Joint Finance and Space & Properties Committees — Agenda Packet
Portage County · Portage County · Finance Committee · meeting of Nov 10, 2025 · Agenda packets
Open the original document More from Portage County
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
PORTAGE COUNTY
MEETING AGENDA JfoJff
JOINT MEETING OF FINANCE AND
SPACE & PROPERTIES COMMITTEE
PORTAGE COUNTY ANNEX
CONFERENCE ROOMS 1 & 2
1462 STRONGS AVENUE
STEVENS POINT, WI 54481
Monday, November 10, 2025 4:30 PM
REMOTE ATT
ENDANCE & COMMENT
To attend this meeting by telephone : dial 1-872-242-7813 , after dialing the number you will then be asked to enter in a
meeting number. Use the following meeting number: 678 345 508, then press #
To attend this meeting by video: Join the meeting now
Page 1 of 1
CALL TO ORDER
CORRESPONDENCE
REPORTS
1. Vendor Invoice Lists
2. Special Meeting Attendance Reports (Portage County Ordinance 3.1.47 & 3.1.48)
PUBLIC NOTICE
Members of the public who wish to address the Committee on specific agenda items must register their request at this time,
with such comments subject to the public comment ordinance and the reasonable control of the Committee Chair as set forth
in Robert’s Rules of Order.
APPROVAL OF MINUTES
DISCUSSION/POSSIBLE ACTION
3. Discussion and Possible Action regarding Resolution Approving and Adopting Amendments to the Portage County
2026-2031 Capital Improvement Plan
NEXT MEETING DATE
ADJOURNMENT
Notice: Any person who has special needs and plans on attending this meeting in-person or remotely should contact the Facilities
Office at 715-346-1598 as soon as possible to ensure that reasonable accommodations can be made.
Notice: Remote comment by the public during the meeting will be at the discretion of the Chair.
Notice: A quorum of the Portage County Board of Supervisors, or any committee thereof, may be present at this meeting.
Page 1 of 10
RESOLUTION NO. ___________________
TO: THE HONORABLE CHAIR AND MEMBERS OF THE PORTAGE COUNTY BOARD
OF SUPERVISORS:
RE: RESOLUTION APPROVING AND ADOPTING AMENDMENTS TO THE PORTAGE
COUNTY 2026-2031 CAPITAL IMPROVEMENT PLAN
WHEREAS, at its March 18, 2025 meeting, the Portage County Board of Supervisors
unanimously approved and authorized the schematic design for both the new Jail and Law Enforcement
Center construction and Courthouse remodel capital improvement projects; and
WHEREAS, the schematic design for both capital improvement projects has concluded and
afterwards, County staff and an owner’s representative gave a presentation of the Government Facilities
Master Plan Project addressing the Jail and Law Enforcement Center and Courthouse remodel projects at
the Board of Supervisors Committee of the Whole meeting on October 30, 2025; and
WHEREAS, based upon completion of the schematic design phase, it is necessary to update the
scope, timing, and costs of the new Jail and Law Enforcement Center construction and Courthouse
remodel projects and the corresponding amendments to the Portage County 2026-2031 Capital
Improvement Plan.
FISCAL NOTE: There are no additional fiscal obligations for the County immediately associated
with this resolution, nor does this resolution appropriate funds. The projects do not need any
additional appropriation until such time the County determines a financing plan and issues debt to
finance the projects or appropriates funds for the projects to proceed with construction.
The funds for these projects will be included in the County’s Capital budget.
NOW, THEREFORE, BE IT RESOLVED that the Portage County Board of Supervisors hereby
approves the updates to the Jail and Law Enforcement Center and Courthouse remodel projects and
approves and adopts the corresponding amendments to the existing 2026-2031 Portage County Capital
Improvement Plan.
DATED THIS 18TH DAY OF NOVEMBER, 2025.
RESPECTFULLY SUBMITTED,
SPACE AND PROPERTIES COMMITTEE
Date: November 10, 2025
______________________________ ______________________________
Dave Medin - Chair Jeanne Dodge - Vice Chair
______________________________ ______________________________
Dave Ladick Janell Wehr
______________________________
Nancy Eggleston
Page 2 of 10
FINANCE COMMITTEE
Date: November 10, 2025
______________________________ ______________________________
Larry Raikowski - Chair Dave Ladick - Vice Chair
______________________________ ______________________________
Andrew Rockman Julie Morrow
______________________________
Vinnie Miresse
Page 3 of 10
CAPITAL IMPROVEMENT PLAN 2026-2031
` Proposed
Budget
# Department Project Title Project
Number Score Priority Action Year Current
Appropriation 2026 2027 2028 2029 2030 2031 TOTAL Grants & Other
Revenue
Fund Balance
Applied Debt Proceeds County Levy
1 Highway Road Improvement Projects - Special Revenue Fund 310-99-01 83.60 High Updated Annual Ongoing 4,930,250 4,560,800 8,530,000 8,556,250 3,420,500 5,255,650 35,253,450 9,300,000 12,680,750 13,272,700 -
2 Solid Waste Elevator 310-25-01 42.60 Low Updated 2025 Not Yet Funded 160,450 160,450 - 160,450 - -
3 Parks Standing Rocks - Piston Bully Groomer 510-26-01 50.60 Medium Delayed 2026 Not Yet Funded 265,000 265,000 - - - 265,000
4 Parks Standing Rocks - Snowmaking Equipment 510-28-01 42.00 Low Delayed 2028 Not Yet Funded 150,000 150,000 - - - 150,000
5 Parks Tractor Front End Loader 510-28-02 55.60 Medium As Planned 2028 Not Yet Funded 95,000 95,000 - - - 95,000
6 Planning & Zoning Aerial Photography 610-99-01 66.00 High New 2028 Not Yet Funded 170,000 190,000 360,000 60,000 - - 300,000
7 Facilities Library Flooring 850-24-01 51.80 Medium As Planned 2024 Not Yet Funded 200,000 200,000 - - - 200,000
8 Facilities Emergency Generator Replacement - Law Enforcement Center 850-24-04 67.40 High In Progress 2024 10,000 300,000 310,000 - - - 310,000
9 Facilities Chiller Replacement - Law Enforcement Center 850-24-08 52.40 Medium Delayed 2024 5,000 200,000 205,000 - - - 205,000
10 Facilities Jail/Law Enforcement Center - New Construction 850-25-01 81.40 High In Progress 2025 2,775,000 55,170,000 60,000,000 40,000,000 157,945,000 - - 157,945,000 -
11 Facilities Courthouse - Remodel Construction 850-25-02 78.20 High In Progress 2025 900,000 4,830,000 25,000,000 30,730,000 - - 30,730,000 -
12 Facilities Walk-in Compressor Replacement - Lincoln Center 850-25-05 55.00 Medium Delayed 2025 Not Yet Funded 125,000 125,000 - - - 125,000
13 Facilities Exterior Building Repair - Law Enforcement Center 850-25-10 55.20 Medium Delayed 2025 Not Yet Funded 50,000 50,000 - - - 50,000
14 Facilities Parking Lot Resurfacing - Annex Facility 850-26-03 60.40 Medium As Planned 2026 Not Yet Funded 500,000 500,000 - - - 500,000
15 Facilities Relocation Building for Courthouse 850-26-04 71.80 High New 2026 Not Yet Funded 4,650,000 4,650,000 - - 4,650,000 -
16 Facilities Warehouse Building - Jordan Park 850-26-05 57.80 Medium New 2026 Not Yet Funded 35,000 715,000 750,000 - - - 750,000
17 Information Tech Fiber Installation - Jordan Parks Location 860-26-01 47.50 Medium New 2026 Not Yet Funded 250,000 250,000 250,000 - - -
18 Information Tech Data Center Equipment 860-28-01 75.60 High As Planned 2027 Not Yet Funded 540,000 540,000 540,000 - - -
19 Information Tech Network Switching Infrastructure 860-29-01 78.20 High New 2029 Not Yet Funded 670,000 670,000 670,000 - - -
Gross Expenditures 3,690,000 71,040,700 65,690,800 48,830,000 9,941,250 3,420,500 30,595,650 233,208,900 10,820,000 12,841,200 206,597,700 2,950,000
2026 2027 2028 2029 2030 2031 TOTAL
Funding Source Estimates
Estimated County Tax Levy 950,000 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000 5,950,000
Estimated CIP Fund Balance - Applied/(Designated for Future) 4,930,000 (410,000) (720,000) (285,000) (1,000,000) (700,000) 1,815,000
Grants/Other Revenue 650,000 740,000 3,820,000 5,070,000 - 540,000 10,820,000
Fund Balance 4,690,700 - 4,730,000 - 3,420,500 - 12,841,200
Estimated CIP Debt Service 59,820,000 60,000,000 40,000,000 - - 25,000,000 184,820,000
Estimated Enterpise Debt Service - - - - - - -
Estimated Highway (HWY) Debt Service - 4,360,800 - 4,156,250 - 4,755,650 13,272,700
71,040,700 65,690,800 48,830,000 9,941,250 3,420,500 30,595,650 229,518,900
Future Anticipated Appropriation Anticipated Revenue Sources
Page 4 of 10
County of Portage
Finance Department
Capital Project
Funding Request Form
Policy #: TBD
Effective: December 11, 2024
Project # 850-25-01 Project Title Jail/Law Enforcement Center Construction
Department Facilities Manager Todd Neuenfeldt/Chris Schultz/Michael Lukas
Phase Design
Budget Action In Progress Date Updated November 10, 2025
Project Scope & Description
This project is to build a modern facility that meets current correctional standards and supports law enforcement
operations.
Cost Summary
Source of Funds 2025 &
Prior Years FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 Project Total
Debt Financing $2,775,000 $55,170,000 $60,000,000 $40,000,000 $157,945,000
Grants/Aids
Other:
Tax Levy
Total $2,775,000 $55,170,000 $60,000,000 $40,000,000 $0 $0 $157,945,000
Cost Documentation 2025 &
Prior Years FY 2026 FY 2027 FY 2028 FY 2027 FY 2030 Project Total
Design & Engineering $2,775,000 $5,105,987 $1,078,730 $719,153 $9,678,870
Site Preparation $6,889,195 $1,377,839 $918,559 $9,185,593
Land Acquisition
Construction $5,921,701 $80,190,885 $29,095,612 $115,208,198
Furniture & Equipment $3,013,925 $6,027,850 $9,041,775
Contingency $721,171 $9,766,001 $3,543,392 $14,030,564
Financing Costs $96,589 $494,538 $208,873 $800,000
Total $2,775,000 $18,734,643 $95,921,918 $40,513,439 $0 $0 $157,945,000
Operating Impact
Analysis of Need
Over 26 years ago, the current LEC was constructed, and was outdated and undersized the day it opened for business.
Numerous studies, both internal and external, and shown that the facility is inadequate and in need of replacement or
improvement. Numerous studies are available which outline the analysis of the current building. In summary, problems
with the current Jail and Law Enforcement Center facility have been identified as such:
Jail & Juvenile Detention
• Existing facility is overcrowded
Page 5 of 10
Page 2 of 3
CIP Form 1 (12/11/2024)
• Lacks adequate facilities to properly segregate inmate population
• Lacks adequate basic security holding and medical facilities needed to safeguard inmates and staff
• Lacks adequate security design needed to prevent contraband and weapons from entering the facility
• Lacks adequate storage facilities
• Lacks adequate programming and recreational space
• Vehicle sallyport poorly designed, making entry difficult, and cannot accommodate an ambulance, or second
vehicle
• Lacks ability to bullpen incoming inmates causing unnecessary security problems
• Lacks adequate employee facilities (office space, bathroom, locker, break area, etc.)
• Lacks adequate facilities to address the growing need for pre-trial to post-conviction monitoring of prisoners
• Lack the ability to safely and securely transport inmates and children to court
• Aging facilities that will need replacement (e.g. locks, cameras, HVAC)
• Environmental controls are inadequate to properly and efficiently regulate the building
Sheriff’s Office
• Lacks sufficient office space and related facilities
• Lacks adequate room for proper communications center
• Lacks adequate garage space to protect and safeguard the fleet
• Lacks sufficient room for vehicle and equipment maintenance
• Garage poorly designed making entry difficult in the winter, and detached garage is inadequate
• Lacks sufficient storage space
• Evidence room is overcrowded and inadequate for legal storage needs
• Lacks adequate bathroom and locker facilities for the number of staff
• Environmental controls are inadequate to properly and efficiently regulate the building
• Emergency Operations Center (EOC) is undersized, ill equipped, and poorly situated
• EOC lacks security needed during ongoing operations
Ongoing Operational Costs & Alternatives
The alternatives include an extensive remodel of the current facility but severely reducing the number of beds and
category placement within the jail at an extensive cost. Another alternative is to continue to operate as is, suffering
from the inefficiencies, waste, safety issues, health concerns, legal difficulties, and increased liability concerns identified
in the numerous studies commissioned by Portage County.
As outlined in the previous studies and analysis for the County Board, costs will only increase over time.
Sustainability, Maintenance, and Replacement
A modern facility will require proper maintenance and preventative maintenance on new mechanical systems. The new
facility is expected to last 25-40 years.
Citizen & Community Impact
A new modern facility will provide a secure and accessible facility, improve the overall functionality and operational
efficiency of sheriff and jail operations, and address long-term planning for space needs of the department while doing
so in a fiscally responsible manner.
Page 6 of 10
Page 3 of 3
CIP Form 1 (12/11/2024)
Location & Map
Corner of County Road R and Black Oak Drive, Plover, WI 54467
Previous Actions
2004: The Portage County Board of Supervisors reviewed a comprehensive study of County Facilities, prepared by the
DLR Group, which identified the Portage County Jail facility as inadequate due to overcrowding, which in turn causes a
high cost of transporting inmates, thus creating the need to study, review, and implement a new Justice Center Facility.
The Portage County Board of Supervisors endorsed the need to study, review, and implement a new Justice Center
Facility as the number one priority in Portage County.
2006: Another extensive and costly study by Mark Goldman & Associates highlighted the deficiencies of the present
Portage County Jail facility, identifying prime factors including overcrowding, poor design and layout, and inefficient staff
configurations. The same study highlighted the projected growth of court and criminal cases in the years ahead,
showcasing the requirement that any new facility be prudently designed to assure decades of safe and cost-efficient use.
2009: Subsequent research by the Venture Architects firm has corroborated and confirmed the conclusions of the
earlier studies finding a need for a new jail.
2011 and 2012: The Sheriff’s Office submitted capital improvement requests to address some of the issues in the LEC.
Those projects were put on hold pending future action on a new facility.
2013: The Portage County Board of Supervisors endorsed the concept of constructing a new unified correctional
institution, housing the Jail, Juvenile Detention Facility, rehabilitation programming facilities, and a transitional housing
unit in a single structure connected or incorporated with the Circuit Courts.
2014: A staff work group was instituted by the Space and Properties Committee to assist in the development of a new
facility concept.
2015: Venture Architects was hired to begin conceptualizing a new facility as outlined by the County Board.
2018: Hired Dewberry for conceptual design options for government facility including jail/LEC and courthouse options
for both new construction and remodel of existing facilities.
2022: Hired Tegra as the County owner’s representative and Findorff as construction manager to work with Dewberry
to further design options.
2023: Considered four options to address justice center facility needs, which included options for new construction and
renovating existing County buildings. A resolution to finance a new justice center (courthouse/LEC/jail) on a greenfield
site was forwarded to the County Board and failed due to the cost and location. After the failed option, the County
Board decided to split the LEC/jail and Courthouse facilities.
2024: Purchased land for a new LEC/jail facility in Plover, WI.
2025: Passed a resolution to finance schematic design of a new Sheriff’s Office/Jail.
2025-2030 Capital Plan: Submitted as a new request.
2026-2031 Capital Plan: In Progress. Updated project cost.
Page 7 of 10
County of Portage
Finance Department
Capital Project
Funding Request Form
Policy #: TBD
Effective: December 11, 2024
Project # 850-25-02 Project Title Courthouse Remodel Construction
Department Facilities Manager Todd Neuenfeldt
Phase Design
Budget Action In Progress Date Updated November 10, 2025
Project Scope & Description
The County/City Building is 66 years old, completed in 1959. Although the building has held up well through the years,
the County must make significant renovations in order to maintain the aging infrastructure and make it a viable
Courthouse for the next 20-25 years. This project requires the City of Stevens Point to vacate its existing space and
move out in order for this renovation to be successful.
In Spring of 2024, Dewberry Architects, Findorff Construction, along with MEP Consultants, and structural engineers
started a full review of all 72,000 sq ft to be presented at the beginning of 2025. A conceptual design along with a full
report on MEP and Structural integrity will be contained in that report. Preliminary reports indicated that the project is
feasible based on initial areas under review.
Some features being incorporated are as follows:
1. Developing one secure entrance to the Courthouse.
2. Increased judicial space, office space, and security for the Family Court Commissioner.
3. Improved ADA Compliance Access
4. Upgrade Court Technology and AV Equipment for the Courtrooms.
This project is essential to address immediate concerns of the Courthouse in the way of Safety and Security, prior to
moving forward with the remainder of the remodel and renovation.
The full remodel of the Courthouse is planned to begin in 2030 and to include the following:
1. The addition of a fourth branch courtroom as requested by Judges, plus a full courthouse suite renovation for
Family Court.
2. Update entrance for security purposes and relocate security operations to provide for improved safety and
security throughout the building.
3. Secure parking for Judges and District Attorney along with garden level sallyport, additional elevator, and third
floor security bar and holding cells for secure movement of inmates.
4. Remodeling space for Justice Programs area with proper access and security, along with County Board and
training room, and Veterans Services on the garden level of the existing building.
5. Expansion of District Attorney and Clerk of Courts offices to the existing space occupied by the City of Stevens
Point, to include renovation and updating for office needs.
6. Refresh and update existing programming spaces to modern facilities for Corporation Counsel, County Clerk,
Register of Deeds, Register of Probate, Treasurer, and County Board offices.
Page 8 of 10
Page 2 of 3
CIP Form 1 (12/11/2024)
Cost Summary
Source of Funds
2025 &
Prior
Years
FY 2026 FY 2027 FY 2030 FY 2031 FY 2032 Project
Total
Debt Financing $900,000 $4,830,000 $25,000,000 $30,000,000 $60,730,000
Grants/Aids
Other:
Tax Levy
Total $900,000 $4,830,000 $0 $0 $25,000,000 $30,000,000 $60,730,000
Cost Documentation
2025 &
Prior
Years
FY 2026 FY 2027 FY 2030 FY 2031 FY 2032 Project
Total
Design & Engineering $900,000 $480,000 $1,380,000
Site Preparation
Building Improvements $2,000,000 $25,000,000 $30,000,000 $57,000,000
Furniture & Equipment $2,120,000 $2,120,000
Contingency $230,000 $230,000
Fees & Bonds
Insurance
Financing Costs
Total $900,000 $4,830,000 $0 $0 $25,000,000 $30,000,000 $60,730,000
Operating Impact
Analysis of Need
The Courthouse is over 65 years old and has had very few improvements. The current HVAC system is antiquated; it
does not meet the needs of the building and many building features are past their useful life. The sanitary piping
between floors and the buried pipes are in poor repair and past their useful life. Most of the bathrooms are not ADA
compliant and require re-piping verses just fixture replacement to be brought to code.
All of the projects improve the structural quality of the building, add safety features of a modern-day courthouse, and
allow continued use as a Courthouse for the next 20-25 years. Many of the upgrades bring the building into Adults with
Disabilities Act (ADA) compliance. Given the age of the building, if repairs and/or replacement parts (e.g. for elevators)
are not purchased now, they may not be available in the future and reliability will decrease.
Ongoing Operational Costs & Alternatives
If the project was to terminate, various other capital projects to make building improvements would follow, or the
facility repairs would be done as needed. The ongoing operational costs will be determined based on the project scope
as determined during the design phase.
Sustainability, Maintenance, and Replacement
This will be determined during the remodel design phase as the scope is further refined.
Page 9 of 10
Page 3 of 3
CIP Form 1 (12/11/2024)
Citizen & Community Impact
A remodeled and redesigned modern facility will provide a secure and accessible facility for staff and the public while
keeping the courthouse in its downtown location. The project will help to improve the overall functionality and
operational efficiency of courthouse operations while completing the project in a fiscally responsible manner.
Location & Map
Portage County Courthouse, 1516 Church Street, Stevens Point, WI 54481
Previous Actions
Several of the projects have been proposed in previous capital plans. This new proposal incorporates them into one
complete project.
2017: Venture Architects contract for $24,950, for a Scope of Work to include updating space program, layouts, and
cost estimates. Contract work with be completed in conjunction with a RFP for an Owner’s Representative.
2018: Owner’s Representative hired and an RFP is in process to hire an Architect for design of a new Government
Building and the remodel of the Current Courthouse. The City of Stevens Point has moved the Police Department out of
the current Courthouse, freeing up additional space available for County operations. The City of Stevens Point is in the
process of designing a New City Hall.
2018: Hired Dewberry for conceptual design options for government facility including jail/LEC and courthouse options
for both new construction and remodel of existing facilities.
2022: Hired Tegra as the County owner’s representative and Findorff as construction manager to work with Dewberry
to further design options.
2023: Considered four options to address justice center facility needs, which included options for new construction and
renovating existing County buildings. A resolution to finance a new justice center (courthouse/LEC/jail) on a greenfield
site was forwarded to the County Board and failed due to the cost and location. After the failed option, the County
Board decided to split the LEC/jail and Courthouse facilities.
2025-2030 Capital Plan: Submitted as a new request.
2026-2031 Capital Plan: In Progress. Updated project cost and timeline.