September 9, 2026 Board Mtg Minutes
Village of Hewitt · Wood County · meeting of Sep 9, 2026 · Minutes
Open the original document More from Village of Hewitt
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
VILLAGE OF HEWITT
Board Meeting Minutes
September 9, 2026
The September 9, 2026 meeting of the Village of Hewitt Board was called to order at 6:30 p.m. by President
Marlene Stueland.
Present: Heather Gehrt, Tom Iwanski, Dan Sommers, Cassie Horn, Travis Wienke, and Marlene Stueland.
Absent: None
Guests: Romelle Bymers, Jeff Binder, Mike Draxler (6:45).
Announcements/Communications from the public: Jeff Binder spoke about the ditch between 4th Street and
the trail. The ditch needs to be cleaned out. It is not immediate problem, but should be done in the near
future. It was suggested that a waterway committee be formed to look at this problem since it is not a part of
the road system in the Village.
Approval of Minutes: Tom moved to approve the minutes from the August 12, 2026 Village Board meeting.
Dan seconded. Motion carried. Dan moved to approve the minutes from the Special Board meeting held on
August 19, 2026. Travis seconded. Motion carried.
Correspondence: Correspondence was routed.
Department Reports:
A. Hewitt Area Fire Commission:
Approval of Monthly Bills & Payments: Cassie moved to approve the monthly bills and payments
as submitted. Tom seconded. Motion carried.
Review of Ordinance 16.01 and Job Description for Fire Commission Clerk: There was a meeting
on August 16th. They are still waiting for one more member to be named on the personnel
committee. The next meeting will be September 21st at 7:00 at which time there will be an
evaluation of the financial secretary and a review of the fire commission by-laws.
Roller Funds from 2023, 2024, 2025 Use: Questions were asked as to what is the intended use of
these funds. The money had been budgeted to cover costs of repairs if the insurance claim was not
approved. The insurance did cover those costs, so it is unsure what the money will be earmarked
for now. The invoice for the blacktopping by American Asphalt was incorrect and a refund of the
difference will be made by the company. The Town of Marshfield will be receiving a new invoice
for this changed amount.
B. Sanitary System –
Sanitary System & Treatment Plant Monthly Maintenance Report: The monthly report was
reviewed. After a discussion with the head of the Marshfield Wastewaters, several items will
need to be discussed about the direction that the Village takes in the future. Possible future
changes may be that DNR requires disinfection of any water going into Mill Creek. This is done
through ultra-violet light and will probably be required in 2-3 years. Other future items include
the cleaning of the clarifier, the phosphorus compliance requirements, and the replacing of the
sludge silo.
Phosphorus Compliance Planning Updates: Nothing new to report at this time.
Update on Staffing: The Sanitary Committee met on August 26 for a discussion with Chad
Kohlbeck on his position as the Sanitary System Wastewater Treatment Operator. The Board will
meet on September 21 at 6:30 to consider Chad’s counter offer.
Sludge Hauling – Land Application Re-submitted: A follow up will be made next week on the
application.
Sewer Line Cleaning/Televising Scheduled: Marshfield Sanitary Utility will be doing the 2nd
quadrant of the Village. The amount is covered in the budget.
C. Zoning Administrator Report:
Re-visit Fee for Variance Requests – to be considered when compiling the 2027 budget:
Nothing new to report at this time. Board members are to be thinking about this for the
upcoming budget meetings.
Financial Reports:
Monthly Bills: The monthly reports were reviewed. A motion was made by Travis and seconded
by Dan to approve the September 9, 2026 treasurer’s report. Motion carried. It was moved by
Tom and seconded by Dan to approve the bills as of September 9, 2026 of $92,167.42 as
submitted. Motion carried.
2027 Budget Preparation: There will be several meetings in the next few months to prepare the
2027 budget for the Village.
Committee Reports:
Roads: General Street Maintenance Updates: The road committee met on August 25. Minutes
from the meeting were shared with the Board. Chip seal was completed on the Yellowstone
Recreational Park asphalt areas. Paving will be done at a later time on the completion of the two
culvert replacements on 2nd Street and Fir Street. The MPH signpost on Main Street has been
replaced. The NO PARKING signpost on Allen Street broke in the wind. Contacts will be made for
a replacement. The culvert replacement and ditching on Fir Street and 7th Street has been
completed. A culvert on Main Street, south of the railroad tracks is failing. The County has been
contacted for repairs.
Road Commissioner Report: Chip seal sweeping will be done on September 12. Whirlwind will
then do the fall sweeping.
1st & 2nd Street Ditch Draining Update: This project will be finished as soon the crop is off the
field. There were a few wash outs with the last heavy rains. The road mats will be picked up if
the residents have removed them and they are placed on the side of the road. In 2027 fine
tuning and seeding will be done as needed.
Soo Lane Damage Repair/Insurance Payment Status: Waiting final invoicing for the work from
the county.
Insurance Claims Update – Hard Surface Cover Claim Request: Travis moved that the Village
turn down two residents’ request for the Village’s insurance to pay for the hard surfacing of their
driveways. Tom seconded. Motion passed with a roll call vote – Cassie – Yes, Tom – Yes, Dan –
Yes, Travis – Yes, Marlene – Yes.
Other: The consensus was that the Fandrich property on 2nd Street does not need a culvert
when he redoes his driveway next year. Weed cutting along the ditches can be handled with the
equipment that the Village has and a firm does not need to hired to do this.
A. Building Maintenance:
1. Administration Building: Nothing at this time.
2. Village Hall/Shelter Building: The parking lot needs looking at as it is bad repair.
o Yellowstone Park: Tom presented the Village with a check from the Rec. Department for
$2000 for use of the park this summer for their programs. An addition $1000 has also been
donated for park improvements. The swing set seats have been replaced and repairs were
made in the volleyball area. The removal of the memorial planter is on hold at this time.
Five dog signs were purchased and installed at the park. The lawns will be sprayed for weed
control for a cost of $2500 which is covered in the budget.
o Fire Station: Nothing at this time
B. Trails: The resident on the corner of the trail and Staadt has been mowing along the west end of
the trail. The Town of Marshfield has not reimbursed him for this service. The Village will get him a
thank you for his time and gas used. The Town of Marshfield only gives the Village $1000 yearly for
park expenses.
C. Animal Officer Control Report: Dogs have been reported running at large. The owner was
contacted about the problem.
D. Emergency Government: Nothing to report. The alarms will be serviced again in October.
E. Banners/Flags: The insurance company will be invoiced for the damaged flag. Cassie will set up a
date to have the banners and flags taken down. She will be getting new lights for some of the
Christmas decorations.
F. Weed Ordinance: Notifications were sent to 3 residents because they did not comply with the
August deadline to remove their weeds. The weeds need to be removed, not just sprayed. Fines
will be levied on those residents.
Old Business:
Retention Pond – New Information: The DNR has given permission to empty the retention pond
and spread it on an open field. The Village will try to locate a field for spreading. Continued
research is needed on who can do this work and the cost. It will be considered in the 2027
budget.
New Business:
2026-27 Insurance Renewal: Information on possible insurance carriers for the Village are being
looked into. A meeting may be needed before the October Board meeting to make a final decision.
Offer to Purchase – In Process: The paper work will be signed soon.
Garbage/Recycling 5 Year Contract Renewal: Tabled for further discussion at the October Board
meeting.
Approve Contract for 2027 Assessor Services: Travis moved to approve the 2027 assessor services
with Greg Schmidt for $8500. Cassie seconded. Motion carried.
Other: A resident’s check for the payment of the sewer bill was returned for insufficient funds.
The payment will now go on their bill as a special assessment. On the corner of 5th and Evergreen a
large dumpster was used to clean out a resident’s home. When it was removed by the company
large ruts were made in the ditch. The company has not replied with payment for the damage.
The resident will be billed for the damage.
Future Meetings: Wednesday, October 14, 2026 – Hewitt Village Board meeting – 6:30 pm
Adjournment: Moved by Travis and seconded by Cassie to adjourn. Motion carried. Meeting adjourned at
9:00 p.m.
Respectfully submitted by: Romelle Bymers