Park Commission — Agenda Packet
City of Stevens Point · Portage County · Park Commission · meeting of Oct 1, 2025 · Agenda packets
Open the original document More from City of Stevens Point
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
REGULAR MEETING
Board of Park Commissioners
October 1, 2025 - 6:30 PM
Community Room
933 Michigan Avenue, Stevens Point, WI
OR
Zoom Teleconferencing
Meeting ID: 862 8880 8260 | Passcode: 295799
By Computer: Join
By Phone: +1-312-626-6799 (US Chicago)
AGENDA
Discussion and Possible Action on:
1. Roll Call.
2. Approval of August 6, 2025 meeting minutes
3. Approval of Goerke Park master plan concept.
4. To award the Plover River Crossing Project to Highway Landscapers, Inc. in
the amount of $1,796,643.43.
5. Director's Report
- Forest Cemetery entrance stone arch project update
- Horticulturist position recruitment update
6. Adjournment.
Meeting Rider
Any person who has special needs while attending this meeting or needing agenda materials for this meeting should
contact the City Clerk as soon as possible to ensure a reasonable accommodation can be made. The City Clerk can
be reached by telephone at (715) 346-1569, TDD # 346-1556 or by mail at 1515 Strongs Ave., Stevens Point, WI
54481.
Copies of ordinances, resolutions, reports and minutes of the committee meetings are on file at the office of the City
Clerk for inspection during normal business hours from 7:30 a.m. to 4:00p.m.
SPECIAL NOTICE
Please take notice that a quorum of the Common Council, City Boards/Commissions may attend this
meeting.
Page 1 of 10
Agenda Notes
3. Approval of Goerke Park master plan.
Included in the packet is the final version of the Goerke Park Master plan which was
reviewed by the park commission in August. Since that meeting, Rettler Corporation has
completed cost estimates for the various components and improvements proposed within
the plan. Those cost estimates are included in the packet for review. The estimates are
based on current market conditions, and they are for reference only at this point. No
fundraising has occurred and no budgeting for these improvements has taken place at this
point.
The master plan is the result of several community meetings, an extensive online survey,
several park commission discussions and nearly two years of work since the planning
process began. The action item before the park commission is to consider approving the
concept/drawing. Phasing and budgeting of improvements in Goerke Park will take place
over the next many years and when funding for different components are identified,
prioritized and become available.
Staff recommends approval of the Goerke Park Master plan as shown in the packet.
4. To award the Plover River Crossing Project to Highway Landscapers, Inc. in the amount
of $796,643.43.
A memo is included in the packet for your review.
Page 2 of 10
REGULAR MEETING MINUTES
Board of Park Commissioners
August 6, 2025 - 6:30 PM
Community Room
933 Michigan Avenue, Stevens Point, WI
OR
Zoom Teleconferencing
Meeting ID: 847 0967 2800 | Passcode: 880399
By Computer: Join
By Phone: +1-312-626-6799 (US Chicago)
Discussion and Possible Action on:
1. Roll Call.
Present: Alder Buse, Freckmann, Disher, Glodosky, Alder Keymer, McDonald, Okonek,
Przybylski, Sorenson, Winn
Excused: Alder Broderick
Also Present: Alder Dean Shuda, Kathy Chiszo, Council President Marc Christianson,
Archie Sawyer, Trina Dorn, Danielle Belesky, Meg Erler, Kin Fiers, Mayor Mike Wiza,
Chris Wiza, Steve McKay
2. Approval of June 4, 2025 meeting minutes
Motion to approve June 4, 2025 meeting minutes by Glodosky, second by Przybylski;
passed 10-0.
3. Naming of parcel #'s 281240832403401, 281240832403305, and
281240832403308 (approximately 1.2 acres) to Leary Park in honor of Herb
and Theresa Leary, as requested by the Friends of 2713 and John
Kedrowski.
Motion to approve naming of parcels to Leary Park in honor of Herb and Theresa Leary,
as requested by the Friends of 2713 and John Kedrowski by Alder Keymer, second by
McDonald; passed 10-0.
4. Goerke Park master plan draft concept.
Motion to move toward the pricing stage of the Goerke Park master plan draft concept
by Disher, second by McDonald; motion passed 10-0.
5. Director's Report
1. 40 years of service on the Park Commission - Liz McDonald (8/9/1985–
8/9/2025)
2. Riverfront Rendezvous recap
3. Park Technician position vacancy
- Jonathan Hankins last day was 8/1/2025; he transferred to the Utility
Page 3 of 10
Department.
No action.
6. Adjournment.
Meeting adjourned at 7:21 pm.
Page 4 of 10
D
R
A
F
T
Page 5 of 10
PRELIMINARY COST ESTIMATE
Goerke Park
Stevens Point, Wisconsin
Park Facility Redevelopment
Rettler Project No.: 24.039
Item Estimated Category
No. Item Description Units Quantity Unit Price Extension Sub Total
$1,887,120.00
$949,000.00
MULTIUSE SPORTS FIELD (SYNTHETIC TURF) $2,627,870.00
BATTING CAGES $64,000.00
SOUTH PARKING LOT (~55 SPACES) $155,850.00
NORTH PARKING LOT (~100 SPACES) $353,420.00
PARK DRIVE (THROUGH PARK, SOUTH OF STADIUM) $151,620.00
RESURFACE EXISTING WILLETT PARKING LOT (EAST OF WILLETT) $82,300.00
REDESIGNED PARKING LOT AND DROP OFF (~105 SPACES) (BETWEEN PARKS DEPT AND P.J. JACOBS) $483,750.00
REDEVELOP MAIN DRIVE INTO PARKS DEPT PARKING LOT $123,390.00
WALK CONNECTIONS $194,440.00
STADIUM ENTRY PLAZA $102,040.00
AQUATIC COMPLEX $11,000,000.00
BASKETBALL COURT $59,920.00
PLAYGROUND $370,130.00
$35,000.00
FIELD EVENTS - SHOT PUT $15,000.00
PICKLEBALL COURTS - 4 COURTS $119,220.00
BUILDINGS AND MISCELLANEOUS SITE AMENITIES $425,000.00
SUMMARY
CONSTRUCTION ITEMS TOTAL: $19,199,070.00
CONTINGENCY at 7%: $1,343,940.00
CONSTRUCTION ESTIMATE SUBTOTAL: $20,543,010.00
SURVEY & GEOTECHNICAL BORINGS $35,000.00
SUMMARY - PROJECT TOTAL $20,578,010.00
Notes:
Topographic Survey not completed at time of study. Existing base map conditions may impact cost estimate.
Geotechnical study not completed at time of study. Soil conditions may impact cost estimate.
UTILITIES
FIELD EVENTS - DISCUS
September 24, 2025
EARTHWORK / DEMOLITION
Page 6 of 10
City of Stevens Point
2442 Sims Avenue
Stevens Point, WI 54481-3594
Memo
TO: Park Commission, Finance Committee and Common Council
FROM: Dan Kremer, Director of Parks, Recreation, Forestry
DATE: September 25, 2025
RE: Approval of Plover River Crossing Project contract
Bids were solicited and opened on Tuesday, September 16, 2025 for the Plover River Crossing Trail
Project. The city and the Friends of the Plover River Crossing acquired a Federal Transportation
Alternatives Program Grant for this project that totals $1,819,000. Within that grant amount, up to
80% ($1,455,200) is grant reimbursable and the remaining 20% local match ($363,000) has been
met through fundraising efforts.
A total of seven (7) bids were received on the project, and the low, qualified bid was received
from Highway Landscapers, Inc. in the amount of $1,796,643.43. The bids have been reviewed by
city staff, Rettler Corporation and the Wisconsin Department of Transportation and all approvals
from the grant coordinators have been received.
A complete bid tabulation and the signed/approved request to award from the WisDOT is
attached to this memo for reference.
I would like to extend a heartfelt thank you to Tori Jennings and Steve Menzel (Friends of the
Plover River Crossing Trail co-chairs), Rettler Corporation, Mayor Wiza, the city park commission,
the city common council, numerous donors, advocates and volunteers for the unwavering
support of this project over the last five plus years. It has truly taken a community to see this
project come from concept to the brink of construction!
The project is scheduled for completion in September of 2026.
Staff Recommendation:
1. Award the contract to Highway Landscapers, Inc. in the amount of $1,796,643.43.
a. Comptroller Ladick confirmed the city will pay for the project up front and be
reimbursed from the WisDOT and Friends of Plover River Crossing at the end of
construction.
Page 7 of 10
Project: City of Stevens Point Plover River Crossing
Bid Item Estimated
No. Item Description Units Quantity Unit Price Extension Unit Price Extension Unit Price Extension Unit Price Extension Unit Price Ext ension
201.0105 Clearing STA 16.0 $950.00 $15,200.00 $593.00 $9,488.00 $950.00 $15,200.00 $ 1,200.00 $19,200.00 $1,782.00 $28,512.00 $1,050.00 $16,8 00.00 $1,500.00 $24,000.00
201.0205 Grubbing STA 13.0 $950.00 $12,350.00 $599.00 $7,787.00 $950.00 $12,350.00 $800.00 $10,400.00 $ 1,725.00 $22,425.00 $700.00 $9,100.00 $1,450.00 $18,850. 00
213.0100 Finishing Roadway (6998-14-71) EACH 1.0 $500.00 $500.00 $330.00 $330.00 $1,500.00 $1,500.00 $2,50 0.00 $2,500.00 $1,782.00 $1,782.00 $5,000.00 $5,000.00 $1 ,500.00 $1,500.00
305.0120 Base Aggregate Dense 1 1/4-Inch TON 670.0 $30.00 $20,100.00 $25.00 $16,750.00 $30.00 $20,100.00 $30 .70 $20,569.00 $26.50 $17,755.00 $24.80 $16,616.00 $22.25 $14,907.50
465.0105 Asphaltic Surface TON 207.0 $231.50 $47,920.50 $231.50 $47,920.50 $231.50 $47,920.50 $231.50 $47,920.50 $185.00 $38,295.00 $235.00 $48,645.00 $231.50 $47,920.50
465.0315 Asphaltic Flumes S.Y. 7.0 $70.00 $490.00 $70.00 $490.00 $70.00 $490.00 $70.00 $490.0 0 $179.00 $1,253.00 $88.00 $616.00 $70.00 $490.00
502.0100 Concrete Masonry Bridges C.Y. 16.2 $500.00 $8,100.00 $1,255.00 $20,331.00 $500.00 $8,100.00 $4,000.00 $64,800.00 $2,115.00 $34,263.00 $3,000.00 $48, 600.00 $2,050.00 $33,210.00
502.3200 Protective Surface Treatment S.Y. 60.0 $2.00 $120.00 $4.95 $297.00 $2.00 $120.00 $60.00 $3,600.00 $28.00 $1,680.00 $3.00 $180.00 $7.00 $420.00
505.0600 Bar Steel Reinforcement HS Coated
Structures LB 2760.0 $2.49 $6,872.40 $3.10 $8,556.00 $2.49 $6,872.40 $8.00 $22, 080.00 $1.50 $4,140.00 $4.00 $11,040.00 $3.50 $9,660.00
506.0105 Structural Steel Carbon LB 86.0 $5.00 $430.00 $20.00 $1,720.00 $5.00 $430.00 $20.00 $1,720 .00 $13.00 $1,118.00 $20.00 $1,720.00 $56.00 $4,816.00
506.8006.S Prefabricated Steel Truss Pedestrian Bridge
B-49-201 LRFD EACH 1.0 $200,000.00 $200,000.00 $200,000.00 $200,000.00 $200,00 0.00 $200,000.00 $300,000.00 $300,000.00 $230,000.00 $23 0,000.00 $205,000.00 $205,000.00 $320,000.00 $320,000.0 0
511.1200 Temporary Shoring R-49-31 S.F. 1600.0 $40.00 $64,000.00 $37.00 $59,200.00 $40.00 $64,000.00 $40 .00 $64,000.00 $30.50 $48,800.00 $60.00 $96,000.00 $26.00 $41,600.00
550.0500 Pile Points EACH 6.0 $350.00 $2,100.00 $135.00 $810.00 $350.00 $2,100.00 $29,5 00.00 $177,000.00 $366.00 $2,196.00 $250.00 $1,500.00 $26 5.00 $1,590.00
550.2126 Piling CIP Concrete 12 3/4 X 0.375-Inch L.F. 480.0 $60.00 $28,800.00 $92.00 $44,160.00 $60.00 $28,800.00 $80 .00 $38,400.00 $68.00 $32,640.00 $75.00 $36,000.00 $98.00 $47,040.00
601.0411 Concrete Curb & Gutter 30-Inch Type D L.F. 29 5.0 $95.00 $28,025.00 $83.00 $24,485.00 $36.96 $10,903.20 $30 .00 $8,850.00 $113.00 $33,335.00 $58.00 $17,110.00 $46.00 $13,570.00
602.0415 Concrete Sidewalk 6-Inch S.F. 122.0 $17.00 $2,074.00 $18.00 $2,196.00 $33.71 $4,112.62 $10.00 $1,220.00 $12.00 $1,464.00 $24.00 $2,928.00 $40.00 $4,880 .00
602.0515 Curb Ramp Detectable Warning Field Natural
Patina S.F. 40.0 $55.00 $2,200.00 $53.00 $2,120.00 $50.00 $2,000.00 $45.00 $1,800.00 $60.00 $2,400.00 $60.00 $2,400.00 $50.00 $2,000 .00
606.0200 Riprap Medium C.Y. 3.0 $150.00 $450.00 $123.00 $369.00 $150.00 $450.00 $200.00 $6 00.00 $150.00 $450.00 $280.00 $840.00 $125.00 $375.00
612.0406 Pipe Underdrain Wrapped 6-Inch L.F. 300.0 $15.00 $4,500.00 $6.70 $2,010.00 $15.00 $4,500.00 $30.00 $ 9,000.00 $3.00 $900.00 $28.00 $8,400.00 $17.00 $5,100.00
619.1000 Mobilization EACH 1.0 $361,367.07 $361,367.07 $121,585.00 $121,585.00 $271,50 4.66 $271,504.66 $65,000.00 $65,000.00 $228,125.00 $228, 125.00 $296,000.00 $296,000.00 $357,000.00 $357,000.00
625.0500 Salvaged Topsoil S.Y. 1164.0 $8.00 $9,312.00 $7.00 $8,148.00 $8.00 $9,312.00 $5.00 $5,8 20.00 $4.50 $5,238.00 $8.00 $9,312.00 $3.50 $4,074.00
627.0200 Mulching S.Y. 273.0 $2.50 $682.50 $3.00 $819.00 $2.50 $682.50 $3.00 $819.00 $3. 00 $819.00 $3.00 $819.00 $2.50 $682.50
628.1504 Silt Fence L.F. 1279.0 $2.00 $2,558.00 $4.00 $5,116.00 $2.00 $2,558.00 $3.50 $4,4 76.50 $2.50 $3,197.50 $3.50 $4,476.50 $2.00 $2,558.00
628.1520 Silt Fence Maintenance L.F. 1279.0 $0.01 $12.79 $0.10 $127.90 $0.01 $12.79 $0.10 $127.90 $1.50 $1,918.50 $0.50 $639.50 $1.00 $1,279.00
628.2002 Erosion Mat Class I Type A S.Y. 501.0 $2.50 $1,252.50 $1.05 $526.05 $2.50 $1,252.50 $3.00 $1,503 .00 $3.00 $1,503.00 $2.50 $1,252.50 $2.50 $1,252.50
628.2006 Erosion Mat Urban Class I Type A S.Y. 391.0 $3.00 $1,173.00 $2.00 $782.00 $3.00 $1,173.00 $4.50 $1,759 .50 $3.50 $1,368.50 $5.00 $1,955.00 $2.75 $1,075.25
628.6005 Turbidity Barriers S.Y. 102.0 $50.00 $5,100.00 $34.00 $3,468.00 $50.00 $5,100.00 $60.00 $6,120.00 $66.50 $6,783.00 $55.00 $5,610.00 $55.75 $5,686 .50
628.7504 Temporary Ditch Checks L.F. 36.0 $25.00 $900.00 $6.00 $216.00 $25.00 $900.00 $25.00 $900.00 $9.00 $324.00 $20.00 $720.00 $7.50 $270.00
628.7560 Tracking Pads EACH 2.0 $1,500.00 $3,000.00 $1,600.00 $3,200.00 $1,500.00 $3,000 .00 $2,000.00 $4,000.00 $2,080.00 $4,160.00 $1,500.00 $3, 000.00 $1,750.00 $3,500.00
629.0210 Fertilizer Type B C.W.T. 0.7 $300.00 $219.00 $225.00 $164.25 $300.00 $219.00 $300.00 $2 19.00 $200.00 $146.00 $250.00 $182.50 $195.00 $142.35
630.0120 Seeding Mixture No. 20 L.B. 53.0 $15.00 $795.00 $7.00 $371.00 $15.00 $795.00 $25.00 $1,325. 00 $6.00 $318.00 $22.00 $1,166.00 $5.00 $265.00
630.0170 Seeding Mixture No. 70 L.B. 0.5 $1,000.00 $500.00 $635.00 $317.50 $1,000.00 $500.00 $1,00 0.00 $500.00 $125.00 $62.50 $800.00 $400.00 $105.00 $52.50
634.0814 Posts Tubular Steel 2x2-Inch x 14 Feet EACH 2 .0 $350.00 $700.00 $273.00 $546.00 $350.00 $700.00 $325.00 $6 50.00 $150.00 $300.00 $300.00 $600.00 $125.00 $250.00
637.2210 Signs Type II Reflective H S.F. 8.0 $60.00 $480.00 $22.50 $180.00 $60.00 $480.00 $50.00 $400.0 0 $54.00 $432.00 $45.00 $360.00 $45.00 $360.00
643.5000 Traffic Control EACH 1.0 $3,500.00 $3,500.00 $565.00 $565.00 $2,362.00 $2,362.00 $ 2,362.00 $2,362.00 $2,855.00 $2,855.00 $20,000.00 $20,00 0.00 $3,500.00 $3,500.00
645.0120 Geotextile Type HR S.Y. 6.0 $10.00 $60.00 $12.50 $75.00 $10.00 $60.00 $10.00 $60.00 $9. 00 $54.00 $10.00 $60.00 $7.00 $42.00
650.4500 Construction Staking Subgrade L.F. 1074.0 $1.50 $1,611.00 $1.50 $1,611.00 $1.50 $1,611.00 $1.50 $1,6 11.00 $2.00 $2,148.00 $1.50 $1,611.00 $1.50 $1,611.00
Date and Time: 9/16/25 11:00AM
CONTRACT "A" - GENERAL SITE CONSTRUCTION - BASE BID
Unit Price
Janke General Contractors, Inc. Zenith Tech Inc.Earth, Inc.Lunda Construction Company Advance Construction, Inc .
Unit Price Extension
Highway Landscapers, Inc. Michael's Construction, Inc.
Extension
Page 8 of 10
650.5000 Construction Staking Base L.F. 1074.0 $1.50 $1,611.00 $1.50 $1,611.00 $1.50 $1,611.00 $1.50 $1,6 11.00 $2.00 $2,148.00 $1.50 $1,611.00 $1.50 $1,611.00
650.5500 Construction Staking Curb Gutter and Curb &
Gutter L.F. 295.0 $2.65 $781.75 $2.65 $781.75 $2.65 $781.75 $2.65 $781.75 $4. 00 $1,180.00 $2.75 $811.25 $3.00 $885.00
650.6501.01 Construction Staking Structure Layout (B-49-
201) EACH 1.0 $2,000.00 $2,000.00 $2,000.00 $2,000.00 $2,000.00 $2,000 .00 $2,000.00 $2,000.00 $2,400.00 $2,400.00 $2,000.00 $2, 000.00 $2,000.00 $2,000.00
650.6501.02 Construction Staking Structure Layout (R-49-
31) EACH 1.0 $1,500.00 $1,500.00 $1,500.00 $1,500.00 $1,500.00 $1,500 .00 $1,500.00 $1,500.00 $1,785.00 $1,785.00 $1,500.00 $1, 500.00 $1,500.00 $1,500.00
650.6501.03 Construction Staking Structure Layout
(Boardwalk) EACH 1.0 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $ 10,000.00 $10,000.00 $10,000.00 $12,000.00 $12,000.00 $1 0,000.00 $10,000.00 $10,000.00 $10,000.00
650.9000 Construction Staking Curb Ramps EACH 2.0 $200.00 $400.00 $200.00
$400.00 $200.00 $400.00 $200.00 $400.00 $238.00 $476.00 $200.00 $4 00.00 $200.00 $400.00
650.9911 Construction Staking Supplemental Control
(6998-14-71) EACH 1.0 $2,000.00 $2,000.00 $2,000.00 $2,000.00 $2,000.00 $2,000 .00 $2,000.00 $2,000.00 $2,340.00 $2,340.00 $2,000.00 $2, 000.00 $2,000.00 $2,000.00
650.9920 Construction Staking Slope Stakes L.F. 1074.0 $1.00 $1,074.00 $1.00 $1,074.00 $1.00 $1,074.00 $1.00 $1,0 74.00 $1.50 $1,611.00 $1.00 $1,074.00 $1.00 $1,074.00
690.0150 Sawing Asphalt L.F. 10.0 $10.00 $100.00 $2.50 $25.00 $10.00 $100.00 $5.00 $50.00 $7. 50 $75.00 $10.00 $100.00 $6.00 $60.00
SPV.0060.01 Helical Pile EACH 82.0 $1,450.00 $118,900.00 $2,455.00 $201,310.00 $2,225.00 $1 82,450.00 $3,800.00 $311,600.00 $3,165.00 $259,530.00 $3 ,650.00 $299,300.00 $5,150.00 $422,300.00
SPV.0090.01 Treated Lumber and Timber Boardwalk 12'
Clear L.F. 734.0 $680.18 $499,252.12 $878.00 $644,452.00 $875.00 $642,250 .00 $670.00 $491,780.00 $780.50 $572,887.00 $995.00 $730, 330.00 $650.00 $477,100.00
SPV.0090.02
Treated Lumber and Timber Boardwalk 15'-10"
Clear L.F. 20.0 $831.38 $16,627.60 $1,083.00 $21,660.00 $1,050.00 $21,00 0.00 $900.00 $18,000.00 $1,140.00 $22,800.00 $1,490.00 $2 9,800.00 $950.00 $19,000.00
SPV.0090.03 Timber Pedestrian Railing R-49-31 L.F. 258 .0 $161.90 $41,770.20 $261.00 $67,338.00 $115.00 $29,670.00 $400.00 $103,200.00 $335.00 $86,430.00 $174.00 $44,892.0 0 $275.00 $70,950.00
SPV.0105.01 Excavation Common (Approximately 580 C.Y.) L.S. 1.0 $17,400.00 $17,400.00 $27,600.00 $27,600.00 $17,400.00 $ 17,400.00 $39,000.00 $39,000.00 $14,815.00 $14,815.00 $3 9,000.00 $39,000.00 $20,000.00 $20,000.00
SPV.0165.01 Wall Modular Block Mechanically Stabilized
Earth (R-49-31) S.F. 2050.0 $119.24 $244,442.00 $122.00 $250,100.00 $119.24 $244,442 .00 $95.00 $194,750.00 $160.00 $328,000.00 $86.25 $176,81 2.50 $140.00 $287,000.00
SPV.0195.01 Crushed Granite 6" TON 14.0 $95.00 $1,330.00 $126.00 $1,764.00 $95.00 $1,330.00 $55.0 0 $770.00 $44.00 $616.00 $80.00 $1,120.00 $37.00 $518.00
$1,796,643.43 $1,830,452.95 $1,890,179.92 $2,070,319.1 5 $2,072,253.00 $2,217,409.75 $2,291,927.60
Total Base Bid as Written $1,799,493.43 $1,830,334.15 $1,890,179.92 $2,070,319.15 $2,072,253.00 $2,217,409.7 5 $2,291,927.60
Difference -$2,850.00 $118.80 $0.00 $0.00 $0.00 $0.00 $0.0 0
Total Base Bid - Contract "A" - General Site Construction
Page 9 of 10
Page 10 of 10