaluating
rehabilitation options for LM#1. Within the scope of services, Ruekert Mielke reviewed alternative techniques to rehabilitate the
outfall and apron of LM#1. To date, village staff and engineers have completed the preliminary site review, met with impacted
residents, and evaluated rehabilitation alternatives including construction access and costs.
LM#1 rehabilitation includes the following recommendations:
- Temporary and Permanent Easements
- Cured-in-Place Pipe (CIPP) Lining
- Geopolymer Manhole Lining
- Outfall Structure Replacement
Alternative rehabilitation activities may be considered including:
- Klode Park Beach Stabilization (assist with construction access to the north)
- CIPP Lining – Drop Manhole west to Lake Drive
MCC made recommendations to install a safety grate to the LM#3 outfall to prevent unwarranted access to the outfall. Due to long-
term monitoring and maintenance required to keep the grate clear of debris, accessibility would be a requirement for DPW staff to
routinely access the outfall. The only way to access the LM#3 outfall is through Silver Spring Park where no formal access path exists
and substantial erosion makes it difficult to traverse the site. Based on concerns with access, village staff and Ruekert Mielke
recommend placing warning signage on the outfall, but not to install safety grates at this time.
Village staff and Ruekert Mielke are seeking recommendations from the Public Works Committee to narrow the scope of work to
LM#1 and LM#3. Once the Public Works Committee agrees on the scope of construction activities, the design team will present the
final recommendations to the Village Board prior to finalizing design, easement documents, and budget estimates. It is anticipated
that the final plans, specifications, and easements will be completed by late 2027 with construction planned for 2028. Final project
budget estimates will be included within the 2028 – 2033 Capital Improvement Plan Storm Utility budget recommendations that will
be reviewed and adopted by the Village Board in 2027.
Refer to attached presentation for a complete overview of the proposed project scope and budg et estimates.
Village Staff Recommends to the Public Works Committee:
To recommend to the Village Board the proposed design and construction scope of the LM#1 storm sewer outfall.
VILLAGE OF WHITEFISH BAY
STORM SEWER REHABILITATION
PROJECT UPDATE
11/9/2026
• Review recommendations from July 2025 Inspection Report
• LM1 Storm Sewer Rehabilitation
• Easement Acquisition
• Alternative Overview & Cost Estimates
• Recommended Alternative
• LM3 Outfall Safety Grate
• Project Schedule & Next Steps
Overview
Recommendations from July 2025 Inspection Report
LM1
Repair/replace approximately 50-feet of 48”
storm sewer tunnel immediately west of
outfall structure
Repair outfall structure
LM1
LM3 Install safety grate at outfall structureLM3
LM1 Storm Sewer & Outfall Structure
• LM1 storm sewer and outfall is located on private
property north of Klode Park
• Outfall structure is in failure
• A drop manhole structure is located mid-yard along the
property line between 5960 & 6000 N. Shore Drive
• Structure is in fair to good condition
• 84-feet deep
• 48” storm sewer tunnel condition:
• 50-feet immediately west of outfall structure is in failure
• Severe deterioration
• Missing sections
• Radial and longitudinal cracks
• Remaining pipe to mid-yard manhole is in fair condition:
• Ground water infiltration
• Minor cracks
• Pipe from drop manhole to manhole in intersection of Lake
Drive and Montclaire Avenue:
• Ground water infiltration
• No significant structural deficiencies noted
LM1 Storm Sewer Easements
• No recorded easements for the properties adjacent to the LM1 storm sewer and
outfall have been located
• 9/15/2026 - Letters sent to property owners of 5960 & 6000 N. Shore Drive to
provide project information and request meeting to discuss proposed easements
• 10/2/2026 - Met with residents to discuss project and proposed easements
• Property owners expressed interest in having work completed comprehensively to minimize future risk of
the storm sewer failing & impacts to the properties
• Proposed easements to acquire include:
• Permanent Storm Sewer Easement on 6000 N. Shore Drive
• Temporary Construction Easement on 5960 N. Shore Drive
• Permanent Access Easement on 5960 N. Shore Drive along the beach
LM1 Storm Sewer Easements
LM1 Storm Sewer
Rehabilitation
Alternatives
Overview & Cost
Estimates
• Outfall Structure Replacement
• Klode Park Beach Stabilization
• LM1 Storm Sewer Rehabilitation Alternatives
• Slipline & Open-cut replacement
• Geopolymer Mortar Lining & Open-cut
replacement
• Hand-mined Tunnel Pipe Installation
• Cured-in-Place Pipe (CIPP) Lining
• Drop Manhole Rehabilitation
• Geopolymer Manhole Lining
• Fiberglass Insert Manhole Lining
• Recommended Alternative
LM1 Outfall Structure Replacement
• Outfall structure is in failure and
cannot be rehabilitated due to:
• Degradation of concrete
• Exposure of reinforcing steel
• Replacement of outfall structure
will largely be in kind
* All estimated costs expressed in 2028 dollars
Item No. Item Description Unit Quantity Unit Price Cost
1 Mobilization and Access L.S. 1 80,000$ 80,000$
2 Remove and Replace Cast-in-Place Outfall Structure L.S. 1 108,000$ 108,000$
3 Klode Park Path Restoration S.Y. 500 100$ 50,000$
4 Erosion Control L.S. 1 32,500$ 32,500$
270,500$
68,500$
339,000$
LM1 Outfall Structure Replacement
Subtotal
Engineering, Administration, Legal, & Construction Contingency (25%, Rounded)
Total Estimated Rehabilitation Costs
LM1 Outfall Structure Replacement
• Construction access to be from Klode Park
• Permanent access easement from Klode
Park to outfall to be acquired from 5960 N.
Shore Drive
• Construction access within Klode Park
proposed to include permanent beach
stabilization (5:1 slope between jetties)
Item No. Item Description Unit Quantity Unit Price Cost
1 Heavy Riprap TON 1400 85$ 119,000$
2 Fine Sand TON 550 55$ 30,250$
149,250$
37,750$
187,000$
Klode Park Beach Stabilization
Subtotal
Engineering, Administration, Legal, & Construction Contingency (25%, Rounded)
Total Estimated Rehabilitation Costs
LM1 Storm Sewer Rehabilitation
Geopolymer Mortar Lining & Open-cut Replacement
• Geopolymer mortar sprayed onto pipe
to provide:
• Structural support
• Corrosion resistance
• 3-inch-thick mortar layer would be
required to provide required structural
support resulting in a 42-inch Diameter
pipe
• Existing deficiencies in the pipe would
require open-cut replacement of 50-feet
immediately west of LM1 outfall structure
• Pipe needs to be clean and dry to be able
to apply mortar
• Minimal work footprint:
• Excavation at drop manhole would not be
required
Advantages
• Minimal work footprint at
drop manhole
Disadvantages
• Reduced hydraulic capacity
of pipe
• Increased efforts needed to
have pipe clean and dry
Item No. Item Description Unit Quantity Unit Price Cost
1 Mobilization and Access L.S. 1 80,000$ 80,000$
2 Remove and Replace 48-inch CL V Storm Sewer L.F. 50 1,300$ 65,000$
3 Cast-in-Place Pipe Encasement L.F. 50 850$ 42,500$
4 Geopolymer Mortar L.F. 270 1,000$ 270,000$
5 Temporary Bypass Pumping L.S. 1 50,000$ 50,000$
507,500$
127,500$
635,000$
Subtotal
Engineering, Administration, Legal, & Construction Contingency (25%, Rounded)
Total Estimated Rehabilitation Costs
Geopolymer Mortar Lining
LM1 Storm Sewer Rehabilitation
Slipline & Open-cut Replacement
• Fiberglass reinforced polymer mortar
(FRPM) pipe installed within the
existing pipe and the annular space
would be grouted
• Existing deficiencies in the pipe would
require open-cut replacement of 50-
feet immediately west of LM1 outfall
structure
• Anticipated that a 41-inch Diameter
pipe would need to be installed
• Minimal work footprint:
• Excavation at drop manhole would be
required to remove casting and brick
chimney section
Advantages
• Minimal work
footprint at drop
manhole
Disadvantages
• Reduced hydraulic
capacity of pipe
Item No. Item Description Unit Quantity Unit Price Cost
1 Mobilization and Access L.S. 1 80,000$ 80,000$
2 Remove and Replace 48-inch CL V Storm Sewer L.F. 50 1,300$ 65,000$
3 Cast-in-Place Pipe Encasement L.F. 50 850$ 42,500$
4 41-inch FRPM Pipe (Slip Line) L.F. 270 1,600$ 432,000$
5 Cementitious Grouting of Annular Space C.Y. 30 540$ 16,200$
6 Temporary Bypass Pumping L.S. 1 26,500$ 26,500$
662,200$
165,800$
828,000$
Engineering, Administration, Legal, & Construction Contingency (25%, Rounded)
Total Estimated Rehabilitation Costs
Slipline with FRPM Pipe
Subtotal
LM1 Storm Sewer Replacement
Hand-Mined Tunneling
• Full replacement of the pipe from the
outfall to the drop manhole by hand-
mined tunneling due to depth
• A vertical shaft would need to be
excavated at the drop manhole to
connect the new pipe
• Substantially longer construction
duration compared to other
alternatives
Advantages
• Full pipe replacement
Disadvantages
• Cost
• Large construction
footprint and disruption to
properties
• Construction duration
Item No. Item Description Unit Quantity Unit Price Cost
1 Mobilization and Access L.S. 1 270,000$ 270,000$
2 Hand-mining 48-inch RCP CL V Storm Sewer L.F. 270 5,900$ 1,593,000$
3 Temporary Bypass Pumping L.S. 1 26,500$ 26,500$
1,889,500$
472,500$
2,362,000$
Hand-Mined Tunnel
Subtotal
Engineering, Administration, Legal, & Construction Contingency (25%, Rounded)
Total Estimated Rehabilitation Costs
• LM1 Storm Sewer Rehabilitation
Cured-in-Place Pipe (CIPP) Lining – Drop Manhole to Outfall
• Liner saturated with resin is inserted,
inflated, & cured within the existing
pipe
• 1.5-inch-thick liner would be required
to provide required structural support
resulting in a 45-inch Diameter pipe
• 50-feet immediately west of LM1
outfall structure would not need to be
replaced
• Minimal work footprint:
• Excavation at drop manhole would be
required to remove casting and brick
chimney section
Advantages
• Cost
• Minimal work
footprint at drop
manhole
Disadvantages
• Slightly reduced
hydraulic capacity
Item No. Item Description Unit Quantity Unit Price Cost
1 Mobilization and Access L.S. 1 53,000$ 53,000$
2 48-inch Storm Sewer CIPP Lining L.F. 270 1,300$ 351,000$
3 Temporary Bypass Pumping L.S. 1 26,500$ 26,500$
430,500$
108,500$
539,000$
Cured-in-Place Pipe (CIPP) Lining (Outfall to Drop Manhole)
Subtotal
Engineering, Administration, Legal, & Construction Contingency (25%, Rounded)
Total Estimated Rehabilitation Costs
LM1 Storm Sewer Rehabilitation
Cured-in-Place Pipe (CIPP) Lining – Drop Manhole to Lake/Montclaire Intersection
• CIPP lining from drop manhole to manhole in
the Lake/Montclaire intersection
• No significant structural deficiencies noted in pipe
presently
• Current groundwater infiltration may exacerbate
future structural issues
• Long-term & comprehensive solution
• Economy of scale
• Time value of money
• Contractor is mobilized
• Acquisition of temporary construction easements &
restoration
• Additional CIPP bid as Mandatory Alternate
Item No. Item Description Unit Quantity Unit Price Cost
1 48-inch Storm Sewer CIPP Lining L.F. 720 675$ 486,000$
486,000$
122,000$
608,000$
Cured-in-Place Pipe (CIPP) Lining (Drop Manhole to Lake/Montclaire Manhole)
Subtotal
Engineering, Administration, Legal, & Construction Contingency (25%, Rounded)
Total Estimated Rehabilitation Costs
LM1 Storm Sewer Drop Manhole Rehabilitation
• Drop manhole is in fair to good
condition
• Long-term & comprehensive solution
• Rehabilitation of manhole can be
completed by:
• Geopolymer lining
• Installation of fiberglass inserts (sliplining)
Item No. Item Description Unit Quantity Unit Price Cost
1 Mobilization and Access L.S. 1 10,800$ 10,800$
2 72-inch Geopolymer Manhole Lining V.F. 90 530$ 47,700$
3 Temporary Bypass Pumping L.S. 1 26,500$ 26,500$
85,000$
22,000$
107,000$
Geopolymer Manhole Lining
Subtotal
Engineering, Administration, Legal, & Construction Contingency (25%, Rounded)
Total Estimated Rehabilitation Costs
Item No. Item Description Unit Quantity Unit Price Cost
1 Mobilization and Access L.S. 1 53,000$ 53,000$
2 72-inch Fiberglass Insert Manhole Lining V.F. 90 970$ 87,300$
3 Temporary Bypass Pumping L.S. 1 26,500$ 26,500$
166,800$
42,200$
209,000$
Engineering, Administration, Legal, & Construction Contingency (25%, Rounded)
Total Estimated Rehabilitation Costs
Subtotal
Fiberglass Insert Manhole Lining
LM1 Storm Sewer & Outfall Recommended Alternative
Item Description Cost
LM1 Outfall Structure Replacement 270,500$
Klode Park Beach Stabilization 149,250$
Cured-in-Place Pipe (CIPP) Lining (Outfall to Drop Manhole) 430,500$
Cured-in-Place Pipe (CIPP) Lining (Drop Manhole to Lake/Montclaire Manhole) 486,000$
Geopolymer Manhole Lining 85,000$
Subtotal 1,421,250$
Construction Contingency (10%, Rounded) 143,500$
Engineering, Administration, Legal (15%, Rounded) 215,250$
Total Estimated Rehabilitation Costs 1,780,000$
LM1 Storm Sewer and Outfall
Recommended Alternative
LM3 Outfall
• LM3 storm sewer outfall is located
north of Silver Spring Park
• LM3 Outfall structure in good
condition
• Wooded path present from the
maintained park area east towards
the outfall structure
• 20-foot vertical drop in grade just
above the outfall structure
LM3 Outfall
• Installation of a safety grate would:
• Prevent persons from accessing
the storm sewer
• Require long-term monitoring &
maintenance
• Access improvements needed to
install and maintain the safety grate
• Current recommendation is to not
install the safety grate
• Warning signage may be added in the
future
Project Schedule & Next Steps
11/9/2026
Update to Public Works
Committee
12/31/2026
Biddable Plans &
Specifications Completed
2027
Easement Acquisition and
Permitting
Late 2027
Bidding
8 weeks
2028 Construction
Questions?
Village of Whitefish Bay Public Works Department
155 W. Fairmount Ave Whitefish Bay, Wisconsin 53217 (414) 962-6690 Fax (414) 967-1391
Mathew Collins, Director of Public Works
November 9, 2026
Memo to: Chairperson Serebin and Village of Whitefish Bay Public Works Committee
From: Matthew Collins, Director of Public Works
Re: Private Property Infiltration and Inflow (PPII) Project Updates
In May, 2025, the Public Works Committee and Village Board approved new Private Property Infiltration and Inflow
(PPII) Reduction Program guidelines for homeowners to participate with the MMSD program. Within Priority Area
#1, there are over 100 properties that have been identified with public and private lead service lines (LSLs) . The
program had 63 properties originally sign up to participate with the joint PPII/LSL program with 30 completed in
2026. Of the 63 properties, nine homeowners later declined to move into construction. The original goal of the
2026 program was to complete a total of 33 properties based on available MMSD and Water Utility funds
available.
A lottery system was used to select the properties for participation in the 2026 PPII program. Properties that
signed up for the program that were not completed in 2026 were placed on the waitlist and are considered
turnkey construction in 2027 since design has already been completed. In October, the Village was notified by
MMSD that $500,000 in construction funds will be awarded to continue efforts with the PPII program to replace
sanitary sewer laterals. The funding will allow for approximately 20 properties to be completed in 2027.
The Village adopted the the 2026 – 2031 Capital Improvement Plan that supported the funding to replace lead
service lines in conjunction with the PPII program. The total funding for the public LSL replacement for 2026 -2027
is $420,000. The anticipated cost of the 2026 LSL replacements is $275,000 leaving a remaining balance of
$145,000 for the replacement of public LSLs in 2027. This would allow for approximately 17 properties to have
their LSLs replaced if construction and engineering services do not exceed $8,500 per public LSL replacement.
Given that there are 22 properties that remain on the waiting list that have been fully designed, it is recommended
to complete the remaining waitlist properties in 2027. There will likely be residents that choose to dropout of the
program, so the total number of replacements will be close to the available budgets. Once all properties have been
completed that have shown a willingness to participate with the program, village staff will evaluate the program to
make further recommendations to the Public Works Committee and Village Board on future PPII programs beyond
2027.
Once MMSD finalizes the 2027 Funding Agreement, village staff will make formal recommendations to the Village
Board for the 2027 PPII program.
Informational Only – No Action Required by the Public Works Committee
Village of Whitefish Bay
MMSD Sanitary Lateral Program and Lead Water Service Line Replacements
Whitefish Bay Public Works Committee Meeting: November 9 th , 2026
AGENDA
2
› Quick Recap of Program Goals
– 2025 Design (Completed)
– 2026 Construction (Ongoing / Wrapping Up)
– 2027 Construction (Future)
› Lessons Learned
› Funding
› Open Discussion / Next Steps
PROGRAM OVERVIEW
Program Goals:
› General:
– Replace 70 LSLs & 70 Sanitary Laterals.
• 2026: 35 Replacements
• 2027: 35 Replacements
› Village:
– Replace lead water services lines.
› MMSD:
– Remove Inflow and Infiltration (I&I) from
private sanitary sewer laterals.
› Homeowner:
– Remove Lead Water Service Lines..
– New Sanitary Sewer Lateral.
3
Program Criteria:
› Must Be:
– Located within project area
– Willing to participate
› Must Have:
– Private Lead Water Service
– Public Lead Water Service
– I&I present in Sanitary Lateral
2025 DESIGN OVERVIEW
4
2026 CONSTRUCTION OVERVIEW
5
2026 CONSTRUCTION: STATUS
6
# Address (Constructed 2026 Project)
1 4610 N Idlewild Ave
2 4768 N C umberland Blvd
3 4753 N Larkin St
4 4616 N Sheffield Ave
5 1606 E C umberland Blvd
6 4630 N Morris Blvd
7 1550 E C umberland Blvd
8 4616 N Bartlett Ave
9 1628 E C umberland Blvd
10 4624 N Newhall St
11 4633 N Larkin St
12 4664 N Morris Blvd
13 4765 N Woodburn St
14 1700 E C umberland Blvd
15 4750 N Larkin St
16 4759 N Larkin St
17 4792 N Ardmore Ave
18 4610 N Morris Blvd
19 1100 E C ourtland Pl
20 4620 N Newhall St
21 4621 N Bartlett Ave
22 1107 E C ourtland Pl
23 4614 N Morris Blvd
24 4634 N Woodruff Ave
25 4798 N Ardmore Ave
26 4651 N Larkin St
27 4615 N Newhall St
28 4617 N Morris Blvd
29 4613 N Morris Blvd
30 4744 N Larkin St
31 4633 N Morris Blvd
32 4737 N Larkin St
Address (Drop Out 2026 Project)
1 4791 N Woodburn St
2 1221 E C ourtland Pl
3 4627 N Bartlett Ave
4 4633 N Bartlett Ave
5 4782 N C umberland Blvd
6 4786 N Ardmore Ave
7 4629 N Marlborough Dr
8 1584 E C umberland Blvd
9 4611 N Newhall St
Address (2027 Project - On Waitlist)
1 4626 N Bartlett Ave
2 1614 E C umberland Blvd
3 4643 N Wildwood Ave
4 4632 N Bartlett Ave
5 4777 N Woodburn St
6 4722 N Ardmore Ave
7 4658 N Morris Blvd
8 4659 N Ardmore Ave
9 4700 N Sheffield Ave
10 4767 N Larkin St
11 4626 N Larkin St
12 4617 N Larkin St
13 4657 N Woodburn St
14 4627 N Larkin St
15 4746 N C umberland Blvd
16 4732 N C umberland Blvd
17 4620 N Bartlett
18 4758 N Larkin St
19 4610 - 4612 N Larkin St
20 4610 N Newhall St
21 4659 N Morris Blvd
22 4628 N Newhall St
2026 Construction:
32 Homes Completed
(Varying Scopes of Work)
2026 Construction:
9 Homes Dropped out
Residents on the Waitlist:
22 Homes
2026 CONSTRUCTION: PHOTOS
7
2026 CONSTRUCTION: PHOTOS
8
2026 CONSTRUCTION: PHOTOS
9
2026 CONSTRUCTIONL: LESSONS LEARNED
10
› Lessons Learned: Homeowner
– Finished basements
– Separated sanitary and water services
– Electrical grounding
• Plastic vs. Copper Water Services
– Internal plumbing needs
› Lessons Learned: Village / MMSD
– Lead service line cost share with Homeowner (PSC)
– Road impacts
– Tree impacts
– LSL Records
› Steps Forward
– Pre-Construciton Home Visits
• Verifying Records and Home Impacts
– Continue to Improve Bidding Documents
FUNDING OVERVIEW
11
ORIGINAL
BUDGET
2025 2026 2027 BUDGET TOTAL # OF HOMES BUDGET COST PER
EACH HOME
WHITEFISH BAY $0 $210,000 $210,000 $420,000 70 $6,000
MMSD $222,500 $929,455 $500,000 $1,651,955 70 $23,599
HOMEOWNER $0 $210,000 $210,000 $420,000 70 $6,000
2027 BUDGET BUDGET COST PER
EACH HOME # OF HOMES 2027 GOAL
WHITEFISH BAY $145,000 $8,500 17.1 20
MMSD $500,000 $25,000 20.0 20
HOMEOWNER $210,000 $8,000 26.3 20
2026 ENGINEERING CONSTRUCTION ALL IN (TO DATE) TOTAL # OF H OMES COST PER EACH HOME REMAINING BUDGET
(+/-)
WHITEFISH BAY $30,000 $245,000 $275,000 26 $10,600 $145,0 00
MMSD $124,900 $700,000 $824,900 30 $27,500 $500,000
HOMEOWNER $22,000 $50,000 $72,000 26 $2,800 $210,000
NEXT STEPS / OPEN DISCUSSION
12
› Original Goal: Replace 70 LSLs/Sanitary Laterals.
– Engaged over 100+ Homes
– 63 Participants
› 2026 Original Goal: 35 Replacements
– MMSD Funded: 33 Sanitary Laterals
– 2026 Completed: 30 Sanitary Laterals
– 2026 Completed: 26 Lead Water Services
› 2027 Original Goal: 35 Replacements
– MMSD Funded: 20 Sanitary Laterals
– Complete the waitlist homes: 22 Homes Currently
– Revised Goal: 20 Sanitary Laterals & 20 Lead Service Lines
› Final Anticipated Program: Replace 50 LSLs/Sanitary Laterals.
› 2028+ Goals:
– Revisit Future Sanitary Lateral Program Goals
• Leverage Village Capital Projects?
• Village’s LSL Replacement # per year?
• Standalone MMSD Projects?
– Continue Engaging MMSD for Funding Opportunities
https://arcg.is/115C04
Project Website
Village of Whitefish Bay Public Works Department
155 W. Fairmount Ave Whitefish Bay, Wisconsin 53217 (414) 962-6690 Fax (414) 967-1391
Mathew Collins, Director of Public Works
1 | Page
Memo to: Chairperson Serebin and Village of Whitefish Bay Public Works Committee
From: Maxine Miller, Staff Engineer
Re: 2028 Watermain, Water Service Line Replacement Proposed Project Locations
Starting in 2028, the Village will be mandated to replace 188 lead water service lines annually to meet
EPA and DNR Lead and Copper Rule Improvement (LCRI) requirements. To meet this obligation while
continuing to improve the Village's water distribution system and roadway infrastructure, village staff
conducted a comprehensive evaluation of roadway segments throughout the community to identify the
most suitable locations for coordinated watermain replacement, water service line replacement, and
street resurfacing projects.
DPW staff reviewed Village maps, historical infrastructure records, and roadway data. Several factors
were considered as part of the evaluation, including:
• Number of confirmed public and private lead water service lines connected to each watermain
• Street condition
• Age and material of existing watermains
• Frequency and dates of watermain breaks
• Overall project constructability and coordination of infrastructure improvements
Based on this evaluation, staff identified the following two roadway segments as the highest priorities
for the 2028 construction program:
• N. Kent Avenue: E. Devon Street to E. Lakeview Avenue
• N. Cumberland Boulevard: N. Lake Drive to E. Hampton Road
By 2028, the pavement condition of these roadway segments is projected to have an average rating of
approximately 4 to 5 on the 10-point PASER pavement rating scale, further supporting the coordination
of underground utility improvements with street resurfacing. Upon completion of the watermain and
LSL replacements, each street will be fully resurfaced.
The proposed project areas provide an opportunity to replace a significant number of lead water service
lines while coordinating improvements with the planned watermain and roadway work. The following
table summarizes the existing water service line inventory within the proposed project limits:
2 | Page
Water Service Line Classification Number of Properties
Non-Lead service line on public and private 12
Lead service line on public side only 29
Lead service line on private side only 12
Lead service lines on both public and private sides 145
Total lead service lines to be replaced 186
Total properties served within project area 198
The proposed 2028 project would result in the replacement of approximately 1.08 miles of watermain
and 186 lead service lines. In addition, the Village typically replaces an average of 25 resident-initiated
or service line breaks annually outside of watermain replacement project limits. Together, these efforts
would allow the Village to achieve its annual requirement of 188 lead service line replacements in 2028.
Prior to construction, DPW staff will conduct a comprehensive inspection of existing utility infrastructure
within the proposed project limits and complete any necessary repairs to minimize future disruptions
and avoid unnecessary roadway restoration.
Additional project coordination and evaluations will include:
• Sanitary Sewer Infrastructure: Continue annual sanitary sewer inspections and identify
opportunities for necessary repairs and lining.
• Stormwater and Flooding: Review the Village's stormwater and sanitary sewer studies and flood
risk assessment to identify recommendations applicable to the proposed project areas.
• Pedestrian and Bicycle Facilities: Review the Village's pedestrian and bicycle study to identify
potential improvements or recommendations that can be incorporated into the projects.
• Geotechnical Investigation: Obtain geotechnical samples to evaluate existing subsurface soil
and pavement conditions and assist with determining appropriate roadway reconstruction and
resurfacing methods.
These evaluations will help ensure that the proposed projects address not only immediate water
infrastructure needs but also other long-term infrastructure and transportation priorities within the
project areas. Refer to attached map for the proposed 2028 watermain and LSL program area.
Village Staff Recommends to the Public Works Committee:
To recommend approval of the proposed 2028 project locations for the annual watermain and LSL
replacement program area.
2028 Watermain Replacement and Street Resurfacing Map
Watermain Replacement, Water Service Line
Replacements, and Street Resurfacing
Street Resurfacing Only
DRAFT
Village of Whitefish Bay Public Works Department
155 W. Fairmount Ave Whitefish Bay, Wisconsin 53217 (414) 962-6690 Fax (414) 967-1391
Mathew Collins, Director of Public Works
1 | P a g e
Public Works Committee
Status Report for November 2026
Note: New status updates are in red text.
5111 N. Lydell Ave. Public Works Site:
• Project Budget: $590,000
• Engineer/Contract: Sigma/$29,800
• Current Phase: Rezoning & Environmental Assessment
• Target Completion: Winter, 2025/2026
Project Overview: Sigma had completed a Phase I and Phase II report for the Department
of Public Works (DPW) site located at 5111 N. Lydell located in Glendale. The purpose of
documents included a Focused Environmental Site Assessment (ESA) a condensed Property
Condition Assessment (PCA), site survey, existing building repair planning, design
development of salt storage facility, and site planning/civil engineering, and municipal
interviews to determine the feasibility of shared use within neighboring communities.
Sigma is currently under contract to assist with the Phase II Environmental Site Assessment
(ESA) and undergo a rezoning application with the City of Glendale to receive approvals for
the proposed facility site plan construction activities.
The Phase II ESA has been completed by Sigma. Based on the results of the report, it will be
necessary to notify the results with the DNR that will likely trigger further site investigations
and potential soil remediation efforts.
The Village Board approved the MOU with the City of Glendale and Village of Shorewood
on 5/4/26 for the planning, development, and shared use of a salt storage facility. The
timeline for the shared salt storage facility includes design and construction contracts by July
to be considered by the Village Board with final completion of the facility by December,
2026.
The Phase II Environmental Site Assessment (ESA) activities were completed in
summer/fall 2025 which included the advancement of soil borings, installation of temporary
groundwater monitoring wells, and the collection of soil and groundwater samples. The
Phase II activities were completed to evaluate the potential presence of impacted soil and
groundwater at the Site based on Recognized Environmental Conditions (RECs) identified
within a Focused Phase I ESA completed in 2023. Considering the detected impacts, Sigma
2 | P a g e
recommended the preparation of a release notification in accordance with the Wisconsin
Hazardous Substance Spill Law.
The existing cold storage/salt storage facility located at 5111 N. Lydell had an existing roof
analysis completed to develop potential roof system options. The inspection and core
samples were taken to evaluate options for roof maintenance and found that the roof will
require a full replacement due to saturated decking below the existing roof membrane.
Design is anticipated to be completed in fall with bidding to occur late 2026. Construction is
planned for 2027.
Glendale is currently constructing a new salt storage facility with capacity for Whitefish Bay
and Shorewood. All three municipalities entered into an agreement to have a shared salt
storage facility to help with future storage and operational needs. DPW met with Glendale
and Shorewood to review salt loading and operating procedures in October. The new salt
storage facility is expected to be completed in December, 2026. DPW will deplete the salt
from the current 5111 N. Lydell site during the winter of 26-27 and then transition to
Glendale in 27-28.
Phase II Environmental Site Assessment (ESA) activities were completed in summer/fall
2025 which included the advancement of soil borings, installation of temporary groundwater
monitoring wells, and the collection of soil and groundwater samples. The Phase II activities
were completed to evaluate the potential presence of impacted soil and groundwater at the
Site based on Recognized Environmental Conditions (RECs) identified within a Focused
Phase I ESA completed in 2023. Based on review of the results of the Phase II ESA soil and
groundwater analytical results the Village prepared and submitted a release notification in
accordance with the Wisconsin Hazardous Substance Spill Law. Next steps will include site
and field investigation activities per DNR requirements.
Ash Tree Replacement, Planting & Treatment Annual Program
• Project Budget: $215,000
• Engineer/Contract: Wachtel Tree Science/$35,000
• EAB Removal/Planting Contractor M&M Tree Care/146,304
• EAB Injection Contractor Crawford Tree & Landscape Services/$28,256
• Current Phase: Construction
• Target Completion: Summer, 2026
Project Overview:
In 2010, the Village’s street trees consisted of 47% ash. As of 2022, the ash tree population was
reduced to 24% due to the Village’s adopted annual ash tree replacement and treatment program.
This program aids in the incremental replacement and diversification of street trees to limit the risk
of the EAB and impact of future tree diseases. At the end of 2026, the Village will have 1,565
remaining ash trees, roughly 18% total street tree population. In July, 2024, the Village adopted a
policy to reduce the total ash tree population to 10% by the end of 2031. The Village is on target to
meet this objective with the removal and replacement of 105 ash trees per year.
3 | P a g e
The Village has five years of removals remaining meet the 10% ash tree population goal. A total of
1,040 ash trees will remain in the Village and will continue to be treated to the end of the ash trees
natural lifespan. This amounts to a remaining 525 trees to be removed at 105 trees per year as in past
practice. Based on these known goals, it was determined to best align the EAB treatment program
with the removal program. Currently, the Village treats ash trees once every three years. This is still
the recommended treatment schedule from the Village’s arborist consultants.
Village staff worked alongside arborist/consultants to proactively identify 525 ash trees that will be
part of the next five year removal plan. Based on research and past practice, consultants are
comfortable with removing these 525 trees from the EAB treatment program and will no longer be
selected for insecticide treatments. These trees have been previously treated and the insecticide will
support tree health until the planned removal occurs over the five year period. In the 2026 program
year, the Village will reduce the treatment from 248 ash trees. This is an estimated cost savings of
$18,710 in treatments in 2026. Over the next five years, it is anticipated that the Village will save
$83,000 - $97,000 in treatments with the removal of the 525 ash trees from the EAB treatment
program.
The 2026 street tree replacements will be funded through the MMSD program’s remaining grant
funds. Due to lower than expected bid results from the 2025 program, the Village was able to
leverage $72,000 from this grant to fund the 2026 street tree replacements.
All ash tree replacements have been planted per plan.
Fall tree replacements are set to replace approximately 70 street trees as well as new trees donated by
the Little League at Craig Counsell Park will start in early November. Plantings are expected to be
completed by mid-December.
Bicycle and Pedestrian Safety Improvements
• Project Budget: $35,000 – 2026 Roadway Safety Funds
• Project Budget (Construction): $200,000
• Contractor N/A
• Current Phase: Temporary & Permanent Improvements
• Target Completion: 2026
The Village Board accepted the Bicycle and Pedestrian Safety Study on April 7, 2025 that includes
• Public Involvement & Findings
• Data Collection & Findings
• Safety Analysis
• Recommendations
o Short-Term & Long-Term Street Improvement Recommendations
o Traffic Calming Policy Recommendations
o Law Enforcement Recommendations
4 | P a g e
o Street Lighting Evaluation
• Bicycle & Safety Education Program Recommendations
• Funding Options
Village staff created a webpage for residents to review the Study and ongoing projects:
https://www.wfbvillage.gov/435/7262/Village-Wide-Bike-Pedestrian-Safety-Stud
In addition to the permanent improvements, the Public Works Committee gave village staff the
recommendation on additional temporary traffic calming locations. These locations were chosen
based on the Safe School Zone TAP grant project:
The following projects are planned for 2026:
1. Safe School Zone Signage Improvements (2026 – 2027)
a. JCC School Zone Area Complete including updated signs and new dynamic speed
feedback signage
b. Lake Drive – Replace/modernize existing overhead school zone signs (Richards
Elementary School) – New overhead signs ordered.
2. Safe School Zone Intersection Improvements (Design in 2026: Construction 2027)
a. 90% design complete. Construction administrative services approved by the Village
Board on 10/5/26. Project on schedule to be constructed in 2027.
3. Lake Drive and Beaumont: RRFB, curb extensions, and pedestrian refuge on Lake Drive
a. Feature substantially complete.
4. Silver Spring Dr. & Hollywood Ave.: Curb Extension & Pedestrian Median
a. Feature substantially complete.
5. Silver Spring Dr. & Consaul Pl./Diversey Blvd.: New traffic signals
a. New curb ramps substantially complete. New electrical conduits, utilities, and signal
cabinet will be ready for new traffic signal installation. Light poles that will be used
with the traffic signals have been ordered but have a long lead-time for delivery.
Signals are expected to be installed in late November, 2026.
6. Marlborough & Colfax: Permanent traffic calming installations
a. 7Complete.
7. Santa Monica and Belle: Temporary Traffic Calming per proposed Safe School Zone design
a. Temporary delineators installed
8. Santa Monia and Day: Temporary Traffic Calming per proposed Safe School Zone design
a. Temporary delineators installed
9. Hampton and Ardmore: Temporary Traffic Calming per proposed Safe School Zone design
a. Temporary delineators installed
10. Traffic Calming Policy: Draft a traffic calming policy for response to resident requests
Whitefish Bay participated with Milwaukee County’s Safe Streets for All grant that was submitted in
May. Whitefish Bay requested a total of $2,000,000 in project funding (80/20 split) for Lake Drive
gateway/traffic calming features as outlined in the Village Wide Bicycle & Pedestrian Safety Study
5 | P a g e
(page 53). Milwaukee County applied for a total of $25,000,000 in funding requests as part of the
grant application. The Village’s consultant, raSmith developed concepts and budget estimates for
each of the proposed project locations that were presented to the Public Works Committee on June
8th for comments, feedback, and recommendations. These concepts and budget estimates will be
used to further apply for grant funding as well as utilized to develop demonstration sites to evaluate
the effects of the features temporarily prior to final design or implementation.
Hampton & Santa Monica Intersection Traffic Signal Replacement & Safety
Improvements:
• Project Budget: $1,543,487
• Designer/Contract: Strand/$186,360.93
• Contractor/Contract: TBD
• Current Phase: Design Contracts
• Target Completion: Design, 2026 – Construction, 2028
Project Overview:
The Village has applied for and received Highway Safety Improvement Program 90% funding
from the Wisconsin Department of Transportation (WisDOT) for complete intersection traffic
signal replacement and safety improvements within the intersection of Hampton and Santa
Monica. The intersection has experienced a history of severe crashes. Nine crashes have
occurred at this intersection in the five-year period from 2019 through 2023, including one
involving a pedestrian. Traffic signal poles have also been struck four times as well as the Village
median sign struck two times in the past five years. There are many contributing factors to the
frequency and severity of the crashes, including the lack of protected left-turning movements,
older traffic signal equipment, no signal heads present over the northbound and southbound
lanes, and signal poles being in the medians on the north and south legs. For pedestrians, there
are no high-visibility crosswalks and the curb ramps are not up to ADA standards. WisDOT
HSIP funding was granted based on the high accident rate at this intersection as well as age of
current infrastructure and other safety factors.
The project scope will include updates to traffic signals, including new poles to provide signal
heads with retro-reflective back plates over each approach lane, install new controller/cabinet,
install new video vehicle detection, install audible push buttons, install new emergency vehicle
preemption, and replace all conduit/wiring/pull boxes. It is also proposed to add left-turn
protection to all left-turn movements via new left-turn signal heads. Signal heads with flashing
yellow capabilities are requested because they can operate in protected-only mode, as proposed,
but offer more flexibility for accommodating future travel demands and incorporating features
like adaptive protected phasing for pedestrians. Geometric improvements include pavement
repair, friction treatment via concrete grooving, and curb bumpouts (where feasible) with ADA
compliant curb ramps and high-visibility crosswalks.
6 | P a g e
The intersection of Hampton and Santa Monica border the Village of Whitefish Bay and the
City of Milwaukee municipal boundaries. Seventy-five percent of the intersection is within the
Village and twenty-five percent (southwest corner) is within the City of Milwaukee. The Village
and the City have a MOU that that agreed to terms of design, construction, maintenance, and
cost share. The updated MOU allows for the Village and the City to work together to modernize
the intersection and allow both municipalities to cost share the HSIP grant.
Village staff received final authorization for expenditures from WisDOT to start on the design
phase of the intersection improvement project. Village staff drafted and submitted a Request for
Proposals (RPF) to qualified design firms on September 30th. RFPs are due on Friday, October
24th and will then be evaluated and ranked prior to making recommendations to the Public
Works Committee, Village Board, and WisDOT. Once a firm is approved, design work will
kickoff in late 2025 and is expected to continue throughout 2026.
The Village Board approved the draft design and engineering services agreement to Strand
Associates on February 2nd. The final agreement has been signed by WisDOT allowing for
design work to begin. Strand gathered traffic counts in April including the installation of
temporary cameras within the intersection. Survey activities occurred the week of April 13 – 17.
The design kick-off meeting was on April 17th to further review design goals with the municipal
stakeholders (City of Milwaukee, WisDOT, and Village). The Operational Planning Meeting was
conducted in May with all necessary stakeholders.
A Public Information Meeting occurred on Wednesday, June 24th from 5 – 7pm at the Whitefish
Bay Library. Representatives from the Whitefish Bay Department of Public Works and the
engineering design consultant were available to discuss the proposed project and address any
questions or concerns. Project-related sketches and three concepts were displayed at the
meeting. Strand Associates presented the three concepts and public input during the July Public
Works Committee meeting
Draft concepts were presented to the Village Board on 8/31/26. Board comments and
stakeholder feedback will be evaluated to develop final design recommendations. Real estate
meetings for temporary limited construction easements started in October and will continue
through 2027.
Klode Park Warming House Redevelopment:
• Project Budget: $1,500,000
• Designer/Contract: TBD
• Contractor/Contract: TBD
• Current Phase: Request for Proposals
• Target Completion: Design, 2026 – Construction, 2027
7 | P a g e
Project Overview: On August 7th, 2023, the Village Board and Public Works Committee adopted
the 2024 - 2028 Comprehensive Outdoor Recreation Plan (CORP). The CORP created the
framework for the Village to develop a strategic plan to optimize outdoor park and recreation spaces
which was then integrated into the Village Board’s adopted 2026 – 2031 Capital Improvement Plan
(CIP). These guiding policy documents are used to aid in the strategic planning and prioritization of
public infrastructure projects.
As part of the CIP public meetings held in 2025, the Village Board made the request to include $1.5
million into the 2027 budget to support improvements to the Klode Park Warming House. The
existing Klode Park warming shelter functions as a year-round facility that includes two single stall
restrooms and a small gathering place. The facility is heated to accommodate for winter activities
including ice skating when weather allows.
Based on the goal to construct the warming house in 2027, there is a need to start design in 2026.
Village staff created a Request for Proposals (RFP) with submissions due on March 27th, 2026.
After village staff reviews and ranks the RFP submissions, the final recommended design firm
proposal will be presented to the Public Works Committee and Village Board in April, 2026.
Meetings with key stakeholders occurred with neighbors as well as a Focus Group with
representatives attending from the Village Board and Civic Foundation. Two a additional public
meetings included a Kids Charrette and an Open House Public Meeting. These meetings helped the
design team build the framework on the three concepts based on the vision, goals, challenges, and
opportunities for the warming house and band shelter. These concepts were then shared with the
public to create a survey to gain additional feedback and opinions to narrow the direction of the
proposed new warming house and band shelter/pavilion.
The Village Board reviewed public survey comments and feedback to narrow the Klode Park
warming house design to one concept. The project concepts were presented to the Architectural
Review Commission on 10/15/26 and approved on 11/5/26. Village staff met with stakeholders on
11/2 to review the site plans and verify special events and recreational activities layouts. The design
team will transition to design development with final plans presented to the Village Board on
November 16th. The anticipated construction documents are planned to be completed by mid-
December.
Library Boiler Replacement:
• Project Budget: $240,000
• Engineer/Bid Assistance Clark Dietz/$31,600
• Contractor: Southport Mechanical, LLC/$199,249
• Current Phase: Construction
• Target Completion: Fall, 2026
8 | P a g e
Project Overview: The Library boilers were installed in 1999 with numerous repairs required over
the years, but the system runs inefficiently and is at the end of its useful life. The risk of not
replacing the boilers will result in higher expenses for emergency repairs or necessary emergency
replacements.
A project design kick-off meeting occurred on January 15th to review existing mechanical equipment
and controls to start on design scope of the boiler replacement project. A focus will be on energy
efficiency with the design and specifications of a new boiler system to continue to reduce energy
costs. The project was awarded to Southport Mechanical with contracts anticipated to be completed
in early June.
The boiler replacement project is substantially complete. Boiler startup and training occurred on
9/9/26. Final punch list items are ongoing.
Lead Service Line Replacement Development Plan:
• Project Budget: $50,000
• Engineer/Contract: City Water, LLC/$40,500
• Current Phase: Study
• Target Completion: 2025/2026
Project Overview: The Village along with all US municipalities are required by the US EPA
to submit a Lead Service Line Replacement Plan (LSLRP) in accordance with Lead and
Copper Rule (LCR) revisions. On October 30th, 2024, the EPA finalized the Lead and
Copper Rule Improvements (LCRI). These updates were shared and presented during the
Village’s Open House event held on 12/2/24. Residents can review lead service line
information on the Village’s webpage: https://wfbvillage.gov/439/Lead-Service-Line-
Replacement-Project
City Water was hired by the Village to create a material inventory of water mains, services,
and private laterals to comply with the LSLRP deadline of October, 16 2024. The current
project scope by City Water will include a development plan for replacements of lead service
lines (LSL), assist in development of a customer outreach program, identify potential private
funding sources, identify and recommend any ordinance changes, develop standards for
replacement/construction, prioritize replacement of LSLs, and develop investigation
protocols and procedures in the event of a sample result above the action lead level.
The North Shore Water Commission is responsible for the coordination of lead and copper
sample collections used for regulatory compliance. In addition, the Commission manages
and monitors a corrosion control inhibitor called orthophosphate to reduce the amount of
lead and copper that can leach from pipes and plumbing materials owned by member
municipalities and their property owners. Over the years, the Commission has participated in
a number of research projects to optimize corrosion control. In 2022, the Commission
9 | P a g e
completed its latest corrosion control optimization study and was authorized by WDNR to
implement the recommendations from that study. As a result, the Commission increased the
level of its corrosion inhibitor from 1 part per million (ppm) to 3 ppm. After the study
officially concluded, plant staff monitored water quality, and the monitoring showed, and
continues to show, that 3.0 ppm of orthophosphate effectively reduces lead and copper
corrosion. The Village continues to be in compliance with all lead and copper levels.
Additional details can be reviewed as part of the 2025 Annual Water Quality Report.
City Water is contracted to assist the Village with the following consultation services:
o Service Line Inventory – Completed (2024 & 2025)
https://www.wfbvillage.gov/DocumentCenter/View/3004/Lead-Line-Inventory-
o Customer Outreach
▪ Community webpage - https://wfbvillage.gov/439/Lead-Service-Line-
Replacement-Project
▪ Utility Policies/standards – Ongoing
▪ Assistance with ordinance changes – Completed. On August 10, 2026 the
Village approved Ordinance No. 1929 establishing a private lead service line
replacement program and establishing a financing program
▪ How to identify a lead service line –New webpage & Contact Us page
(above)
▪ Customer Notification Letters – Completed
• Annual lead service line material mailings
• Anticipated new sampling procedures
o Financial Plan
▪ Private/Public Options – Completed – 10-year loan program adopted by
Village Board as part of the service line replacement special charge program.
▪ Lead Service Line Replacement Plan – Completed. Updates will occur
annually to determine locations of 1-mile of watermain and LSL replacement
areas.
o Standards for replacement/construction – PPII & LSL replacements ongoing for
2026. Design for the 2027 watermain & LSL replacements are 90% complete with
bidding set for November, 2026.
o Sampling
▪ Investigation protocols and procedures – Site monitoring plan for 2026 was
approved by the DNR. Test kits are sent out to select residents bi-annually
(2x per year).
o Final reports
Questions regarding the subject of lead service lines can also be emailed at:
leadquestions@wfbvillage.gov
The DNR has posted a Lead Service Line Replacement Outreach Funding grant for
communities to apply for financial support to aid in community outreach and education. The
Village of Whitefish Bay and Shorewood have mutually desired goals on community
outreach and education. The management team met with the North Shore Health
10 | P a g e
Department to collaborate on a shared full-time dedicated case manager to be a front line
representative to assist each Village with outreach initiatives along with GIS/online
educational features. This grant was awarded in fall, 2025 with additional funding in
approved in 2026.
Village staff worked with a student intern paid through UW-Milwaukee to review archive
building permits to confirm/update a batch of water utility material records (lead service
lines). This assisted with improved accuracy of the Village’s lead service line inventory and
aid in future planned water main replacement projects. The next step in the process is to
evaluate data to prioritize a water main replacement program. Village staff annually evaluate
road condition ratings, lead service line inventories, water main break data, and water main
age to determine project priority areas.
Village staff and the health department specialist are working to develop standard operating
procedures and the review of archive documents to ensure that service line identification and
record keeping is compliant with EPA/DNR guidelines. This will also assist with building
the foundation for GIS recordkeeping and the development of the LSL community
dashboard that is planned to rollout in 2026.
Village staff along with the NSHD Environmental Specialist have continued to work on
integrating the Village’s GIS as the main platform for service line records and inventory.
Continuous improvements have been made to the record system to improve the accuracy of
historic archives, construction documents, and future replacements.
North Shore Water Commission Basin #5 Repair Project
• Project Budget $904,109
• Current Phase: Design
• Engineer/Contract: SEH/$118,481
• Contactor: J.H. Hassinger, Inc/$1,035,495
• Target Completion: 2026
Project Overview: The Village is part owner of the North Shore Water Commission
(NSWC) along with the City of Glendale and Village of Fox Point. The three municipalities
share financial responsibilities and oversight of the NSWC based on percentage of water
usage rates (Whitefish Bay owns approximately 31.5% share of the NSWC). The NSWC
plant operates a water treatment plant (WTP) in Glendale and is generally considered a
conventional surface water treatment plant. As part of the treatment processes, there are five
(5) below grade flocculation and sedimentation basins. Basins No. 1-3 were built as part of
the original plant construction project in 1962 and Basins No. 4 & 5 were built as part of the
plant expansion project in 1972. In 2018, NSWC staff identified equipment failures in Basin
No. 5 and it was subsequently removed from service. In 2023, NSWC commissioned Baxter
11 | P a g e
& Woodman to prepare a preliminary engineering report (PER) to identify necessary
improvements bring the basin back into service. The long term vision for the WTP is to
operate Basin No. 5, rehabilitate Basin No. 4, and abandon Basins No. 1-3 based on the
current needs of the communities.
The NSWC approved the engineering proposal by Short Elliott Hendrickson Inc. (SEH) in
the amount of $118,481 for design services for the Basin No. 5 Repair Project. Whitefish
Bay’s financial responsibility through the Water Utility will be approximately $35,550 based
on water utilization rates. Design will continue throughout 2024 with final design anticipated
to be completed by spring, 2025.
Basin #5 bids were open on 9/30/25 with four bidders submitting for this project. The low
bidder was awarded to J.H. Hassinger, Inc. in the amount of $1,035,495. The project is
within the Village’s portion of allocated 2025 budget. Due to change orders, supply chain,
and custom fabrication, the project completion is now anticipated to be early 2027.
Private Property Infiltration & Inflow & Lead Service Line Replacement:
• Project Budget: $1,571,955
• Current Phase: Construction
• Engineer/Contract: Clark-Dietz/$441,650
• Design Completion: Fall, 2026
• Contractor/Contract: Mid City Corporation
• Target Completion: 2026
Project Overview: MMSD has established the Private Property Infiltration and Inflow
(PPII) Reduction Program to provide guidelines, requirements, and a funding structure to
allow for local municipalities to participate in a joint effort to reduce stormwater from
entering into the wastewater collection and treatment utilities. It has been found that during
wet weather events, infiltration and inflow (I&I) into privately owned sewer laterals
contributes to the risk of sewer overflows. The reduction of clear water flows into the
sanitary sewer system has greatly assisted in reducing and eliminating sewer basement
backups in a previously identified prioritized area of the Village. The MMSD PPII Program
was implemented in 2010 utilizing monies set aside from property tax levy capital budget
revenues paid into the MMSD from each of the 28 MMSD municipalities. Those allocated
monies could then only be used for clear water removal work on the private side of the
sanitary sewer system. From 2017-2019, the Village was able to complete 303 private
property sanitary sewer lateral linings under this program out of the 407 applicants.
As part of the annual PPII program, the Village has worked with MMSD representatives in
2024 to realign best practices with the construction methods used to manage private
property laterals. Due to MMSD’s concerns of Cure in Place Pipe (CIPP) construction
methods, the Village and MMSD agreed that CIPP will not be an accepted construction
activity for future projects. The Village approved the use of the 2024 - 2025 PPII funding to
12 | P a g e
design for full private sanitary lateral replacements based on existing data of high I&I areas
within the Village.
The Village was awarded funding resources to educate residents of the PPII program,
develop design/specifications, and cost estimates for a total of 70 homes to have their lateral
replaced. The project area will continue to focus on Priority Area #1 located on the southern
section of the Village’s municipal boundary as shown on the WWPF Metersheds. There are
over 200 residents that are within this area that would qualify for the program of which, 28
properties have signed up to participate with the new program.
A Public Information Meeting (PIM) occurred on Wednesday, June 11th. Eligible properties
(108 within Priority Area #1) had until June 27th, 2025 to sign a Right of Entry (ROE)
agreement showing interest in the program. The Village received a total of 42 ROE
applications with the goal of receiving 70 participants. Televising of the sanitary sewer
laterals has been completed with the 42 properties to qualify these residents for the program
and will transition these properties to final design and construction documents. The Village
applied for MMSD competitive funding on 9/2 to financially support the construction of all
42 properties in 2026.
MMSD approved the final funding agreement to support 33 of the 42 properties to
participate in the PPII/LSL program. A lottery system was used to qualify the 33 property
owners.
30 properties completed in 2026 with final restoration and punch list items remaining.
MMSD notified the Village of $500,000 in PPII funding for 2027 sanitary sewer
replacements.
Roadway Rehabilitation Program:
• Project Budget: $ 700,741
• Current Phase: Construction
• Engineer/Contract: Clark-Dietz/$6,500
• Contractor/Contract: LaLonde Contractors/$630,095
• Target Completion: 2026
The resurfacing of Devon Street and Bay Ridge Avenue was initially planned to be a
standard asphalt mill and overlay project. However, during storm sewer repair in anticipation
of the resurfacing program, it was discovered that the asphalt on Devon Street does not have
an adequate subbase. The existing road surface was installed directly on soil. A standard mill
and overlay project on a modern roadway would typically resurface the road pavement
utilizing the support from the existing subsurface. In addition to the lack of proper road
subbase, the soil in the project area experiences a notable amount of natural groundwater
drainage; Village staff have observed groundwater surfacing through cracks in the pavement.
The improper ground water drainage, compiled with the freeze-thaw cycles in Wisconsin’s
winter conditions, exacerbates the pavement’s cracking. To provide an adequate drainage
13 | P a g e
route for groundwater, the project must account for the addition of modern drain tile, which
will extend the useful life of the road.
The project was awarded to LaLonde Contractors to complete the roadway rehabilitation
project on Devon and Bay Ridge in 2026. The contractor is required to be substantially
complete with the project by November 6th with final completion by November 20th with 45
calendar days to complete from formal notice to proceed.
Devon and Bay Ridge projects are substantially compete. Final walkthroughs occurred in late
October to identify punchlist items that need to be completed prior to final payments.
Sanitary Sewer Main Lining:
• Project Budget: $ 515,000
• Current Phase: Construction
• Engineer/Contract: Clark-Dietz/$33,000
• Contractor/Contract: Visu-Sewer/$247,094.50
• Target Completion: 2026
The Village conveys sanitary sewer through over 37 miles of mainline and 920 manhole
structures. This sewer is transported to Milwaukee Metro Sewerage District (MMSD) for
treatment via the Milwaukee Interceptor Sewer (MIS). The Village sanitary sewer mainlines,
ranging from 8” to 36” in diameter, are routinely televised using a crawler camera which
identify needed repairs to sanitary lines typically through cure in place pipe technologies.
This is an annual program to ensure the Village owned sanitary sewer mains and manholes
are maintained to reduce risk of basement backups to residents.
Currently, 64% of the Village’s sanitary mains are lined with 36% unlined. The 2026 project
includes a proposed 1.3 miles of 8” pipe to be lined in 2026. This project will combine the
borrowed funds from 2025 and 2026 for a larger area of lining since this was not completed
in 2025. The Village Board approved the contract to Visu-Sewer during the February 2nd
meeting.
Visu-Sewer has started to complete onsite fieldwork in preparation for the lining program.
Construction is anticipated to start in mid-December. Based on available budgets, Village
staff has increased the amount of sanitary sewer main lining to occur during this program
year. Approximately 2 miles of sanitary sewer main will be lined this season.
School Zone Safety Improvement Project:
• Project Budget: $822,000
• Current Phase: Design
• Engineer/Contract: raSmith/$140,030.76
• Design Completion: November 2026
14 | P a g e
• Contractor/Contract: TBD
• Target Completion: 2027
Project Overview: The Village was awarded a WisDOT Transportation Alternatives
Program (TAP) grant with the intent of updating the signing as well as implementing
numerous other safety enhancements for all eight school zones. The goal is to substantially
reduce the crash risk for walking or bicycle riding within these high pedestrian traffic areas.
The Village received and signed the State/Municipal Agreement (SMA) TAP grant to
proceed with implementing the project. The TAP grant will cover up to 80% of design and
construction costs for this project. WisDOT has authorized $61,600 in design funding for
this project and the Village budgeted $15,400 for the 20% cost share within the 2025 budget.
The Public Works Committee and Village Board voted to award the consultant project
contract to raSmith to assist with design/engineering of five school zone areas:
o Santa Monica & Belle – Bump out/intersection improvements (Richards Elementary
School)
o Santa Monica & Day - Bump out/intersection improvements (Richards Elementary
School)
o Beaumont & Santa Monica – Intersection improvements per 2024 Beaumont TADI
Traffic Study (St. Monica School)
o Ardmore & Hampton – Bump out/intersection improvements (Cumberland
Elementary School)
The Village hosted a kickoff Operational Planning Meeting with internal stakeholders on
7/31/25 to review project goals and outcomes. A Public Involvement Meeting occurred on
October 22nd from 5pm – 7pm at the Whitefish Bay Public Library. The Village and design
team compiled feedback from residents on the proposed improvements and shared input
with the Public Works Committee. These proposed improvements were further discussed
with the Public Works Committee in November to give designers direction on project
construction scope.
Short-term traffic cones and delineators were installed on Santa Monica & Belle, Santa
Monica & Day, and Ardmore & Hampton. These features will be part of the traffic calming
temporary improvement zones that reflect the Bicycle and Pedestrian Safety Study
recommendations. These features are planned to be staged until the permanent features are
constructed during the 2027 construction season.
Final plans will be completed by November with bidding schedule for early January.
Construction is anticipated to occur in June when school is out of session.
15 | P a g e
Sendik’s Re-Development Public Improvements:
• Project Budget: $2,764,405
• Current Phase: Bidding
• Engineer/Contract: Clark Dietz/$422,100
• Contractor/Contract: TBD
• Target Completion: 2027
Project Overview: On October 6, 2025, the Village Board approved Ordinance No. 1918 to
rezone the necessary parcels to a Planned Development District (PDD) for the construction and
funding requirements for the Sendik’s Redevelopment project. In addition to the proposed
private redevelopment, there are a number of public improvements as part of the project scope
aimed at addressing utility improvements, traffic, and pedestrian safety. The Village’s engineering
services contractor, Clark Dietz alongside village staff presented these proposed improvements
during the August Village Board meeting as well as final design recommendations approved by
the Village Board on September 15th, 2025.
Clark Dietz, with assistance of village staff and the Sendik’s team have worked to develop
construction documents and specifications that are now finalized. Sendik’s has integrated these
public improvement design documents into a bid package that will be solicited to qualified
contractors to perform these activities during the 2026 construction season.
Major construction activities are now substantially complete. Contractors are working on final
punchlist tasks including signage, bike racks, pavers, and the village monument sign. The traffic
signals for Consaul Pl. and Silver Spring Dr. are planned to be installed in early December.
Sidewalk Replacement Program:
• Project Budget: $175,000
• Current Phase: Construction
• Engineer/Contract: Staff Engineer
• Contractor/Contract: Forward Contractors/$90,304
• Target Completion: Fall, 2026
Project Overview: DPW annually rotates within seven quadrants to replace sidewalk panels that
are at the end of their expected useful life. Sidewalk improvements include replacement of
sidewalks that pose a hazard, terrace grading in areas to improve drainage and reduce icing, and
ADA compliant ramp additions. In addition to panel replacement within the proposed project
area, residents submitted requests to have DPW staff review the need to replace unsafe sections
of sidewalk anywhere within the Village limits.
The annual sidewalk program contract was awarded to Forward Contractors. The sidewalk
replacement program is substantially complete with final improvements to Klode Park multiuse
path and the Police Department sidewalk planned for November.
16 | P a g e
Storm and Sanitary Sewer Improvement Planning:
• Project Budget: $50,000
• Current Phase: Contract Approvals
• Engineer/Contract: Clark-Dietz/$50,000
• Design Completion: Summer, 2026
Project Overview: The Village recorded 9.2” of rainfall during the storm event on August 9th –
10th which was categorized as a 1,000-year flood event (.01% chance of occurring in any given year).
As part of the Village’s response, efforts will be made to evaluate the last event's data, past
storm/sanitary studies, historical records, GIS data and research to make stormwater and sanitary
sewer improvement recommendations in 2026. After the recommendations are presented and
prioritized by the Board, the project scope will transition efforts on project design and engineering
in 2027 to determine the financial impact and recommendations for future CIP borrows.
Village staff worked with the village engineer to scope the planning efforts to be conducted in 2026
including:
• Flow Monitoring/Metering/Bypass Pumping – Standard Operating Procedures
• Sanitary and Strom Sewer Performance Evaluation
• Relief Sewer Needs Evaluation (Basin 6)
• Existing SSO bypass Improvement Recommendations
The Clark Dietz project proposal was approved by the Village Board in March, 2026. The Study’s
kickoff meeting occurred on April 17th with the project scope anticipated to be completed in four
months. The final report and recommendations to be presented to the Village Board.
Clark Dietz started to review historic archives and conduct field investigations as part of the report’s
scope. Field staff and engineers completed site visits to known storm/sanitary bypass locations to
verify measurements on 6/2 & 6/3. Village staff and Clark Dietz met on June 26th to evaluate the
data and field reports to start planning for recommendations to be presented to the Village Board.
The draft report is under review by Village staff with the final draft report to be presented to the
Public Works Committee in October.
The draft report was presented to the Public Works Committee and accepted by the Village Board
on 10/26/26.
Storm Sewer Outfall Rehabilitation Planning:
• Project Budget: $400,000 (2026 & 2027 CIP)
• Current Phase: Design Contract Review
• Engineer/Contract: Ruekert Mielke/$82,801
• Design Completion: Fall, 2026
• Contractor/Contract: TBD
17 | P a g e
• Target Completion: TBD
Project Overview: On February 17, 2025, the Village Board approved the contract for Mid City
Corporation that includes the review of as-built drawings, inspection of the remaining four Lake
Michigan outfalls and contiguous manholes, document existing conditions, and complete inspection
reports including repair suggestions and cost estimates.
In April, 2025, Mid City performed the inspections of all accessible stormwater outfalls that
discharge into Lake Michigan with the exception of LM4 that has recently been rehabilitated. As part
of the inspections, Mid City has completed their analysis, documentation of findings,
recommendations, budget estimates, and project priorities within the report. The final report will be
used to guide the Village with future projects and capital budget planning to maintain these critical
features.
Village staff utilized the Mid City Report’s recommendations to transition to further guide design
and engineering for the necessary repairs to Lake Michigan #1 (LM1) outfall as well as safety grate
outfall installations. Village staff have evaluated the recommendations with specialized engineers that
have experience with unique storm sewer projects in similar size and scope. Ruekert Mielke was
awarded the design service agreement by the Village Board. Design and survey activities will
continue through spring and summer with anticipated design completion by fall, 2026. This project
is funded with the “Storm Sewer Main & Manhole Repair/Lining CIP” budget. Future storm sewer
outfall and main repair recommendations will be included within the 2026-2027 CIP as well as
future priorities within the next 6-year CIP outlook.
Draft reports and recommendations were presented to village staff for review. Final
recommendations include Cure in Place Pipe rehabilitation of the LM#1 outfall. Conceptual reports
and recommendations were presented to the homeowners on 10/2/26 who are directly impacted
with construction activities to gain their input prior to presenting final recommendations to the
Public Works Committee. Village staff and consultants are starting to draft both temporary
construction easements and permanent utility easements as part of the project scope.
Watermain/LSL Replacement:
• Project Budget: $4,610,000
• Current Phase: Design
• Engineer/Contract: Clark Dietz/$276,775
• Design Completion: November 2026
• Contractor/Contract: TBD
• Target Completion: 2027
Project Overview: The Village is responsible for the management of 47 miles of watermain with
86% of all watermains determined to be 80 years or older. The life cycle of a watermain is 80 - 100
years. There is a need to increase the replacement rate of ageing mains within the next 40 years. As
18 | P a g e
part of this goal, the Village will undergo a minimum of 1-mile of watermain replacement annually
which will also replace public and private lead service lines (LSL) within the project area. The
watermain and lead service line replacement will allow the Village to comply with EPA's Lead and
Copper Rule Improvements (LCRI).
In addition to the proposed watermain/LSL design/construction activities, storm sewer and sanitary
sewer inspections will be completed by village staff and engineers during design to determine if
additional repairs and/or improvements should be incorporated within the project scope. This will
also assist with managing these project areas holistically to be proactive with necessary utility
maintenance.
After examining these factors, the Village has approved the 2026-2026 watermain & LSL project
areas on N Hollywood Avenue, from E Henry Clay Street to E Hampton Road, and N Shoreland
Avenue, from 6135 N Shoreland Ave to E Lakeview Avenue. This project will also include an
estimated 145 lead service line replacements.
Bidding is scheduled to occur in December, 2026. Design is currently at 90%.
A planned Public Information Meeting occurred on 9/24/26 with residents located within the
project area. The overall feedback was positive, and residents were engaged with questions and given
feedback and contacts to better serve them during construction. Residents can find project updates
under the new watermain/LSL construction webpage:
https://storymaps.arcgis.com/stories/b60931c8dd74439f8d9026653b3c184c
A new Public facing dashboard was completed for all residents to quickly determine their service
line material. Refer to link to the new water service line dashboard: https://v-
whitefishbay.maps.arcgis.com/apps/dashboards/30c445a5df784e91920de7d277c38eeb#
Project plans and design were submitted and approved by the DNR. Village staff applied for the
Safe Drinking Water Loan Program (SDWLP) funding for a low interest loan for the watermain and
public service line as well as the lead service line (Public & Private). On October 22, 2026, the DNR
released the SDWLP Lead Service Line Replacement Funding List, in which Whitefish Bay did not
receive any of its requested funding. Funding was prioritized using the Priority Evaluation and
Ranking Formula (PERF), which considers factors such as the number of lead service lines, income
levels, population under age five, lead sampling results, system optimization, and whether the project
will eliminate all remaining lead service lines. Higher scores increase the likelihood of funding, with
Whitefish Bay receiving a score of 72 compared to the median of 93. DNR has postponed
implementation of the Environmental Loans Process Improvements (ELPI) until SFY 2029,
maintaining the existing application process for SFY 2028 and extending the ITA/PERF submission
deadline to January 15, 2027. This is unlikely to impact Whitefish Bay’s standing for SFY 2028
funding, as the existing ranking criteria will remain unchanged.