RecordWell Data

Board of Public Works — Agenda Packet

City of Stevens Point · Portage County · Board of Public Works · meeting of Apr 14, 2025 · Agenda packets

Open the original document More from City of Stevens Point

Text

Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.

Our intention is to have in-person meetings going forward. For the time being, we will hold the City Committee Meetings, Plan Commission, Council and most others at the Community Room at 933 Michigan Avenue. This in-person location will meet the legal requirement for our open meetings. We will have a virtual option available, but the technology for the hybrid style meeting may not be reliable all of the time. CITY OF STEVENS POINT BOARD OF PUBLIC WORKS MEETING April 14, 2025 - 6:15 PM (or immediately following previously scheduled meeting) Community Room 933 Michigan Avenue, Stevens Point, WI OR Zoom Teleconferencing Meeting ID: 852 6405 4662 | Passcode: 909157 By Computer: https://us02web.zoom.us/j/85264054662?pwd=9jjfI5mJxnGKgbN6uLcQlShITkAsNI.1 By Phone: +1-312-626-6799 (US Chicago) (A quorum of the City Council may attend this meeting) AGENDA Roll Call Informational 1. Director's Report a. 2025 Street Improvements Project (Madison/Monroe) b. West River Drive c. West Zinda Bridge Discussion and Possible Action 2. To approve the ordinance amendment in Chapter 9, Section 9.12, as it relates to Bicycle Ways, and Chapter 10, Subsections 10.01 and 10.05, as they relate to City Parks. 3. To award the Street Improvements Project (Washington Avenue) #25-101 to Haas Sons, Inc. out of Thorp, Wisconsin in an amount not to exceed $4,792,534.90. 4. To award the Street Improvements Project (Madison Street) #25-102 to Switlick & Sons, Inc. out of Athens, Wisconsin in an amount not to exceed $3,811,709.50. Adjourn Meeting Rider Any person who has special needs while attending this meeting or needing agenda materials for this meeting should Page 1 of 16 contact the City Clerk as soon as possible to ensure a reasonable accommodation can be made. The City Clerk can be reached by telephone at (715) 346-1569, TDD # 346-1556 or by mail at 1515 Strongs Ave., Stevens Point, WI 54481. Copies of ordinances, resolutions, reports and minutes of the committee meetings are on file at the office of the City Clerk for inspection during normal business hours from 7:30 a.m. to 4:00p.m. Page 2 of 16 s t e v e n s p o i n t . c o m April 4, 2025 DIRECTOR OF PUBLIC WORKS REPORT Scott Beduhn 1. Engineering Division •Country Club Drive: oAfter several delays, the engineering and design are nearing completion. oBidding is anticipated to occur later this spring with construction taking place in the late summer and early fall. oWPS is currently relocating utilities in anticipation of the reconstruction work. •Division and Church Streets Reconstruction Project: oAECOM continues working to complete final designs for the North Segment (North Point Drive to Fourth Avenue) and far South Segment (South City Limits to Michigan Avenue) which are both at a 60 percent design stage. ▪Preliminary matters related to real estate acquisition for both projects is underway. ▪WPS is preparing for the relocation of overhead utilities throughout the North Segment which should occur later this year. •2024 Street Improvement Project (Northside): oThe contractor has begun mobilizing and setting up traffic control. Pavement removals and temporary water installation will begin soon before the installation of utilities. oThe contractor is anticipating completing the remaining work by June. oIn addition, the contractor will be addressing warranty issues pertaining to the work completed last year. •2024 Street Improvement Project (Southside): oAll work is complete. The contractor will return this spring to address any warranty items. •2025 Street Improvement Project (Washington Ave): oA bid opening was held on April 1, 2025. The lowest bid was submitted by Haas Sons, Inc. out of Thorp, Wisconsin in an amount of $4,167,21.65. oA public “preconstruction meeting” will be held for both the Washington Avenue and Madison/Monroe projects on April 23, 2025. ▪The purpose of the meeting is to give residents and property owners the opportunity to meet our inspection staff and ask last-minute questions they may have before the start of construction. •2025 Street Improvement Project (Madison/Monroe): oA bid opening was held on April 2, 2025. The lowest bid was submitted by Switlick and Sons, Inc. out of Athens, Wisconsin, in an amount of $3,314,530.00, including alternate bid City of Stevens Point 1515 Strongs Avenue Stevens Point, WI 54481 Public Works Engineering Department: Phone: 715-346-1561 Fax: 715-346-1650 Streets Department: Phone: 715-346-1537 Fax: 715-346-1687 Page 3 of 16 s t e v e n s p o i n t . c o m items. ▪Alternates were included in this project after the initial capital request was reduced in the final approved budget. The alternates are portions of the original project that could either be included or excluded based upon if the actual bid price was within or outside of the project budgeted amount. oA public “preconstruction meeting” will be held for both the Washington Ave and Madison/Monroe projects on April 23, 2025. ▪The purpose of the meeting is to give residents and property owners the opportunity to meet our inspection staff and ask last-minute questions they may have prior to the start of construction. •East Park Commerce Center Badger Avenue Extension: oDue to delays in materials and electrical service installation, the lighting system is not yet operable. All the other work is complete. ▪The remaining materials have recently been delivered, and the contractor is coordinating the installation of the electrical service with WPS. •Forest Creek Subdivision: oNothing new to report •Curb Gutter and Sidewalk Repair Project: oNothing new to report. •Fall Paving Project: oNothing new to report. •Pavement Maintenance Project: oStaff is preparing a scope of work for this year’s pavement maintenance, which should be bid later this spring. •West River Drive: oAECOM is preparing a draft technical memo to present the general findings of the traffic evaluation ▪A final technical memo will be created after receiving public input at the second planned public informational meeting. •A second public informational meeting is anticipated for May. •West Zinda Bridge: oWork on the bridge should take place this summer; however, staff is waiting to hear from WisDOT on the contractors' anticipated construction schedule. •Michigan Avenue Underpass: oAfter receiving additional public input at the second public informational meeting, the City’s consultant is preparing a scope of work for the next phases of the project. •Hoover Road Intersection Signalizations: oThe installation contractor is anticipating completing preliminary work before the delivery of the signal equipment, including the installation of buried conduits and signal bases. ▪A preconstruction conference with the contractor is planned for later this month, at which time the contractor will provide a more detailed schedule •The latest anticipated delivery timeframe for the signal equipment is now mid- August. Page 4 of 16 s t e v e n s p o i n t . c o m •Park Street Railroad Crossing Closure investigation: oStaff is beginning to evaluate truck route options and potential roadway improvements for the possible rail crossing closure. oAfter completing some preliminary engineering, staff anticipates holding a public informational meeting in late spring or early summer. •SS4A Grant – Demonstration Activities (DAs): oThe SS4A stakeholder members (Demonstration Activities subcommittee) have identified three Demonstration Activities to be completed within the City of Stevens as part of the SS4A grant. The three activities include: ▪Temporary curb extensions at the intersection of Fourth Avenue and Isadore Street. ▪Buffered bike lanes along Water Street between Riverview Avenue and Kwik Trip. ▪Buffered bike lanes along Michigan Avenue between Patch Street and Dixon Street. oThese DAs will take place during the months of April and May. ▪Public Works staff will be installing delineators to create the temporary curb extensions and buffered bike lanes and will also be conducting both pre- and post-installation data collection. •Additional Miscellaneous Projects: oEngineering Staff continue working on proposed 2026 and 2027 roadway projects, including gathering survey data, researching right of way, and preparing bidding documents. oEngineering staff have been working with university staff on several fronts to improve the University environment. These include: ▪Discussions in conjunction with Community Development on the future of the old Maytag lot. ▪Discussions regarding the reconstruction of Fourth Avenue through campus, which is tentatively scheduled for reconstruction in 2027. oStaff continue to work with the Utility Department on various water, sanitary, stormwater, and fiber projects. oStaff continue to work with the Community Development Department on various projects. These projects include: ▪Forest Creek subdivision ▪Shopko redevelopment 2. Streets Division- February Continued Operations: oGarbage and Recycling oStreet Sign Compliance and replacement oStreet Light Maintenance oStreet Patching/Trumbull oDrop off Site Operations Staffing: The Streets Department remains fully staffed this month. However, one Lead is currently on leave and is expected to be away for the next couple of months. Winter Maintenance: The department has responded to seventeen winter events so far this season, including four in March. Notably, March recorded the highest total snowfall of the season to date. The storms were wet, heavy snow, and ice, which added challenges and Page 5 of 16 s t e v e n s p o i n t . c o m frustration for both crews and residents. March also marked the highest salt usage of the season—approximately double the amount used during the rest of the winter combined. Patching: March’s weather patterns made pothole patching challenging. Our crews plowed snow nearly every week in March. The streets experienced a consistent freeze-thaw cycle. This caused much of the cold patch material applied the previous week to come lose. This was a larger challenge on our rougher sections of W. Clark Street, and Church and Division Street. We also received our new Trumbull machine (used for patching our concrete roads) in March. This unit has a wand similar to our crack fill machine, which should make the patching process more efficient. As we transition into April and the weather begins to warm up, we hope to quickly patch the potholes around the city. Sweeping: As weather permitted, we began our initial pass of street sweeping for 2025 in February. Unfortunately March’s weather slowed progress. We are about 30% complete with the first sweep of the city. Equipment maintenance/garage: In March, we conducted another auction for old fleet vehicles. We are still awaiting delivery of the remaining 2024 squads from our vendor. All 2025 fleet replacement vehicles have been ordered. Upcoming events: -Sumer maintenance crews to start at the end of April. -Various safety trainings to take place for all crews in April Respectfully submitted, Superintendent Johnson Page 6 of 16 s t e v e n s p o i n t . c o m April 1, 2025 To: Board of Public Works From: Scott Beduhn, Director of Public Works Re: Ordinance Amendments The ordinance amendment of Section 9.12(q)(I) 21, amending Bicycle Ways, is the result of an error discovered in the description of the ordinance. The ordinance amendment of Section 10.01(2), amending Definitions and Terms, is the result of changing the name and the addition of a city park. The ordinance amendment of Section 10.05, Closing Hours, is the result of a request made by the Stevens Point Police Department. If there are any questions, please do not hesitate to contact me. Thank you City of Stevens Point 1515 Strongs Avenue Stevens Point, WI 54481 Public Works Engineering Department: Phone: 715-346-1561 Fax: 715-346-1650 Streets Department: Phone: 715-346-1537 Fax: 715-346-1687 Page 7 of 16 ORDINANCE AMENDING THE REVISED MUNICIPAL CODE OF THE CITY OF STEVENS POINT, WISCONSIN The Common Council of the City of Stevens Point do ordain as follows: SECTION I: That subsection 21 of Section 9.12(q)(I) of the Revised Municipal Code, Bicycle Ways is hereby amended to read as follows: 9.12(q)(I) 21. The path on the west side of Badger Avenue from E.M. Copps Drive to County Road HH. SECTION II: That subsection (2) of Section 10.01 of the Revised Municipal Code, Definitions and Terms is hereby amended to read as follows: 10.01 (2) Park, City Park, and Stevens Point Park. The terms "park,” "city park,” and "Stevens Point Park" are defined to mean all lands and water heretofore and hereafter acquired by the city for park or recreational purposes or placed under the jurisdiction of the parks commission and include without limitation parks, beaches, swimming pools, and privately owned lands, the use of which has been granted to the city for park, recreational, or like public purposes. The following areas are designated as Stevens Point parks: Admiral Grant Atwell Bukolt Conifer East Oaks Goerke Green Circle Hein Iverson John S. Groholski Koziczkowski McGlachlin Mead Morton Parkwood Pfiffner Pioneer Park Plover Hills Park 1 Plover Hills Park 2 Plover River Rice Street Riverwoods Rogers Park Sculpture Park Seramur Slomann Texas Veterans Memorial Village Green Whitetail Yulga Zenoff SECTION III: That Section 10.05 of the Revised Municipal Code, Closing Hours is hereby amended to read as follows: 10.05 CLOSING HOURS. It shall be unlawful for any person to enter or be in any city park between the hours of 11:00 P.M. and one-half hour before sunrise with the following exceptions: (1) A city-sponsored or city-approved event. Page 8 of 16 (2) When a park lodge has been rented for a special event, on which occasion the closing hour shall be 1:00 A.M. (3) Activities directly related to boating or fishing in boat launching and trailer parking areas. (4) No parking is permitted in John S. Groholski Park outside of the regular park hours. SECTION IV: These Ordinance changes shall take effect upon passage and publication. APPROVED: Mike Wiza, Mayor ATTEST: Kari Yenter, City Clerk Dated: April 1, 2025 Approved: April 21, 2025 Published: May 1, 2025 Page 9 of 16 s t e v e n s p o i n t . c o m April 2, 2025 To: Board of Public Works From: Scott Beduhn, Director of Public Works Re: Contract Award Recommendation 2025 Street Improvements – Washington Avenue, Project 25-101 Bids for the 2025 Street Improvements – Washington Avenue Project were received on April 1, 2025. A total of four bids were received ranging from approximately $4.17 million to $4.94 million. The bids are summarized in the attached bid tabulation. The two lowest bids were separated by 1.3 percent. The lowest bid was submitted by Haas Sons, Inc. out of Thorp, WI. The City has worked with Haas in the past, most recently on the Badger Avenue Extension Project in 2024. Based upon their past performance staff believes that Haas is a responsible bidder and is qualified and capable of performing the work. It is staff’s recommendation that the project be awarded to Haas Sons, Inc. in an amount not to exceed $4,792,534.90, including a 15 percent contingency. If there are any questions, please do not hesitate to contact me. Thank you. Z:\90 - MEETINGS\2025 - MEETINGS\04 - April\Memo - Award Street Improvements - Washington - Project 25-101.doc City of Stevens Point 1515 Strongs Avenue Stevens Point, WI 54481 Public Works Engineering Department: Phone: 715-346-1561 Fax: 715-346-1650 Streets Department: Phone: 715-346-1537 Fax: 715-346-1687 Page 10 of 16 2025 Street Improvements - Washington Avenue Project 25-101 (#9586416) Owner: City of Stevens Point 04/01/2025 10:00 AM CDT Line Item Item Code Item Description UofM Quantity Unit Price Extension Unit Price Extension Unit Price Extension Unit Price Extension 1 B1 Mobilization LS 1 $263,850.00 $263,850.00 $153,113.00 $153,113.00 $370,000.00 $370,000.00 $300,000.00 $300,000.00 2 B2 Common Excavation CY 12600 $18.00 $226,800.00 $19.00 $239,400.00 $17.00 $214,200.00 $20.00 $252,000.00 3 B3 Rock Excavation - Utility Trench (Undistributed) CY 300 $1.00 $300.00 $1.00 $300.00 $100.00 $30,000.00 $10.00 $3,000.00 4 B4 Utility Demolition LS 1 $84,500.00 $84,500.00 $80,000.00 $80,000.00 $21,000.00 $21,000.00 $45,000.00 $45,000.00 5 B5 Excavation Below Subgrade (EBS)(Undistributed) CY 2000 $18.00 $36,000.00 $16.00 $32,000.00 $17.00 $34,000.00 $10.00 $20,000.00 6 B6 Concrete Sidewalk Removal SF 33695 $0.72 $24,260.40 $1.00 $33,695.00 $1.00 $33,695.00 $1.10 $37,064.50 7 B7 Concrete Curb and Gutter Removal LF 6404 $3.50 $22,414.00 $4.00 $25,616.00 $2.75 $17,611.00 $4.00 $25,616.00 8 B8 Prepare Foundation for Asphaltic Paving LS 1 $26,000.00 $26,000.00 $30,000.00 $30,000.00 $25,840.00 $25,840.00 $26,000.00 $26,000.00 9 B9 Biaxial Geogrid SY 18000 $2.25 $40,500.00 $2.00 $36,000.00 $2.25 $40,500.00 $2.10 $37,800.00 10 B10 Dense Graded Base, 1 1/4-in TON 20050 $15.35 $307,767.50 $18.00 $360,900.00 $16.75 $335,837.50 $18.00 $360,900.00 11 B11 Dense Graded Base, 3/4-in TON 140 $23.85 $3,339.00 $28.00 $3,920.00 $19.00 $2,660.00 $30.00 $4,200.00 12 B12 Granular Backfill, Imported LF 15000 $9.40 $141,000.00 $0.01 $150.00 $0.01 $150.00 $5.00 $75,000.00 13 B13 HMA Pavement - 3MT 58-28 S TON 2100 $95.20 $199,920.00 $96.00 $201,600.00 $95.20 $199,920.00 $96.00 $201,600.00 14 B14 HMA Pavement - 4MT 58-34 S TON 2055 $103.70 $213,103.50 $104.00 $213,720.00 $103.70 $213,103.50 $104.00 $213,720.00 15 B15 Concrete Sidewalk, 4-in. SF 33160 $5.00 $165,800.00 $6.00 $198,960.00 $5.50 $182,380.00 $5.20 $172,432.00 16 B16 Concrete Sidewalk, 6-in. SF 11260 $6.15 $69,249.00 $6.50 $73,190.00 $6.20 $69,812.00 $6.35 $71,501.00 17 B17 Detectable Warning Field SF 660 $35.00 $23,100.00 $29.00 $19,140.00 $30.00 $19,800.00 $35.00 $23,100.00 18 B18 Concrete Driveway, 6-in. SF 7620 $6.40 $48,768.00 $6.50 $49,530.00 $6.50 $49,530.00 $6.60 $50,292.00 19 B19 Curb and Gutter, 18-in. LF 72 $14.75 $1,062.00 $58.00 $4,176.00 $15.00 $1,080.00 $15.00 $1,080.00 20 B20 Curb and Gutter, 24-in. LF 9030 $15.75 $142,222.50 $16.00 $144,480.00 $16.00 $144,480.00 $16.00 $144,480.00 21 B21 Concrete Pedestrian Curb LF 250 $17.00 $4,250.00 $100.00 $25,000.00 $16.00 $4,000.00 $17.50 $4,375.00 22 B22 Concrete Poured in Place Wall LF 310 $25.00 $7,750.00 $105.00 $32,550.00 $24.00 $7,440.00 $30.00 $9,300.00 23 B23 Concrete Steps SF 140 $90.00 $12,600.00 $79.00 $11,060.00 $80.00 $11,200.00 $100.00 $14,000.00 24 B24 Class "B" Bedding (Storm Sewer and Water Main) LF 7700 $14.00 $107,800.00 $1.00 $7,700.00 $0.01 $77.00 $15.00 $115,500.00 25 B25 Storm Sewer Pipe, Corrugated HDPE, Class III-A, 12-in. LF 713 $53.00 $37,789.00 $73.00 $52,049.00 $73.00 $52,049.00 $74.00 $52,762.00 26 B26 Storm Sewer Pipe, Corrugated HDPE, Class III-A, 15-in. LF 2604 $58.50 $152,334.00 $73.00 $190,092.00 $92.00 $239,568.00 $76.00 $197,904.00 27 B27 Storm Sewer Pipe, Corrugated HDPE, Class III-A, 18-in. LF 332 $64.00 $21,248.00 $83.00 $27,556.00 $98.00 $32,536.00 $87.00 $28,884.00 28 B28 Storm Sewer Pipe, Corrugated HDPE, Class III-A, 24-in. LF 633 $77.00 $48,741.00 $141.00 $89,253.00 $126.00 $79,758.00 $95.00 $60,135.00 29 B29 Storm Sewer Pipe, Corrugated HDPE, Class III-A, 30-in. LF 850 $96.00 $81,600.00 $153.00 $130,050.00 $142.00 $120,700.00 $110.00 $93,500.00 30 B30 Storm Sewer Lateral, Schedule 40 PVC, 4-in. LF 1748 $66.00 $115,368.00 $65.00 $113,620.00 $100.00 $174,800.00 $98.00 $171,304.00 31 B31 Storm Sewer Lateral, SDR 35 PVC, 10-in. LF 30 $105.00 $3,150.00 $92.00 $2,760.00 $152.00 $4,560.00 $72.00 $2,160.00 32 B32 Drain Basin with Casting, 24-in. EA 42 $4,275.00 $179,550.00 $4,475.00 $187,950.00 $4,000.00 $168,000.00 $3,200.00 $134,400.00 33 B33 Drain Basin with Casting, 30-in. EA 2 $5,975.00 $11,950.00 $6,265.00 $12,530.00 $5,800.00 $11,600.00 $4,800.00 $9,600.00 34 B34 Relocate Drain Basin with Casting, 24-in. EA 7 $4,150.00 $29,050.00 $3,500.00 $24,500.00 $2,630.00 $18,410.00 $2,000.00 $14,000.00 35 B35 Storm Sewer Manhole, with Casting, 48-in. DIA EA 9 $4,800.00 $43,200.00 $5,420.00 $48,780.00 $5,000.00 $45,000.00 $5,400.00 $48,600.00 36 B36 Storm Sewer Manhole, with Casting, 60-in. DIA EA 2 $8,800.00 $17,600.00 $9,855.00 $19,710.00 $9,000.00 $18,000.00 $10,000.00 $20,000.00 37 B37 Storm Sewer Manhole, with Casting, 72-in. DIA EA 2 $12,800.00 $25,600.00 $13,315.00 $26,630.00 $12,000.00 $24,000.00 $13,500.00 $27,000.00 38 B38 Storm Sewer Manhole, with Casting, 48-in. DIA, Doghouse Style EA 2 $7,900.00 $15,800.00 $6,430.00 $12,860.00 $8,050.00 $16,100.00 $9,000.00 $18,000.00 39 B39 Sanitary Lateral, SDR 35 PVC, 6-in. LF 2155 $67.00 $144,385.00 $88.00 $189,640.00 $128.00 $275,840.00 $95.00 $204,725.00 40 B40 Sanitary Sewer, SDR 35 PVC, 8-in. LF 3703 $67.50 $249,952.50 $86.00 $318,458.00 $134.00 $496,202.00 $145.00 $536,935.00 41 B41 Sanitary Sewer, SDR 35 PVC, 12-in. LF 34 $224.00 $7,616.00 $124.00 $4,216.00 $300.00 $10,200.00 $232.00 $7,888.00 42 B42 Sanitary Sewer Manhole, with Casting, 48-in. DIA EA 6 $5,975.00 $35,850.00 $6,270.00 $37,620.00 $5,590.00 $33,540.00 $6,800.00 $40,800.00 43 B43 Adjust Existing Structure EA 10 $1,950.00 $19,500.00 $2,400.00 $24,000.00 $3,372.00 $33,720.00 $2,200.00 $22,000.00 Haas Sons, Inc. A-1 Excavating LLC Integrity Grading and Excavating, Inc. Earth Inc. Page 11 of 16 44 B44 Watermain, C900 PVC, 6-in. LF 364 $87.75 $31,941.00 $101.00 $36,764.00 $130.00 $47,320.00 $130.00 $47,320.00 45 B45 Watermain, C900 PVC, 8-in. LF 3114 $80.00 $249,120.00 $101.00 $314,514.00 $121.00 $376,794.00 $152.00 $473,328.00 46 B46 Watermain, C900 PVC, 12-in. LF 20 $465.50 $9,310.00 $316.00 $6,320.00 $300.00 $6,000.00 $400.00 $8,000.00 47 B47 Polyethylene Water Service Lateral, 1-in. LF 2053 $77.75 $159,620.75 $100.00 $205,300.00 $89.00 $182,717.00 $98.00 $201,194.00 48 B48 Fire Hydrant Assembly EA 6 $9,050.00 $54,300.00 $8,065.00 $48,390.00 $9,300.00 $55,800.00 $10,000.00 $60,000.00 49 B49 Install Valve Box EA 2 $1,400.00 $2,800.00 $830.00 $1,660.00 $535.00 $1,070.00 $1,100.00 $2,200.00 50 B50 Insulation, 4-in. SF 160 $4.50 $720.00 $8.00 $1,280.00 $4.00 $640.00 $10.00 $1,600.00 51 B51 Temporary Water Service LS 1 $76,000.00 $76,000.00 $33,020.00 $33,020.00 $160,000.00 $160,000.00 $48,000.00 $48,000.00 52 B52 Temporary Mailboxes EA 81 $150.00 $12,150.00 $150.00 $12,150.00 $250.00 $20,250.00 $250.00 $20,250.00 53 B53 Subsurface Exploration (Undistributed) EA 5 $1,500.00 $7,500.00 $400.00 $2,000.00 $1,400.00 $7,000.00 $1,200.00 $6,000.00 54 B54 Seed Restoration SY 7650 $10.15 $77,647.50 $1.00 $7,650.00 $6.95 $53,167.50 $10.50 $80,325.00 55 B55 Water for Seeded Areas MGAL 130 $10.00 $1,300.00 $1.00 $130.00 $10.00 $1,300.00 $40.00 $5,200.00 56 B56 Erosion Control LS 1 $16,275.00 $16,275.00 $7,400.00 $7,400.00 $12,775.00 $12,775.00 $25,000.00 $25,000.00 57 B57 Clearing and Grubbing ID 140 $52.00 $7,280.00 $55.00 $7,700.00 $18.00 $2,520.00 $56.00 $7,840.00 58 B58 Traffic Control LS 1 $7,300.00 $7,300.00 $12,250.00 $12,250.00 $7,250.00 $7,250.00 $12,500.00 $12,500.00 59 B59 Staking LS 1 $41,518.00 $41,518.00 $37,220.00 $37,220.00 $36,218.00 $36,218.00 $38,000.00 $38,000.00 Total Base Bid: $4,167,421.65 $4,222,222.00 $4,853,720.50 $4,935,314.50 Total Base Bid with Contingency: $4,792,534.90 $4,855,555.30 $5,581,778.58 $5,675,611.68 Page 12 of 16 s t e v e n s p o i n t . c o m April 4, 2025 To: Board of Public Works From: Scott Beduhn, Director of Public Works Re: Contract Award Recommendation 2025 Street Improvements – Madison Street, Project 25-102 Bids for the 2025 Street Improvements – Madison Street Project were received on April 2, 2025. A total of five bids were received ranging from approximately $3.31 million to $4.16 million. The bids are summarized in the attached bid tabulation. This project was split into a base bid and two separate alternate bids. This approach allowed the City to truncate the project to stay within the council approved budget if bid prices came in unfavorably. Fortunately, bid prices came back competitive and we are able to include the additional alternate work while staying within the council approved capital budget. The two lowest bids were separated by one percent. The lowest bid was submitted by Switlick & Sons Inc. out of Athens, WI. The City has not worked with Switlick in the past. Switlick has performed projects of this size in central Wisconsin for neighboring communities. Staff reached out to two separate communities to gather feedback on the work performed by Switlick and received positive feedback. Staff believe that Switlick is a responsible bidder and is qualified and capable of performing the work. It is staff’s recommendation that the project, inclusive of the base bid and alternates one and two, be awarded to Switlick & Sons Inc. in an amount not to exceed $3,811,709.50, including a 15 percent contingency. If there are any questions, please do not hesitate to contact me. Thank you. Z:\90 - MEETINGS\2025 - MEETINGS\04 - April\Memo - Award Street Improvements - Madison - Project 25-102.doc City of Stevens Point 1515 Strongs Avenue Stevens Point, WI 54481 Public Works Engineering Department: Phone: 715-346-1561 Fax: 715-346-1650 Streets Department: Phone: 715-346-1537 Fax: 715-346-1687 Page 13 of 16 2025 Street Improvements - Madison Street Project 25-102 (#9586420) Owner: City of Stevens Point WI 04/02/2025 10:00 AM CDT Line Item Item Code Item Description UofM Quantity Unit Price Extension Unit Price Extension Unit Price Extension Unit Price Extension Unit Price Extension 1 B1 Mobilization LS 1 $250,000.00 $250,000.00 $184,500.00 $184,500.00 $175,000.00 $175,000.00 $225,776.33 $225,776.33 $200,000.00 $200,000.00 2 B2 Common Excavation CY 9488 $14.00 $132,832.00 $17.00 $161,296.00 $16.00 $151,808.00 $14.00 $132,832.00 $20.00 $189,760.00 3 B3 Rock Excavation - Utility Trench (Undistributed) CY 100 $1.00 $100.00 $1.00 $100.00 $60.00 $6,000.00 $185.00 $18,500.00 $10.00 $1,000.00 4 B4 Utility Demolition LS 1 $60,000.00 $60,000.00 $80,000.00 $80,000.00 $22,500.00 $22,500.00 $36,700.00 $36,700.00 $70,000.00 $70,000.00 5 B5 Excavation Below Subgrade (EBS) (Undistributed) CY 615 $14.00 $8,610.00 $17.00 $10,455.00 $16.00 $9,840.00 $14.61 $8,985.15 $35.00 $21,525.00 6 B6 Prepare Foundation for Asphaltic Paving LS 1 $40,000.00 $40,000.00 $25,000.00 $25,000.00 $23,100.00 $23,100.00 $23,100.00 $23,100.00 $24,000.00 $24,000.00 7 B7 Biaxial Geogrid (Undistributed) SY 1845 $3.00 $5,535.00 $2.00 $3,690.00 $2.25 $4,151.25 $3.92 $7,232.40 $4.00 $7,380.00 8 B8 Dense Graded Base, 1 1/4-in TON 11692 $18.00 $210,456.00 $17.00 $198,764.00 $16.75 $195,841.00 $20.98 $245,298.16 $18.00 $210,456.00 9 B9 Granular Backfill - Imported TON 100 $23.00 $2,300.00 $24.00 $2,400.00 $26.00 $2,600.00 $13.00 $1,300.00 $25.00 $2,500.00 10 B10 HMA Pavement - 3MT 58-28 S TON 1809 $95.00 $171,855.00 $96.00 $173,664.00 $94.30 $170,588.70 $94.30 $170,588.70 $95.00 $171,855.00 11 B11 HMA Pavement - 4MT 58-34 S TON 1448 $102.00 $147,696.00 $103.00 $149,144.00 $101.20 $146,537.60 $101.20 $146,537.60 $102.00 $147,696.00 12 B12 Concrete Sidewalk, 4-in. SF 25740 $6.00 $154,440.00 $5.90 $151,866.00 $5.60 $144,144.00 $4.99 $128,442.60 $5.40 $138,996.00 13 B13 Concrete Sidewalk, 6-in. SF 8390 $7.00 $58,730.00 $6.30 $52,857.00 $6.25 $52,437.50 $6.81 $57,135.90 $6.50 $54,535.00 14 B14 Concrete Sidewalk Removal SF 29035 $1.00 $29,035.00 $0.80 $23,228.00 $1.20 $34,842.00 $0.55 $15,969.25 $1.00 $29,035.00 15 B15 Detectable Warning Field SF 370 $50.00 $18,500.00 $29.00 $10,730.00 $34.00 $12,580.00 $49.71 $18,392.70 $35.00 $12,950.00 16 B16 Concrete Driveway, 6-in. SF 8640 $7.00 $60,480.00 $6.30 $54,432.00 $6.80 $58,752.00 $6.81 $58,838.40 $6.60 $57,024.00 17 B17 Concrete Driveway, 8-in. SF 5960 $9.00 $53,640.00 $7.80 $46,488.00 $6.90 $41,124.00 $8.61 $51,315.60 $7.50 $44,700.00 18 B18 Asphaltic Driveway, 3-in. TON 70 $190.00 $13,300.00 $196.00 $13,720.00 $190.00 $13,300.00 $190.00 $13,300.00 $200.00 $14,000.00 19 B19 Remove and Replace Aggregate Driveway, 12-in. SF 1220 $4.00 $4,880.00 $3.00 $3,660.00 $3.80 $4,636.00 $1.29 $1,573.80 $10.00 $12,200.00 20 B20 Curb and Gutter, 18-in. LF 600 $20.00 $12,000.00 $17.00 $10,200.00 $15.00 $9,000.00 $16.26 $9,756.00 $15.00 $9,000.00 21 B21 Curb and Gutter, 24-in. LF 7320 $16.00 $117,120.00 $16.00 $117,120.00 $15.00 $109,800.00 $16.81 $123,049.20 $16.00 $117,120.00 22 B22 Curb and Gutter, 30-in. LF 170 $22.00 $3,740.00 $57.00 $9,690.00 $23.00 $3,910.00 $20.22 $3,437.40 $25.00 $4,250.00 23 B23 Concrete Pedestrian Curb (Undistributed) LF 600 $30.00 $18,000.00 $57.00 $34,200.00 $18.00 $10,800.00 $64.73 $38,838.00 $20.00 $12,000.00 24 B24 Concrete Poured in Place Wall LF 40 $100.00 $4,000.00 $103.00 $4,120.00 $25.00 $1,000.00 $100.12 $4,004.80 $35.00 $1,400.00 25 B25 Concrete Steps SF 60 $65.00 $3,900.00 $78.00 $4,680.00 $90.00 $5,400.00 $72.06 $4,323.60 $100.00 $6,000.00 26 B26 Curb and Gutter Removal LF 9140 $2.00 $18,280.00 $3.00 $27,420.00 $2.50 $22,850.00 $3.28 $29,979.20 $4.00 $36,560.00 27 B27 Class "B" Bedding (undistributed) LF 650 $8.00 $5,200.00 $14.00 $9,100.00 $0.01 $6.50 $7.57 $4,920.50 $20.00 $13,000.00 28 B28 Storm Sewer Pipe, Corrugated HDPE, Class III-A, 12-in. LF 805 $43.00 $34,615.00 $60.00 $48,300.00 $48.00 $38,640.00 $52.70 $42,423.50 $74.00 $59,570.00 29 B29 Storm Sewer Pipe, Corrugated HDPE, Class III-A, 15-in. LF 1135 $47.00 $53,345.00 $60.00 $68,100.00 $49.00 $55,615.00 $51.35 $58,282.25 $76.00 $86,260.00 30 B30 Storm Sewer Pipe, 10" PVC LF 27 $57.00 $1,539.00 $64.00 $1,728.00 $70.00 $1,890.00 $57.69 $1,557.63 $70.00 $1,890.00 31 B31 Drain Basin with Casting, 24-in EA 29 $3,500.00 $101,500.00 $4,100.00 $118,900.00 $3,700.00 $107,300.00 $4,357.00 $126,353.00 $4,200.00 $121,800.00 32 B32 Drain Basin with Casting, 36-in EA 2 $4,500.00 $9,000.00 $9,300.00 $18,600.00 $8,000.00 $16,000.00 $9,609.00 $19,218.00 $8,500.00 $17,000.00 33 B33 Storm Sewer Manhole, with Casting, 48-in DIA EA 6 $3,500.00 $21,000.00 $5,600.00 $33,600.00 $5,050.00 $30,300.00 $4,211.75 $25,270.50 $5,500.00 $33,000.00 34 B34 Adjust Existing Structure EA 7 $500.00 $3,500.00 $1,800.00 $12,600.00 $1,125.00 $7,875.00 $1,774.29 $12,420.03 $2,200.00 $15,400.00 35 B35 Reconstruct Manhole, Storm, 48-in. DIA EA 2 $1,500.00 $3,000.00 $3,300.00 $6,600.00 $1,575.00 $3,150.00 $2,740.50 $5,481.00 $3,500.00 $7,000.00 36 B36 Controlled Low Strength Material CY 50 $180.00 $9,000.00 $300.00 $15,000.00 $365.00 $18,250.00 $416.00 $20,800.00 $200.00 $10,000.00 37 B37 Repair Existing Pipe Tap Opening EA 5 $700.00 $3,500.00 $1,400.00 $7,000.00 $3,300.00 $16,500.00 $5,215.20 $26,076.00 $750.00 $3,750.00 38 B38 PVC Sanitary Lateral, SDR 35, 6-in. LF 2050 $55.00 $112,750.00 $58.00 $118,900.00 $95.00 $194,750.00 $87.96 $180,318.00 $85.00 $174,250.00 39 B39 PVC Sanitary Lateral with Riser, SDR 35, 6-in. LF 135 $55.00 $7,425.00 $58.00 $7,830.00 $157.00 $21,195.00 $164.84 $22,253.40 $100.00 $13,500.00 40 B40 PVC Sanitary Sewer, SDR 35, 8-in. LF 3335 $63.00 $210,105.00 $63.00 $210,105.00 $71.00 $236,785.00 $67.99 $226,746.65 $84.00 $280,140.00 41 B41 Sanitary Sewer Manhole, with Casting, 48-in. DIA EA 10 $4,500.00 $45,000.00 $6,300.00 $63,000.00 $5,750.00 $57,500.00 $5,439.30 $54,393.00 $8,000.00 $80,000.00 42 B42 Construct Outside Sanitary Drop, All Sizes VF 18 $500.00 $9,000.00 $550.00 $9,900.00 $1,025.00 $18,450.00 $1,618.06 $29,125.08 $300.00 $5,400.00 43 B43 Sewer Bypass Pumping LS 1 $15,000.00 $15,000.00 $15,000.00 $15,000.00 $13,000.00 $13,000.00 $29,400.00 $29,400.00 $20,000.00 $20,000.00 44 B44 PVC Watermain, C900, 6-in. LF 465 $64.00 $29,760.00 $91.00 $42,315.00 $88.00 $40,920.00 $113.33 $52,698.45 $117.00 $54,405.00 45 B45 PVC Watermain, C900, 8-in. LF 3435 $67.00 $230,145.00 $80.00 $274,800.00 $79.00 $271,365.00 $98.58 $338,622.30 $100.00 $343,500.00 46 B46 Polyethylene Water Service Lateral, 1-in. LF 1438 $64.00 $92,032.00 $69.00 $99,222.00 $125.00 $179,750.00 $64.01 $92,046.38 $96.00 $138,048.00 47 B47 Fire Hydrant Assembly EA 9 $6,500.00 $58,500.00 $8,500.00 $76,500.00 $8,155.00 $73,395.00 $8,876.44 $79,887.96 $10,000.00 $90,000.00 48 B48 Temporary Water Service LS 1 $30,000.00 $30,000.00 $25,000.00 $25,000.00 $128,000.00 $128,000.00 $32,097.00 $32,097.00 $50,000.00 $50,000.00 49 B49 Temporary Mailboxes EA 63 $50.00 $3,150.00 $150.00 $9,450.00 $307.00 $19,341.00 $54.00 $3,402.00 $200.00 $12,600.00 50 B50 Subsurface Exploration (Undistributed) EA 20 $50.00 $1,000.00 $400.00 $8,000.00 $1,225.00 $24,500.00 $1,500.00 $30,000.00 $1,200.00 $24,000.00 Switlick & Sons Inc. A-1 Excavating LLC Integrity Grading and Excavating, Inc. Merrill Gravel & Construction Co Earth Inc. Page 14 of 16 51 B51 Seed Restoration SY 7250 $8.00 $58,000.00 $1.00 $7,250.00 $7.25 $52,562.50 $8.95 $64,887.50 $10.00 $72,500.00 52 B52 Water for Seeded Areas MGAL 150 $5.00 $750.00 $1.00 $150.00 $55.00 $8,250.00 $65.00 $9,750.00 $20.00 $3,000.00 53 B53 Erosion Control LS 1 $3,000.00 $3,000.00 $8,000.00 $8,000.00 $7,000.00 $7,000.00 $5,600.00 $5,600.00 $30,000.00 $30,000.00 54 B54 Clearing and Grubbing ID 294 $30.00 $8,820.00 $40.00 $11,760.00 $14.82 $4,357.08 $25.00 $7,350.00 $56.00 $16,464.00 55 B55 Traffic Control LS 1 $15,000.00 $15,000.00 $8,200.00 $8,200.00 $3,108.00 $3,108.00 $3,500.00 $3,500.00 $10,000.00 $10,000.00 56 B56 Staking LS 1 $52,000.00 $52,000.00 $33,600.00 $33,600.00 $32,246.00 $32,246.00 $32,300.00 $32,300.00 $34,000.00 $34,000.00 57 B57 Remove and Reset Street Sign EA 19 $100.00 $1,900.00 $200.00 $3,800.00 $100.00 $1,900.00 $100.00 $1,900.00 $500.00 $9,500.00 58 B58 Pavement Marking Line Epoxy 4-Inch LF 530 $3.00 $1,590.00 $8.00 $4,240.00 $2.10 $1,113.00 $2.00 $1,060.00 $8.00 $4,240.00 59 B59 Pavement Marking Line Epoxy 8-Inch LF 75 $3.00 $225.00 $6.00 $450.00 $2.95 $221.25 $5.00 $375.00 $6.00 $450.00 60 B60 Pavement Marking Arrow Epoxy EA 2 $500.00 $1,000.00 $300.00 $600.00 $410.00 $820.00 $300.00 $600.00 $300.00 $600.00 61 B61 Pavement Marking Symbol Epoxy EA 1 $300.00 $300.00 $200.00 $200.00 $275.00 $275.00 $350.00 $350.00 $200.00 $200.00 62 B62 Pavement Marking Stop Line Epoxy 18-Inch LF 25 $30.00 $750.00 $20.00 $500.00 $28.75 $718.75 $50.00 $1,250.00 $20.00 $500.00 63 B63 Insulation, 4-in. SF 512 $4.00 $2,048.00 $6.00 $3,072.00 $4.00 $2,048.00 $3.51 $1,797.12 $9.00 $4,608.00 64 B64 Storm Sewer Pipe PVC, 6-In. LF 37 $55.00 $2,035.00 $71.00 $2,627.00 $65.00 $2,405.00 $53.51 $1,979.87 $75.00 $2,775.00 65 B65 Polyethylene Water Service Lateral, 2-in. (Undistributed) LF 152 $67.00 $10,184.00 $111.00 $16,872.00 $152.00 $23,104.00 $113.16 $17,200.32 $85.00 $12,920.00 Total Base Bid: $2,846,097.00 $2,954,295.00 $3,147,148.13 $3,238,899.23 $3,452,212.00 66 A1.1 Mobilization LS 1 $2,000.00 $2,000.00 $8,800.00 $8,800.00 $13,000.00 $13,000.00 $47,979.00 $47,979.00 $12,500.00 $12,500.00 67 A1.2 Common Excavation CY 766 $14.00 $10,724.00 $17.00 $13,022.00 $16.00 $12,256.00 $14.00 $10,724.00 $21.00 $16,086.00 68 A1.3 Rock Excavation - Utility Trench (Undistributed) CY 50 $1.00 $50.00 $1.00 $50.00 $60.00 $3,000.00 $185.00 $9,250.00 $100.00 $5,000.00 69 A1.4 Utility Demolition LS 1 $5,000.00 $5,000.00 $7,500.00 $7,500.00 $2,250.00 $2,250.00 $2,500.00 $2,500.00 $7,500.00 $7,500.00 70 A1.5 Excavation Below Subgrade (EBS) (Undistributed) CY 50 $14.00 $700.00 $17.00 $850.00 $16.00 $800.00 $21.50 $1,075.00 $40.00 $2,000.00 71 A1.6 Prepare Foundation for Asphaltic Paving LS 1 $5,000.00 $5,000.00 $3,000.00 $3,000.00 $2,640.00 $2,640.00 $2,640.00 $2,640.00 $3,000.00 $3,000.00 72 A1.7 Biaxial Geogrid (Undistributed) SY 150 $3.00 $450.00 $2.00 $300.00 $2.25 $337.50 $4.82 $723.00 $5.00 $750.00 73 A1.8 Dense Graded Base, 1 1/4-in TON 1137 $18.00 $20,466.00 $17.00 $19,329.00 $16.75 $19,044.75 $20.98 $23,854.26 $19.00 $21,603.00 74 A1.9 Granular Backfill - Imported TON 20 $23.00 $460.00 $24.00 $480.00 $26.00 $520.00 $13.00 $260.00 $30.00 $600.00 75 A1.10 HMA Pavement - 3MT 58-28 S TON 188 $96.00 $18,048.00 $98.00 $18,424.00 $95.50 $17,954.00 $95.50 $17,954.00 $97.00 $18,236.00 76 A1.11 HMA Pavement - 4MT 58-34 S TON 150 $105.00 $15,750.00 $107.00 $16,050.00 $104.00 $15,600.00 $104.10 $15,615.00 $105.00 $15,750.00 77 A1.12 Concrete Sidewalk, 4-in. SF 2972 $6.00 $17,832.00 $5.90 $17,534.80 $6.25 $18,575.00 $5.04 $14,978.88 $6.70 $19,912.40 78 A1.13 Concrete Sidewalk, 6-in. SF 806 $7.00 $5,642.00 $6.30 $5,077.80 $8.50 $6,851.00 $7.05 $5,682.30 $8.20 $6,609.20 79 A1.14 Concrete Sidewalk Removal SF 3778 $1.00 $3,778.00 $0.80 $3,022.40 $0.95 $3,589.10 $0.55 $2,077.90 $1.00 $3,778.00 80 A1.15 Detectable Warning Field SF 80 $50.00 $4,000.00 $29.00 $2,320.00 $42.00 $3,360.00 $49.71 $3,976.80 $40.00 $3,200.00 81 A1.16 Concrete Driveway, 6-in. SF 710 $7.00 $4,970.00 $6.30 $4,473.00 $8.50 $6,035.00 $6.84 $4,856.40 $8.25 $5,857.50 82 A1.17 Asphaltic Driveway, 3-in. TON 10 $190.00 $1,900.00 $196.00 $1,960.00 $190.00 $1,900.00 $200.00 $2,000.00 $200.00 $2,000.00 83 A1.18 Curb and Gutter, 24-in. LF 690 $16.00 $11,040.00 $17.00 $11,730.00 $36.00 $24,840.00 $16.84 $11,619.60 $35.00 $24,150.00 84 A1.19 Concrete Pedestrian Curb (Undistributed) LF 60 $30.00 $1,800.00 $47.00 $2,820.00 $39.00 $2,340.00 $64.72 $3,883.20 $42.00 $2,520.00 85 A1.20 Curb and Gutter Removal LF 690 $2.00 $1,380.00 $3.00 $2,070.00 $2.50 $1,725.00 $3.28 $2,263.20 $4.00 $2,760.00 86 A1.21 Class "B" Bedding (Undistributed) LF 40 $8.00 $320.00 $14.00 $560.00 $0.01 $0.40 $7.57 $302.80 $25.00 $1,000.00 87 A1.22 Storm Sewer Pipe, Corrugated HDPE, Class III-A, 12-in. LF 145 $43.00 $6,235.00 $60.00 $8,700.00 $65.00 $9,425.00 $54.82 $7,948.90 $75.00 $10,875.00 88 A1.23 Drain Basin with Casting, 24-in EA 4 $3,500.00 $14,000.00 $4,100.00 $16,400.00 $5,775.00 $23,100.00 $4,357.00 $17,428.00 $4,200.00 $16,800.00 89 A1.24 Storm Sewer Manhole, with Casting, 48-in DIA EA 1 $4,000.00 $4,000.00 $5,600.00 $5,600.00 $4,600.00 $4,600.00 $3,680.75 $3,680.75 $5,600.00 $5,600.00 90 A1.25 Adjust Existing Structure EA 3 $300.00 $900.00 $1,800.00 $5,400.00 $1,155.00 $3,465.00 $1,772.00 $5,316.00 $2,200.00 $6,600.00 91 A1.26 PVC Sanitary Lateral with Riser, SDR 35, 6-in. LF 180 $55.00 $9,900.00 $58.00 $10,440.00 $68.00 $12,240.00 $212.80 $38,304.00 $100.00 $18,000.00 92 A1.27 PVC Watermain, C900, 6-in. LF 340 $64.00 $21,760.00 $91.00 $30,940.00 $69.00 $23,460.00 $82.08 $27,907.20 $117.00 $39,780.00 93 A1.28 PVC Watermain, C900, 8-in. LF 70 $67.00 $4,690.00 $80.00 $5,600.00 $158.00 $11,060.00 $186.68 $13,067.60 $100.00 $7,000.00 94 A1.29 Polyethylene Water Service Lateral, 1-in. LF 105 $64.00 $6,720.00 $69.00 $7,245.00 $85.00 $8,925.00 $56.10 $5,890.50 $100.00 $10,500.00 95 A1.30 Fire Hydrant Assembly EA 1 $6,500.00 $6,500.00 $8,500.00 $8,500.00 $8,200.00 $8,200.00 $8,709.00 $8,709.00 $10,000.00 $10,000.00 96 A1.31 Temporary Water Service LS 1 $5,000.00 $5,000.00 $1,200.00 $1,200.00 $7,500.00 $7,500.00 $7,400.00 $7,400.00 $10,000.00 $10,000.00 97 A1.32 Temporary Mailboxes EA 9 $50.00 $450.00 $150.00 $1,350.00 $309.00 $2,781.00 $54.00 $486.00 $150.00 $1,350.00 98 A1.33 Seed Restoration SY 650 $8.00 $5,200.00 $1.00 $650.00 $7.25 $4,712.50 $8.70 $5,655.00 $10.00 $6,500.00 99 A1.34 Water for Seeded Areas MGAL 20 $5.00 $100.00 $1.00 $20.00 $55.00 $1,100.00 $65.00 $1,300.00 $40.00 $800.00 100 A1.35 Erosion Control LS 1 $1,000.00 $1,000.00 $800.00 $800.00 $2,000.00 $2,000.00 $2,500.00 $2,500.00 $2,000.00 $2,000.00 101 A1.36 Clearing and Grubbing ID 18 $30.00 $540.00 $40.00 $720.00 $14.82 $266.76 $25.00 $450.00 $60.00 $1,080.00 102 A1.37 Traffic Control LS 1 $1,000.00 $1,000.00 $1,200.00 $1,200.00 $675.00 $675.00 $700.00 $700.00 $2,000.00 $2,000.00 103 A1.38 Staking LS 1 $5,000.00 $5,000.00 $3,900.00 $3,900.00 $3,741.00 $3,741.00 $3,750.00 $3,750.00 $5,000.00 $5,000.00 104 A1.39 Remove and Reset Street Sign EA 5 $100.00 $500.00 $200.00 $1,000.00 $100.00 $500.00 $100.00 $500.00 $500.00 $2,500.00 105 A1.40 Pavement Marking Crosswalk Epoxy Transverse Line 6-Inch LF 280 $25.00 $7,000.00 $14.00 $3,920.00 $20.50 $5,740.00 $15.00 $4,200.00 $15.00 $4,200.00 Total Alternate 1: $231,805.00 $268,623.30 $333,812.24 $296,793.08 $352,110.10 106 A2.1 Mobilization LS 1 $2,000.00 $2,000.00 $8,500.00 $8,500.00 $50,000.00 $50,000.00 $19,405.00 $19,405.00 $12,500.00 $12,500.00 Page 15 of 16 107 A2.2 Common Excavation CY 733 $14.00 $10,262.00 $17.00 $12,461.00 $16.00 $11,728.00 $14.00 $10,262.00 $21.00 $15,393.00 108 A2.3 Rock Excavation - Utility Trench (Undistributed) CY 50 $1.00 $50.00 $1.00 $50.00 $60.00 $3,000.00 $185.00 $9,250.00 $100.00 $5,000.00 109 A2.4 Utility Demolition LS 1 $5,000.00 $5,000.00 $12,000.00 $12,000.00 $2,250.00 $2,250.00 $4,000.00 $4,000.00 $7,500.00 $7,500.00 110 A2.5 Excavation Below Subgrade (EBS) (Undistributed) CY 45 $14.00 $630.00 $17.00 $765.00 $16.00 $720.00 $22.33 $1,004.85 $40.00 $1,800.00 111 A2.6 Prepare Foundation for Asphaltic Paving LS 1 $5,000.00 $5,000.00 $3,000.00 $3,000.00 $2,240.00 $2,240.00 $2,240.00 $2,240.00 $2,500.00 $2,500.00 112 A2.7 Biaxial Geogrid (Undistributed) SY 135 $3.00 $405.00 $2.00 $270.00 $2.25 $303.75 $5.01 $676.35 $5.00 $675.00 113 A2.8 Dense Graded Base, 1 1/4-in TON 971 $18.00 $17,478.00 $17.00 $16,507.00 $16.75 $16,264.25 $20.98 $20,371.58 $20.00 $19,420.00 114 A2.9 Granular Backfill - Imported TON 20 $23.00 $460.00 $24.00 $480.00 $26.00 $520.00 $13.00 $260.00 $30.00 $600.00 115 A2.10 HMA Pavement - 3MT 58-28 S TON 154 $96.00 $14,784.00 $98.00 $15,092.00 $95.50 $14,707.00 $95.50 $14,707.00 $97.00 $14,938.00 116 A2.11 HMA Pavement - 4MT 58-34 S TON 124 $105.00 $13,020.00 $107.00 $13,268.00 $104.10 $12,908.40 $104.10 $12,908.40 $106.00 $13,144.00 117 A2.12 Concrete Sidewalk, 4-in. SF 2240 $6.00 $13,440.00 $6.00 $13,440.00 $6.00 $13,440.00 $5.04 $11,289.60 $6.70 $15,008.00 118 A2.13 Concrete Sidewalk, 6-in. SF 1313 $7.00 $9,191.00 $6.30 $8,271.90 $7.50 $9,847.50 $7.00 $9,191.00 $8.20 $10,766.60 119 A2.14 Concrete Sidewalk Removal SF 3553 $1.00 $3,553.00 $0.80 $2,842.40 $1.50 $5,329.50 $0.55 $1,954.15 $1.00 $3,553.00 120 A2.15 Detectable Warning Field SF 80 $50.00 $4,000.00 $29.00 $2,320.00 $42.00 $3,360.00 $49.75 $3,980.00 $40.00 $3,200.00 121 A2.16 Concrete Driveway, 6-in. SF 1070 $7.00 $7,490.00 $6.30 $6,741.00 $7.50 $8,025.00 $6.84 $7,318.80 $8.25 $8,827.50 122 A2.17 Curb and Gutter, 24-in. LF 620 $16.00 $9,920.00 $16.00 $9,920.00 $34.00 $21,080.00 $16.89 $10,471.80 $35.00 $21,700.00 123 A2.18 Curb and Gutter Removal LF 620 $2.00 $1,240.00 $3.00 $1,860.00 $2.50 $1,550.00 $3.28 $2,033.60 $5.00 $3,100.00 124 A2.19 Class "B" Bedding (undistributed) LF 50 $8.00 $400.00 $14.00 $700.00 $0.01 $0.50 $7.57 $378.50 $25.00 $1,250.00 125 A2.20 Storm Sewer Pipe, Corrugated HDPE, Class III-A, 12-in. LF 115 $43.00 $4,945.00 $60.00 $6,900.00 $60.00 $6,900.00 $46.36 $5,331.40 $75.00 $8,625.00 126 A2.21 Storm Sewer Pipe, Corrugated HDPE, Class III-A, 15-in. LF 140 $47.00 $6,580.00 $60.00 $8,400.00 $70.00 $9,800.00 $50.17 $7,023.80 $78.00 $10,920.00 127 A2.22 Drain Basin with Casting, 24-in EA 4 $3,500.00 $14,000.00 $4,100.00 $16,400.00 $2,100.00 $8,400.00 $4,357.00 $17,428.00 $4,200.00 $16,800.00 128 A2.23 Drain Basin with Casting, 36-in EA 1 $5,000.00 $5,000.00 $9,300.00 $9,300.00 $8,250.00 $8,250.00 $9,609.00 $9,609.00 $8,500.00 $8,500.00 129 A2.24 Storm Sewer Manhole, with Casting, 48-in DIA EA 2 $4,000.00 $8,000.00 $5,600.00 $11,200.00 $4,700.00 $9,400.00 $3,592.25 $7,184.50 $5,600.00 $11,200.00 130 A2.25 PVC Sanitary Lateral, SDR 35, 6-in. LF 60 $55.00 $3,300.00 $58.00 $3,480.00 $106.00 $6,360.00 $38.61 $2,316.60 $90.00 $5,400.00 131 A2.26 PVC Sanitary Sewer, SDR 35, 8-in. LF 215 $63.00 $13,545.00 $63.00 $13,545.00 $75.00 $16,125.00 $67.18 $14,443.70 $88.00 $18,920.00 132 A2.27 Sanitary Sewer Manhole, with Casting, 48-in. DIA EA 2 $4,500.00 $9,000.00 $6,300.00 $12,600.00 $9,367.00 $18,734.00 $6,546.50 $13,093.00 $8,500.00 $17,000.00 133 A2.28 Sewer Bypass Pumping LS 1 $2,000.00 $2,000.00 $2,500.00 $2,500.00 $5,000.00 $5,000.00 $5,000.00 $5,000.00 $5,000.00 $5,000.00 134 A2.29 PVC Watermain, C900, 6-in. LF 285 $64.00 $18,240.00 $91.00 $25,935.00 $74.00 $21,090.00 $92.28 $26,299.80 $120.00 $34,200.00 135 A2.30 PVC Watermain, C900, 8-in. LF 65 $67.00 $4,355.00 $80.00 $5,200.00 $148.00 $9,620.00 $175.23 $11,389.95 $150.00 $9,750.00 136 A2.31 Polyethylene Water Service Lateral, 1-in. LF 65 $64.00 $4,160.00 $69.00 $4,485.00 $105.00 $6,825.00 $57.18 $3,716.70 $100.00 $6,500.00 137 A2.32 Fire Hydrant Assembly EA 1 $6,500.00 $6,500.00 $8,500.00 $8,500.00 $8,300.00 $8,300.00 $8,809.00 $8,809.00 $10,000.00 $10,000.00 138 A2.33 Temporary Water Service LS 1 $5,000.00 $5,000.00 $1,000.00 $1,000.00 $5,000.00 $5,000.00 $7,400.00 $7,400.00 $7,500.00 $7,500.00 139 A2.34 Temporary Mailboxes EA 8 $50.00 $400.00 $150.00 $1,200.00 $309.00 $2,472.00 $54.00 $432.00 $150.00 $1,200.00 140 A2.35 Seed Restoration SY 690 $8.00 $5,520.00 $1.00 $690.00 $7.25 $5,002.50 $8.70 $6,003.00 $10.00 $6,900.00 141 A2.36 Water for Seeded Areas MGAL 20 $5.00 $100.00 $1.00 $20.00 $55.00 $1,100.00 $65.00 $1,300.00 $30.00 $600.00 142 A2.37 Erosion Control LS 1 $1,000.00 $1,000.00 $1,700.00 $1,700.00 $2,500.00 $2,500.00 $2,500.00 $2,500.00 $2,000.00 $2,000.00 143 A2.38 Clearing and Grubbing ID 12 $30.00 $360.00 $40.00 $480.00 $14.82 $177.84 $25.00 $300.00 $60.00 $720.00 144 A2.39 Traffic Control LS 1 $1,000.00 $1,000.00 $1,200.00 $1,200.00 $675.00 $675.00 $700.00 $700.00 $2,000.00 $2,000.00 145 A2.40 Staking LS 1 $5,000.00 $5,000.00 $4,800.00 $4,800.00 $4,507.00 $4,507.00 $4,510.00 $4,510.00 $6,000.00 $6,000.00 146 A2.41 Remove and Reset Street Sign EA 3 $100.00 $300.00 $200.00 $600.00 $100.00 $300.00 $100.00 $300.00 $500.00 $1,500.00 Total Alternate Bid 2: $236,628.00 $268,623.30 $333,812.24 $296,793.08 $352,110.10 Total Base Bid including Alternates: $3,314,530.00 $3,491,541.60 $3,814,772.61 $3,832,485.39 $4,156,432.20 Total Bid including Alternates & Contingencey: $3,811,709.50 $4,015,272.84 $4,386,988.50 $4,407,358.20 $4,779,897.03 Page 16 of 16

Source: City of Stevens Point website. First collected Nov 18, 2026.