1) Call to Order
2) Roll Call
3) Approve Minutes for May 18, 2026
4) Updated Non-Motorized Boat Launch Repair and Maintenance Items Cost Estimate
5) Discussion on Alley Improvements Behind Cherry Street and Orange Street
6) Other Business
a) Riverfront and Sunset Park Signs
7) Adjourn
NOTICE
ACCESS TO THE MUNICIPAL BUILDING FOR THE DISABLED IS AVAILABLE AT
THE MAIN ENTRANCE. ALL THOSE WITH SPECIAL NEEDS SHOULD CALL CITY
HALL OFFICES (715-262-5544) IF ASSISTANCE IS REQUIRED
IT IS POSSIBLE THAT A QUORUM OF THE COMMON COUNCIL OR OTHER CITY
COMMITTEES MAY BE PRESENT AT THIS MEETING. THIS IS INCIDENTAL AND
NO ACTION WILL BE TAKEN BY THE COUNCIL OR ANY OTHER COMMITTEES.
Parks and Public Works Committee Meeting Minutes
May 18th, 2026
Pursuant to due call and notice thereof, a meeting of the Parks and Public Works
Committee was held May 18th, 2026, Municipal Building, 800 Borner Street, Prescott,
Wisconsin, 54021. The meeting was called to order at 5:00 PM.
Committee Present: Mike Gerke, Dar Hintz (Left early), Lindsey Sorenson
Staff Present: City Administrator Matt Wolf and Planner Luke Wiese
Others Present: Franz Altpeter of 1110 Lake St, Kris Sampson of 611 Lake St
1. Approve Minutes for April 20th, 2026
Hintz motioned to approve the minutes for April 20th. Gerke seconded; motion passed
without a negative voice (3-0).
2. Non-Motorized Boat Launch – Repair and Maintenance Items
City Administrator Wolf presented items related to repairs and maintenance at the Prescott
Non-Motorized Boat Launch. Staff noted that a second quote was previously pursued, but
no additional contractors expressed interest in completing the work.
Franz Altpeter, 1110 Lake St, stated he was surprised by the current condition of the boat
launch and commented that the stairs were in poor condition. He supported making
improvements, including the addition of railings, and noted that the park is well used.
Kris Sampson agreed the launch receives frequent use and commented that accessibility
improvements for visitors and kayakers should be considered. Sampson also suggested
adding garbage cans near the beach area.
Committee Member Bettis suggested evaluating whether replacing the stairs entirely with a
ramp may be a better long-term option and encouraged reviewing different improvement
alternatives for the site.
Committee Member Hintz supported addressing safety concerns promptly, particularly the
stairs and potential installation of railings, and suggested larger improvements could be
planned in phases.
Committee Member Sorenson directed staff to obtain an updated quote from Luke Busker
Masonry and bring the item back to the Parks & Public Works Committee for further
discussion and direction on next steps.
Review and Discussion on Magee Park Sign Layout
City Planner Luke Wiese presented the Magee Park Sign Layout map. The map identifies
proposed signage locations throughout the park and shows different sign types including
informational, safety, directional, trail marker, and boundary signs.
Kris Sampson, 611 Lake St, commented on including signs that identify park rules and
permitted uses. Sampson also suggested considering the multiple transportation and
recreational uses accommodated on the trail system.
The Committee agreed that incorporating rules and using information into the signage plan
would be beneficial.
Discussion on Transportation Resolution Requested from the League of Wisconsin
Municipalities
City Administrator Wolf presented information from the League of Wisconsin Municipalities
regarding a proposed transportation funding resolution. The resolution is intended to
advocate for a long-term transportation funding solution at the State level ahead of
development of the 2027–2029 biennial budget.
Discussion included increasing transportation costs, transportation aid not keeping pace
with inflation, and the impacts these funding trends have on local roadway maintenance
and infrastructure responsibilities.
Committee member Sorenson made a recommendation to the City Council to adopt
the resolution provided by the League of Wisconsin Municipalities, Bettis seconded;
motion passed without a negative voice (2-0).
3. Other Business
City Administrator Wolf explained that the motorized boat launch has gotten repeatedly hit
this spring. The rubber rail along the dock has been ripped off multiple times by passing
boats.
Committee member Bettis attested to this happening and suggesting getting better
material to prevent it from getting ripped off. The dock will have continual issues if the issue
is not addressed properly. Committee member Bettis told staff he would provide an
example of a product that could help.
Kris Sampson explained that with the parks in Prescott it would be nice to have a cohesive
opening date so the public could be more informed on when the parks will be fully opened.
Sampson also had additional feedback on garbage in the parks and irrigation along the
boat launch.
Commissioner Bettis motioned to adjourn. Sorenson seconded; motion passed
without a negative voice (2-0). The meeting was adjourned at 5:58 PM.
The next Parks & Public Works Committee will be June 15, 2026, at 5:00 PM.
Respectfully Submitted,
Luke Wiese, Planner
To: Parks and Public Works Committee
From: Matt Wolf, City Administrator
Date: June 11, 2026
Subject: Non-Motorized Boat Launch Repairs and Maintenance
Background
In October 2024, the City’s Parks and Public Works Committee discussed repairs to the non-
motorized boat launch located at the end of Lake Street. At that time, the City received a quote from
Luke Busker Masonry totaling $60,625 for the identified repairs, with an additional optional cost of
$29,250 to extend the limestone retaining wall. During the discussion, the Committee requested that
staff obtain a second quote for the project.
Public Works Director Mike Kinneman attempted to obtain an additional quote; however, was unable
to find another contractor interested in completing the work. At the last Parks and Public Works
Committee meeting the Council approved getting an updated bid from Luke Busker Masonry.
Discussion
The City obtained updated proposals from Luke Busker Masonry on June 10, 2026 (see attached).
Repairs and Maintenance
The proposal for repairs and maintenance totals $72,375 and includes:
• Demolition and replacement of existing sidewalks and concrete stairs;
• Concrete pumping;
• Removal of existing mortar and tuckpointing of fieldstone stairway walls;
• Fabrication and installation of new stone plinths for planter bowls;
• Tuckpointing and resetting limestone wall stones along the existing retaining walls;
• Restoration and recoating of bench seats;
• Removal and restoration of cast iron bowls and concrete stands; and
• Mobilization and delivery costs.
Additional Improvements
Luke Busker Masonry also provided a proposal for additional improvements that were discussed at
the last Committee meeting, totaling $42,020, including:
• Extending approximately 450 feet of limestone retaining wall in areas that currently consist
primarily of riprap;
• Construction of a new five-foot-wide concrete access ramp; and
• Mobilization and delivery costs.
The combined cost of the repairs and additional improvements is $114,395.
Bidding Requirements
The repair and maintenance work consists of the restoration and rehabilitation of existing
infrastructure and is considered maintenance work. Maintenance and repair projects are exempt
from the public bidding requirements contained in Wisconsin Statutes.
In addition, 2025 Wisconsin Act 188 increased the public works bidding threshold under Wis. Stat. §
62.15(1b). Under the revised statute, municipalities are required to competitively bid only public
construction projects with an estimated cost exceeding $50,000. Projects between $10,000 and
$50,000 require a Class 1 notice without formal bidding.
Because the additional improvements are estimated at $42,020, they fall below the statutory
threshold and may be awarded directly without competitive bidding, but a class 1 notice is required.
Financing
The City's 2026 budget includes $50,000 for park improvements and repairs. To date, approximately
$4,881 has been expended, leaving an estimated balance of $45,119 available. If the entire remaining
amount were utilized for this project, no funding would remain for other park projects or unforeseen
maintenance items that may arise during the remainder of the year.
In addition, the City currently has a balance of $77,781.84 in its Parks Improvement Fund after paying
$32,760 for the recent Freedom Park repair projects. However, the City has a pending $20,000
matching obligation under the grant agreement with Friends of Freedom Park/Coulee River Trails for
future trail improvements. Additionally, pursuant to its Development Agreement with Capital
Investment Partners, the City will be responsible for reimbursing Capital Investment Partners in 2027
for the construction of a trail connection between Dexter Street and Borner Street.
The City also has $105,000 that was previously loaned from the Capital Fund to Tax Increment
District No. 4. These funds are scheduled to be repaid to the City's Capital Fund later this year and are
intended to be used for future one-time capital expenses. Accordingly, these funds represent
another potential source of funding for the proposed improvements.
Recommendation
Discuss the proposed repairs, improvements, and available funding options for the Non-Motorized
Boat Launch. Due to the overall cost of the project, staff recommend proceeding with the $72,375
repair and maintenance items at this time. Utilizing a combination of the remaining funds available
within the City's 2026 Parks Improvement budget and the City's Capital Fund to finance the repairs.
Staff also recommends delaying the additional improvement items, including the limestone wall
extension and concrete access ramp, until they can be incorporated into the City's Capital
Improvement Plan and evaluated alongside other future park priorities.
Attachments
1. Current Pictures of Non-Motorized Boat Launch
2. Cost Proposals from Luke Busker Masonry
Figure 1 Cast Iron Bowls and Concrete Benches
Figure 3 Cracking concrete stairs
Figure 2 Stone plinths and concrete planters
Figure 4 Fieldstone wall with worn mortar
Figure 5 Stones falling out of fieldstone wall Figure 6 Limestone wall with no mortar
Page 1
PROPOSAL # DATE
L241005 6/10/2026
Rev.6.3.26
START DATE TERMS
DESCRIPTION Qty Price AMOUNT
1 6,528.00$ 6,528.00$
1 11,724.00$ 11,724.00$
1 840.00$ 840.00$
250 66.00$ 16,500.00$
2 1,524.00$ 3,048.00$
450 54.00$ 24,300.00$
2 2,244.00$ 4,488.00$
2 1,536.00$ 3,072.00$
5 375.00$ 1,875.00$
Total 72,375.00$
Remove bench seat, sandblast clean and re-surface with flame applied coating-
Prescott, WI 54021
Prescott, WI 54021
Concrete pump-
>Beach Access Project- Price includes labor and material for the following:
Tuckpoint reset as needed limestone wall stone on entire existing limestone walls-
Form and pour new concrete stairs and sidewalk-
Remove existing mortar/tuckpoint stairway walls-little fieldstone-
Demo existing sidewalk and stair concrete/removal-
Fabricate and install new stone plinths at planter bowls-
800 Borner Street
Remove cast iron bowls and concrete stands with coating-
Mobilization and deliveries-
This proposal does not include anything not clearly outlined within it.
This proposal does not include building or extending existing walls.
ACCEPTANCE OF PROPOSAL
Thank you for your business!
If you have any questions about this proposal, please contact
612-490-1037 or luke@lukebuskermasonry.com
PROJECT ADDRESS
Lake Street North River Access
PROPOSAL
ROBERTS, WI 54023
612.490.1037
BILL TO
City of Prescott
www.lukebuskermasonry.com
PO BOX 180
Page 1
PROPOSAL # DATE
L241005 6/10/2026
Adder 6.3.26
START DATE TERMS
DESCRIPTION Qty Price AMOUNT
450 78.00$ 35,100.00$
1 6,170.00$ 6,170.00$
2 375.00$ 750.00$
Total 42,020.00$
Prescott, WI 54021
Prescott, WI 54021
>Beach Access Project Part 2- Price includes labor and material for the following:
800 Borner Street
Option to extend limestone retaining walls where wall is basically rip rap today-
Install 5' wide concrete ramp-
Mobilization and deliveries-
This proposal does not include anything not clearly outlined within it.
ACCEPTANCE OF PROPOSAL
Thank you for your business!
If you have any questions about this proposal, please contact
612-490-1037 or luke@lukebuskermasonry.com
PROJECT ADDRESS
Lake Street North River Access
PROPOSAL
ROBERTS, WI 54023
612.490.1037
BILL TO
City of Prescott
www.lukebuskermasonry.com
PO BOX 180
To: Parks and Public Works Committee
From: Matt Wolf, City Administrator
Date: June 11, 2026
Subject: Discussion on Alley Improvements Behind Cherry Street and Orange Street
Background
The City of Prescott owns an alley that connects Cherry Street to Orange Street behind several
businesses located along Broad Street/State Highway 35. The alley currently experiences drainage
issues. In addition, a prospective purchaser of 216 Broad Street, Megan Langer, is seeking to address
significant stormwater issues affecting the property. Addressing these issues would likely require the
installation of a storm inlet on the property that would connect to the City's stormwater system,
similar to the existing connection serving the gas station at 236 Broad Street. Due to the potential
improvements at 216 Broad Street this is also believed to be a potential time to fix other issues
within the alley.
Discussion
In evaluating the best long-term solution to address the drainage issues, staff has prepared a rough
concept map showing potential improvements. These improvements would include the construction
of curb and gutter along the rear of the buildings on the southwest side of the block. As part of the
project, an additional storm inlet could be installed farther down the alley toward Orange Street to
provide access to the City's stormwater system for 216 Broad Street.
While this option would be more costly and would require additional analysis by Cedar Corporation,
staff believes it represents the best long-term solution and would be most efficiently completed in
conjunction with the potential redevelopment of 216 Broad Street.
To implement the improvements, the City would work with Cedar Corporation to design the
placement of the curb and gutter in relation to the adjoining property lines and to determine the
location of the proposed stormwater inlet shown on the attached map. In accordance with the City's
Special Assessment Policy and City Code, the costs associated with the curb and gutter
improvements would be specially assessed to the benefiting properties.
Recommendation
Staff will present the proposed improvements and seek direction from the Committee on whether it
would like to proceed with further engineering and cost analysis.
Attachments
1. Alley Improvements Image
Source: City of Prescott website. First collected Oct 9, 2026.